Vogtle Units No. 3 and No. 4 Construction Project
9 Months Ended
Sep. 30, 2017
Vogtle Units No. 3 and No. 4 Construction Project  
Vogtle Units No. 3 and No. 4 Construction Project

 

(L)         Vogtle Units No. 3 and No. 4 Construction Project.    We, Georgia Power, the Municipal Electric Authority of Georgia, and the City of Dalton, Georgia, acting by and through its Board of Water, Light and Sinking Fund Commissioners, doing business as Dalton Utilities (collectively, the Co-owners) are parties to an Ownership Participation Agreement that, along with other agreements, governs our participation in two additional nuclear units at Plant Vogtle, Units No. 3 and No. 4. The Co-owners appointed Georgia Power to act as agent under this agreement. Our binding ownership interest and proportionate share of the cost to construct these units is 30%. Pursuant to this agreement, Georgia Power has designated Southern Nuclear Operating Company, Inc. as its agent for licensing, engineering, procurement, contract management, construction and pre-operation services.

In 2008, Georgia Power, acting for itself and as agent for the Co-owners, entered into an Engineering, Procurement and Construction Agreement (the EPC Agreement) with Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the EPC Contractor). Stone & Webster was subsequently acquired by Westinghouse and changed its name to WECTEC Global Project Services Inc. (WECTEC). Pursuant to the EPC Agreement, the EPC Contractor agreed to design, engineer, procure, construct and test two 1,100 megawatt nuclear units using the Westinghouse AP1000 technology and related facilities at Plant Vogtle.

Under the EPC Agreement, the Co-owners agreed to pay a purchase price subject to certain price escalations and adjustments. The EPC Agreement also provided for liquidated damages upon the EPC Contractor's failure to fulfill the schedule and certain performance guarantees, each subject to an aggregate cap of 10% of the contract price, or approximately $920 million.

Toshiba Corporation guaranteed certain payment obligations of the EPC Contractor under the EPC Agreement (the Toshiba Guarantee), including any liability of the EPC Contractor for abandonment of work. In January 2016, Westinghouse delivered to the Co-owners $920 million of letters of credit from financial institutions (Westinghouse Letters of Credit) to secure a portion of the EPC Contractor's potential obligations under the EPC Agreement. The Westinghouse Letters of Credit are subject to annual renewals through June 30, 2020, and require 60 days' written notice to Georgia Power, as agent of the Co-owners, in the event the Westinghouse Letters of Credit will not be renewed.

Under the terms of the EPC Agreement, the EPC Contractor did not have the right to terminate the EPC Agreement for convenience. In the event of an abandonment of work by the EPC Contractor, the maximum liability of the EPC Contractor under the EPC Agreement was 40% of the contract price, or $3.68 billion, of which our proportionate share is approximately $1.1 billion.

On March 29, 2017, the EPC Contractor filed for bankruptcy protection under Chapter 11 of the United States Bankruptcy Code. To provide for a continuation of work at Vogtle Units No. 3 and No. 4, Georgia Power, acting for itself and as agent for the other Co-owners, entered into an Interim Assessment Agreement with the EPC Contractor and WECTEC Staffing Services LLC, which the bankruptcy court approved on March 30, 2017. The Interim Assessment Agreement provided, among other items, that during the term of the Interim Assessment Agreement Georgia Power was obligated to pay, on behalf of the Co-owners, all costs accrued by the EPC Contractor for subcontractors and vendors for services performed or goods provided. The Interim Assessment Agreement, as amended, expired on July 27, 2017.

Subsequent to the EPC Contractor's bankruptcy filing, a number of subcontractors to the EPC Contractor, including Fluor Enterprises, Inc., a subsidiary of Fluor Corporation, alleged non-payment by the EPC Contractor for amounts owed for work performed on Vogtle Units No. 3 and No. 4. Georgia Power, acting for itself and as agent for the Co-owners, has taken, and continues to take, actions to remove liens filed by these subcontractors through the posting of surety bonds. Georgia Power estimates the aggregate liability, through September 30, 2017, of the Co-owners for the removal of subcontractor liens and payment of other EPC Contractor pre-petition accounts payable to total approximately $386 million, of which our proportionate share totals approximately $115 million. As of September 30, 2017, $340 million of this aggregate liability had been paid or accrued by Georgia Power, on behalf of the Co-owners.

