XML 62 R50.htm IDEA: XBRL DOCUMENT v3.22.0.1
Commitments and Guarantees (Tables)
12 Months Ended
Dec. 31, 2021
Long-term Purchase Commitment [Line Items]  
Unrecorded Unconditional Purchase Obligations Disclosure [Table Text Block]
As of December 31, 2021, PGE’s estimated future minimum payments pursuant to purchase obligations for the following five years and thereafter are as follows (in millions):
 Payments Due
 20222023202420252026ThereafterTotal
Capital and other purchase commitments$146 $58 $$$$43 $257 
Purchased power and fuel:
Electricity purchases486 353 367 341 242 2,284 4,073 
Capacity contracts18 22 23 27 12 88 190 
Public utility districts13 12 12 11 10 31 89 
Natural gas81 44 39 38 36 202 440 
Coal and transportation27 27 27 27 — — 108 
Total$771 $516 $475 $446 $301 $2,648 $5,157 
Schedule of Long-term Contracts for Purchase of Electric Power [Table Text Block] PGE has long-term power purchase agreements with certain public utility districts (PUDs) in the state of Washington:
Grant County PUD for the Priest Rapids and Wanapum Hydroelectric Projects, and
Douglas County PUD for the Wells Hydroelectric Project.

Under the Grant County agreements, the Company is required to pay its proportionate share of the operating and debt service costs of the hydroelectric projects whether they are operable or not. Under the Douglas County agreement, the Company is required to make monthly payments for capacity that will not vary with annual project generation provided to PGE. The Company has estimated the capacity payments, which are subject to annual adjustments based on Douglas County’s loads, and included the estimated amounts in the table above. The future minimum payments for the PUDs in the preceding table reflect the principal and capacity payments only and do not include interest, operation, or maintenance expenses.
Selected information regarding these projects is summarized as follows (dollars in millions):
 
 Capacity Charges and Revenue Bonds as of December 31, 2021PGE’s Average Share as of December 31, 2021Contract
Expiration
Total PGE Contract Costs
OutputCapacity202120202019
   (in MW)    
Priest Rapids and Wanapum$1,976 8.6 %163 2052$26 $25 $21 
Wells496 17.6 105 202813 23 16