EX-99.4 5 d180315dex994.htm EX-99.4 EX-99.4
Exhibit 99.4
Management’s Discussion
and Analysis (“MD&A”)

Management’s Discussion and Analysis (“MD&A”) is intended to help the reader understand Barrick Gold Corporation (“Barrick”, “we”, “our”, the “Company” or the “Group”), our operations, financial performance and the present and future business environment. This MD&A, which has been prepared as of February 15, 2022, should be read in conjunction with our audited consolidated financial statements (“Financial Statements”) for the year ended December 31, 2021. Unless otherwise indicated, all amounts are presented in US dollars.
For the purposes of preparing our MD&A, we consider the materiality of information. Information is considered material if: (i) such information results in, or would reasonably be expected to result in, a significant change in the market price or value of our shares; (ii) there is a substantial likelihood that a reasonable investor would
consider it important in making an investment decision; or (iii) it would significantly alter the total mix of information available to investors. We evaluate materiality with reference to all relevant circumstances, including potential market sensitivity.    
Continuous disclosure materials, including our most recent Form 40-F/Annual Information Form, annual MD&A, audited consolidated financial statements, and Notice of Annual Meeting of Shareholders and Proxy Circular will be available on our website at www.barrick.com, on SEDAR at www.sedar.com and on EDGAR at www.sec.gov. For an explanation of terminology unique to the mining industry, readers should refer to the glossary on page 128.



Cautionary Statement on Forward-Looking Information
 
Certain information contained or incorporated by reference in this MD&A, including any information as to our strategy, projects, plans or future financial or operating performance, constitutes “forward-looking statements”. All statements, other than statements of historical fact, are forward-looking statements. The words “believe”, “expect”, “anticipated”, “contemplate” “vision”, “aim”, “strategy”, “target”, “plan”, “opportunities”, “guidance”, “forecast”, “outlook”, “objective”, “intend”, “project”, “pursue”, “goal”, “continue”, “committed”, “budget”, “estimate”, “potential”, “prospective”, “future”, “focus”, “ongoing”, “following”, “subject to”, “scheduled”, “may”, “will”, “can”, “could”, “would”, “should” and similar expressions identify forward-looking statements. In particular, this MD&A contains forward-looking statements including, without limitation, with respect to: Barrick’s forward-looking production guidance; estimates of future cost of sales per ounce for gold and per pound for copper, total cash costs per ounce and C1 cash costs per pound, and all-in-sustaining costs per ounce/pound; cash flow forecasts; projected capital, operating and exploration expenditures; the share buyback program and performance dividend policy, including the criteria for dividend payments; mine life and production rates; Barrick’s engagement with local communities to manage the Covid-19 pandemic, including Covid-19 vaccination initiatives and Covid-19 protocols at Barrick’s minesites; projected capital estimates and anticipated permitting timelines related to the Goldrush Project, as well as opportunities for development in the Red Hill mining zone during the permitting process; our plans and expected completion and benefits of our growth projects, including the Goldrush Project and construction of the twin exploration declines, Turquoise Ridge Third Shaft, Pueblo Viejo plant expansion and mine life extension project, Bulyanhulu production ramp-up and results of the internal feasibility study, including further planned reserve conversion drilling at Deep West, Zaldívar chloride leach project, and Veladero Phase 7 leach pad and power transmission projects; capital expenditures related to upgrades and ongoing management initiatives, including at North Mara; Barrick’s global exploration strategy and
planned exploration activities, including at North Leeville and the acquisition of prospecting licenses in Tanzania; the impact of Nevada’s new mining excise tax on Nevada Gold Mines and of proposed changes to the U.S. General Mining Law; the timeline for execution and effectiveness of definitive agreements and formation of a new joint venture to implement the binding Framework Agreement between Papua New Guinea and Barrick Niugini Limited (“BNL”) and the timeline for resolution of outstanding tax audits with Papua New Guinea’s Internal Revenue Commission (“IRC”); the duration of the temporary suspension of operations at Porgera and timeline to recommence operations; steps required prior to the distribution of cash and equivalents held at Kibali in banks in the Democratic Republic of Congo; our pipeline of high confidence projects at or near existing operations; potential mineralization and metal or mineral recoveries; our ability to convert resources into reserves and future reserve replacement; asset sales, joint ventures and partnerships, including the expected benefits of the South Arturo asset exchange, the sale of Lagunas Norte, and the sale of several other legacy closure properties; Barrick’s strategy, plans, targets and goals in respect of environmental and social governance issues, including climate change, greenhouse gas emissions reduction targets, tailings storage facility management, biodiversity and human rights initiatives; and expectations regarding future price assumptions, financial performance and other outlook or guidance.
Forward-looking statements are necessarily based upon a number of estimates and assumptions including material estimates and assumptions related to the factors set forth below that, while considered reasonable by the Company as at the date of this MD&A in light of management’s experience and perception of current conditions and expected developments, are inherently subject to significant business, economic and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements and
BARRICK YEAR-END 2021
24
MANAGEMENT’S DISCUSSION AND ANALYSIS


undue reliance should not be placed on such statements and information. Such factors include, but are not limited to: fluctuations in the spot and forward price of gold, copper or certain other commodities (such as silver, diesel fuel, natural gas and electricity); risks associated with projects in the early stages of evaluation and for which additional engineering and other analysis is required; risks related to the possibility that future exploration results will not be consistent with the Company’s expectations, that quantities or grades of reserves will be diminished, and that resources may not be converted to reserves; risks associated with the fact that certain of the initiatives described in this MD&A are still in the early stages and may not materialize; changes in mineral production performance, exploitation and exploration successes; risks that exploration data may be incomplete and considerable additional work may be required to complete further evaluation, including but not limited to drilling, engineering and socioeconomic studies and investment; the speculative nature of mineral exploration and development; lack of certainty with respect to foreign legal systems, corruption and other factors that are inconsistent with the rule of law; changes in national and local government legislation, taxation, controls or regulations and/or changes in the administration of laws, policies and practices; expropriation or nationalization of property and political or economic developments in Canada, the United States or other countries in which Barrick does or may carry on business in the future; risks relating to political instability in certain of the jurisdictions in which Barrick operates; timing of receipt of, or failure to comply with, necessary permits and approvals, including the issuance of a Record of Decision for the Goldrush Project and/or whether the Goldrush Project will be permitted to advance as currently designed under its Feasibility Study; non-renewal of key licenses by governmental authorities, including non-renewal of Porgera’s special mining lease; failure to comply with environmental and health and safety laws and regulations; contests over title to properties, particularly title to undeveloped properties, or over access to water, power and other required infrastructure; the liability associated with risks and hazards in the mining industry, and the ability to maintain insurance to cover such losses; increased costs and physical risks, including extreme weather events and resource shortages, related to climate change; damage to the Company’s reputation due to the actual or perceived occurrence of any number of events, including negative publicity with respect to the Company’s handling of environmental matters or dealings with community groups, whether true or not; risks related to operations near communities that may regard Barrick’s operations as being detrimental to them; litigation and legal and administrative proceedings; operating or technical difficulties in connection with mining or development activities, including geotechnical challenges, tailings dam and storage facilities failures, and disruptions in the maintenance or provision of required infrastructure and information technology systems; increased costs, delays, suspensions and technical challenges associated with the construction of capital projects; risks associated with working with partners in jointly controlled assets; risks related to disruption of supply
routes which may cause delays in construction and mining activities; risk of loss due to acts of war, terrorism, sabotage and civil disturbances; risks associated with artisanal and illegal mining; risks associated with Barrick’s infrastructure, information technology systems and the implementation of Barrick’s technological initiatives; the impact of global liquidity and credit availability on the timing of cash flows and the values of assets and liabilities based on projected future cash flows; the impact of inflation; adverse changes in our credit ratings; fluctuations in the currency markets; changes in U.S. dollar interest rates; risks arising from holding derivative instruments (such as credit risk, market liquidity risk and mark-to-market risk); risks related to the demands placed on the Company’s management, the ability of management to implement its business strategy and enhanced political risk in certain jurisdictions; uncertainty whether some or all of Barrick's targeted investments and projects will meet the Company’s capital allocation objectives and internal hurdle rate; whether benefits expected from recent transactions being realized; business opportunities that may be presented to, or pursued by, the Company; our ability to successfully integrate acquisitions or complete divestitures; risks related to competition in the mining industry; employee relations including loss of key employees; availability and increased costs associated with mining inputs and labor; risks associated with diseases, epidemics and pandemics, including the effects and potential effects of the global Covid-19 pandemic; risks related to the failure of internal controls; and risks related to the impairment of the Company’s goodwill and assets. Barrick also cautions that its 2022 guidance may be impacted by the unprecedented business and social disruption caused by the spread of Covid-19.
In addition, there are risks and hazards associated with the business of mineral exploration, development and mining, including environmental hazards, industrial accidents, unusual or unexpected formations, pressures, cave-ins, flooding and gold bullion, copper cathode or gold or copper concentrate losses (and the risk of inadequate insurance, or inability to obtain insurance, to cover these risks).
Many of these uncertainties and contingencies can affect our actual results and could cause actual results to differ materially from those expressed or implied in any forward-looking statements made by, or on behalf of, us. Readers are cautioned that forward-looking statements are not guarantees of future performance. All of the forward-looking statements made in this MD&A are qualified by these cautionary statements. Specific reference is made to the most recent Form 40-F/Annual Information Form on file with the SEC and Canadian provincial securities regulatory authorities for a more detailed discussion of some of the factors underlying forward-looking statements and the risks that may affect Barrick’s ability to achieve the expectations set forth in the forward-looking statements contained in this MD&A. We disclaim any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law.


BARRICK YEAR-END 2021
25
MANAGEMENT’S DISCUSSION AND ANALYSIS


Use of Non-GAAP Financial Performance Measures
We use the following non-GAAP financial performance measures in our MD&A:
“adjusted net earnings”
“free cash flow”
“EBITDA”
“adjusted EBITDA”
“minesite sustaining capital expenditures”
“project capital expenditures”
“total cash costs per ounce”
“C1 cash costs per pound”
“all-in sustaining costs per ounce/pound”
“all-in costs per ounce” and
“realized price”

For a detailed description of each of the non-GAAP measures used in this MD&A and a detailed reconciliation to the most directly comparable measure under International Financial Reporting Standards (“IFRS”), please refer to the Non-GAAP Financial Performance Measures section of this MD&A on pages 94 to 120 . Each non-GAAP financial performance measure has been annotated with a reference to an endnote on page 121 . The non-GAAP financial performance measures set out in this MD&A are intended to provide additional information to investors and do not have any standardized meaning under IFRS, and therefore may not be comparable to other issuers, and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS.



Changes in Presentation of Non-GAAP Financial Performance Measures

Capital Expenditures
Starting with this MD&A, we have identified minesite sustaining capital expenditures and project capital expenditures as non-GAAP financial performance measures as a result of adopting National Instrument 52-112 - Non-GAAP and Other Financial Measures Disclosure issued by the Canadian Securities Administrators. We have included the required disclosures for these non-GAAP financial measures, although there is no change to our calculation of these measures.











BARRICK YEAR-END 2021
26
MANAGEMENT’S DISCUSSION AND ANALYSIS



Index

Overview
Our Vision
Our Business
Our Strategy
Financial and Operating Highlights
Environmental, Social and Governance
Reserves and Resources
Key Business Developments
Outlook for 2022
Risks and Risk Management
Market Overview
Production and Cost Summary
Operating Performance
Nevada Gold Mines
Carlin
Cortez
Turquoise Ridge
Other Mines - Nevada Gold Mines
Pueblo Viejo
Loulo-Gounkoto
Kibali
Veladero
North Mara
Bulyanhulu
Other Mines - Gold
Other Mines - Copper
Growth Project Updates
Exploration and Mineral Resource Management
Review of Financial Results
Revenue
Production Costs
Capital Expenditures
General and Administrative Expenses
Exploration, Evaluation and Project Costs
Finance Costs, Net
Additional Significant Statement of Income Items
Income Tax Expense
Financial Condition Review
Balance Sheet Review
Shareholders’ Equity
Financial Position and Liquidity
Summary of Cash Inflow (Outflow)
Summary of Financial Instruments
Commitments and Contingencies
Review of Quarterly Results
Internal Control Over Financial Reporting and Disclosure Controls and Procedures
IFRS Critical Accounting Policies and Accounting Estimates
Non-GAAP Financial Performance Measures
Technical Information
Endnotes
Glossary of Technical Terms
Mineral Reserves and Mineral Resources Tables
138 Management’s Responsibility
139 Management’s Report on Internal Control Over Financial Reporting
140 Independent Auditor’s Report
144 Financial Statements
149 Notes to Consolidated Financial Statements

BARRICK YEAR-END 2021
27
MANAGEMENT’S DISCUSSION AND ANALYSIS

Overview

Our Vision
We strive to be the world’s most valued gold mining business by finding, developing and owning the best assets, with the best people, to deliver sustainable returns for our owners and partners.

