XML 22 R13.htm IDEA: XBRL DOCUMENT v3.23.2
Plant Closure and Consolidation
6 Months Ended
Jun. 30, 2023
Restructuring and Related Activities [Abstract]  
Plant Closure and Consolidation Plant Closure and Consolidation
During the three and six months ended June 30, 2023 and 2022, the Company incurred the following expenses related to plant closure and consolidation in connection with its profit-improvement actions across its segments. These charges are included in Restructuring and other special charges in the Condensed Consolidated Statements of Income.

 Facility-Related CostsSeverance and Other Total
Three months ended June 30, 2023:
Assembly Components$0.2 $— $0.2 
Engineered Products0.7 1.9 2.6 
Total$0.9 $1.9 $2.8 
Three months ended June 30, 2022:
Assembly Components$1.5 $— $1.5 
Engineered Products0.8 — 0.8 
Total$2.3 $— $2.3 

 Facility-Related CostsSeverance and Other Total
Six months ended June 30, 2023:
Assembly Components$0.5 $— $0.5 
Engineered Products2.7 1.9 4.6 
Total$3.2 $1.9 $5.1 
Six months ended June 30, 2022:
Assembly Components$3.0 $— $3.0 
Engineered Products1.2 0.1 1.3 
Total$4.2 $0.1 $4.3 

The actions in the Assembly Components segment were primarily in connection with actions taken to close and consolidate its extrusion operations in Tennessee and its fuel operations in Michigan, relocate certain production to lower-cost facilities with open capacity, and complete other cost-reduction actions.

The actions in the Engineered Product segment were primarily in connection with plant closure and consolidation of multiple locations, and to complete other cost-reduction actions.
The Company expects to incur expenses of less than $1.0 million in the remainder of 2023 in connection with its plant closure and consolidation activities.