All the acquisitions discussed below were accounted for as asset acquisitions.

Acquisition of a Wind Generation Facility in Nebraska

In January 2019, we completed the acquisition of an 80% membership interest in Upstream, a commercially operational 202.5 MW wind generating facility, for $268.2 million, which included transactions costs and is net of cash and restricted cash acquired of $9.2 million. Upstream is located in Antelope County, Nebraska and supplies energy to the Southwest Power Pool. Upstream's revenue will be substantially fixed over a 10-year period through an agreement with an unaffiliated third party. Under the Tax Legislation, our investment in Upstream qualifies for production tax credits and 100% bonus depreciation. Upstream is included in the non-utility energy infrastructure segment.

Acquisition of a Wind Generation Facility in South Dakota

In December 2018, we acquired an 80% ownership interest in Coyote Ridge, a 97.5 MW wind generating facility under construction in Brookings County, South Dakota, for $61.6 million, which included transaction costs. This wind generating facility is expected to be in service by the end of 2019. Upon completion, we expect our total investment in Coyote Ridge to be $145 million. The project has a 12-year offtake agreement with an unaffiliated third party for all of the energy produced by the facility. Under the Tax Legislation, our investment in Coyote Ridge is expected to qualify for production tax credits and 100% bonus depreciation. We are entitled to 99% of the tax benefits related to this facility for the first 11 years of commercial operation, after which we will be entitled to tax benefits equal to our ownership interest. Coyote Ridge is included in the non-utility energy infrastructure segment.

Acquisition of a Wind Energy Generation Facility in Illinois

In August 2018, we completed the acquisition of an 80% membership interest in a commercially operational 132 MW wind generating facility located in Henry County, Illinois, known as Bishop Hill III, for $144.7 million, which included transaction costs and was net of restricted cash acquired of $4.5 million. In December 2018, we completed the acquisition of an additional 10% membership interest in Bishop Hill III, for $18.2 million. Bishop Hill III has a 22-year offtake agreement with an unaffiliated third party for all of the energy produced by the facility. Under the Tax Legislation, our investment in Bishop Hill III qualifies for production tax credits and 100% bonus depreciation. Bishop Hill III is included in the non-utility energy infrastructure segment.

Acquisition of a Wind Energy Generation Facility in Wisconsin

In April 2018, WPS, along with two unaffiliated utilities, completed the purchase of Forward Wind Energy Center, which consists of 86 wind turbines located in Wisconsin with a total capacity of 138 MW. The aggregate purchase price was $172.9 million of which WPS’s proportionate share was 44.6%, or $77.1 million. In addition, we incurred transaction costs that are recorded to a regulatory asset. Since 2008 and up until the acquisition, WPS purchased 44.6% of the facility’s energy output under a power purchase agreement.

Under a joint ownership agreement with the two other utilities, WPS is entitled to its share of generating capability and output of the facility equal to its ownership interest. WPS is also paying its ownership share of additional capital expenditures and operating expenses. Forward Wind Energy Center is included in the Wisconsin segment.