Our Business
Barrick is one of the world’s leading gold mining companies with annual gold production and gold reserves that are among the largest in the industry. We are principally engaged in the production and sale of gold and copper, as well as related activities such as exploration and mine development. We hold ownership interests in thirteen producing gold mines, including six Tier One Gold Assets1 and a diversified exploration portfolio positioned for growth in many of the world’s most prolific gold districts. These gold mines are geographically diversified and are located in Argentina, Canada, Côte d’Ivoire, the Democratic Republic of Congo, the Dominican Republic, Mali, Tanzania and the United States. Our mine in Papua New Guinea was placed on care and maintenance in April 2020. Our three copper mines are located in Zambia, Chile and Saudi Arabia. Our exploration and development projects are located throughout the Americas and Africa. We sell our production in the world market through the following distribution channels: gold bullion is sold in the gold spot market or to independent refineries; gold and copper concentrate is sold to independent smelting or trading companies; and copper cathode is sold to third-party purchasers or on exchange. Barrick shares trade on the New York Stock Exchange under the symbol GOLD and the Toronto Stock Exchange under the symbol ABX.

2021 REVENUE ($ millions)

revenue.jpg

Our Strategy
Our strategy is to operate as business owners by attracting and developing world-class people who understand and are involved in the value chain of the business, act with integrity and are tireless in their pursuit of excellence. We are focused on returns to our stakeholders by optimizing free cash flow, managing risk to create long-term value for our
shareholders and partnering with host governments and our local communities to transform their country’s natural resources into sustainable benefits and mutual prosperity. We aim to achieve this through the following:1

Asset Quality
Grow and invest in a portfolio of Tier One Gold Assets1, Tier Two Gold Assets2, Tier One Copper Assets3 and Strategic Assets4 with an emphasis on organic growth to leverage our existing footprint. We will focus our efforts on identifying, investing in and developing assets that meet our investment criteria. The required internal rate of return (“IRR”) for Tier One Gold Assets and Tier Two Gold Assets is 15% and 20%, respectively, based on our long-term gold price assumption. The required IRR for Tier One Copper Assets is 15% based on our long-term copper price assumption. A Tier One Gold Asset is an asset with a reserve potential to deliver a minimum 10-year life, annual production of at least 500,000 ounces of gold and total cash costs per ounce6 over the mine life that are in the lower half of the industry cost curve. A Tier Two Gold Asset is an asset with a reserve potential to deliver a minimum 10-year life, annual production of at least 250,000 ounces of gold and total cash costs per ounce6 over the mine life that are in the lower half of the industry cost curve. A Tier One Copper Asset is an asset with a reserve potential of greater than five million tonnes of contained copper and C1 cash costs per pound6 over the mine life that are in the lower half of the industry cost curve.
Invest in exploration across extensive land positions in many of the world’s most prolific gold and copper districts.
Maximize the long-term value of our strategic Copper Business5.
Sell non-core assets over time in a disciplined manner.

Operational Excellence
Strive for zero harm workplaces.
Operate a flat management structure with a strong ownership culture.
Streamline management and operations, and hold management accountable for the businesses they manage.
Leverage innovation and technology to drive industry-leading efficiencies.
Build trust-based partnerships with our host governments, business partners, and local communities to drive shared long-term value.

Sustainable Profitability
Follow a disciplined approach to growth and proactively manage our impacts on the wider environment, emphasizing long-term value for all stakeholders.
Increase returns to shareholders, driven by a focus on return on capital, internal rate of return and free cash flow.

1 Numerical annotations throughout the text of this document refer to the endnotes found on page 121.
BARRICK YEAR-END 2021
28
MANAGEMENT’S DISCUSSION AND ANALYSIS

Financial and Operating Highlights
For the three months ended For the years ended
   12/31/21 9/30/21 Change 12/31/21 12/31/20  Change 12/31/19
Financial Results ($ millions)
Revenues 3,310  2,826  17% 11,985  12,595  (5%) 9,717 
Cost of sales 1,905  1,768  8% 7,089  7,417  (4%) 6,911 
Net earningsa
726  347  109% 2,022  2,324  (13%) 3,969 
Adjusted net earningsb
626  419  49% 2,065  2,042  1% 902 
Adjusted EBITDAb
2,070  1,669  24% 7,258  7,492  (3)% 4,833 
Adjusted EBITDA marginb,c
63  % 59  % 7% 61  % 59  % 3% 50  %
Minesite sustaining capital expendituresb,d
431  386  12% 1,673  1,559  7% 1,320 
Project capital expendituresb,d
234  179  31% 747  471  59% 370 
Total consolidated capital expendituresd,e
669  569  18% 2,435  2,054  19% 1,701 
Net cash provided by operating activities 1,387  1,050  32% 4,378  5,417  (19%) 2,833 
Net cash provided by operating activities marginf
42  % 37  % 14% 37  % 43  % (14%) 29  %
Free cash flowb
718  481  49% 1,943  3,363  (42%) 1,132 
Net earnings per share (basic and diluted) 0.41  0.20  105% 1.14  1.31  (13%) 2.26 
Adjusted net earnings (basic)b per share
0.35  0.24  46% 1.16  1.15  1% 0.51 
Weighted average diluted common shares (millions of shares) 1,779  1,779  0% 1,779  1,778  0% 1,758 
Operating Results
Gold production (thousands of ounces)g
1,203  1,092  10% 4,437  4,760  (7%) 5,465 
Gold sold (thousands of ounces)g
1,234  1,071  15% 4,468  4,879  (8%) 5,467 
Market gold price ($/oz) 1,795  1,790  0% 1,799  1,770  2% 1,393 
Realized gold priceb,g ($/oz)
1,793  1,771  1% 1,790  1,778  1% 1,396 
Gold cost of sales (Barrick’s share)g,h ($/oz)
1,075  1,122  (4)% 1,093  1,056  4% 1,005 
Gold total cash costsb,g ($/oz)
715  739  (3)% 725  699  4% 671 
Gold all-in sustaining costsb,g ($/oz)
971  1,034  (6)% 1,026  967  6% 894 
Copper production (millions of pounds)g
126  100  26% 415  457  (9%) 432 
Copper sold (millions of pounds)g
113  101  12% 423  457  (7%) 355 
Market copper price ($/lb) 4.40  4.25  4% 4.23  2.80  51% 2.72 
Realized copper priceb,g ($/lb)
4.63  3.98  16% 4.32  2.92  48% 2.77 
Copper cost of sales (Barrick’s share)g,i ($/lb)
2.21  2.57  (14)% 2.32  2.02  15% 2.14 
Copper C1 cash costsb,g ($/lb)
1.63  1.85  (12)% 1.72  1.54  12% 1.69 
Copper all-in sustaining costsb,g ($/lb)
2.92  2.60  12% 2.62  2.23  17% 2.52 
   As at 12/31/21 As at 9/30/21 Change As at 12/31/21 As at 12/31/20 Change As at 12/31/19
Financial Position ($ millions)
Debt (current and long-term) 5,150  5,154  0% 5,150  5,155  0% 5,536 
Cash and equivalents 5,280  5,043  5% 5,280  5,188  2% 3,314 
Debt, net of cash (130) 111  (217)% (130) (33) 294% 2,222 
a.Net earnings represents net earnings attributable to the equity holders of the Company.
b. Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.Represents adjusted EBITDA divided by revenue.
d.Amounts presented on a consolidated cash basis. Project capital expenditures are included in our calculation of all-in costs, but not included in our calculation of all-in sustaining costs.
e.Total consolidated capital expenditures also includes capitalized interest of $4 million and $15 million, respectively, for the three months and year ended December 31, 2021 (September 30, 2021: $4 million; 2020: $24 million; 2019: $11 million).
f.Represents net cash provided by operating activities divided by revenue.
g. On an attributable basis.
h.Gold cost of sales per ounce is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).
i.Copper cost of sales per pound is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).
BARRICK YEAR-END 2021
29
MANAGEMENT’S DISCUSSION AND ANALYSIS

GOLD PRODUCTIONa (thousands of ounces)
COPPER PRODUCTIONa (millions of pounds)
graphsgoldprod.jpg graphscuprod.jpg
GOLD COST OF SALESc, TOTAL CASH COSTSd,
COPPER COST OF SALESc, C1 CASH COSTSd,
AND ALL-IN SUSTAINING COSTSd ($ per ounce)
AND ALL-IN SUSTAINING COSTSd ($ per pound)
graphsgoldaisc.jpg graphscuaisc.jpg

ADJUSTED EBITDAd AND
ADJUSTED EBITDA MARGINe
CAPITAL EXPENDITURES ($ millions)
graphsadjebitda.jpg graphscapex.jpg

OPERATING CASH FLOW AND FREE CASH FLOWd
    SHAREHOLDER DISTRIBUTIONSf (cents per share)

graphscashflow.jpg graphsdistributions.jpg
a.On an attributable basis.
b.Based on the midpoint of the guidance range.
c.Gold cost of sales per ounce is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).
d.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
e.Represents adjusted EBITDA divided by revenue.
f.Dividend per share declared in respect of the stated period. Return of capital distribution was paid contemporaneously with the dividend for that period.
BARRICK YEAR-END 2021
30
MANAGEMENT’S DISCUSSION AND ANALYSIS

Factors affecting net earnings and adjusted net earnings6 - three months ended December 31, 2021 versus September 30, 2021
Net earnings attributable to equity holders of Barrick ("net earnings") for the three months ended December 31, 2021 were $726 million compared to $347 million in the prior quarter. The increase was primarily due to a $205 million gain on the sale of Lone Tree in addition to the drivers described immediately below.
After adjusting for items that are not indicative of future operating earnings, adjusted net earnings6 of $626 million for the three months ended December 31, 2021 was $207 million higher than the prior quarter. The increase in adjusted net earnings6 was mainly due to an increase in gold sales volumes and lower cost of sales per ounce/pound6. This was combined with a higher realized copper price6 of $4.63 per pound for the three months ended December 31, 2021, compared to $3.98 per pound in the prior quarter and to a lesser extent, a higher realized gold price6 of $1,793 per ounce for the three months ended December 31, 2021, compared to $1,771 per ounce in the prior quarter.
The significant adjusting item in the three months ended December 31, 2021 was $109 million ($198 million before tax and non-controlling interest) in acquisition/disposition gains, primarily resulting from the sale of Lone Tree.
Refer to page 94 for a full list of reconciling items between net earnings and adjusted net earnings6 for the current and previous periods.

Factors affecting net earnings and adjusted net earnings6 - year ended December 31, 2021 versus December 31, 2020
Net earnings for the year ended December 31, 2021 were $2,022 million compared to $2,324 million in the prior year. The decrease was primarily due to:
a net impairment reversal of $91 million ($304 million before tax) resulting from the Framework Agreement with the Government of Tanzania (“GoT”) being signed and made effective in the first quarter of 2020 occurring in the prior year;
a gain of $172 million ($180 million before tax and non-controlling interest) in acquisitions/dispositions, primarily resulting from the sale of Eskay Creek, Massawa, Morila and Bullfrog, occurring in the prior year;
a gain of $104 million (no tax impact) on the remeasurement of the residual cash liability relating to our silver sale agreement with Wheaton Precious Metals (“Wheaton”), occurring in the prior year; and
$125 million in current year significant tax expense items mainly due to deferred tax expense as a result of tax reform measures in Argentina, the foreign exchange impact on current tax expense in Peru and the remeasurement of current and deferred tax balances, the acquisition of the 40% interest in South Arturo that Nevada Gold Mines (“NGM”) did not already own, the sale of Lagunas Norte, the settlement of the Massawa Senegalese tax dispute and the recognition/derecognition of our deferred taxes in various jurisdictions compared to $119 million of prior year significant positive tax items related to deferred tax recoveries as a result of tax reform measures in Argentina and adjustments made in recognition of the net settlement of all outstanding disputes with the GoT.

These impacts were partially offset by current year positive items consisting of:
a gain of $94 million ($213 million before tax and non-controlling interest) in acquisition/disposition gains, primarily resulting from the sale of Lone Tree; and
an impairment reversal of $64 million ($63 million before tax and non-controlling interests), primarily resulting from the sale of our 100% interest in the Lagunas Norte mine, occurring in the current year.

After adjusting for items that are not indicative of future operating earnings, adjusted net earnings6 of $2,065 million for the year ended December 31, 2021 was $23 million higher than the prior year. The increase in adjusted net earnings6 was primarily due to a higher realized copper price6 of $4.32 per pound in 2021 compared to $2.92 per pound in the prior year and to a lesser extent, a higher realized gold price6 of $1,790 per ounce in 2021 compared to $1,778 per ounce in the prior year. These impacts were largely offset by a decrease in gold and copper sales volumes and higher cost of sales per ounce/pound7.
Refer to page 94 for a full list of reconciling items between net earnings and adjusted net earnings6 for the current and previous periods.

