XML 132 R75.htm IDEA: XBRL DOCUMENT v3.22.0.1
Regulatory Matters (Duke Energy Progress Narrative) (Details) - USD ($)
$ in Millions
12 Months Ended
May 21, 2021
Apr. 16, 2021
Oct. 16, 2020
Oct. 30, 2019
Oct. 11, 2019
May 21, 2019
Nov. 08, 2018
Nov. 22, 2017
Jun. 01, 2017
Dec. 31, 2021
Dec. 31, 2020
Dec. 31, 2019
Public Utilities, General Disclosures [Line Items]                        
Regulatory assets                   $ 14,637 $ 14,062  
Impairment of assets and other charges                   356 984 $ (8)
Other income and expenses, net                   643 453 430
Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Regulatory assets                   4,651 4,468  
Impairment of assets and other charges                   63 499 12
Other income and expenses, net                   143 75 $ 100
2017 North Carolina Rate Case | NCUC | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Requested rate increase (decrease)                 $ 477      
Requested rate increase (decrease), amended, amount                 $ 420      
Requested return on equity, percentage               9.90%        
Requested capital structure, percentage               52.00%        
Requested debt structure, percentage               48.00%        
2019 North Carolina Rate Case | NCUC | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Requested rate increase (decrease)       $ 464                
Requested rate increase (decrease), percent       12.30%                
Requested gross rate case revenue increase       $ 586                
Requested rate increase (decrease), rider reduction, tax cuts and jobs act and return deferred revenue       122                
Requested EDIT rider decrease       $ 120                
2019 North Carolina Rate Case | North Carolina Utilities Commission | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Approved rate increase (decrease) amount by state commission $ 178                      
2019 North Carolina Rate Case, Additional Agreement and Stipulation of Partial Settlement | North Carolina Utilities Commission | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Approved return on equity, percentage   9.60%                    
Approved capital structure, percentage   52.00%                    
Approved debt structure, percentage   48.00%                    
2018 South Carolina Rate Case | PSCSC | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Requested rate increase (decrease)             $ 59          
Approved return on equity, percentage           9.50%            
Approved capital structure, percentage           53.00%            
Approved debt structure, percentage           47.00%            
Tax benefit from change in enacted tax rates           $ (17)            
Measurement period adjustment           (12)            
FERC Return on Equity Complaint, North Carolina Eastern Municipal Power Agency | FERC | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Approved return on equity, percentage         11.00%              
FERC Return on Equity Complaint, North Carolina Electric Membership Corporation | FERC | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Approved return on equity, percentage     11.00%                  
Grid Improvement | 2019 North Carolina Rate Case, Additional Agreement and Stipulation of Partial Settlement | North Carolina Utilities Commission | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Regulatory assets   $ 400                    
Storm cost deferrals                        
Public Utilities, General Disclosures [Line Items]                        
Regulatory assets                   213 1,102  
Storm cost deferrals | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Regulatory assets                   170 785  
Storm cost deferrals | 2019 North Carolina Rate Case, Additional Agreement and Stipulation of Partial Settlement | North Carolina Utilities Commission | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Regulatory assets   $ 714                    
AROs – coal ash                        
Public Utilities, General Disclosures [Line Items]                        
Regulatory assets                   3,408 3,408  
AROs – coal ash | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Regulatory assets                   1,389 $ 1,347  
AROs – coal ash | 2018 South Carolina Rate Case | PSCSC | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Regulatory assets           4            
Denied recovery costs           $ 65            
Impairment of assets and other charges                   42    
Other income and expenses, net                   $ 6    
Asset retirement obligations - unprotected EDIT, Property, Plant and Equipment | 2018 South Carolina Rate Case | PSCSC | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Recovery period           20 years            
Asset retirement obligations - Unprotected EDIT | 2018 South Carolina Rate Case | PSCSC | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Recovery period           5 years            
Asset retirement obligations - deferred revenue | 2018 South Carolina Rate Case | PSCSC | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Recovery period           3 years            
State | North Carolina DOR | 2018 South Carolina Rate Case | PSCSC | Duke Energy Progress                        
Public Utilities, General Disclosures [Line Items]                        
Approved increase (decrease) through EDIT Rider           $ 12