On June 9, 2017, Georgia Power and the other Co-owners and Toshiba entered into a settlement agreement regarding the Toshiba Guarantee (the Guarantee Settlement Agreement). Pursuant to the Guarantee Settlement Agreement, Toshiba acknowledged the amount of its obligation under the Toshiba Guarantee is $3.68 billion (the Guarantee Obligations), of which our proportionate share is approximately $1.1 billion, and that the Guarantee Obligations exist regardless of whether Vogtle Units No. 3 and No. 4 are completed. The Guarantee Settlement Agreement also provides for a schedule of payments for the Guarantee Obligations that began in October 2017 and continues through January 2021. In the event Toshiba receives certain payments, including sale proceeds, from or related to Westinghouse (or its subsidiaries) or Toshiba Nuclear Energy Holdings (UK) Limited (or its subsidiaries), it will hold a portion of such payments in trust for the Co-owners and promptly pay them as offsets against any remaining Guarantee Obligations. Under the Guarantee Settlement Agreement, the Co-owners will forbear from exercising certain remedies, including drawing on the Westinghouse Letters of Credit, until June 30, 2020, unless certain events of nonpayment, insolvency, or other material breach of the Guarantee Settlement Agreement by Toshiba occur. If such an event occurs, the balance of the Guarantee Obligations will become immediately due and payable, and the Co-owners may exercise any and all rights and remedies, including drawing on the Westinghouse Letters of Credit without restriction. In addition, the Guarantee Settlement Agreement does not restrict the Co-owners from fully drawing on the Westinghouse Letters of Credit in the event they are not renewed or replaced prior to the expiration date. In October and November 2017, Georgia Power, on behalf of the Co-owners, received the first two installments of the Guarantee Obligations totaling $377.5 million from Toshiba, of which our proportionate share was $113.3 million. We are considering potential options with respect to our right to payments under the Guarantee Settlement Agreement and our claims against the EPC Contractor in the EPC Contractor's bankruptcy proceeding, including a potential sale of those payment rights and bankruptcy claims. Execution of any such transaction cannot be assured and would require certain consents from and cooperation by the Department of Energy.

On November 9, 2017, Toshiba released its financial results for the second quarter of fiscal year 2017, which reflected a negative shareholders' equity balance of approximately $5.5 billion as of September 30, 2017. Toshiba also reiterated the existence of material events and conditions that raise substantial doubt about Toshiba's ability to continue as a going concern. As a result, substantial risk regarding the Co-owners' ability to fully collect the Guarantee Obligations continues to exist. An inability or other failure by Toshiba to perform its obligations under the Guarantee Settlement Agreement could have a further material impact on the net cost to the Co-owners of Vogtle Units No. 3 and No. 4, and, therefore, on our financial condition and results of operations as well.

Additionally, on June 9, 2017, Georgia Power, acting for itself and as agent for the other Co-owners, and the EPC Contractor entered into a services agreement, which was amended and restated on July 20, 2017 (the Services Agreement), for the EPC Contractor to transition construction management of Vogtle Units No. 3 and No. 4 to Southern Nuclear and to provide ongoing design, engineering, and procurement services to Southern Nuclear. On July 20, 2017, the bankruptcy court approved the EPC Contractor's motion seeking authorization to (i) enter into the Services Agreement, (ii) assume and assign to the Co-owners certain project-related contracts, (iii) join the Co-owners as counterparties to certain assumed project-related contracts, and (iv) reject the EPC Agreement. The Services Agreement became effective upon approval by the Department of Energy on July 27, 2017 and will continue until the start-up and testing of Vogtle Units No. 3 and No. 4 is complete and electricity is generated and sold from both units. The Services Agreement is terminable by the Co-owners upon 30 days' written notice.

On August 31, 2017, Georgia Power filed its 17th Vogtle Construction Monitoring report (VCM 17 Report) with the Georgia Public Service Commission. In the VCM 17 Report, Georgia Power recommended that construction on Vogtle Units No. 3 and No. 4 be continued with Southern Nuclear serving as project manager. The recommendation to continue construction is supported by all the Co-owners and is based on the results of a comprehensive schedule, cost-to-complete and cancellation assessment. The Georgia Public Service Commission will render a decision on these matters by February 6, 2018.

The revised project schedule Georgia Power submitted to the Georgia Public Service Commission for approval included commercial operation dates of November 2021 for Unit No. 3 and November 2022 for Unit No. 4. Based on comprehensive cost-to complete assessments and the revised commercial operation dates, our revised project budget is $7.0 billion, which includes capital costs, allowance for funds used during construction and a contingency amount. This budget assumes 100% recovery of our $1.1 billion share of the Guarantee Obligations from Toshiba. As of September 30, 2017, our total investment in the additional Vogtle units was approximately $3.9 billion without taking into account any amounts recoverable from Toshiba. Amounts recovered in connection with the Guarantee Settlement Agreement will be recorded as a reduction to the construction work in progress balance as payments are received.