Factors affecting Operating Cash Flow and Free Cash Flow6 - three months ended December 31, 2021 versus September 30, 2021
In the three months ended December 31, 2021, we generated $1,387 million in operating cash flow, compared to $1,050 million in the prior quarter. The increase of $337 million was primarily due to lower cash taxes paid, combined with an increase in realized gold and copper prices6 as well as higher gold and copper sales volumes. Operating cash flow was further impacted by lower cost of sales per ounce/pound7. These impacts were partially offset by an unfavorable movement in working capital, mainly in other current assets and receivables, which was partially offset by a favorable movement in inventory.
Free cash flow6 for the three months ended December 31, 2021 was $718 million, compared to $481 million in the prior quarter, reflecting higher operating cash flows, partially offset by higher capital expenditures. In the three months ended December 31, 2021, capital expenditures on a cash basis were $669 million compared to $569 million in the prior quarter due to an increase in both minesite sustaining capital expenditures6 and project capital expenditures6. The increase in minesite sustaining capital expenditures6 is primarily at Lumwana due to new mining equipment and stripping, at North Mara resulting from the initial capital spend on the restart of the open-pit mine and at Bulyanhulu, mainly related to the long-term underground fleet. Higher project capital expenditures6 is attributed to the plant expansion and mine life extension project at Pueblo Viejo, the development of the third underground mine and expansion of power capacity at Loulo-Gounkoto, and the commencement of construction for the Phase 7A leach pad at Veladero.

Factors affecting Operating Cash Flow and Free Cash Flow6 - year ended December 31, 2021 versus December 31, 2020
For the year ended December 31, 2021, we generated $4,378 million in operating cash flow, compared to $5,417 million in the prior year. The decrease of $1,039 million was primarily due to higher cash taxes paid, lower gold and copper sales volumes and higher cost of sales per ounce/
BARRICK YEAR-END 2021
31
MANAGEMENT’S DISCUSSION AND ANALYSIS

pound7. This was partially offset by higher realized gold and copper prices6.
For 2021, we generated free cash flow6 of $1,943 million compared to $3,363 million in the prior year. The decrease primarily reflects lower operating cash flows and higher capital expenditures. In 2021, capital expenditures on a cash basis were $2,435 million compared to $2,054 million in the prior year, mainly due to higher project capital expenditures6. The increase in project capital expenditures6 is mainly attributable to the Pueblo Viejo plant expansion and mine life extension project, as well as the development of the third underground mine and expansion of power capacity at Loulo-Gounkoto, partially offset by a decrease at Carlin due to lower cost development and exploration activities at Goldrush underground.

Environmental, Social and Governance ("ESG")
At Barrick, sustainability is entrenched in our DNA.
Our sustainability strategy has four main pillars: (1) ensuring we respect human rights; (2) protecting the health and safety of our people and local communities; (3) sharing the benefits of our operations; and (4) managing our impacts on the environment.
We implement this strategy by blending top-down accountability with bottom-up responsibility. This means we place the day-to-day ownership of sustainability, and the associated risks and opportunities, in the hands of individual sites. In the same way that each site must manage its geological, operational and technical capabilities to meet business objectives, it must also manage and identify programs, metrics, and targets that measure progress and deliver real value for the business and our stakeholders, including our host countries and local communities. The Group Sustainability Executive, supported by regional sustainability leads, provides oversight and direction over this site-level ownership, to ensure alignment with the strategic priorities of the overall business.

Governance
The bedrock of our sustainability strategy is strong governance. We established the Environmental and Social Oversight Committee ("E&S Committee") to connect site-level ownership of our sustainability strategy with the leadership of the Group. It is chaired by the President and Chief Executive Officer and includes: (1) regional Chief Operating Officers; (2) minesite General Managers; (3) Health, Safety, Environment and Closure Leads; (4) the Group Sustainability Executive; (5) in-house legal counsel; and (6) an independent sustainability consultant in an advisory role. The E&S Committee meets on a quarterly basis to review our performance across a range of key performance indicators, and to provide independent oversight and review of sustainability management.
The President and Chief Executive Officer reviews the reports of the E&S Committee with the Board's Environmental, Social, Governance & Nominating Committee (“ESG & Nominating Committee”), formerly known as the Corporate Governance & Nominating Committee. The change to this Committee's name was approved by the Board on February 15, 2022, to better reflect the critical role this Committee plays in overseeing Barrick's sustainability performance. The reports are reviewed to ensure the implementation of our sustainability policies and drive performance of our environmental, health and safety, corporate social responsibility, and human rights programs.
This is supplemented by weekly meetings, at a minimum, between the Regional Sustainability Leads and the Group Sustainability Executive. These meetings examine the sustainability-related risks and opportunities facing the business in real time, as well as the progress and issues integrated into weekly Executive Committee review meetings.
Sustainability is a fundamental business priority for the company and this was reflected in the S&P Global Corporate Sustainability Assessment as Barrick retained its listing in the prestigious Dow Jones Sustainability Index’s (“DJSI”) World Index, ranking in the 95th percentile of all mining companies assessed.
This is the 14th consecutive year Barrick has been listed in the DJSI World Index, in which 2,500 companies are evaluated against governance, social performance, environmental management and economic contribution factors to identify the top 10 percent or “best in class” performers in every industry. The DJSI World Index is the longest-running global sustainability benchmark worldwide and has become the key reference point in sustainability investment.
Our strong performance was demonstrated by scoring full marks (100th percentile) in the categories of environmental reporting, water-related risks, social reporting and human rights, and improved scores in policy influence, operational eco-efficiency, biodiversity and occupational health and safety.
This performance reinforces our sustainability strategy, policies, procedures and management and is reflected in some of our performance metrics through the year, with a trend of continued performance improvement since the merger of Barrick and Randgold Resources (the “Merger”).
Throughout the year, we have been tracking our progress against our Sustainability Scorecard, which we introduced as part of our 2019 Sustainability Report. Our motivation for developing the scorecard was to both transparently disclose to external stakeholders what we viewed as the most important ESG metrics in the industry and our performance against them, while also driving internal improvement at a regional and site level.
Our performance on the scorecard accounts for 25% of the long-term incentive awards for senior leaders in 2021 as part of the Barrick Partnership Plan. Overall, we have improved our score and were it not for the tragic fatalities late in the year we would have seen an increase in our grade to A. We, however, have a zero tolerance for fatalities and as a result remain at a B grade, unchanged from 2020 (on a scale where A represents top performance and E represents bottom performance). As we strive for continued performance, the 2022 Sustainability Scorecard targets and metrics will be updated.
In late 2021 and early 2022, we actively sought feedback by reaching out to a number of our largest shareholders owning over 30% of our issued and outstanding common shares (as of December 31, 2021). Our Lead Director and the Chair of the Compensation Committee participated in these discussions which covered a variety of topics, including our performance, sustainability strategy, environmental goals, human capital strategy, continued active oversight during the Covid-19 pandemic, and executive compensation matters, as well as key governance priorities, including Board composition and renewal. The meetings were an instructive two-way discussion where we heard about our shareholders’ priorities, discussed Barrick’s sustainability vision and provided an opportunity for our performance to be constructively challenged. Sustainability-related topics and
BARRICK YEAR-END 2021
32
MANAGEMENT’S DISCUSSION AND ANALYSIS

key areas of concern are shared and provided as part of our annual ESG materiality assessment.

Human rights
In December 2021, coinciding with the United Nations International Human Rights Day, we published our first, post-Merger, Human Rights Report. This report details how we embed our human rights policy throughout the organization and our commitment to respect human rights at every site. We have zero tolerance for human rights violations wherever we operate. We avoid causing or contributing to human rights violations and facilitate access to remedies.
The report follows the United Nations Guiding Principles (“UNGP”) Reporting Framework and described some of the challenges faced and lessons learned as we work to continually improve our human rights performance.
Our commitment to respect human rights is fulfilled on the ground via our Human Rights Program, the fundamental principles of which include: monitoring and reporting, due diligence, training, and disciplinary action and remedy.
We continue to provide security and human rights training to security forces across our sites. In the first quarter of 2022, we will publish our annual Voluntary Principles on Security and Human Rights Plenary Report, which will include a full detailed report as part of a three-year reporting cycle.

Safety
We are committed to the safety, health and well-being of our people, their families and the communities in which we operate. Our safety vision is “Every person going home safe and healthy every day.”
To achieve this, we continue to implement our “Journey to Zero Harm” initiative. This is focused on engagement with our workforce through Visible Felt Leadership, and by aligning and improving our standards across the Group, ensuring accountability to our safety commitments, and ensuring our employees are fit for duty.
We report our safety performance quarterly as both part of our E&S Committee meetings and to the Board's ESG & Nominating Committee. Our safety performance is a regular standing agenda item on our weekly Executive Committee review meeting.
We achieved our target to certify all operational sites to the internationally recognized ISO 45001 standard by the end of 2021.
Safety key performance indicators for the fourth quarter of 2021 include our Lost Time Injury Frequency Rate ("LTIFR")8 at 0.42 and our Total Recordable Injury Frequency Rate ("TRIFR")8 at 1.57. Our annual indicators for 2021 was LTIFR at 0.38, a 12% increase from 2020, and TRIFR at 1.47, which was an improvement of 13% from 2020.
The indicator that is the most meaningful, however, is the two fatalities we had in 2021. The first was on July 14, 2021, when an incident occurred at Hemlo which resulted in the tragic fatality of an employee from our underground mining contractor. The second was on September 1, 2021, when an incident at Tongon resulted in the tragic fatality of a drilling contractor. Unfortunately, we also had an incident on January 17, 2022 at North Mara, which resulted in a fatality of a contractor. A full investigation into the cause of the fatality is ongoing.
We have held numerous regional and group workshops to strategize and improve our safety approach and action plans. One such initiative to improve safety is its consideration as part of the recruitment and retention
process. Safety starts with our people and their behavior, and this means ensuring we attract people who live and demonstrate safe behavior and do not compromise on safety standards.
We continue to focus on safeguarding our employees and operations from Covid-19. Strict Covid-19 screening and prevention measures remain in place at our mine gates, including ‘test to enter’ policies at some higher risk operations. We have undertaken extensive vaccination awareness campaigns to encourage uptake of the vaccines by our employees. To date, approximately 59% of our employees are fully vaccinated, and a further 8% are partially vaccinated.

Social
We regard our host communities and countries as important partners in our business. Our sustainability policies commit us to transparency in our relationships with host communities, government authorities, the public and other key stakeholders. Through these policies, we commit to conducting our business with integrity and with absolute opposition to corruption. We require our suppliers to operate ethically and responsibly as a condition of doing business with us.

Community and economic development
Our commitment to social and economic development is set out in our overarching Sustainable Development and Social Performance policies. The approach is encapsulated in three concepts:
Paying our fair share of taxes: the taxes, royalties and dividends we pay provide significant income for our host countries and help fund vital services and infrastructure. We report all government and tax payments transparently, primarily through the reporting mechanism of the Canadian Extractive Sector Transparency Measures Act (“ESTMA”). In addition, we plan to publish our first annual tax contribution report in April 2022 covering the 2021 year, which will highlight our overall contribution to our host countries. Our comprehensive tax policy covers governance, tax risk management, tax planning principles, compliance, relationships with tax authorities as well as transparency and disclosure.
Prioritizing local hiring and buying: the employment opportunities created by our presence in a community is one of our largest social and economic contributions to our host communities and countries. Our aim is to maximize this contribution. We work to identify and nurture local talent at every level of our business through a range of skills and formal training. We also strive to maximize the value that stays in our communities and countries of operation through procurement processes that prioritize local companies, followed by those from the larger region or host country.
Investing in community-led development initiatives: we believe that no one knows the needs of local communities better than the communities themselves. We have community development committees (“CDCs”) established at every operating site. The role of the CDC is to allocate the community investment budget to those projects and initiatives most needed and desired by local stakeholders. Each CDC is elected and made up of a mix of local leaders, community members, as well as representatives from local women and youth groups.
For 2021, we invested approximately $26.5 million in local community development projects. Some community initiatives include the following:
At NGM, a Cultural Awareness video was created in partnership with the local Tribes to better
BARRICK YEAR-END 2021
33
MANAGEMENT’S DISCUSSION AND ANALYSIS

educate the workforce on cultural awareness. This video was a request from Tribal Leaders in our partnering communities due to the mine sites being located on or around traditionally inhabited lands of the Western Shoshone, Northern Paiute, and Goshute people. The video will be used to train NGM's entire workforce on an annual basis.
At Veladero, seven water treatment plants were commissioned in Bella Vista and Villa Iglesia to provide potable water for the communities. Beneficiaries include over 7,000 people from Iglesia.
At Loulo-Gounkoto, we undertook a socioeconomic study and validation workshop to understand community needs and identify major projects for development. Outputs will be used to issue a 5-year development plan for Kenieba.

Environment
Being responsible stewards of the environment is the third pillar of our sustainability strategy. Environmental matters such as how we use water, prevent incidents, manage tailings, respond to a changing climate, and protection of biodiversity are key focuses.
We maintained our strong track record of stewardship and did not record any Class 19 environmental incidents throughout 2021.

