(G)  Contingencies and Regulatory Matters.

 

We do not anticipate that the liabilities, if any, for any current proceedings against us will have a material effect on our financial condition or results of operations. However, at this time, the ultimate outcome of any pending or potential litigation cannot be determined.

a.    Vogtle Units No. 3 and No. 4 Construction Litigation

In 2008, Georgia Power, acting for itself and as agent for us, the Municipal Electric Authority of Georgia and the City of Dalton, Georgia, acting by and through its Board of Water, Light and Sinking Fund Commissioners, doing business as Dalton Utilities (collectively, the Co-owners) and Westinghouse Electric Company LLC and Stone & Webster, Inc. (collectively, the Contractor) entered into an Engineering, Procurement and Construction Agreement (the EPC Agreement). Pursuant to the EPC Agreement, the Contractor will design, engineer, procure, construct and test two 1,100 megawatt nuclear units using the Westinghouse AP1000 technology and related facilities at Plant Vogtle, Units No. 3 and No. 4. Our ownership interest and proportionate share of the cost to construct these units is 30%, representing 660 megawatts of total capacity.

On December 31, 2015, Westinghouse and the Co-owners entered into a settlement agreement to resolve certain disputes between the Co-owners and the Contractor under the EPC Agreement which were dismissed with prejudice on January 5, 2016. Future claims by the Contractor or Georgia Power, on behalf of the Co-owners, could arise throughout construction. These claims may be resolved through formal and informal dispute resolution procedures under the EPC Agreement and, under the resolution procedures, may be resolved through litigation after the completion of nuclear fuel load for both units.

For additional information about the Vogtle construction project, see "Item 8—FINANCIAL STATEMENTS AND SUPPLEMENTARY DATA—Notes to Consolidated Financial Statements" in our 2015 Form 10-K and "Management's Discussion and Analysis of Financial Condition and Results of Operations—Financial Condition—Capital Requirements and Liquidity and Sources of Capital—Vogtle Units No. 3 and No. 4."

b.    Patronage Capital Litigation

There have been no material changes to this litigation from the disclosure included under Note G of Notes to Unaudited Consolidated Financial Statements in our Form 10-Q for the quarterly period ended June 30, 2016. For additional information regarding this litigation, see Note G of Notes to Unaudited Consolidated Financial Statements in our Form 10-Q for the quarterly period ended March 31, 2016.

c.    Environmental Matters

As is typical for electric utilities, we are subject to various federal, state and local environmental laws which represent significant future risks and uncertainties. Air emissions, water discharges and water usage are extensively controlled, closely monitored and periodically reported. Handling and disposal requirements govern the manner of transportation, storage and disposal of various types of waste. We are also subject to climate change regulations that impose restrictions on emissions of greenhouse gases, including carbon dioxide, for certain new and modified facilities.

In general, these and other types of environmental requirements are becoming increasingly stringent. Such requirements may substantially increase the cost of electric service, by requiring modifications in the design or operation of existing facilities or the purchase of emission allowances. Failure to comply with these requirements could result in civil and criminal penalties and could include the complete shutdown of individual generating units not in compliance. Certain of our debt instruments require us to comply in all material respects with laws, rules, regulations and orders imposed by applicable governmental authorities, which include current and future environmental laws or regulations. Should we fail to be in compliance with these requirements, it would constitute a default under those debt instruments. We believe that we are in compliance with those environmental regulations currently applicable to our business and operations. Although it is our intent to comply with current and future regulations, we cannot provide assurance that we will always be in compliance.

At this time, the ultimate impact of any new and more stringent environmental regulations described above is uncertain and could have an effect on our financial condition, results of operations and cash flows as a result of future additional capital expenditures and increased operations and maintenance costs.

Additionally, litigation over environmental issues and claims of various types, including property damage, personal injury, common law nuisance, and citizen enforcement of environmental requirements such as air quality and water standards, has increased generally throughout the United States. In particular, personal injury and other claims for damages caused by alleged exposure to hazardous materials, and common law nuisance claims for injunctive relief, personal injury and property damage allegedly caused by coal combustion residue, greenhouse gas and other emissions have become more frequent.