XML 116 R20.htm IDEA: XBRL DOCUMENT v3.19.3
Contractual Obligations, Commercial Commitments and Contingencies
9 Months Ended 12 Months Ended
Sep. 30, 2019
Dec. 31, 2018
Contractual Obligations, Commercial Commitments and Contingencies Contractual Obligations, Commercial Commitments and Contingencies

Guarantees
In the normal course of business, DPL enters into various agreements with its wholly-owned subsidiary, AES Ohio Generation, providing financial or performance assurance to third parties. These agreements are entered into primarily to support or enhance the creditworthiness otherwise attributed to this subsidiary on a stand-alone basis, thereby facilitating the extension of sufficient credit to accomplish this subsidiary's intended commercial purposes.

At September 30, 2019, DPL had $21.0 million of guarantees on behalf of AES Ohio Generation to third parties for future financial or performance assurance under such agreements. The guarantee arrangements entered into by DPL with these third parties cover select present and future obligations of AES Ohio Generation to such beneficiaries and are terminable by DPL upon written notice to the beneficiaries within a certain time. At
September 30, 2019 and December 31, 2018, we had no outstanding balance of obligations covered by these guarantees.

To date, DPL has not incurred any losses related to the guarantees of AES Ohio Generation’s obligations and we believe it is unlikely that DPL would be required to perform or incur any losses in the future associated with any of the above guarantees.

Equity Ownership Interest
DP&L has a 4.9% equity ownership interest in OVEC, which is recorded using the cost method of accounting under GAAP. DP&L, along with several non-affiliated energy companies party to an OVEC arrangement, receive and pay for OVEC capacity and energy and are responsible for OVEC debt obligations and other fixed costs in proportion to their power participation ratios under the arrangement which, for DP&L, is the same as its equity ownership interest. At September 30, 2019, DP&L could be responsible for the repayment of 4.9%, or $67.2 million, of $1,371.3 million OVEC debt obligations if they came due, comprised of both fixed and variable rate securities with maturities from 2022 to 2040. OVEC could also seek additional contributions from DP&L to avoid a default in the event that other OVEC members defaulted on their respective OVEC obligations. One of the other OVEC members, with a 4.85% interest in OVEC, filed for bankruptcy protection and the bankruptcy court approved that member's rejection of the OVEC arrangement and its related obligations on July 31, 2018. We do not expect these events to have a material impact on our financial condition, results of operations or cash flows.

Contingencies
In the normal course of business, we are subject to various lawsuits, actions, proceedings, claims and other matters asserted under various laws and regulations. We believe the amounts provided in our Condensed Consolidated Financial Statements, as prescribed by GAAP, are adequate considering the probable and estimable contingencies. However, there can be no assurances that the actual amounts required to satisfy alleged liabilities from various legal proceedings, claims, tax examinations and other matters discussed below, and to comply with applicable laws and regulations, will not exceed the amounts reflected in our Condensed Consolidated Financial Statements. As such, costs, if any, that may be incurred in excess of those amounts provided as of September 30, 2019, cannot be reasonably determined.

Environmental Matters
DPL’s and DP&L’s facilities and operations are subject to a wide range of federal, state and local environmental regulations and laws. The environmental issues that may affect us include:

The federal CAA and state laws and regulations (including State Implementation Plans) which require compliance, obtaining permits and reporting as to air emissions;
Litigation with federal and certain state governments and certain special interest groups;
Rules and future rules issued by the USEPA, the Ohio EPA or other authorities associated with the federal Clean Water Act, which prohibits the discharge of pollutants into waters of the United States except pursuant to appropriate permits; and
Solid and hazardous waste laws and regulations, which govern the management and disposal of certain waste. The majority of solid waste created from the combustion of coal and fossil fuels consists of fly ash and other coal combustion by-products.

In addition to imposing continuing compliance obligations, these laws and regulations authorize the imposition of substantial penalties for noncompliance, including fines, injunctive relief and other sanctions. In the normal course of business, we have investigatory and remedial activities underway at our facilities to comply, or to determine compliance, with such regulations. We record liabilities for loss contingencies related to environmental matters when a loss is probable of occurring and can be reasonably estimated in accordance with the provisions of GAAP. Accordingly, we have immaterial accruals for loss contingencies for environmental matters. We also have several environmental matters for which we have not accrued loss contingencies because the risk of loss is not probable, or a loss cannot be reasonably estimated. We evaluate the potential liability related to environmental matters quarterly and may revise our estimates. Such revisions in the estimates of the potential liabilities could have a material adverse effect on our results of operations, financial condition and cash flows.

We have several pending environmental matters associated with our current and previously owned coal-fired generation units. Some of these matters could have a material adverse effect on our results of operations, financial condition and cash flows.

Guarantees
In the normal course of business, DPL enters into various agreements with its wholly-owned subsidiary, AES Ohio Generation, providing financial or performance assurance to third parties. These agreements are entered into primarily to support or enhance the creditworthiness otherwise attributed to this subsidiary on a stand-alone basis, thereby facilitating the extension of sufficient credit to accomplish this subsidiary's intended commercial purposes.