Climate Change
The Board’s ESG & Nominating Committee is responsible for overseeing Barrick’s policies, programs and performance relating to the environment, including climate change. The Audit & Risk Committee assists the Board in overseeing the Group’s management of enterprise risks as well as the implementation of policies and standards for monitoring and mitigating such risks. Climate change is built into our formal risk management process, outputs of which are regularly reviewed by the Audit & Risk Committee.
Barrick’s climate change strategy has three pillars: (1) identify, understand and mitigate the risks associated with climate change; (2) measure and reduce our impacts on climate change; and (3) improve our disclosure on climate change. Our climate disclosure is based on the recommendations of the Task Force for Climate-related Financial Disclosures ("TCFD").
We are also acutely aware of the impacts that climate change has on our host communities and countries, particularly developing nations who are often most vulnerable. As the world economy transitions to renewable power, it is imperative that developing nations are not left behind. As a responsible business, we have focused our efforts on building resilience in our host communities and countries, just as we do for our business.

Identify, understand and mitigate the risks associated with climate change
We identify and manage risks, build resilience to climate change, as well as position ourselves for new opportunities. Climate change-related factors continue to be incorporated into our formal risk assessment process. We have identified several climate-related risks and opportunities for our business including: physical impacts of climate change; an increase in regulations that seek to address climate change; and an increase in global investment in innovation and low-carbon technologies. The risk assessment process includes scenario analysis, which is being rolled out to all sites with an initial focus on our Tier One Gold Assets1, to assess site-specific climate related risks and opportunities.

Measure and reduce the Group’s impact on climate change
Mining is an energy-intensive business, and we understand the important link between energy use and greenhouse gas (“GHG”) emissions. By measuring and effectively managing our energy use, we can reduce our GHG emissions, achieve more efficient production, and reduce our costs.
We have climate champions at each site that are tasked with identifying roadmaps and assessing feasibility for our GHG emissions reductions and carbon offsets for hard-to-abate emissions. Any carbon offsets that we pursue must have appropriate socioeconomic and/or biodiversity benefits. We have published an achievable emissions reduction roadmap and continue to assess further reduction opportunities across our operations.

Improve our disclosure on climate change
As part of our commitment to improve our disclosure on climate change, we complete the annual CDP (formerly known as the Carbon Disclosure Project) Climate Change and Water Security questionnaires. This ensures our investor-relevant water use, emissions and climate data is widely available.
Our CDP scores were positive and although we maintained our B score for Water Security, we improved our Climate Change score a full grade from a C in 2020 to B in 2021. We are also pleased to score as industry leaders for several indicators. For Climate Change, we scored as industry leaders for Governance, Emission Reduction Initiatives, as well as Scope 1 & 2 Emissions. Similarly we achieved industry leader scores in Water-Related Opportunities, Integrated Approach to Environmental Challenges and Business Impacts for Water Security.

Emissions
As detailed in our 2020 Sustainability Report, Barrick’s GHG emissions reduction target is for a minimum 30% reduction by 2030, while maintaining a steady production profile. The basis of this reduction is against a 2018 baseline of 7,541 kt CO2-e.
Our emissions reduction target is grounded in climate science and has a detailed pathway for achievement. Our target is not static and will be updated as we continue to identify and implement new GHG reduction opportunities.
Ultimately, our vision is net zero GHG emissions by 2050, achieved primarily through GHG reductions, with some offsets for hard-to-abate emissions. Site-level plans to improve energy efficiency, integrate clean and renewable energy sources and reduce GHG emissions will also be strengthened, and we plan to supplement our corporate emissions reduction target with context-based site-specific emissions reduction targets.
Our GHG emissions for 2021 were 7,096kt CO2-e10 (Scope 1 and Scope 2: Market-Based), representing a 5.9% reduction from our 2018 baseline. The reduction in our market-based emissions are due to the extensive effort by Nevada Gold Mines to implement Power Purchase Agreements that prioritize renewable energy and maximize power usage from our own power plants.

Water
Water is a vital and increasingly scarce global resource. Managing and using water responsibly is one of the most critical parts of our sustainability strategy. Our commitment to responsible water use is codified in our Environmental Policy. Steady, reliable access to water is critical to the effective operation of our mines. Access to water is also a fundamental human right.
BARRICK YEAR-END 2021
34
MANAGEMENT’S DISCUSSION AND ANALYSIS

In 2021, we reviewed our definition of water stress against global reporting, disclosure frameworks and tools which helped define our operations that are exposed or potentially exposed to water stress, either in terms of water scarcity or surplus water. Understanding the water stress in the regions we operate enables us to better understand the risks and manage our water resources through site-specific water balances, based on the International Council on Mining and Metals’ (“ICMM”) Water Accounting Framework, aimed at minimizing our water withdrawal and maximizing water reuse and recycling within our operations.
We include each mine’s water risks in its operational risk register. These risks are then aggregated and incorporated into the corporate risk register. Our identified water-related risks include: (1) managing excess water in regions with high rainfall; (2) maintaining access to water in arid areas and regions prone to water scarcity; and (3) regulatory risks related to permitting limits as well as municipal and national regulations for water use.
We are pleased that our 2021 water recycling and reuse rate of 83% was above our annual target of 80%.

Tailings
We are committed to ensuring our tailings storage facilities ("TSFs") meet global best practices for safety. Our TSFs are carefully engineered and regularly inspected, particularly those in regions with high rainfall and seismic events.
We continue to progress our compliance to the Global Industry Standard for Tailings Management ("GISTM"), and have completed the consequence classification for a majority of sites. Sites are currently working to complete a gap assessment against the GISTM using the Conformance Protocols developed by the ICMM.
Since we assumed operating control of the mines previously managed by Acacia Mining plc (“Acacia”) in 2019, a critical project has been the corrective management and responsible operations of the North Mara TSF. At the time we assumed operational control, the TSF had 7.5 million cubic meters of water and was operating well above its design capacity; an Environmental Protection Order had been issued to Acacia by the authorities to close the TSF. To safely reopen the TSF, one of the commitments agreed between Barrick and the Government of Tanzania was to reduce the water in the TSF to below 800,000 cubic meters by the end of 2021. After an exceptional team effort, approximately $60 million in capital investment for water treatment, as well as extensive studies, we achieved the target ahead of schedule.

Biodiversity
Biodiversity underpins many of the ecosystem services on which our mines and their surrounding communities depend. If improperly managed, mining and exploration activities have the potential to negatively affect biodiversity and ecosystem services. We work to proactively manage our impact on biodiversity and strive to protect the ecosystems in which we operate. Wherever possible, we aim to achieve a net neutral biodiversity impact, particularly for ecologically sensitive environments.
We established a target to develop Biodiversity Action Plans (“BAPs”) for all our operational sites by the end of 2021. We achieved this target and are in the process of implementing these BAPs, which outline our strategy to achieve net-neutral impacts and associated management plans. In 2021, we disclosed our first CDP questionnaire for forests, which incorporates biodiversity disclosures. Although the CDP forests questionnaires are not yet scored for the metals and mining industry, we feel biodiversity
disclosures are imperative for the industry and are currently under-reported.
We have made progress in developing conservation and offset projects, including sagebrush and mule habitats in Nevada, forestry conservation in Zambia and establishing a partnership at the Fina Reserve in Mali.

Reserves and Resources11
For full details of our mineral reserves and mineral resources, refer to page 129 of the Fourth Quarter 2021 Report.

Gold Reserves
Barrick’s 2021 mineral reserves are estimated using a gold price assumption of $1,200 per ounce and are reported to a rounding standard of two significant digits, both unchanged from 2020. As of December 31, 2021, Barrick’s proven and probable gold reserves were 69 million ounces12 at an average grade of 1.71 g/t, compared to 68 million ounces13 at an average grade of 1.66 g/t in 2020. Year-over-year, grade has increased by approximately 3%, while reserves have increased by approximately 1.5%. Notably, this year-over-year change incorporates the net removal of 0.91 million ounces from mineral reserves, due to the expected change in our equity interest in Porgera from 47.5% to 24.5%, partially offset by the net impact of the asset exchange of Lone Tree to i-80 Gold for the remaining 40% of South Arturo that NGM did not already own. Excluding the impact of these changes, reserve replacement was 150% of depletion. Similarly, when adjusting for the above ownership changes, the net increase in reserves year-over-year is approximately 3%.
Mineral reserve growth, net of depletion, was achieved at three of Barrick’s Tier One Gold Assets1 - Kibali, Cortez and Turquoise Ridge - while Bulyanhulu, North Mara, and Phoenix also all achieved this milestone. This further moves the Bulyanhulu and North Mara mines closer to potential Tier One status as a combined complex, while the Covid-19 pandemic continued to impact drilling activities at Veladero. Our core focus on geological modeling is delivering results with year-over-year mineral reserves growing, net of depletion.
During 2021, the Company converted a net of 8.1 million ounces to attributable proven and probable reserves. Compared to mining depletion of 5.4 million ounces, this represents an impressive 150% replacement of ounces.
The Africa & Middle East region converted a net of 3.1 million ounces to attributable proven and probable reserves, before depletion, with contributions from Loulo-Gounkoto, Kibali, North Mara, Bulyanhulu and Tongon. At Loulo-Gounkoto, this was principally from extensions at the Yalea, Gara and Gounkoto underground mines. At Kibali, this was driven by the addition and expansion of multiple open pits, together with the Karagba, Chauffeur and Durba (“KCD”) underground extensions of the 3,000 and 9,000 lodes. Given the year-over-year growth from the open pits, the average grade of proven and probable mineral reserves at Kibali has decreased from 3.84 g/t to 3.60 g/t. However, this growth continues to support a balanced and flexible underground and open-pit feed blend. We have now achieved a similar optimized and balanced life of mine profile at North Mara, with conversions in 2021 driven by extensions to the Gokona, Gena and Rama pits.
The North America region converted a net of 5.3 million ounces to attributable proven and probable reserves, primarily from Cortez and Turquoise Ridge, before depletion. At Cortez, the increase in reserves was driven by the completion of the Goldrush Underground feasibility study, while additions at Turquoise Ridge were driven by
BARRICK YEAR-END 2021
35
MANAGEMENT’S DISCUSSION AND ANALYSIS

improvements to geological models. The core focus on improving geological models is a key contributor to mineral resource and reserve growth at Nevada Gold Mines.
In the Latin America & Asia Pacific region, there was a net reduction of 0.3 million ounces before depletion in 2021, mainly as the drilling required to convert resources into reserves was unable to be completed due to the impact of Covid-19 at Veladero. The potential for reserve conversion remains at Pueblo Viejo, where a significant indicated resource base requires the completion of a tailings expansion study to support the potential conversion to reserves. For further information on the Pueblo Viejo Plant Expansion and Mine Life Extension Project, please refer to the Growth Project Updates section of this MD&A.

ATTRIBUTABLE CONTAINED GOLD RESERVES12,13,a (Moz)
goldreserves.jpg
a Figures rounded to two significant digits.

Gold Resources
In 2021, all mineral resources were estimated using a gold price assumption of $1,500 per ounce, unchanged from 2020. Barrick’s mineral resources for 2021 continue to be reported on an inclusive basis, incorporating all areas that form mineral reserves. All open-pit mineral resources are contained within a Whittle shell, while all underground mineral resources are contained within optimized mining shapes. Excluding the impact of the expected change in equity interest at Porgera, the disposal of Lagunas Norte, and the South Arturo asset exchange with i-80 Gold, Barrick’s total attributable mineral resources grew in 2021 by an impressive 126%, net of depletion. This growth in total mineral resources stems from a combination of our increased confidence in our geological models as well as a more integrated approach to our mine planning, resulting in improved optimizations that ultimately support increased mineral resource conversion. In particular, this is reflected in both the open pit and underground interface studies of the Gokona deposit at North Mara, and the extension of the Deep West zone at Bulyanhulu and across our portfolio at Nevada Gold Mines. This integrated planning approach continues to gather momentum.
Growth in total attributable mineral resources for North America, net of depletion, was encouraging. At Carlin, optimized pit shells at both Gold Quarry and South Arturo delivered year-over-year total open-pit resource growth at consistent grades. Notably at Gold Quarry, the mineral resource estimates were further optimized based on process routing options only made possible with the multiple processing facilities available following the formation of NGM. Within Leeville at Carlin, drilling at Turf and West Leeville, along with improved mine designs, delivered total mineral resource growth, net of depletion. Drilling at the Ren and North Leeville underground projects delivered maiden additions to the resource base, and are expected to be growth areas for Carlin into the future with mineralization open in all directions. At Cortez, total mineral
resource growth was principally driven by the Robertson open pit and to a lesser extent, updated geological modeling and mine design improvements at Goldrush, Crossroads and Cortez Hills Underground. A portion of inferred resources were upgraded to the indicated category at Robertson which, together with year-over-year total mineral resource growth, supports our plan for the deposit to contribute meaningfully to Cortez’s production profile starting in 2025.
Challenging operating environments throughout Latin America due to the Covid-19 pandemic impacted drilling activities in 2021. However, we continued our focus on geological and metallurgical studies to grow our understanding of Veladero, Pascua-Lama and Alturas-Del Carmen over the course of the year.
Barrick’s resources are reported to a rounding standard of two significant digits, unchanged from 2020. As of December 31, 2021, Barrick’s attributable measured and indicated resources were 160 million ounces12 at an average grade of 1.50 g/t Au. This compares to measured and indicated resources of 160 million ounces13 at an average grade of 1.52 g/t Au in 2020. As of December 31, 2021, Barrick’s attributable inferred resources were 42 million ounces12 at an average grade of 1.3 g/t Au. This compares to inferred resources in 2020 of 43 million ounces13 at an average grade of 1.4 g/t Au.

