Contingencies and Commitments (Details) (USD $)
12 Months Ended 1 Months Ended 12 Months Ended 1 Months Ended 1 Months Ended 12 Months Ended 1 Months Ended 12 Months Ended 1 Months Ended 0 Months Ended 1 Months Ended 1 Months Ended 3 Months Ended 12 Months Ended 1 Months Ended
Dec. 31, 2013
Dec. 31, 2012
Dec. 31, 2011
Tutor-Saliba-Perini Joint Venture vs. Los Angeles MTA Matter
Jan. 31, 2013
Perini/Kiewit/Cashman Joint Venture-Central Artery/Tunnel Project Matter
Feb. 29, 2012
Perini/Kiewit/Cashman Joint Venture-Central Artery/Tunnel Project Matter
Oct. 31, 2011
Perini/Kiewit/Cashman Joint Venture-Central Artery/Tunnel Project Matter
Dec. 31, 2010
Perini/Kiewit/Cashman Joint Venture-Central Artery/Tunnel Project Matter
Dec. 31, 2013
Perini/Kiewit/Cashman Joint Venture-Central Artery/Tunnel Project Matter
item
Dec. 31, 2000
Perini/Kiewit/Cashman Joint Venture-Central Artery/Tunnel Project Matter
Feb. 29, 2012
Long Island Expressway/Cross Island Parkway Matter
Mar. 31, 2011
Long Island Expressway/Cross Island Parkway Matter
May 31, 2012
Long Island Expressway/Cross Island Parkway Matter
Sep. 30, 2011
Long Island Expressway/Cross Island Parkway Matter
Feb. 28, 2006
Long Island Expressway/Cross Island Parkway Matter
Nov. 30, 2009
Gaylord Hotel and Convention Center Matter
Dec. 31, 2009
Fontainebleau Matter
item
Jul. 31, 2010
Fontainebleau Matter
May 31, 2010
Fontainebleau Matter
Jun. 30, 2009
Fontainebleau Matter
Oct. 31, 2013
MGM CityCenter Matter
Aug. 31, 2013
MGM CityCenter Matter
Jul. 30, 2013
MGM CityCenter Matter
Jul. 31, 2012
MGM CityCenter Matter
item
Mar. 31, 2005
MGM CityCenter Matter
item
acre
Dec. 31, 2012
MGM CityCenter Matter
Dec. 31, 2013
MGM CityCenter Matter
Jun. 30, 2003
Honeywell Street/Queens Boulevard Bridges Matter
Mar. 31, 2010
Honeywell Street/Queens Boulevard Bridges Matter
Feb. 28, 2013
Westgate Planet Hollywood Matter
Dec. 31, 2010
Westgate Planet Hollywood Matter
Jan. 31, 2014
Westgate Planet Hollywood Matter
TSC
Feb. 28, 2013
Westgate Planet Hollywood Matter
TSC
Apr. 30, 2013
Brightwater Matter
Dec. 31, 2012
Brightwater Matter
Apr. 30, 2010
Brightwater Matter
Dec. 31, 2012
Brightwater Matter
Dec. 31, 2013
Brightwater Matter
Dec. 31, 2011
Brightwater Matter
Jun. 30, 2012
156 Stations Matter
Dec. 31, 2003
156 Stations Matter
item
Feb. 28, 2013
156 Stations Matter
Contingencies and Commitments                                                                                  
Judgment in favor of TSP     $ 3,000,000                                                                            
Tunnel handrail verdict against TSP     500,000                                                                            
Ownership percentage in joint venture               56.00%                                                         20.00%        
Estimated minimum costs of owner-directed changes to work                 100,000,000                                                                
Number of construction experts in Disputes Review Board               3                                                                  
Total number of Disputes Review Board panels               5                                                                  
Total value of DRB awards issued in PKC's favor               128,000,000                                                                  
Total value of binding DRB awards issued in PKC's favor               110,000,000                                                                  
Amount of Third DRB awards previously awarded to PKC which have been vacated by Court             56,500,000                                                                    
Amount of Fourth DRB awards that MHD moved to vacate             13,700,000                                                                    
Amount of Fourth DRB awards previously awarded to PKC which have been vacated by Court           8,000,000                                                                      
Interest award payment received by PKC from MHD         22,000,000                                                                        
Payment for back charges and interest       14,800,000                                                                          
Estimated value of project completed in Feb. 2006                           130,000,000                                                      
Value of claim filed                   53,800,000 53,800,000       40,000,000                       8,750,000               74,000,000     132,000,000      
Amount receivable as per final agreement                         500,000                                                        
Value of cross complaint filed                                                           51,000,000                      
Value of counterclaim filed                       151,000,000                               74,600,000   45,000,000         75,000,000            
Business interruption costs assigned to PTJV                             11,000,000                                                    
Number of rooms in hotel/casino complex                               3,800                                                  
Amount of court order in favor of plaintiff                                   45,000,000                           9,000,000                 12,300,000
Amount set aside from approved sale for distribution to satisfy creditor claims                                 125,000,000                                                
Estimated sustainable lien amount                                 350,000,000                                                
Number of contracts in project                                               19                                  
Area allotted to the project (in acres)                                               66                                  
Number of CityCenter buildings included in motion to be demolished                                             1                                    
Estimated cost to repair facility                                                 21,000,000                                
Estimated cost to repair facility due to design defects                                                 15,000,000                                
Third party settlements attributable to alleged damages on the Harmon                                       33,000,000                                          
Amount settled with MGM                                                   348,000,000                              
Contract receivables 1,291,246,000 1,224,613,000                                               165,700,000                              
Total outstanding liens on property, including subcontractors' liens                                     44,000,000             166,800,000       23,200,000                      
Value of mechanic's lien release bond                                                           22,300,000                      
Verdict awarded by jury                                                                   155,800,000              
Damages awarded                                                                   26,300,000              
Damages awarded to WPH which are anticipated to be paid by the OCIP carrier                                                         2,600,000                        
Amount of legal fees under plaintiff's motion granted by court                                                             5,800,000                    
Attorney's fees to be paid by VPFK                                                                 14,700,000                
Provision for contingency accrual                                                                       5,000,000          
Number of stations for the New York City Transit Authority                                                                               156  
Settlement on judgment                                           39,800,000                                 11,900,000    
Maximum number of days awarded claim must be paid                                                                             45 days    
Settlement receipt                                         $ 39,800,000