XML 26 R16.htm IDEA: XBRL DOCUMENT v3.23.2
Restructuring Charges
6 Months Ended
Jun. 30, 2023
Restructuring and Related Activities [Abstract]  
Restructuring Charges Restructuring Charges
In May 2023, we approved a worldwide plan (the 2023 Plan) designed to improve profitability and cash flow by reducing complexity, streamlining processes, and driving further operational efficiencies. This will be achieved in part, through the expansion of the Company's shared services activities, further centralization and standardization of processes, increased automation and the closure and consolidation of select facilities in North America.
We expect to eliminate 400-500 positions worldwide. Total charges are expected to be $40 million-$50 million, consisting of employee severance and facility consolidation costs. We expect to substantially complete these actions by the first half of 2024.
Activity in our restructuring reserves was as follows:
2023 PlanPrior PlanTotal
Balance at January 1, 2023$— $7,647 $7,647 
Amounts charged to expense22,443 3,599 26,042 
Cash payments(1,637)(11,246)(12,883)
Noncash activity(1,478) (1,478)
Balance at June 30, 2023$19,328 $ $19,328 
Balance at January 1, 2022$— $5,747 $5,747 
Amounts charged to expense— 8,408 8,408 
Cash payments— (8,255)(8,255)
Noncash activity— (275)(275)
Balance at June 30, 2022$— $5,625 $5,625 

Components of restructuring expense were as follows:
Three Months Ended June 30, 2023Three Months Ended June 30, 2022
2023 PlanPrior PlanTotalPrior Plan
Severance$20,965 $ $20,965 $3,170 
Facilities and other1,478  1,478 1,054 
Total$22,443 $ $22,443 $4,224 
Six Months Ended June 30, 2023Six Months Ended June 30, 2022
2023 PlanPrior PlanTotalPrior Plan
Severance$20,965 $3,057 $24,022 $6,377 
Facilities and other1,478 542 2,020 2,031 
Total$22,443 $3,599 $26,042 $8,408