Copper
Copper mineral reserves for 2021 are estimated using a copper price of $2.75 per pound and mineral resources are estimated at $3.50 per pound, both unchanged from 2020. Copper reserves and resources for 2021 are reported to a rounding standard of two significant digits, also unchanged from 2020.
As of December 31, 2021, attributable proven and probable copper mineral reserves were 12 billion pounds12 at an average grade of 0.38%. This compares to 13 billion pounds13 at an average grade of 0.39% in the prior year.
Attributable measured and indicated copper mineral resources were 24 billion pounds12 at an average grade of 0.35%, and inferred copper mineral resources were 2.1 billion pounds12 at an average grade of 0.2% as of December 31, 2021. This compares to prior year attributable measured and indicated copper mineral resources of 25 billion pounds12 at an average grade of 0.36%, and inferred copper mineral resources of 2.2 billion pounds13 at an average grade of 0.2%.
2021 mineral reserves and mineral resources are estimated using the combined value of gold, copper and silver. Accordingly, mineral reserves and mineral resources are reported for all assets where copper or silver is produced and sold as a primary product or a by-product.

ATTRIBUTABLE CONTAINED COPPER RESERVES12,13,a (Blb)
cureserves.jpg
a Figures rounded to two significant digits.
BARRICK YEAR-END 2021
36
MANAGEMENT’S DISCUSSION AND ANALYSIS

Key Business Developments
2021 Highlights
Gold and copper production achieves guidance for third consecutive year with the Africa & Middle East and Latin America & Asia Pacific regions at the top end of guidance;
Record $1.4 billion in total cash returns paid to shareholders in 2021, inclusive of a $750 million return of capital distribution;
Announcement of performance dividend policy and share buyback program for up to $1.0 billion starting in 2022, further demonstrates our strong commitment to return surplus funds to shareholders;
Disciplined operational execution in achieving production guidance highlights benefit and flexibility of six Tier One Gold Assets1, notwithstanding a mechanical mill failure at Carlin;
Our decentralized and agile management structure mitigated the flow-through challenges created by the Covid-19 pandemic such as supply chain pressures and tighter labor markets;
Kibali paid a total of $200 million in dividends over the course of the second half of 2021, providing a mechanism for repatriation of cash from the Democratic Republic of Congo;
Further optimization and simplification of the North America portfolio with the successful asset exchange of Lone Tree to i-80 Gold Corp. for the remaining 40% of South Arturo that Nevada Gold Mines did not already own
Successfully completed the sale of Lagunas Norte as well as the sale or option of seven legacy closure properties over the past 18 months, in line with our strategy of divesting non-core assets and portfolio optimization
Achieved zero debt, net of cash at the end of 2021 for the second straight year-end, notwithstanding record cash returns to shareholders during the year of $1.4 billion
Further ounces added to our 10-year production outlook, highlighting the quality of our portfolio and ability to generate strong cash flow well into the future;
Attributable gold reserves replaced 150% of depletion, before acquisition and equity changes related to South Arturo and Porgera, at a higher grade;
Future reserve replacement and 10-year production outlook reinforced by a robust pipeline of advanced exploration targets;
Generative work drives a newly invigorated exploration team into under-explored and prospective new frontiers;
Reinforced our industry-leading approach to ESG by further enhancement to our Sustainability Scorecard, designed to ensure transparent reporting that aligns key performance indicators against strategic priorities; and
Completed the implementation of SAP at our operations throughout the Americas and Africa, which has allowed us to significantly simplify our systems landscape by decommissioning several legacy Enterprise Resource Planning (ERP) platforms.

Covid-19 pandemic
Barrick continues to work closely with our local communities on managing the impacts of the Covid-19 pandemic on our people and business. Barrick has a strong culture of caring for the welfare of its employees and communities.  Our well-established prevention practices and procedures, as well as the experience we gained in past years from managing two Ebola outbreaks around our African operations, has assisted us with managing this unprecedented challenge.  We continue to work actively in supporting government
responses to the Covid-19 pandemic including vaccination programs, financial assistance as well as using our supply chain to secure key supplies for the benefit of the communities in which we operate. 
Our preference for employing local nationals where we operate rather than expatriates, means that we are not dependent upon a workforce traveling to site on a regular basis from other parts of the globe. We continue to enforce certain operating procedures to respond to Covid-19, and to date, our operations have not been significantly impacted by the pandemic with the exception of Veladero, where the commissioning of the Phase 6 leach pad was delayed to the second quarter of 2021 following movement restrictions implemented by the government of Argentina during the construction phase. Hemlo also experienced a slower ramp-up of underground development in 2021 due to Covid-19 movement restrictions which impacted production.
Our ongoing vigilance around social distancing, screening and contact tracing has allowed our sites to continue to produce and sell their production as well as keep our people and local communities safe at the same time. These actions have minimized the impacts of the pandemic at our operations and facilitated the continued delivery of strong operating cash flow since the onset of the pandemic. 
We believe that our focus on strengthening our balance sheet in recent years has given us the financial flexibility to endure any short-term impacts to our operations, affording us the opportunity to participate in our industry's inevitable consolidation.  We have $5.3 billion in cash, an undrawn $3.0 billion credit facility and no significant debt repayments due until 2033, providing us with sufficient liquidity to execute on our strategic goals. 
Although the global rollout of vaccination programs is progressing, we recognize the situation remains dynamic. We continue to monitor developments around the world and believe we have positioned Barrick as best we can to weather the storm and take advantage of any value opportunities should they present themselves.

Performance Dividend Policy
At the February 15, 2022 meeting, the Board of Directors approved a performance dividend policy that will enhance the return to shareholders when the Company’s liquidity is strong. In addition to our base dividend, the amount of the performance dividend on a quarterly basis will be based on the amount of cash, net of debt, on our consolidated balance sheet at the end of each quarter as per the schedule below. This performance dividend calculation will commence after our March 31, 2022 consolidated balance sheet, with a potential payment in the second quarter of the year.

Performance Dividend Level Threshold Level Quarterly Base Dividend Quarterly Performance Dividend Quarterly Total Dividend
Level I Net cash <$0 $0.10
per share
$0.00
per share
$0.10
per share
Level II Net cash
>$0 and <$0.5B
$0.10
per share
$0.05
per share
$0.15
per share
Level III Net cash
>$0.5B and <$1B
$0.10
per share
$0.10
per share
$0.20
per share
Level IV Net cash >$1B $0.10
per share
$0.15
per share
$0.25
per share
BARRICK YEAR-END 2021
37
MANAGEMENT’S DISCUSSION AND ANALYSIS

The declaration and payment of dividends is at the discretion of the Board of Directors, and will depend on the company’s financial results, cash requirements, future prospects, the number of outstanding common shares, and other factors deemed relevant by the Board.

Share Buyback Program
At the February 15, 2022 meeting, the Board of Directors authorized a share buyback program for the repurchase of up to $1.0 billion of the Company’s outstanding common shares over the next 12 months.
The actual number of common shares that may be purchased, if any, and the timing of any such purchases, will be determined by Barrick based on a number of factors, including the Company’s financial performance, the availability of cash flows, and the consideration of other uses of cash, including capital investment opportunities, returns to shareholders, and debt reduction.
The repurchase program does not obligate the Company to acquire any particular number of common shares, and the repurchase program may be suspended or discontinued at any time at the Company’s discretion.

Return of Capital
At the Annual and Special Meeting on May 4, 2021, shareholders approved a $750 million return of capital distribution. This distribution was derived from a portion of the proceeds from the divestiture of Kalgoorlie Consolidated Gold Mines in November 2019 and from other recent dispositions made by Barrick and its affiliates in line with our strategy of focusing on our core assets. The total return of capital distribution was effected in three equal tranches of $250 million. The first tranche was paid on June 15, 2021, to shareholders of record at the close of business on May 28, 2021. The second tranche was paid on September 15, 2021, to shareholders of record at the close of business on August 31, 2021. The third tranche was paid on December 15, 2021, to shareholders of record at the close of business on November 30, 2021.
This return of capital distribution demonstrated Barrick’s commitment to return surplus funds to shareholders as outlined in the strategy stated at the time of the Randgold merger announcement in September 2018. Since that time, the quarterly dividend has more than tripled and together with this capital distribution, established one of the industry's leading returns for shareholders in 2021.

Sale of Lagunas Norte
On February 16, 2021, Barrick announced it had entered into an agreement to sell its 100% interest in the Lagunas Norte gold mine in Peru to Boroo Pte Ltd. ("Boroo") for total consideration of up to $81 million, with $20 million of cash consideration on closing, additional cash consideration of $10 million payable on the first anniversary of closing and $20 million payable on the second anniversary of closing, a 2% net smelter return royalty, which may be purchased by Boroo for a fixed period after closing for $16 million, plus a contingent payment of up to $15 million based on the two-year average gold price. An impairment reversal of $86 million was recognized in the first quarter of 2021. Refer to note 21 of the Financial Statements for further details. The transaction closed on June 1, 2021 and we recognized a gain on sale of $4 million in the second quarter of 2021, based on a final fair value of consideration of $65 million. We remain contractually liable for all tax
matters that existed prior to our divestiture until these matters are resolved.

Acquisition of South Arturo Non-Controlling Interest
On September 7, 2021, Barrick announced it had entered into a definitive asset exchange agreement (the "Exchange Agreement") with i-80 Gold Corp. ("i-80 Gold") to acquire the 40% interest in South Arturo that NGM did not already own, in exchange for the Lone Tree and Buffalo Mountain properties and infrastructure, which were in care and maintenance at the time. The exchange transaction closed on October 14, 2021.
The Exchange Agreement provides for payment to NGM of contingent consideration of up to $50 million based on mineral resources from the Lone Tree property. In connection with the asset exchange, NGM also entered into toll-milling agreements providing i-80 Gold with interim processing capacity at NGM’s autoclave facilities until the earlier of the three-year anniversary of the asset exchange and the date on which the Lone Tree facility is operational, and separately at NGM’s roaster facilities for a 10-year period, which was assigned a fair value of $nil. In addition, each party assumed the environmental liabilities and closure bonding for their acquired properties. In conjunction with the closing of the transaction, on October 14, 2021, NGM subscribed for $48 million in common shares of i-80 Gold.
We assigned a fair value of $175 million to the transaction and recognized a gain of $205 million in the fourth quarter of 2021 in relation to the disposition of Lone Tree. Lone Tree was in a net liability position, which resulted in a gain that exceeded the fair value. In addition, we recognized a loss of $85 million in equity in the fourth quarter, representing our share of the difference between the carrying value of the South Arturo non-controlling interest and the fair value of the transaction.

Porgera Special Mining Lease Extension
On April 9, 2021, BNL signed a binding Framework Agreement with the Independent State of Papua New Guinea (“PNG”) and Kumul Minerals Holdings Limited (“Kumul Minerals”), a state-owned mining company, setting out the terms and conditions for the reopening of the Porgera mine. On February 3, 2022, the Framework Agreement was replaced by the more detailed Porgera Project Commencement Agreement (the “Commencement Agreement”). The Commencement Agreement was signed by PNG, Kumul Minerals, BNL and its affiliate Porgera (Jersey) Limited on October 15, 2021, and it became effective on February 3, 2022, following signature by Mineral Resources Enga Limited (“MRE”), the holder of the remaining 5% of the original Porgera joint venture. The Commencement Agreement reflects the commercial terms previously agreed to under the Framework Agreement, namely that PNG stakeholders will receive a 51% equity stake in the Porgera mine, with the remaining 49% to be held by BNL or an affiliate. BNL is jointly owned on a 50/50 basis by Barrick and Zijin Mining Group. Accordingly, following the implementation of the Commencement Agreement, Barrick’s current 47.5% interest in the Porgera mine is expected to be reduced to a 24.5% interest as reflected in Barrick’s reserve and resource estimates for Porgera. BNL will retain operatorship of the mine. The Commencement Agreement also provides that PNG stakeholders and BNL and its affiliates will share the economic benefits derived from the reopened Porgera Mine on a 53% and 47% basis over the remaining life of mine, respectively, and that the Government of PNG will retain the
BARRICK YEAR-END 2021
38
MANAGEMENT’S DISCUSSION AND ANALYSIS

option to acquire BNL’s or its affiliate’s 49% equity participation at fair market value after 10 years.
The provisions of the Commencement Agreement will be implemented, and work to recommence full mine operations at Porgera will begin, following the execution of a number of definitive agreements and satisfaction of a number of conditions. These include a Shareholders Agreement among the shareholders of a new Porgera joint venture company, an Operatorship Agreement pursuant to which BNL will operate the Porgera mine, as well as a Mine Development Contract to accompany the new Special Mining Lease (“SML”) that the new Porgera joint venture company will apply for following its incorporation. Under the terms of the Commencement Agreement, BNL will remain in possession of the site and maintain the mine on care and maintenance.
Porgera was excluded from our 2021 guidance and will also be excluded from our 2022 guidance. We expect to update our guidance following both the execution of all of the definitive agreements to implement the binding Commencement Agreement and the finalization of a timeline for the resumption of full mine operations. Refer to notes 21 and 35 to the Financial Statements for more information.


