Plant Closure and Consolidation Plant Closure and Consolidation
During the three and nine months ended September 30, 2023 and 2022, the Company incurred the following expenses related to plant closure and consolidation in connection with its profit-improvement actions across its segments. These charges are included in Restructuring and other special charges in the Condensed Consolidated Statements of Income.

 Facility-Related CostsSeverance and Other Total
Three months ended September 30, 2023:
Assembly Components$— $— $— 
Engineered Products— — — 
Total$— $— $— 
Three months ended September 30, 2022:
Assembly Components$1.2 $— $1.2 
Engineered Products1.4 — 1.4 
Total$2.6 $— $2.6 

 Facility-Related CostsSeverance and Other Total
Nine months ended September 30, 2023:
Assembly Components$0.5 $— $0.5 
Engineered Products2.7 1.9 4.6 
Total$3.2 $1.9 $5.1 
Nine months ended September 30, 2022:
Assembly Components$4.2 $— $4.2 
Engineered Products2.7 0.1 2.8 
Total$6.9 $0.1 $7.0 

The actions in the Assembly Components segment were primarily in connection with actions taken to close and consolidate its extrusion operations in Tennessee and its fuel operations in Michigan, relocate certain production to lower-cost facilities with open capacity, and complete other cost-reduction actions.

The actions in the Engineered Product segment were primarily in connection with plant closure and consolidation of multiple locations, and to complete other cost-reduction actions.
As of September 30, 2023, the Company was substantially complete with these actions.