XML 45 R12.htm IDEA: XBRL DOCUMENT v3.3.0.814
Contingencies (Notes)
9 Months Ended
Sep. 30, 2015
Contingencies [Abstract]  
CONTINGENCIES
CONTINGENCIES

PGE is subject to legal, regulatory, and environmental proceedings, investigations, and claims that arise from time to time in the ordinary course of its business. Contingencies are evaluated using the best information available at the time the consolidated financial statements are prepared. Legal costs incurred in connection with loss contingencies are expensed as incurred. The Company may seek regulatory recovery of certain costs that are incurred in connection with such matters, although there can be no assurance that such recovery would be granted.

Loss contingencies are accrued, and disclosed if material, when it is probable that an asset has been impaired or a liability incurred as of the financial statement date and the amount of the loss can be reasonably estimated. If a reasonable estimate of probable loss cannot be determined, a range of loss may be established, in which case the minimum amount in the range is accrued, unless some other amount within the range appears to be a better estimate.

A loss contingency will also be disclosed when it is reasonably possible that an asset has been impaired or a liability incurred if the estimate or range of potential loss is material. If a probable or reasonably possible loss cannot be reasonably estimated, then the Company: i) discloses an estimate of such loss or the range of such loss, if the Company is able to determine such an estimate; or ii) discloses that an estimate cannot be made and the reasons.

If an asset has been impaired or a liability incurred after the financial statement date, but prior to the issuance of the financial statements, the loss contingency is disclosed, if material, and the amount of any estimated loss is recorded in the subsequent reporting period.

The Company evaluates, on a quarterly basis, developments in such matters that could affect the amount of any accrual, as well as the likelihood of developments that would make a loss contingency both probable and reasonably estimable. The assessment as to whether a loss is probable or reasonably possible, and as to whether such loss or a range of such loss is estimable, often involves a series of complex judgments about future events. Management is often unable to estimate a reasonably possible loss, or a range of loss, particularly in cases in which: i) the damages sought are indeterminate or the basis for the damages claimed is not clear; ii) the proceedings are in the early stages; iii) discovery is not complete; iv) the matters involve novel or unsettled legal theories; v) there are significant facts in dispute; vi) there are a large number of parties (including circumstances in which it is uncertain how liability, if any, will be shared among multiple defendants); or vii) there are a wide range of potential outcomes. In such cases, there is considerable uncertainty regarding the timing or ultimate resolution, including any possible loss, fine, penalty, or business impact.

Trojan Investment Recovery Class Actions

In 1993, PGE closed the Trojan nuclear power plant (Trojan) and sought full recovery of, and a rate of return on, its Trojan costs in a general rate case filing with the OPUC. In 1995, the OPUC issued a general rate order that granted the Company recovery of, and a rate of return on, 87% of its remaining investment in Trojan.

Numerous challenges and appeals were subsequently filed in various state courts on the issue of the OPUC’s authority under Oregon law to grant recovery of, and a return on, the Trojan investment. In 2007, following several appeals by various parties, the Oregon Court of Appeals issued an opinion that remanded the matter to the OPUC for reconsideration.

In 2008, the OPUC issued an order (2008 Order) that required PGE to provide refunds of $33 million, including interest, which were completed in 2010. Following appeals, the 2008 Order was upheld by the Oregon Court of Appeals in February 2013 and by the Oregon Supreme Court (OSC) in October 2014.

In 2003, in two separate legal proceedings, lawsuits were filed in Marion County Circuit Court (Circuit Court) against PGE on behalf of two classes of electric service customers. The class action lawsuits seek damages totaling $260 million, plus interest, as a result of the Company’s inclusion, in prices charged to customers, of a return on its investment in Trojan.

In August 2006, the OSC issued a ruling ordering the abatement of the class action proceedings. The OSC concluded that the OPUC had primary jurisdiction to determine what, if any, remedy could be offered to PGE customers, through price reductions or refunds, for any amount of return on the Trojan investment that the Company collected in prices.

The OSC further stated that if the OPUC determined that it can provide a remedy to PGE’s customers, then the class action proceedings may become moot in whole or in part. The OSC added that, if the OPUC determined that it cannot provide a remedy, the court system may have a role to play. The OSC also ruled that the plaintiffs retain the right to return to the Circuit Court for disposition of whatever issues remain unresolved from the remanded OPUC proceedings. In October 2006, the Circuit Court abated the class actions in response to the ruling of the OSC.

In June 2015, based on a motion filed by PGE, the Circuit Court lifted the abatement. On July 27, 2015, the Circuit Court heard oral argument on the Company’s motion for Summary Judgment. The court has yet to issue a decision on the motion.

PGE believes that the October 2, 2014 OSC decision has reduced the risk of a loss to the Company in excess of the amounts previously recorded and discussed above. However, because the class actions remain pending, management believes that it is reasonably possible that such a loss to the Company could result. As these matters involve unsettled legal theories and have a broad range of potential outcomes, sufficient information is currently not available to determine the amount of any such loss.

