Vogtle Units No. 3 and No. 4 Construction Project (Details)
$ in Millions
1 Months Ended 6 Months Ended 12 Months Ended
Jul. 31, 2017
USD ($)
Jun. 09, 2017
USD ($)
Mar. 29, 2017
USD ($)
Jan. 31, 2016
USD ($)
Jun. 30, 2017
USD ($)
item
Dec. 31, 2008
USD ($)
item
MW
Mar. 28, 2017
USD ($)
Vogtle Units Number 3 And Number 4              
Vogtle Units No. 3 and No. 4 Construction Project              
Current investment         $ 3,700.0    
Anticipated additional cost per month         70.0    
Vogtle Units Number 3 And Number 4 | Removal of Subcontractor liens              
Vogtle Units No. 3 and No. 4 Construction Project              
Aggregate liability paid or accrued         $ 354.0    
Vogtle Units Number 3 And Number 4 | Removal of Subcontractor liens | Forecast              
Vogtle Units No. 3 and No. 4 Construction Project              
Liquidated damages $ 120.0            
Vogtle Units Number 3 And Number 4 | Removal of Subcontractor liens | The Contractor and WECTEC Staffing Services LLC | Forecast              
Vogtle Units No. 3 and No. 4 Construction Project              
Liquidated damages $ 400.0            
Vogtle Units Number 3 And Number 4 | Ownership participation agreement              
Vogtle Units No. 3 and No. 4 Construction Project              
Number of additional nuclear units | item         2    
Ownership interest (as a percent)         30.00%    
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Minimum              
Vogtle Units No. 3 and No. 4 Construction Project              
Estimated aggregate cancellation costs of site         $ 210.0    
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Maximum              
Vogtle Units No. 3 and No. 4 Construction Project              
Estimated aggregate cancellation costs of site         240.0    
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor)              
Vogtle Units No. 3 and No. 4 Construction Project              
Number of nuclear units | item           2  
Generating capacity of each nuclear unit | MW           1,100  
Project budget             $ 5,000.0
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor) | In the event of abandonment of work              
Vogtle Units No. 3 and No. 4 Construction Project              
Liquidated damages, as a percent of contract price           40.00%  
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor) | Minimum              
Vogtle Units No. 3 and No. 4 Construction Project              
Project budget         6,500.0    
Estimated aggregate cancellation costs of site         700.0    
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor) | Maximum              
Vogtle Units No. 3 and No. 4 Construction Project              
Liquidated damages, as a percent of contract price           10.00%  
Liquidated damages           $ 920.0  
Project budget         7,300.0    
Estimated aggregate cancellation costs of site         800.0    
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC              
Vogtle Units No. 3 and No. 4 Construction Project              
Written notice period for non-renewal of letter of credit       60 days      
Vogtle Units Number 3 And Number 4 | Interim Assessment Agreement              
Vogtle Units No. 3 and No. 4 Construction Project              
Liquidated damages         195.0    
Vogtle Units Number 3 And Number 4 | Interim Assessment Agreement | The Contractor and WECTEC Staffing Services LLC              
Vogtle Units No. 3 and No. 4 Construction Project              
Liquidated damages         650.0    
Amount paid for services, per week     $ 5.4        
Aggregate liability paid or accrued         $ 552.0    
Vogtle Units Number 3 And Number 4 | Guarantee Settlement Agreement              
Vogtle Units No. 3 and No. 4 Construction Project              
Guarantee obligations, maximum exposure   $ 1,100.0          
Vogtle Units Number 3 And Number 4 | Guarantee Settlement Agreement | The Co-owners and Toshiba              
Vogtle Units No. 3 and No. 4 Construction Project              
Guarantee obligations, maximum exposure   $ 3,680.0          
Recovery of guarantee obligations assumed (as a percent)         100.00%    
Vogtle Units Number 3 And Number 4 | Amended and Restated Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor)              
Vogtle Units No. 3 and No. 4 Construction Project              
Written notice period for termination of agreement   30 days          
Toshiba Corporation              
Vogtle Units No. 3 and No. 4 Construction Project              
Shareholder's equity negative balance         $ 4,500.0    
Toshiba Corporation | Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC              
Vogtle Units No. 3 and No. 4 Construction Project              
Letters of credit       $ 920.0