Effective October 23, 2017, Georgia Power, acting for itself and as agent for the other Co-owners, entered into a construction completion agreement (the Bechtel Agreement) with Bechtel Power Corporation, whereby Bechtel will serve as the primary contractor for the remaining construction activities for Vogtle Units No. 3 and No. 4. Facility design and engineering remains the responsibility of Westinghouse under the Services Agreement. The Bechtel Agreement is a cost reimbursable plus fee arrangement, whereby Bechtel will be reimbursed for actual costs plus a base fee and an at-risk fee, which is subject to adjustment based on Bechtel's performance against cost and schedule targets. Each Co-owner is severally (not jointly) liable for its proportionate share, based on its ownership interest, of all amounts owed to Bechtel under the Bechtel Agreement. The Co-owners may terminate the Bechtel Agreement at any time for their convenience, provided that the Co-owners will be required to pay amounts related to work performed prior to the termination (including the applicable portion of the base fee), certain termination-related costs and, at certain stages of the work, the at-risk fee. Bechtel may terminate the Bechtel Agreement under certain circumstances, including, certain Co-owner suspensions of work, certain breaches of the Bechtel Agreement by the Co-owners, Co-owner insolvency and certain other events.

On November 2, 2017, the Co-owners entered into an amendment to their joint ownership agreements for Vogtle Units No. 3 and No. 4 (as amended, the Joint Ownership Agreements) to provide for, among other conditions, additional Co-owner approval requirements. Pursuant to the Joint Ownership Agreements, the holders of at least 90% of the ownership interests in Vogtle Units No. 3 and No. 4 must vote to continue construction if certain adverse events occur, including: (i) the bankruptcy of Toshiba or, except in the case in which each of the Co-owners has assigned its rights under the Guarantee Settlement Agreement to a third party, a material breach by Toshiba of the Guarantee Settlement Agreement; (ii) termination or rejection in bankruptcy of certain agreements, including the Services Agreement or the Bechtel Agreement; (iii) the Georgia Public Service Commission or Georgia Power determines that any of Georgia Power's costs relating to the construction of Vogtle Units No. 3 and No. 4 will not be recovered in retail rates because such costs are deemed unreasonable or imprudent; or (iv) an increase in the construction budget contained in the seventeenth VCM report of more than $1 billion or extension of the project schedule contained in the seventeenth VCM report of more than one year. In addition, pursuant to the Joint Ownership Agreements, the required approval of holders of ownership interests in Vogtle Units No. 3 and No. 4 is at least (i) 90% for a change of the primary construction contractor and (ii) 67% for material amendments to the Services Agreement or agreements with Southern Nuclear or the primary construction contractor, including the Bechtel Agreement.

The effectiveness of the amendments to the Joint Ownership Agreements related to the Plant Alvin W. Vogtle Additional Units Ownership Participation Agreement, dated as of April 21, 2006, as amended, is subject to the condition that we obtain the approval of the Rural Utilities Service as required under our loan contract with the Rural Utilities Service.

In the event the Vogtle project is cancelled, our proportionate share of the Co-owners' cancellation costs are estimated to be approximately $230 million. If the project is cancelled, we would seek regulatory accounting treatment to amortize our investment in the Vogtle project over a long-term period which would require the approval of our board of directors, and we would submit the regulatory accounting treatment request to the Rural Utilities Service for its approval.

There have been technical and procedural challenges to the construction and licensing of Vogtle Units No. 3 and No. 4 at the federal and state level and additional challenges may arise as construction proceeds. Processes are in place that are designed to assure compliance with the requirements specified in the Westinghouse Design Control Document and the combined construction and operating licenses, including inspections by Southern Nuclear and the Nuclear Regulatory Commission that occur throughout construction. As a result of such compliance processes, certain license amendment requests have been filed and approved or are pending before the Nuclear Regulatory Commission. Various design and other licensing-based compliance matters, including the timely resolution of Inspections, Tests, Analyses, and Acceptance Criteria and the related approvals by the Nuclear Regulatory Commission, may arise if construction proceeds, which may result in additional license amendments or require other resolution. If any license amendment requests or other licensing-based compliance issues are not resolved in a timely manner, there may be further delays in the project schedule that could result in increased costs.

As construction continues, the risk remains that challenges with management of contractors, subcontractors and vendors, labor productivity, fabrication, delivery, assembly, and installation of plant systems, structures, and components, or other issues could arise and may further impact project schedule and cost.

The ultimate outcome of these matters cannot be determined at this time.