Pacific Northwest Refund Proceeding

In response to the Western energy crisis of 2000-2001, the FERC initiated, beginning in 2001, a series of proceedings to determine whether refunds are warranted for bilateral sales of electricity in the Pacific Northwest wholesale spot market during the period December 25, 2000 through June 20, 2001. In an order issued in 2003, the FERC denied refunds. Various parties appealed the order to the Ninth Circuit Court of Appeals (Ninth Circuit) and, on appeal, the Ninth Circuit remanded the issue of refunds to the FERC for further consideration.

On remand, in 2011 and thereafter, the FERC issued several procedural orders that established an evidentiary hearing, defined the scope of the hearing, expanded the refund period to include January 1, 2000 through December 24, 2000 for certain types of claims, and described the burden of proof that must be met to justify abrogation of the contracts at issue and the imposition of refunds. Those orders included a finding by the FERC that the Mobile-Sierra public interest standard governs challenges to the bilateral contracts at issue in this proceeding, and the strong presumption under Mobile-Sierra that the rates charged under each contract are just and reasonable would have to be specifically overcome either by: i) a showing that a respondent had violated a contract or tariff and that the violation had a direct connection to the rate charged under the applicable contract; or ii) a showing that the contract rate at issue imposed an excessive burden or seriously harmed the public interest. The FERC also held that a market-wide remedy was not appropriate, given the bilateral contract nature of the Pacific Northwest spot markets. Refund proponents have filed petitions for appeal of these procedural orders with the Ninth Circuit. Those appeals remain pending.

In response to the evidence and arguments presented during the hearing, in May 2015, the FERC issued an order upholding the decision of an Administrative Law Judge that the refund proponents had failed to meet the Mobile-Sierra burden with respect to all but one respondent. That order is subject to requests for rehearing.

The Company has settled all of the direct claims asserted against it in the proceedings for an immaterial amount. The settlements and associated FERC orders have not fully eliminated the potential for so-called “ripple claims,” which have been described by the FERC as “sequential claims against a succession of sellers in a chain of purchases that are triggered if the last wholesale purchaser in the chain is entitled to a refund.” However, the FERC has acknowledged that the potential for such ripple claims is “speculative” and the Company believes that ripple claims made against it, if any, are unlikely to be successful under the FERC orders currently in effect. Accordingly, unless those FERC orders are overturned or modified, the Company does not believe that it will incur any material loss in connection with this matter.

Management cannot predict the outcome of the various pending appeals and remands concerning this matter. If, on rehearing, appeal, or subsequent remand, the Ninth Circuit or the FERC were to reverse previous FERC rulings and find that the Mobile-Sierra standard is not applicable or that a market-wide remedy is appropriate, it is possible that additional refund claims could be asserted against the Company. However, management cannot predict, under such circumstances, which contracts would be subject to refunds, the basis on which refunds would be ordered, or how such refunds, if any, would be calculated. Further, management cannot predict whether any current respondents, if ordered to make refunds, would pursue additional refund claims against their suppliers, and, if so, what the basis or amounts of such potential refund claims against the Company would be. Due to these uncertainties, sufficient information is currently not available to determine PGE’s liability, if any, or to estimate a range of reasonably possible loss.

EPA Investigation of Portland Harbor

In 1997, an investigation by the EPA of a segment of the Willamette River known as Portland Harbor revealed significant contamination of river sediments. The EPA subsequently included Portland Harbor on the National Priority List pursuant to the federal Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) as a federal Superfund site and listed 69 Potentially Responsible Parties (PRPs). PGE was included among the PRPs as it has historically owned or operated property near the river. In 2008, the EPA requested information from various parties, including PGE, concerning additional properties in or near the original segment of the river under investigation as well as several miles beyond. Subsequently, the EPA has listed additional PRPs, which now number over one hundred.

The Portland Harbor site continues to undergo a remedial investigation (RI) and feasibility study (FS) pursuant to an Administrative Order on Consent (AOC) between the EPA and several PRPs known as the Lower Willamette Group (LWG), which does not include PGE.

In 2012, the LWG submitted a draft FS to the EPA for review and approval. The draft FS, rewritten by the EPA, is now completed and, along with the RI, will provide the framework for the EPA to determine a clean-up remedy for Portland Harbor that will be documented in a Record of Decision, which the EPA is not expected to issue before 2017.

The completed draft FS evaluates several alternative clean-up approaches, which would take from four to 18 years with the present value of estimated costs ranging from $800 million to $2.4 billion, depending on the selected remedial action levels and the choice of remedy. The draft FS does not address responsibility for the costs of clean-up, allocate such costs among PRPs, or define precise boundaries for the clean-up. Responsibility for funding and implementing the EPAs selected remedy will be determined after the issuance of the Record of Decision.

