Regulatory Matters (Notes)
9 Months Ended
Sep. 30, 2018
Schedule of Regulatory Assets and Liabilities [Text Block]
Regulatory Matters

On September 26, 2018 the PUCO issued the DRO establishing new base distribution rates for DP&L, which became effective October 1, 2018. The DRO approved, without modification, a stipulation and recommendation previously filed by DP&L, along with various intervening parties and the PUCO staff. The DRO established a revenue requirement of $248.0 million for DP&L's electric service base distribution rates which reflects an increase to distribution revenues of approximately $29.8 million per year. In addition to the increase in base distribution rates, and among other matters, the DRO provides for a return on equity of 9.999% and a cost of long-term debt of 4.8% and for the following items:

DIR – The DRO authorized DP&L to begin charging a Distribution Investment Rider ("DIR") set initially at $12.2 million annually, effective October 1, 2018. The DIR revenue requirement shall be updated quarterly and will increase as DP&L makes qualified investments in its distribution network, subject to annual revenue limits which increase each year. The DIR will expire in November 2022 unless DP&L files a base distribution rate case on or before October 31, 2022, in which case the DIR will expire in November 2023. Approximately $0.4 million of DIR revenue is included in DP&L’s unbilled revenues at September 30, 2018.

Decoupling Rider – The DRO eliminated provisions in the existing decoupling rider which allowed DP&L to recover lost revenues resulting from the implementation of energy efficiency programs and replaced it with a revenue requirement that attempts to eliminate the impacts of weather and demand on DP&L’s revenues from residential and commercial distribution customers. As a result, in years with very mild weather and/or decreased demand, DP&L will be able to accrue a regulatory asset for recovery through the rider to normalize the revenues. Conversely, in periods of extreme temperatures or high demand for electricity, DP&L may record a liability for future reimbursement to customers. The rider also includes a one-time $3.7 million revenue requirement based on the increase in the number of DP&L’s residential and commercial customers from the rate case test year until September 30, 2018. Such amount was accrued and included in revenues in the third quarter of 2018 and will be collected by DP&L in 2019.

TCJA – The DRO only partially resolved the TCJA impacts. The new distribution rates include the impacts of the decrease in current federal income taxes beginning October 1, 2018. The DRO did not designate how much DP&L may owe for any overcollection of taxes from January 1, 2018 through September 30, 2018, nor did it resolve any decrease in future rates related to amortization of excess accumulated deferred income taxes (“ADIT”). The DRO did, however, stipulate that DP&L must refund its customers an amount no less than $4.0 million per year for the first five years of the amortization period unless all balances owed are fully returned within the first five years. For more on the impacts of the TCJA, please see below.

Vegetation Management Costs – The DRO authorizes DP&L to defer as a regulatory asset, with no carrying costs, annual expenses for vegetation management performed by third-party vendors. For calendar year 2018 annual expenses which are incremental to the baseline of $10.7 million can be deferred up to a $4.6 million cap. For calendar years 2019 and thereafter, annual expenses in excess of $15.7 million can be deferred up to a $4.6 million annual cap. Annual spending of less than the vegetation management baseline amounts will result in a reduction to the regulatory asset or creation of a regulatory liability. In the third quarter of 2018, DP&L accrued a regulatory asset of $3.8 million based upon such provisions and spending above the baseline pro-rated to nine months.

Impact of tax reform
On January 10, 2018, the PUCO initiated a proceeding to consider the impacts of the TCJA to determine the appropriate course of action to pass benefits resulting from the legislation on to ratepayers. The PUCO also directed Ohio utilities to record deferred liabilities for the estimated reduction in federal income tax resulting from the TCJA beginning January 1, 2018. Under the terms of the stipulation in the distribution rate case mentioned above, DP&L agreed to file an application at the PUCO to refund eligible excess ADIT and any related regulatory liability over a 10-year period. Excess ADIT related to depreciation life and method differences will be returned to customers in accordance with federal tax law and related regulations.

FERC proceedings
On March 15, 2018, the FERC initiated “show cause” proceedings against numerous utilities, including DP&L, that had stated transmission rates, directing each utility to file either revised transmission rates to reflect the effects of the TCJA or to show cause why no changes in transmission rates were appropriate. On May 8, 2018, DP&L filed to adjust its FERC jurisdictional transmission rates to reflect this impact. The filing is currently under review by the FERC and DP&L is unable to predict whether the proposed rates will be accepted as filed or if they may be further modified. As proposed, the decrease is approximately $2.4 million annually. DP&L has recorded a reduction to revenues and established regulatory liabilities for the estimated impact.

PJM transmission enhancement settlement
On May 31, 2018, the FERC issued an Order on Contested Settlement regarding the cost allocation method for existing and new transmission facilities contained in the PJM Interconnection’s Open Access Transmission Tariff. The FERC order approved the settlement which reduces DP&L’s transmission costs through PJM beginning in August 2018, including credits to reimburse DP&L for amounts overcharged in prior years. DP&L has estimated the prior overcharge to be $40.4 million, of which approximately $4.8 million has been repaid to DP&L through September 30, 2018 and $24.1 million is classified as current on the accompanying Condensed Consolidated Balance Sheet. All of the transmission charges and credits impacted by this FERC order are items that are included for 100% recovery in DP&L’s nonbypassable TCRR. Accordingly, DP&L has also established offsetting regulatory liabilities. While this development will have a temporary cash flow benefit to DP&L, there is no impact to operating income or net income as all credits will be passed to DP&L’s customers through the TCRR.
Subsidiaries [Member]  
Schedule of Regulatory Assets and Liabilities [Text Block]
Regulatory Matters

