XML 55 R37.htm IDEA: XBRL DOCUMENT v3.8.0.1
Vogtle Units No. 3 and No. 4 Construction Project (Details)
$ in Millions
1 Months Ended 2 Months Ended 9 Months Ended 12 Months Ended
Nov. 02, 2017
USD ($)
Sep. 30, 2017
USD ($)
Jun. 09, 2017
USD ($)
Jan. 31, 2016
USD ($)
Nov. 30, 2017
USD ($)
installment
Sep. 30, 2017
USD ($)
item
Dec. 31, 2008
USD ($)
item
MW
Vogtle Units Number 3 And Number 4              
Vogtle Units No. 3 and No. 4 Construction Project              
Current investment   $ 3,900.0       $ 3,900.0  
Vogtle Units Number 3 And Number 4 | Removal of Subcontractor liens              
Vogtle Units No. 3 and No. 4 Construction Project              
Liquidated damages   115.0          
Aggregate liability paid or accrued   340.0       $ 340.0  
Vogtle Units Number 3 And Number 4 | Removal of Subcontractor liens | The Contractor and WECTEC Staffing Services LLC              
Vogtle Units No. 3 and No. 4 Construction Project              
Liquidated damages   $ 386.0          
Vogtle Units Number 3 And Number 4 | Ownership participation agreement              
Vogtle Units No. 3 and No. 4 Construction Project              
Number of additional nuclear units | item           2  
Ownership interest (as a percent)   30.00%       30.00%  
Vogtle Units Number 3 And Number 4 | Ownership participation agreement | Minimum | Occurrence of certain adverse events              
Vogtle Units No. 3 and No. 4 Construction Project              
Ownership interests voting required to continue construction (as a percent) 90.00%            
Increase in project budget $ 1,000.0            
Project extension term 1 year            
Ownership approval to change primary construction contractor (as a percent) 90.00%            
Ownership approval required for material amendments (as a percent) 67.00%            
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor)              
Vogtle Units No. 3 and No. 4 Construction Project              
Number of nuclear units | item             2
Generating capacity of each nuclear unit | MW             1,100
Project budget   $ 7,000.0       $ 7,000.0  
Estimated aggregate cancellation costs of site           $ 230.0  
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor) | In the event of abandonment of work              
Vogtle Units No. 3 and No. 4 Construction Project              
Liquidated damages, as a percent of contract price             40.00%
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor) | Maximum              
Vogtle Units No. 3 and No. 4 Construction Project              
Liquidated damages, as a percent of contract price             10.00%
Liquidated damages             $ 920.0
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC              
Vogtle Units No. 3 and No. 4 Construction Project              
Written notice period for non-renewal of letter of credit       60 days      
Vogtle Units Number 3 And Number 4 | Guarantee Settlement Agreement              
Vogtle Units No. 3 and No. 4 Construction Project              
Guarantee obligations received in installments         $ 113.3    
Recovery of guarantee obligations assumed (as a percent)   100.00%       100.00%  
Vogtle Units Number 3 And Number 4 | Guarantee Settlement Agreement | In the event of abandonment of work              
Vogtle Units No. 3 and No. 4 Construction Project              
Guarantee obligations, maximum exposure     $ 1,100.0        
Vogtle Units Number 3 And Number 4 | Guarantee Settlement Agreement | The Co-owners and Toshiba              
Vogtle Units No. 3 and No. 4 Construction Project              
Number of installments received | installment         2    
Guarantee obligations received in installments         $ 377.5    
Vogtle Units Number 3 And Number 4 | Guarantee Settlement Agreement | The Co-owners and Toshiba | In the event of abandonment of work              
Vogtle Units No. 3 and No. 4 Construction Project              
Guarantee obligations, maximum exposure     $ 3,680.0        
Vogtle Units Number 3 And Number 4 | Amended and Restated Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor)              
Vogtle Units No. 3 and No. 4 Construction Project              
Written notice period for termination of agreement     30 days        
Toshiba Corporation              
Vogtle Units No. 3 and No. 4 Construction Project              
Shareholder's equity negative balance   $ 5,500.0       $ 5,500.0  
Toshiba Corporation | Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC              
Vogtle Units No. 3 and No. 4 Construction Project              
Letters of credit       $ 920.0