Management believes that it is reasonably possible that this matter could result in a loss to the Company. However, due to the uncertainties discussed above, sufficient information is currently not available to determine PGE’s liability for the cost of any required investigation or remediation of the Portland Harbor site or to estimate a range of potential loss.

DEQ Investigation of Downtown Reach

The Oregon Department of Environmental Quality (DEQ) has executed a memorandum of understanding with the EPA to administer and enforce clean-up activities for portions of the Willamette River that are upriver from the Portland Harbor Superfund site (the Downtown Reach). In 2010, the DEQ issued an order requiring PGE to perform an investigation of certain portions of the Downtown Reach. PGE completed this investigation and entered into a consent order with the DEQ in 2012 to conduct an FS of alternatives for remedial action for the portions of the Downtown Reach that were included within the scope of PGE’s investigation.

PGE submitted a final feasibility study report to the DEQ in September 2014, which described possible remediation alternatives that ranged in estimated cost from $3 million to $8 million. Based on the estimated cost of the alternative recommended by the Company in the FS report, PGE recorded a $3 million reserve for this matter in 2014 and established a regulatory asset of $3 million for future recovery in prices. In April 2015, the DEQ issued its Record of Decision in which it selected the remedy recommended in the FS report. Remediation activity began in the third quarter of 2015 and is expected to be completed during 2016 at a total cost of approximately $3 million.

The final order issued by the OPUC in the 2015 General Rate Case (GRC) included revenues to offset the amortization of the regulatory asset over a two year period that began January 1, 2015. As of September 30, 2015, the Company has a regulatory asset of $2 million remaining for future recovery of costs related to the Downtown Reach.

Alleged Violation of Environmental Regulations at Colstrip

In July 2012, PGE received a Notice of Intent to Sue (Notice) for violations of the Clean Air Act (CAA) at Colstrip Steam Electric Station (CSES) from counsel on behalf of the Sierra Club and the Montana Environmental Information Center (MEIC). The Notice was also addressed to the other CSES co-owners, including PPL Montana, LLC, the operator of CSES. PGE has a 20% ownership interest in Units 3 and 4 of CSES. The Notice alleged certain violations of the CAA, including New Source Review, Title V, and opacity requirements, and stated that the Sierra Club and MEIC would: i) request a United States District Court to impose injunctive relief and civil penalties; ii) require a beneficial environmental project in the areas affected by the alleged air pollution; and iii) seek reimbursement of Sierra Club’s and MEIC’s costs of litigation and attorney’s fees.

The Sierra Club and MEIC asserted that the CSES owners violated the Title V air quality operating permit during portions of 2008 and 2009 and that the owners have violated the CAA by failing to timely submit a complete air quality operating permit application to the Montana Department of Environmental Quality (MDEQ). The Sierra Club and MEIC also asserted violations of opacity provisions of the CAA.

On March 6, 2013, the Sierra Club and MEIC sued the CSES co-owners, including PGE, for these and additional alleged violations of various environmental related regulations. The plaintiffs are seeking relief that includes an injunction preventing the co-owners from operating CSES except in accordance with the CAA, the Montana State Implementation Plan, and the plant’s federally enforceable air quality permits. In addition, plaintiffs are seeking civil penalties against the co-owners including $32,500 per day for each violation occurring through January 12, 2009, and $37,500 per day for each violation occurring thereafter.

In May 2013, the defendants filed a motion to dismiss 36 of 39 claims alleged in the complaint. In September 2013, the plaintiffs filed a motion for partial summary judgment regarding the appropriate method of calculating emission increases. Also in September 2013, the plaintiffs filed an amended complaint that withdrew Title V and opacity claims, added claims associated with two 2011 projects, and expanded the scope of certain claims to encompass approximately 40 additional projects. In July 2014, the court denied both the defendants’ motion to dismiss and the plaintiffs’ motion for partial summary judgment.

In August 2014, the plaintiffs filed a second amended complaint to which the defendants’ response was filed in September 2014. The second amended complaint continues to seek injunctive relief, declaratory relief, and civil penalties for alleged violations of the federal Clean Air Act. The plaintiffs state in the second amended complaint that it was filed, in part, to comply with the court’s ruling on the defendants’ motion to dismiss and plaintiffs’ motion for partial summary judgment. Discovery in this matter is complete. Oral argument on a variety of motions for summary judgment is scheduled for December 1, 2015, with trial now set for May 2016.

Management believes that it is reasonably possible that this matter could result in a loss to the Company. However, due to the uncertainties concerning this matter, PGE cannot predict the outcome, estimate a range of potential loss, or determine whether it would have a material impact on the Company.

Other Matters

PGE is subject to other regulatory, environmental, and legal proceedings, investigations, and claims that arise from time to time in the ordinary course of business that may result in judgments against the Company. Although management currently believes that resolution of such matters, individually and in the aggregate, will not have a material impact on its financial position, results of operations, or cash flows, these matters are subject to inherent uncertainties, and management’s view of these matters may change in the future.