Global Exploration Executive Changes
On November 1, 2021, after 33 years of distinguished service, Rob Krcmarov transitioned from his position as Executive Vice-President, Exploration to a new role as technical advisor to Barrick. During his career with the Company, Mr. Krcmarov has led teams that have discovered and delineated multiple ore bodies for Barrick, including the world-class Goldrush deposit.
On November 3, 2021, Joel Holliday was appointed to the role of Executive Vice-President, Exploration, assuming leadership of Barrick’s global exploration team. Mr. Holliday has served as Barrick’s Senior Vice-President for Global Exploration since the merger with Randgold Resources. Prior to the merger, Mr. Holliday served as Randgold’s Group Executive Exploration.

North America Regional Management Changes
Catherine Raw, Chief Operating Officer, North America, decided to return to the United Kingdom and departed Barrick on December 31, 2021.
On January 6, 2022, Barrick announced that Christine Keener will be appointed Chief Operating Officer of the North America region commencing in February 2022. Ms. Keener has extensive experience in finance, strategy, commercial and operational roles. Prior to joining Barrick, Ms. Keener was Vice-President Operations, Europe and North America of Alcoa Corporation.


BARRICK YEAR-END 2021
39
MANAGEMENT’S DISCUSSION AND ANALYSIS

Outlook for 2022

Operating Division Guidance
Our 2021 actual gold and copper production, cost of sales, total cash costs6, all-in sustaining costs6 and 2022 forecast gold and copper production, cost of sales, total cash costs6 and all-in sustaining costs6 ranges by operating division are as follows: 
Operating Division 2021 attributable production (000s ozs)
2021 cost of salesa
($/oz)
2021 total cash costsb
($/oz)
2021 all-in sustaining costsb
($/oz)
2022 forecast attributable production (000s ozs)
2022 forecast cost of salesa ($/oz)
2022 forecast total cash costsb ($/oz)
2022 forecast all-in sustaining costsb ($/oz)
Gold
Carlin (61.5%)c
923 968 782 1,087 950 - 1,030 900 - 980 730 - 790 1,020 - 1,100
Cortez (61.5%)d
509 1,122 763 1,013 480 - 530 970 - 1,050 650 - 710 1,010 - 1,090
Turquoise Ridge (61.5%) 334 1,122 749 892 330 - 370 1,110 - 1,190 770 - 830 930 - 1,010
Phoenix (61.5%) 109 1,922 398 533 90 - 120 2,000 - 2,080 720 - 780 890 - 970
Long Canyon (61.5%) 161 739 188 238 40 - 50 1,420 - 1,500 540 - 600 540 - 620
Nevada Gold Mines (61.5%) 2,036 1,072 705 949 1,900 - 2,100 1,020 - 1,100 710 - 770 990 - 1,070
Hemlo 150 1,693 1,388 1,970 160 - 180 1,340 - 1,420 1,140 - 1,200 1,510 - 1,590
North America 2,186 1,115 752 1,020 2,100 - 2,300 1,050 - 1,130 740 - 800 1,040 - 1,120
Pueblo Viejo (60%) 488 896 541 745 400 - 440 1,070 - 1,150 670 - 730 910 - 990
Veladero (50%) 172 1,256 816 1,493 220 - 240 1,210 - 1,290 740 - 800 1,270 - 1,350
Porgera (47.5%)e
Latin America & Asia Pacific 660 1,028 622 969 620 - 680 1,140 - 1,220 700 - 760 1,040 - 1,120
Loulo-Gounkoto (80%) 560 1,049 650 970 510 - 560 1,070 - 1,150 680 - 740 940 - 1,020
Kibali (45%) 366 1,016 627 818 340 - 380 990 - 1,070 600 - 660 800 - 880
North Mara (84%) 260 966 777 1,001 230 - 260 820 - 900 670 - 730 930 - 1,010
Bulyanhulu (84%) 178 1,079 709 891 180 - 210 950 - 1,030 630 - 690 850 - 930
Tongon (89.7%) 187 1,504 1,093 1,208 170 - 200 1,700 - 1,780 1,220 - 1,280 1,400 - 1,480
Africa & Middle Eastf
1,591 1,092 740 968 1,450 - 1,600 1,070 - 1,150 720 - 780 950 - 1,030
Total Attributable to Barrickg,h,i
4,437 1,093 725 1,026 4,200 - 4,600 1,070 - 1,150 730 - 790 1,040 - 1,120
  2021 attributable production (M lbs)
2021 cost of salesa
($/lb)
2021 C1 cash costsb
($/lb)
2021 all-in sustaining costsb
($/lb)
2022 forecast attributable production
(M lbs)
2022 forecast cost of salesa
($/lb)
2022 forecast C1 cash costsb ($/lb)
2022 forecast all-in sustaining costsb ($/lb)
Copper
Lumwana 242 2.25 1.62 2.80 250 - 280 2.20 - 2.50 1.60 - 1.80 3.10 - 3.40
Zaldívar (50%) 97 3.19 2.38 2.94 100 - 120 2.70 - 3.00 2.00 - 2.20 2.50 - 2.80
Jabal Sayid (50%) 76 1.38 1.18 1.33 70 - 80 1.40 - 1.70 1.30 - 1.50 1.30 - 1.60
Total Copperh
415 2.32 1.72 2.62 420 - 470 2.20 - 2.50 1.70 - 1.90 2.70 - 3.00
a.Gold cost of sales per ounce is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share). Copper cost of sales per pound is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.Includes our share of South Arturo. On September 7, 2021, NGM announced it had entered into an Exchange Agreement with i-80 Gold to acquire the 40% interest in South Arturo that NGM did not already own in exchange for the Lone Tree and Buffalo Mountain properties and infrastructure. Operating results within our 61.5% interest in Carlin includes NGM’s 60% interest in South Arturo up until May 30, 2021, and 100% interest thereafter, reflecting the terms of the exchange transaction which closed on October 14, 2021. Please refer to page 37 for more details.
d.Includes Goldrush.
e.Porgera was placed on temporary care and maintenance in April 2020 and remains excluded from our 2022 guidance. We expect to update our guidance to include Porgera following both the execution of definitive agreements to implement the Commencement Agreement and the finalization of a timeline for the resumption of full mine operations. Refer to page 72 for further details.
f.2021 results include Buzwagi until the end of the third quarter of 2021.
g.Total cash costs and all-in sustaining costs per ounce include costs allocated to non-operating sites.
h.Operating division guidance ranges reflect expectations at each individual operating division, and may not add up to the company-wide guidance range total. The company-wide 2021 results and 2022 guidance ranges exclude Pierina, Lagunas Norte, Golden Sunlight, and include Buzwagi until the end of the third quarter of 2021. Some of these assets are producing incidental ounces while in closure or care and maintenance. Lagunas Norte was divested in June 2021.
i.Includes corporate administration costs.


BARRICK YEAR-END 2021
40
MANAGEMENT’S DISCUSSION AND ANALYSIS

Operating Division, Consolidated Expense and Capital Guidance
Our 2021 actual gold and copper production, cost of sales, total cash costs6, all-in sustaining costs6, consolidated expenses and capital expenditures and 2022 forecast gold and copper production, cost of sales, total cash costs6, all-in sustaining costs6, consolidated expenses and capital expenditures are as follows:
 
($ millions, except per ounce/pound  data)
2021 Guidancea
2021 Actual
2022 Guidancea
Gold production
Production (millions of ounces) 4.40 - 4.70 4,437 4.20 - 4.60
Gold cost metrics
Cost of sales - gold ($ per oz) 1,020 - 1,070 1,093 1,070 - 1,150
 Total cash costs ($ per oz)b
680 - 730 725 730 - 790
Depreciation ($ per oz) 300 - 330 326 300 - 330
 All-in sustaining costs ($ per oz)b
970 - 1,020 1,026 1,040 - 1,120
Copper production
Production (millions of pounds) 410 - 460 415 420 - 470
Copper cost metrics
Cost of sales - copper ($ per lb) 1.90 - 2.10 2.32 2.20 - 2.50
 C1 cash costs ($ per lb)b
1.40 - 1.60 1.72 1.70 - 1.90
Depreciation ($ per lb) 0.60 - 0.70 0.70 0.70 - 0.80
 All-in sustaining costs ($ per lb)b
2.00 - 2.20 2.62 2.70 - 3.00
Exploration and project expenses 280 - 320 287 310 - 350
Exploration and evaluation 230 - 250 186 180 - 200
Project expenses 50 - 70 101 130 - 150
General and administrative expenses ~190 151 ~180
Corporate administration ~130 118 ~130
 Stock-based compensationc
~60 33 ~50
Other expense (income) 80 - 100 (67) 50 - 70
Finance costs, net 330 - 370 355 330 - 370
Attributable capital expendituresd
Attributable minesite sustainingb,d
1,250 - 1,450 1,364 1,350 - 1,550
Attributable projectb,d
550 - 650 587 550 - 650
Total attributable capital expendituresd
1,800 - 2,100 1,951 1,900 - 2,200

a.Based on the communication we received from the Government of Papua New Guinea that the SML will not be extended, Porgera was placed on temporary care and maintenance on April 25, 2020. Due to the uncertainty related to the timing and scope of future developments on the mine’s operating outlook, our 2021 and 2022 guidance excludes Porgera. We expect to update our guidance to include Porgera following both the execution of definitive agreements to implement the Commencement Agreement and the finalization of a timeline for the resumption of full mine operations. Refer to page 72 for further details.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.2021 actual results are based on a US$19.00 share price and 2022 guidance is based on a one-month trailing average ending December 31, 2021 of US$19.23 per share.
d.Attributable capital expenditures are presented on the same basis as guidance, which includes our 61.5% share of Nevada Gold Mines, our 60% share of Pueblo Viejo, our 80% share of Loulo-Gounkoto, our 89.7% share of Tongon, our 84% share of North Mara and Bulyanhulu and our 50% share of Zaldívar and Jabal Sayid.

BARRICK YEAR-END 2021
41
MANAGEMENT’S DISCUSSION AND ANALYSIS

2022 Guidance Analysis
Estimates of future production, cost of sales per ounce7, total cash costs per ounce6 and all-in sustaining costs per ounce6 presented in this MD&A are based on mine plans that reflect the expected method by which we will mine reserves at each site. Actual gold and copper production and associated costs may vary from these estimates due to a number of operational and non-operational risk factors (see the “Cautionary Statement on Forward-Looking Information” on page 24 of this MD&A for a description of certain risk factors that could cause actual results to differ materially from these estimates).

Gold Production
We expect 2022 gold production to be in the range of 4.2 to 4.6 million ounces, anchored by stable year-over-year performance across our portfolio of six Tier One Gold Assets1, highlighting the importance of a world-class asset base in delivering consistent performance.
Our 2022 gold production guidance currently excludes Porgera. We expect to update our guidance following both the execution of all of the definitive agreements to implement the Commencement Agreement and the finalization of a timeline for the resumption of full mine operations. Refer to page 72 for more information.
This is due to the uncertainty related to the timing and scope of future operations at Porgera following the decision to place the mine on temporary care and maintenance on April 25, 2020 to ensure the safety and security of our employees and communities. As this matter continues to evolve, we will provide further updates in due course. We remain in constructive discussions with the Government of PNG and are optimistic about finding a solution to allow operations at Porgera to resume in 2022.
Outside of our Tier One Gold Assets1, we expect the following significant changes in year-over-year production. As previously disclosed, mining will cease at Long Canyon towards the middle of 2022, with residual leaching to commence thereafter. The focus at Long Canyon is now shifting to permitting Phase 2, which is expected to begin production in 2026. This is partially offset by Veladero, where we expect stronger performance in 2022 following the commissioning of Phase 6 in the second quarter of 2021. Furthermore, we expect higher production at Bulyanhulu in 2022 following the successful ramp-up of underground operations achieved at the end of 2021.
Across the four quarters of 2022, the Company’s gold production is expected to be the lowest in the first quarter mainly due to planned maintenance at Pueblo Viejo, Kibali and North Mara, as well as mine sequencing at Phoenix and Tongon. We expect the fourth quarter to be the strongest quarter for gold production as we continue to expect Goldrush to ramp up towards the end of the year, based on the issuance of a Record of Decision (“ROD”) in the second half of 2022, as well as higher grades from Phoenix and Tongon, and improved underground productivity at Hemlo.

