Costs related to investigation and study under Superfund site | $     $ 2
Southwest Power Outage      
Power outage capacity of transmission line that tripped out of service | kV   500  
Period, after the transmission line went off-line, over which generation and transmission resources for the Yuma area were lost   10 minutes  
Number of customers losing service in Yuma area | Customer   69,700  
Contaminated groundwater wells      
Superfund      
Number of defendants against whom Roosevelt Irrigation District ("RID") filed lawsuit | Defendant 24