Vogtle Units No. 3 and No. 4 Construction Project (Details)
1 Months Ended 3 Months Ended 12 Months Ended
Mar. 29, 2017
USD ($)
Jan. 31, 2016
USD ($)
Mar. 31, 2017
USD ($)
item
Dec. 31, 2008
USD ($)
item
MW
Apr. 11, 2017
USD ($)
Vogtle Units Number 3 And Number 4          
Vogtle Units No. 3 and No. 4 Construction Project          
Current investment     $ 3,432,000,000    
Anticipated additional costs per month on failure to meet revised forecasted in-service dates     $ 20,000,000    
Vogtle Units Number 3 And Number 4 | Ownership participation agreement          
Vogtle Units No. 3 and No. 4 Construction Project          
Number of nuclear units | item     2    
Ownership interest (as a percent)     30.00%    
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor)          
Vogtle Units No. 3 and No. 4 Construction Project          
Number of nuclear units | item       2  
Generating capacity of each nuclear unit | MW       1,100  
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor) | In the event of abandonment of work          
Vogtle Units No. 3 and No. 4 Construction Project          
Liquidated damages, as a percent of contract price       40.00%  
Liquidated damages       $ 1,100,000,000  
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor) | Maximum          
Vogtle Units No. 3 and No. 4 Construction Project          
Liquidated damages, as a percent of contract price       10.00%  
Liquidated damages       $ 920,000,000  
Additional capital cost under the provision       $ 75,000,000  
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC          
Vogtle Units No. 3 and No. 4 Construction Project          
Written notice period for non-renewal of letter of credit   60 days      
Vogtle Units Number 3 And Number 4 | Interim Assessment Agreement          
Vogtle Units No. 3 and No. 4 Construction Project          
Liquidated damages $ 141,000,000        
Aggregate liability paid or accrued     $ 245,000,000    
Vogtle Units Number 3 And Number 4 | Interim Assessment Agreement | The Contractor and WECTEC Staffing Services LLC          
Vogtle Units No. 3 and No. 4 Construction Project          
Liquidated damages $ 470,000,000        
Notice period for termination of agreement, number of business days 5 days        
Amount paid for services, per week $ 5,400,000        
Toshiba Corporation          
Vogtle Units No. 3 and No. 4 Construction Project          
Shareholder's equity negative balance         $ 1,900,000,000
Toshiba Corporation | Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC          
Vogtle Units No. 3 and No. 4 Construction Project          
Letters of credit   $ 920,000,000