Gold Cost of Sales per Ounce7
On a per ounce basis, cost of sales applicable to gold7, after removing the portion related to non-controlling interests, is expected to be in the range of $1,070 to $1,150 per ounce in 2022, compared to the 2021 actual result of $1,093 per ounce.
The expected increase compared to the 2021 guidance range reflects changes in the expected sales mix
with a higher contribution from Carlin and Veladero offset by a lower contribution from Pueblo Viejo and Long Canyon as described further in the Gold Total Cash Costs per Ounce6 section immediately below.

Gold Total Cash Costs per Ounce6
Total cash costs per ounce6 in 2022 is expected to be in the range of $730 to $790 per ounce, compared to the 2021 actual result of $725 per ounce.
The expected increase compared to the 2021 actual result partially reflects the full year impact of the new Mining Education Tax applied to gross proceeds in Nevada and changes in the expected sales mix as well as underlying cost inflation, particularly energy costs. The Nevada Mining Education Tax became effective on July 1, 2021.
In North America, our 2022 guidance for total cash costs per ounce6 for Nevada Gold Mines of $710 to $770 per ounce compares to the 2021 actual result of $705 per ounce. The new Mining Education Tax in Nevada is estimated to have a full year impact of approximately $17 per ounce for Nevada Gold Mines based on our $1,700 per ounce gold price assumption for 2022. Separately, the reduction in the contribution from Long Canyon offset by a higher contribution from Carlin, which has a comparatively higher cost on a per ounce basis, is expected to result in relatively higher costs for Nevada Gold Mines.
In Latin America & Asia Pacific, total cash costs per ounce6 at Pueblo Viejo are expected to be higher in 2022 due to lower grades compared to the prior year. This is in line with the mine and stockpile processing plan at Pueblo Viejo, as we near completion of the plant expansion project to offset the expected decline in grade. At Veladero, which is higher cost relative to Pueblo Viejo, the expected higher production and sales volumes will also drive an increase in total cash costs per ounce6 at the regional level due to the change in sales mix.
For Africa & Middle East, the expected change in sales mix is having a positive impact reflecting the closure of Buzwagi, partially offset by a higher contribution from Bulyanhulu as the underground operation was ramping up through the course of 2021. Total cash costs per ounce6 at Kibali in 2022 are expected to be consistent with the prior year, while expected to slightly increase at Loulo-Gounkoto. As previously disclosed, we have extended the life of mine at Tongon with the prospect of further extensions from our exploration programs, resulting in higher total cash costs per ounce6 due to higher mining costs associated with the satellite pits.

Gold All-In Sustaining Costs per Ounce6
All-in sustaining costs per ounce6 in 2022 is expected to be in the range of $1,040 to $1,120 per ounce, compared to the 2021 actual result of $1,026 per ounce. This is based on the expectation that minesite sustaining capital expenditures on a per ounce basis will be higher (refer to Capital Expenditure commentary below for further detail) and slightly higher total cash costs per ounce6.
The expected increase compared to the 2021 guidance range also reflects the enactment of the new Mining Education Tax in Nevada (effective from July 1, 2021), which was not included in our 2021 guidance, together with the same underlying drivers described in the Gold Total Cash Costs per Ounce6 section above.

BARRICK YEAR-END 2021
42
MANAGEMENT’S DISCUSSION AND ANALYSIS

Copper Production and Costs
We expect 2022 copper production to be in the range of 420 to 470 million pounds, compared to actual production of 415 million pounds in 2021. Production in the second half of 2022 is expected to be stronger than the first half, due to steadily increasing throughput at Lumwana. In addition, major maintenance at Zaldívar is scheduled in the first and third quarters of 2022.
In 2022, cost of sales applicable to copper7 is expected to be in the range of $2.20 to $2.50 per pound, in line with the actual result of $2.32 per pound for 2021. The expected increase compared to the 2021 guidance range reflects cost inflation and the impact of higher royalty expenses due to our copper price assumption increasing to $4.00 per pound (from $2.75 per pound in 2021). C1 cash costs per pound6 guidance of $1.70 to $1.90 per pound for 2022 is also in line with the 2021 actual result of $1.72 per pound. Copper all-in sustaining costs per pound6 guidance of $2.70 to $3.00 for 2022 compares to the actual result of $2.62 in 2021 and is based on the expectation that minesite sustaining capital expenditures on a per pound basis will be higher (refer to Capital Expenditures commentary below for further detail).

Exploration and Project Expenses
We expect to incur approximately $310 to $350 million of exploration and project expenses in 2022. This is an increase compared to our 2021 guidance range of $280 to $320 million and is higher than the 2021 actual result of $287 million.
Within this range, we expect our exploration and evaluation expenditures in 2022 to be approximately $180 to $200 million. This is consistent with the 2021 actual result of $186 million and will continue to support our resource and reserve conversion over the coming years.
We also expect to incur approximately $130 to $150 million of project expenses in 2022, compared to $101 million in 2021. Project expenses are mainly related to the ongoing site costs at Pascua-Lama as well as project evaluation costs across our portfolio, particularly in the Latin America & Asia Pacific region.

General and Administrative Expenses
In 2022, we expect corporate administration costs to be approximately $130 million which is unchanged from our 2021 guidance. This compares to the actual result for 2021 of $118 million as we expect travel and office-related costs to return to pre-pandemic levels in 2022.
Separately, stock-based compensation expense in 2022 is expected to be approximately $50 million based on a share price assumption of $19.23.


Finance Costs, Net
In 2022, net finance costs of $330 to $370 million primarily represents interest expense on long-term debt, non-cash interest expense relating to the gold and silver streaming agreements at Pueblo Viejo, and accretion, net of finance income. This guidance for 2022 is consistent with the actual result for 2021 of $355 million.

Capital Expenditures
Total attributable gold and copper capital expenditure for 2022 is expected to be in the range of $1,900 to $2,200 million. This compares to the actual spend for the 2021 year of $1,951 million. We continue to focus on the delivery of our project capital pipeline and expect attributable project capital expenditures6 to be in the range of $550 to $650 million in 2022, at around the same level as our actual expenditures of $587 million in 2021. This reflects the ongoing construction activities for the plant expansion and mine life extension project at Pueblo Viejo and to a lesser extent, our solar power initiatives at Loulo-Gounkoto and the construction of the Phase 7A leach pad expansion at Veladero. The remainder of expected project capital expenditures6 is mainly related to underground development and infrastructure at Goldrush, the third shaft project at Turquoise Ridge, open pit development at North Mara and optimization projects at Bulyanhulu.
Attributable minesite sustaining capital expenditure6 for 2022 is expected to be in the range of $1,350 to $1,550 million, which compares to the actual spend for 2021 of $1,364 million. The guidance range for 2022 is split between our gold assets ($1,000 to $1,200 million) and copper assets ($340 to $360 million). Compared to the prior year, minesite sustaining capital expenditures6 in 2022 are expected to increase at Lumwana by approximately $100 million, mainly related to higher waste stripping to allow for future production growth over the five-year outlook. At NGM, we are also expecting minesite sustaining capital expenditure6 to be approximately $100 million higher, driven by Cortez and Carlin. At Cortez, this is due to higher waste stripping, infrastructure and equipment related to Cortez Pits as well as tailings dam construction. At Carlin, the key drivers are the expansion of the Gold Quarry Roaster and conversion of the Goldstrike autoclave to a carbon-in-leach circuit.

Effective Income Tax Rate
Based on a gold price assumption of $1,700/oz, our expected effective tax rate range for 2022 is 27% to 32%. The rate is sensitive to the relative proportion of sales in high versus low tax jurisdictions, realized gold and copper prices, the proportion of income from our equity accounted investments and the level of non-tax affected costs in countries where we generate net losses.  


Outlook Assumptions and Economic Sensitivity Analysis
   2022 Guidance Assumption Hypothetical Change
Impact on EBITDAa (millions)
Impact on TCC and AISCa
  
Gold price sensitivity $1,700/oz +/- $100/oz
+/-$580
+/-$5/oz
Copper price sensitivity $4.00/lb
+/-$0.25/lb
+/- $60
+/-$0.01/lb
a.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.



BARRICK YEAR-END 2021
43
MANAGEMENT’S DISCUSSION AND ANALYSIS

Risks and Risk Management
Overview
The ability to deliver on our vision, strategic objectives and operating guidance depends on our ability to understand and appropriately respond to the uncertainties or “risks” we face that may prevent us from achieving our objectives. To achieve this, we:
Maintain a framework that permits us to manage risk effectively and in a manner that creates the greatest value;
Integrate a process for managing risk into all our important decision-making processes so that we reduce the effect of uncertainty on achieving our objectives;
Actively monitor key controls we rely on to achieve the Company’s objectives so they remain in place and are effective at all times; and
Provide assurance to senior management and relevant committees of the Board on the effectiveness of key control activities.

Board and Committee Oversight
We maintain strong risk oversight practices, with responsibilities outlined in the mandates of the Board and related committees. The Board’s mandate is clear on its responsibility for reviewing and discussing with management the processes used to assess and manage risk, including the identification by management of the principal risks of the business, and the implementation of appropriate systems to deal with such risks.
The Audit & Risk Committee assists the Board in overseeing the Company’s management of principal risks and the implementation of policies and standards for monitoring and modifying such risks, as well as monitoring and reviewing the Company’s financial position and financial risk management programs. The ESG & Nominating Committee assists the Board in overseeing the Company’s policies and performance for its environmental, health and safety, corporate social responsibility and human rights programs.

Management Oversight
Our weekly Executive Committee Review is the main forum for senior management to raise and discuss risks facing the operations and organization more broadly. At regularly scheduled meetings, the Board and the Audit & Risk Committee are provided with updates on the key issues identified by management at these weekly sessions.

Principal Risks
The following subsections describe some of our key sources of uncertainty and critical risk modification activities. The risks described below are not the only ones facing Barrick. Our business is subject to inherent risks in financial, regulatory, strategic and operational areas. For a more comprehensive discussion of those inherent risks, see “Risk Factors” in our most recent Form 40-F/Annual Information Form on file with the SEC and Canadian provincial securities regulatory authorities. Also see the “Cautionary Statement on Forward-Looking Information” on page 24 of this MD&A.

Financial position and liquidity
Our liquidity profile, level of indebtedness and credit ratings are all factors in our ability to meet short-and long-term financial demands. Barrick’s outstanding debt balances impact liquidity through scheduled interest and principal
repayments and the results of leverage ratio calculations, which could influence our investment grade credit ratings and ability to access capital markets. In addition, our ability to draw on our credit facility is subject to meeting its covenants. Our primary source of liquidity is our operating cash flow, which is dependent on the ability of our operations to deliver projected future cash flows. The ability of our operations to deliver projected future cash flows, as well as future changes in gold and copper market prices, either favorable or unfavorable, will continue to have a material impact on our cash flow and liquidity.

Key risk modification activities:
Continued focus on generating positive free cash flow by improving the underlying cost structures of our operations in a sustainable manner;
Disciplined capital allocation criteria for all investments, to ensure a high degree of consistency and rigor is applied to all capital allocation decisions based on a comprehensive understanding of risk and reward;
Preparation of budgets and forecasts to understand the impact of different price scenarios on liquidity, including our capacity to provide cash returns to shareholders, and formulate appropriate strategies;
Review of debt and net debt levels to ensure appropriate leverage and monitor the market for liability management opportunities; and
Other options available to the Company to enhance liquidity include drawing on our $3.0 billion undrawn credit facility, asset sales, joint ventures, or the issuance of debt or equity securities.

Improving free cash flow6 and costs
Our ability to improve productivity, drive down operating costs and reduce working capital remains a focus in 2022 and is subject to several sources of uncertainty. This includes our ability to achieve and maintain industry-leading margins by improving the productivity and efficiency of our operations.

Key risk modification activities:
Maximizing the benefit of higher gold prices through agile management and operational execution;
Weekly Executive Committee Review to identify, assess and respond to risks in a timely manner;
Enabling simplification and agile decision making through unification of business systems; and
A flat, operationally focused, agile management structure with a tenet in ownership culture.

Social license to operate
At Barrick, we are committed to building, operating, and closing our mines in a safe and responsible manner. To do this, we seek to build trust-based partnerships with host governments and local communities to drive shared long-term value while working to minimize the social and environmental impacts of our activities. Geopolitical risks such as resource nationalism and incidents of corruption are inherent in the business of a company operating globally. Past environmental incidents in the extractive industry highlight the hazards (e.g., water management, tailings storage facilities, etc.) and the potential consequences to the environment, community health and safety. Our ability to maintain compliance with regulatory and community obligations in order to protect the environment and our host communities alike remains one of our top priorities. Barrick also recognizes climate change
BARRICK YEAR-END 2021
44
MANAGEMENT’S DISCUSSION AND ANALYSIS

as an area of risk requiring specific focus and that reducing emissions to counter the causes of climate change requires strong collective action by the mining industry.
 