At December 31, 2018, DPL had $23.6 million of guarantees on behalf of AES Ohio Generation to third parties for future financial or performance assurance under such agreements. The guarantee arrangements entered into by DPL with these third parties cover present and future obligations of AES Ohio Generation to such beneficiaries and are terminable at any time by DPL upon written notice to the beneficiaries. We had no outstanding balance of obligations for commercial transactions covered by these guarantees at December 31, 2018. The carrying amount of obligations for commercial transactions covered by these guarantees and recorded in our Consolidated Balance Sheets was $0.9 million at December 31, 2017.

To date, DPL has not incurred any losses related to these guarantees and we believe it is remote that DPL would be required to perform or incur any losses in the future associated with any of the above guarantees.

Equity Ownership Interest
DP&L has a 4.9% equity ownership interest in OVEC which is recorded using the cost method of accounting under GAAP. At December 31, 2018, DP&L could be responsible for the repayment of 4.9%, or $68.1 million, of a $1,389.6 million debt obligation comprised of both fixed and variable rate securities with maturities between 2019 and 2040. OVEC could also seek additional contributions from us to avoid a default in the event that other OVEC members defaulted on their respective OVEC obligations. One of the other OVEC members, with a 4.85% interest in OVEC, filed for bankruptcy protection and the bankruptcy court approved that member's rejection of the OVEC arrangement and its related obligations on July 31, 2018. We do not expect these events to have a material impact on our financial condition, results of operations or cash flows.

Contractual Obligations and Commercial Commitments
We enter into various contractual obligations and other commercial commitments that may affect the liquidity of our operations. At December 31, 2018, these include:
 
 
Payments due in:
$ in millions
 
Total
 
Less than
1 year
 
2 - 3
years
 
4 - 5
years
 
More than
5 years
Electricity purchase commitments
 
$
209.4

 
$
139.5

 
$
69.9

 
$

 
$

Purchase orders and other contractual obligations
 
$
40.2

 
$
11.4

 
$
14.8

 
$
14.0

 
$



Electricity purchase commitments:
DPL enters into long-term contracts for the purchase of electricity. In general, these contracts are subject to variable quantities or prices and are terminable only in limited circumstances.

Purchase orders and other contractual obligations:
At December 31, 2018, DPL had various other contractual obligations including non-cancelable contracts to purchase goods and services with various terms and expiration dates. Due to uncertainty regarding the timing and payment of future obligations to the Service Company, and DPL's ability to terminate such obligations upon 90 days' notice, we have excluded such amounts in the contractual obligations table above

Contingencies
In the normal course of business, we are subject to various lawsuits, actions, proceedings, claims and other matters asserted under laws and regulations. We believe the amounts provided in our Consolidated Financial Statements, as prescribed by GAAP, are adequate in light of the probable and estimable contingencies. However, there can be no assurances that the actual amounts required to satisfy alleged liabilities from various legal proceedings, claims, tax examinations, and other matters, including the matters discussed below, and to comply with applicable laws and regulations, will not exceed the amounts reflected in our Consolidated Financial Statements. As such, costs, if any, that may be incurred in excess of those amounts provided as of December 31, 2018, cannot be reasonably determined.

Environmental Matters
DPL’s facilities and operations are subject to a wide range of federal, state and local environmental laws, rules and regulations. The environmental issues that may affect us include the following. However, as described further below, as a result of DPL’s retirement of its Stuart and Killen generating stations, the sale of its ownership interest in the Miami Fort and Zimmer generating stations, the planned 2020 retirement of Conesville and our exiting of our generation business, certain of these environmental regulations and laws are now not expected to have a material impact on DPL with respect to these generating stations.
The federal CAA and state laws and regulations (including SIPs) which require compliance, obtaining permits and reporting as to air emissions;
Litigation with federal and certain state governments and certain special interest groups regarding whether modifications to or maintenance of certain coal-fired generating stations require additional permitting or pollution control technology, or whether emissions from coal-fired generating stations cause or contribute to global climate changes;
Rules and future rules issued by the USEPA, the Ohio EPA or other authorities that require or will require substantial reductions in SO2, particulates, mercury, acid gases, NOx, and other air emissions.
Rules and future rules issued by the USEPA, the Ohio EPA or other authorities that require or will require reporting and reductions of GHGs;
Rules and future rules issued by the USEPA, the Ohio EPA or other authorities associated with the federal Clean Water Act, which prohibits the discharge of pollutants into waters of the United States except pursuant to appropriate permits; and
Solid and hazardous waste laws and regulations, which govern the management and disposal of certain waste. The majority of solid waste created from the combustion of coal and fossil fuels is fly ash and other coal combustion by-products.

In addition to imposing continuing compliance obligations, these laws, rules and regulations authorize the imposition of substantial penalties for noncompliance, including fines, injunctive relief and other sanctions. In the normal course of business, we have investigatory and remedial activities underway at our facilities to comply, or to determine compliance, with such laws, rules and regulations. We record liabilities for loss contingencies related to environmental matters when a loss is probable of occurring and can be reasonably estimated in accordance with the provisions of GAAP. Accordingly, we have immaterial accruals for loss contingencies for environmental matters. We also have a number of environmental matters for which we have not accrued loss contingencies because the risk of loss is not probable, or a loss cannot be reasonably estimated. We evaluate the potential liability related to environmental matters quarterly and may revise our estimates. Such revisions in the estimates of the potential liabilities could have a material adverse effect on our results of operations, financial condition or cash flows.

We have several pending environmental matters associated with our current and previously owned and operated coal-fired generation units. Some of these matters could have material adverse impacts on our results of operations, financial condition or cash flows.