The following table summarizes the activity within the restructuring related balance sheet accounts for the 2016, 2014 and 2013 Projects during the nine months ended September 30, 2016:

 
Accrued Employee Severance
 
Asset Impairments & Net Loss on Sale or Disposal
 
Other Accrued Costs
 
Total
 
(in thousands)
Beginning balance, January 1, 2016
$
26,533

 
$

 
$
3,048

 
$
29,581

Costs charged to expense
34,919

 
5,153

 
1,222

 
41,294

Cash payments
(14,476
)
 

 
(1,331
)
 
(15,807
)
Non-cash items

 
(5,153
)
 

 
(5,153
)
Effect of change in exchange rates
(95
)
 

 
(5
)
 
(100
)
Ending balance, September 30, 2016
$
46,881

 
$

 
$
2,934

 
$
49,815


2016 Projects [Member]  
Restructuring Project [Line Items]  
Restructuring and Related Costs [Table Text Block]
The total expected restructuring costs, the restructuring costs recognized during the nine months ended September 30, 2016, and the remaining expected restructuring costs as of September 30, 2016 related to the 2016 Projects are as follows:

 
Total Expected Costs at September 30, 2016
 
Costs Recognized During the Nine Months Ended September 30, 2016
 
Expected Remaining Costs to be Recognized at September 30, 2016
 
(in thousands)
Employee severance costs
$
44,162

 
$
34,662

 
$
9,500

Asset impairments & net loss on sale or disposal
5,184

 
5,184

 

Other restructuring costs
16,652

 
152

 
16,500

Total
$
65,998

 
$
39,998

 
$
26,000

 
 
 
 
 
 
Segments:
 
 
 
 
 
Electricity
$
10,044

 
$
6,544

 
$
3,500

Gas
33,214

 
20,214

 
13,000

Water
21,410

 
12,410

 
9,000

Corporate unallocated
1,330

 
830

 
500

Total
$
65,998

 
$
39,998

 
$
26,000

2014 Project [Member]  
Restructuring Project [Line Items]  
Restructuring and Related Costs [Table Text Block]
The total expected restructuring costs, the restructuring costs recognized in prior periods, the restructuring costs recognized during the nine months ended September 30, 2016, and the remaining expected restructuring costs as of September 30, 2016 related to the 2014 Projects were as follows:

 
Total Expected Costs at September 30, 2016
 
Costs Recognized in Prior Periods
 
Costs Recognized During the Nine Months Ended September 30, 2016
 
Expected Remaining Costs to be Recognized at September 30, 2016
 
(in thousands)
Employee severance costs
$
34,630

 
$
34,373

 
$
257

 
$

Asset impairments & net loss on sale or disposal
8,849

 
8,880

 
(31
)
 

Other restructuring costs
4,999

 
3,929

 
1,070

 

Total
$
48,478

 
$
47,182

 
$
1,296

 
$

 
 
 
 
 
 
 
 
Segments:
 
 
 
 
 
 
 
Electricity
$
20,610

 
$
21,743

 
$
(1,133
)
 
$

Gas
13,631

 
11,855

 
1,776

 

Water
1,995

 
1,940

 
55

 

Corporate unallocated
12,242

 
11,644

 
598

 

Total
$
48,478

 
$
47,182

 
$
1,296

 
$