On September 26, 2018 the PUCO issued the DRO establishing new base distribution rates for DP&L, which became effective October 1, 2018. The DRO approved, without modification, a stipulation and recommendation previously filed by DP&L, along with various intervening parties and the PUCO staff. The DRO established a revenue requirement of $248.0 million for DP&L's electric service base distribution rates which reflects an increase to distribution revenues of approximately $29.8 million per year. In addition to the increase in base distribution rates, and among other matters, the DRO provides for a return on equity of 9.999% and a cost of long-term debt of 4.8% and for the following items:

DIR – The DRO authorized DP&L to begin charging a Distribution Investment Rider ("DIR") set initially at $12.2 million annually, effective October 1, 2018. The DIR revenue requirement shall be updated quarterly and will increase as DP&L makes qualified investments in its distribution network, subject to annual revenue limits which increase each year. The DIR will expire in November 2022 unless DP&L files a base distribution rate case on or before October 31, 2022, in which case the DIR will expire in November 2023. Approximately $0.4 million of DIR revenue is included in DP&L’s unbilled revenues at September 30, 2018.

Decoupling Rider – The DRO eliminated provisions in the existing decoupling rider which allowed DP&L to recover lost revenues resulting from the implementation of energy efficiency programs and replaced it with a revenue requirement that attempts to eliminate the impacts of weather and demand on DP&L’s revenues from residential and commercial distribution customers. As a result, in years with very mild weather and/or decreased demand, DP&L will be able to accrue a regulatory asset for recovery through the rider to normalize the revenues. Conversely, in periods of extreme temperatures or high demand for electricity, DP&L may record a liability for future reimbursement to customers. The rider also includes a one-time $3.7 million revenue requirement based on the increase in the number of DP&L’s residential and commercial customers from the rate case test year until September 30, 2018. Such amount was accrued and included in revenues in the third quarter of 2018 and will be collected by DP&L in 2019.

TCJA – The DRO only partially resolved the TCJA impacts. The new distribution rates include the impacts of the decrease in current federal income taxes beginning October 1, 2018. The DRO did not designate how much DP&L may owe for any overcollection of taxes from January 1, 2018 through September 30, 2018, nor did it resolve any decrease in future rates related to amortization of excess accumulated deferred income taxes (“ADIT”). The DRO did, however, stipulate that DP&L must refund its customers an amount no less than $4.0 million per year for the first five years of the amortization period unless all balances owed are fully returned within the first five years. For more on the impacts of the TCJA, please see below.

Vegetation Management Costs – The DRO authorizes DP&L to defer as a regulatory asset, with no carrying costs, annual expenses for vegetation management performed by third-party vendors. For calendar year 2018 annual expenses which are incremental to the baseline of $10.7 million can be deferred up to a $4.6 million cap. For calendar years 2019 and thereafter, annual expenses in excess of $15.7 million can be deferred up to a $4.6 million annual cap. Annual spending of less than the vegetation management baseline amounts will result in a reduction to the regulatory asset or creation of a regulatory liability. In the third quarter of 2018, DP&L accrued a regulatory asset of $3.8 million based upon such provisions and spending above the baseline pro-rated to nine months.

Impact of tax reform
On January 10, 2018, the PUCO initiated a proceeding to consider the impacts of the TCJA to determine the appropriate course of action to pass benefits resulting from the legislation on to ratepayers. The PUCO also directed Ohio utilities to record deferred liabilities for the estimated reduction in federal income tax resulting from the TCJA beginning January 1, 2018. Under the terms of the stipulation in the distribution rate case mentioned above, DP&L agreed to file an application at the PUCO to refund eligible excess ADIT and any related regulatory liability over a 10-year period. Excess ADIT related to depreciation life and method differences will be returned to customers in accordance with federal tax law and related regulations.

FERC proceedings
On March 15, 2018, the FERC initiated “show cause” proceedings against numerous utilities, including DP&L, that had stated transmission rates, directing each utility to file either revised transmission rates to reflect the effects of the TCJA or to show cause why no changes in transmission rates were appropriate. On May 8, 2018, DP&L filed to adjust its FERC jurisdictional transmission rates to reflect this impact. The filing is currently under review by the FERC and DP&L is unable to predict whether the proposed rates will be accepted as filed or if they may be further modified. As proposed, the decrease is approximately $2.4 million annually. DP&L has recorded a reduction to revenues and established regulatory liabilities for the estimated impact.

PJM transmission enhancement settlement
On May 31, 2018, the FERC issued an Order on Contested Settlement regarding the cost allocation method for existing and new transmission facilities contained in the PJM Interconnection’s Open Access Transmission Tariff. The FERC order approved the settlement which reduces DP&L’s transmission costs through PJM beginning in August 2018, including credits to reimburse DP&L for amounts overcharged in prior years. DP&L has estimated the prior overcharge to be $40.4 million, of which approximately $4.8 million has been repaid to DP&L through September 30, 2018 and $24.1 million is classified as current on the accompanying Condensed Balance Sheet. All of the transmission charges and credits impacted by this FERC order are items that are included for 100% recovery in DP&L’s nonbypassable TCRR. Accordingly, DP&L has also established offsetting regulatory liabilities. While this development will have a temporary cash flow benefit to DP&L, there is no impact to operating income or net income as all credits will be passed to DP&L’s customers through the TCRR.