Commitments and Contingencies (Details) - USD ($)
$ in Millions
1 Months Ended 3 Months Ended 12 Months Ended
Dec. 13, 2019
Jun. 04, 2019
Feb. 26, 2015
Mar. 31, 2016
Jun. 30, 2015
Aug. 31, 2013
Dec. 31, 2019
Dec. 31, 2019
Jul. 02, 2018
Mar. 31, 2018
Alaskan Way Viaduct Matter [Member]                    
Contingencies and Commitments                    
Settlement on judgment, awarded to other party $ 57.2                  
Settlement on judgment             $ 57.2      
Value of claim filed       $ 57.2 $ 532.0          
Value of counterclaim filed       $ 667.0            
Ownership percentage in joint venture             45.00% 45.00%    
Pre-tax charge, impact from jury verdict             $ 166.8      
Pre-tax accrual, impact from jury verdict             $ 25.7      
George Washington Bridge Bus Station Matter [Member]                    
Contingencies and Commitments                    
Value of claim filed     $ 30.0              
Value of counterclaim filed                   $ 29.0
Value of project           $ 100.0        
Court issued writ of attachment amount   $ 23.0                
Value of damages seeking                 $ 113.0  
Proof of Claim amount $ 113.0                  
Return Of Retainage By Developer [Member] | George Washington Bridge Bus Station Matter [Member]                    
Contingencies and Commitments                    
Value of counterclaim filed                   29.0
Minimum [Member] | George Washington Bridge Bus Station Matter [Member]                    
Contingencies and Commitments                    
Value of counterclaim filed                   $ 113.0