Key risk modification activities:
Our commitment to responsible mining is supported by a robust governance framework, including an overarching Sustainable Development Policy and related policies in the areas of Biodiversity, Social Performance, Occupational Health and Safety, Environment and Human Rights;
Implementation of a Sustainability Scorecard to track our sustainability performance using key performance indicators aligned to priority areas set out in our strategy;
Mandatory training on our Code of Business Conduct and Ethics as well as supporting policies which set out the ethical behavior expected of everyone working at, or with, Barrick;
We take a partnership approach with our host governments. This means we work to balance our own interests and priorities with those of our government partners, working to ensure that everyone derives real value from our operations;
Established Community Development Committees at each of our operational mines to identify community needs and priorities and to allocate funds to those initiatives most meaningful to the local community;
We open our social and environmental performance to third-party scrutiny, including through the ISO 14001 re-certification process, International Cyanide Management Code audits, and annual human rights impact assessments;
Our climate change strategy has three pillars: identify, understand and mitigate the risks associated with climate change; measure and reduce our impacts on climate change; and improve our disclosure on climate change;
We established site-specific emergency response plans as well as regional crisis management plans to manage any manifestation of Covid-19 in or near our mines globally; and
We continuously review and update our closure plans and cost estimates to plan for environmentally responsible closure and monitoring of operations.

Resources and reserves and production outlook
Like any mining company, we face the risk that we are unable to discover or acquire new resources or that we do not convert resources into production. As we move into 2022 and beyond, our overriding objective of growing free cash flow6 continues to be underpinned by a strong pipeline of organic projects and minesite expansion opportunities in our core regions. Uncertainty related to these and other opportunities exists (potentially both favorable and unfavorable) due to the speculative nature of mineral exploration and development as well as the potential for increased costs, delays, suspensions and technical challenges associated with the construction of capital projects.

Key risk modification activities:
Focus on responsible mineral resource management, continuously improve ore body knowledge, and add to reserves and resources;
Grow and invest in a portfolio of Tier One Gold Assets1, Tier Two Gold Assets2, Tier One Copper Assets3 and
Strategic Assets4 with an emphasis on organic growth to leverage our existing footprint; and
Invest in exploration across extensive land positions in many of the world’s most prolific gold districts.

Market Overview
The market prices of gold and, to a lesser extent, copper are the primary drivers of our profitability and our ability to generate free cash flow6 for our shareholders.

Gold
The price of gold is subject to volatile price movements over short periods of time and is affected by numerous industry and macroeconomic factors. During 2021, the gold price ranged from $1,677 per ounce to $1,959 per ounce. The average market price for the year of $1,799 per ounce represented an all-time annual high and an increase of 2% versus 2020.

AVERAGE MONTHLY SPOT GOLD PRICES
(dollars per ounce)
goldprices.jpg
During the year, the gold price remained strong as a result of the continued fiscal and monetary stimulus measures put in place due to the economic uncertainty caused by Covid-19, negative real interest rates, and growing inflation concerns, tempered by an increase in the trade-weighted value of the US dollar.

Copper
During 2021, London Metal Exchange (“LME”) copper prices traded in a wide range of $3.49 to an all-time high of $4.87 per pound, averaged an all-time annual high of $4.23 per pound, and closed the year at $4.40 per pound. Copper prices are significantly influenced by physical demand from emerging markets, especially China.
After copper prices fell to four-year lows in March 2020 due to initial concerns and near-term economic impacts from the spread of Covid-19, they subsequently rose over the next 12 months, reaching all-time highs in May 2021 due to a recovery in demand from China, low global stockpile levels, and the expected impact of global financial stimulus measures. Prices moderated thereafter, but remained robust through the remainder of 2021.


BARRICK YEAR-END 2021
45
MANAGEMENT’S DISCUSSION AND ANALYSIS

AVERAGE MONTHLY SPOT COPPER PRICES
(dollars per pound)
cuprices.jpg
We have provisionally priced copper sales for which final price determination versus the relevant copper index is outstanding at the balance sheet date. As at December 31, 2021, we recorded 45 million pounds of copper sales still subject to final price settlement at an average provisional price of $4.34 per pound. The impact to net income before taxation of a 10% movement in the market price of copper would be approximately $20 million, holding all other variables constant.

Currency Exchange Rates
The results of our mining operations outside of the United States are affected by US dollar exchange rates. We have exposure to the Argentine peso through operating costs at our Veladero mine, and peso denominated VAT receivable balances. In addition, we have exposure to the Canadian and Australian dollars, Chilean peso, Papua New Guinea kina, Peruvian sol, Zambian kwacha, Tanzanian shilling, Dominican peso, West African CFA franc, Euro, South African rand, and British pound through mine operating and capital costs.
Fluctuations in these exchange rates increase the volatility of our costs reported in US dollars. In 2021, the Australian dollar traded in a range of $0.70 to $0.80 against the US dollar, while the US dollar against the Canadian dollar, Argentine peso, and West African CFA franc ranged from $1.20 to $1.30, ARS 84 to ARS 103, and XOF 531 to XOF 586, respectively. Due to inflation pressures in Argentina and government actions, there was a continued weakening of the Argentine peso during the year. During 2021, we did not have any currency hedge positions, and are unhedged against foreign exchange exposures as at December 31, 2021 beyond spot requirements.

Fuel
For 2021, the price of West Texas Intermediate (“WTI”) crude oil traded in a wide range between $47 and $85 per barrel, with an average market price of $68 per barrel, and closed the year at $75 per barrel. Oil prices were significantly impacted by an increase in global economic activity during the year as well as constrained supply.
AVERAGE MONTHLY SPOT CRUDE OIL PRICE (WTI)
(dollars per barrel)
oilprices.jpg
During 2021, we did not have any fuel hedge positions, and are unhedged against fuel exposures as at December 31, 2021.

US Dollar Interest Rates
During March 2020, the US Federal Reserve lowered interest rates to a range of 0.00% to 0.25% as a result of the economic impacts of the spread of Covid-19 and kept rates at that level through the remainder of 2020 and all of 2021. There are growing expectations for increases in benchmark rates in 2022, but the scale of any changes to monetary policy will be dependent on the strength of economic recovery and inflation levels.
At present, our interest rate exposure mainly relates to interest income received on our cash balances ($5.3 billion at December 31, 2021); the mark-to-market value of derivative instruments; the carrying value of certain long-lived assets and liabilities; and the interest payments on our variable-rate debt ($0.1 billion at December 31, 2021). Currently, the amount of interest expense recorded in our consolidated statement of income is not materially impacted by changes in interest rates, because the majority of debt was issued at fixed interest rates. The relative amounts of variable-rate financial assets and liabilities may change in the future, depending on the amount of operating cash flow we generate, as well as the level of capital expenditures and our ability to borrow on favorable terms using fixed rate debt instruments. Changes in interest rates affect the accretion expense recorded on our provision for environmental rehabilitation and therefore would affect our net earnings.



BARRICK YEAR-END 2021
46
MANAGEMENT’S DISCUSSION AND ANALYSIS

Production and Cost Summary - Gold
For the three months ended For the years ended
12/31/21 9/30/21 Change 12/31/21 12/31/20  Change 12/31/19
Nevada Gold Mines (61.5%)a
Gold produced (000s oz) 604  495  22% 2,036 2,131  (4%) 2,218
Cost of sales ($/oz) 1,023  1,123  (9%) 1,072 1,029  4% 924
Total cash costs ($/oz)b
687  734  (6%) 705 702  0% 634
All-in sustaining costs ($/oz)b
893  975  (8%) 949 941  1% 828
Carlin (61.5%)c
Gold produced (000s oz) 295  209  41% 923 1,024  (10%) 968
Cost of sales ($/oz) 899  1,017  (12%) 968 976  (1%) 1,004
Total cash costs ($/oz)b
728  814  (11%) 782 790  (1%) 746
All-in sustaining costs ($/oz)b
950  1,124  (15%) 1,087 1,041  4% 984
Cortez (61.5%)d
Gold produced (000s oz) 169  130  30% 509 491  4% 801
Cost of sales ($/oz) 984  1,164  (15%) 1,122 958  17% 762
Total cash costs ($/oz)b
657  800  (18%) 763 678  13% 515
All-in sustaining costs ($/oz)b
853  1,065  (20%) 1,013 998  2% 651
Turquoise Ridge (61.5%)e
Gold produced (000s oz) 82  82  0% 334 330  1% 335
Cost of sales ($/oz) 1,194  1,169  2% 1,122 1,064  5% 846
Total cash costs ($/oz)b
819  788  4% 749 711  5% 585
All-in sustaining costs ($/oz)b
996  943  6% 892 798  12% 732
Phoenix (61.5%)f
Gold produced (000s oz) 25  31  (19%) 109 126  (13%) 56
Cost of sales ($/oz) 2,047  1,777  15% 1,922 1,772  8% 2,093
Total cash costs ($/oz)b
443  499  (11%) 398 649  (39%) 947
All-in sustaining costs ($/oz)b
614  582  5% 533 814  (35%) 1,282
Long Canyon (61.5%)f
Gold produced (000s oz) 33  43  (23%) 161  160  1% 58
Cost of sales ($/oz) 999  796  26% 739  869  (15%) 1,088
Total cash costs ($/oz)b
325  201  62% 188  236  (20%) 333
All-in sustaining costs ($/oz)b
384  251  53% 238  405  (41%) 681
Pueblo Viejo (60%)
Gold produced (000s oz) 107  127  (16%) 488  542  (10%) 590
Cost of sales ($/oz) 987  895  10% 896  819  9% 747
Total cash costs ($/oz)b
612  521  17% 541  504  7% 471
All-in sustaining costs ($/oz)b
858  728  18% 745  660  13% 592
Loulo-Gounkoto (80%)
Gold produced (000s oz) 126  137  (8%) 560  544  3% 572
Cost of sales ($/oz) 1,139  1,109  3% 1,049  1,060  (1%) 1,044
Total cash costs ($/oz)b
685  708  (3%) 650  666  (2%) 634
All-in sustaining costs ($/oz)b
822  1,056  (22%) 970  1,006  (4%) 886
Kibali (45%)
Gold produced (000s oz) 94  95  (1%) 366  364  1% 366
Cost of sales ($/oz) 979  987  (1%) 1,016  1,091  (7%) 1,111
Total cash costs ($/oz)b
582  597  (3%) 627  608  3% 568
All-in sustaining costs ($/oz)b
776  751  3% 818  778  5% 693
Veladero (50%)
Gold produced (000s oz) 61  48  27% 172  226  (24%) 274
Cost of sales ($/oz) 1,279  1,315  (3%) 1,256  1,151  9% 1,188
Total cash costs ($/oz)b
834  882  (5%) 816  748  9% 734
All-in sustaining costs ($/oz)b
1,113  1,571  (29%) 1,493  1,308  14% 1,105
Porgera (47.5%)g
Gold produced (000s oz) 86 (100%) 284
Cost of sales ($/oz) 1,225 (100%) 994
Total cash costs ($/oz)b
928 (100%) 838
All-in sustaining costs ($/oz)b
1,115 (100%) 1,003
BARRICK YEAR-END 2021
47
MANAGEMENT’S DISCUSSION AND ANALYSIS

Production and Cost Summary - Gold (continued)
For the three months ended For the years ended
12/31/21 9/30/21 Change 12/31/21 12/31/20  Change 12/31/19
Tongon (89.7%)
Gold produced (000s oz) 50  41  22% 187  255 (27%) 245
Cost of sales ($/oz) 1,494  1,579  (5%) 1,504  1,334 13% 1,469
Total cash costs ($/oz)b
1,205  1,139  6% 1,093  747 46% 787
All-in sustaining costs ($/oz)b
1,301  1,329  (2%) 1,208  791 53% 844
Hemlo
Gold produced (000s oz) 35  26  35% 150 223 (33%) 213
Cost of sales ($/oz) 1,770  1,870  (5%) 1,693 1,256 35% 1,137
Total cash costs ($/oz)b
1,481  1,493  (1%) 1,388 1,056 31% 904
All-in sustaining costs ($/oz)b
1,938  2,276  (15%) 1,970 1,423 38% 1,140
North Marah
Gold produced (000s oz) 69  66  5% 260 261 0% 251
Cost of sales ($/oz) 858  993  (14%) 966 992 (3%) 953 
Total cash costs ($/oz)b
679  796  (15%) 777 702 11% 646 
All-in sustaining costs ($/oz)b
1,033  985  5% 1,001 929 8% 802 
Buzwagih,i
Gold produced (000s oz) 40 84 (52%) 83
Cost of sales ($/oz) 1,000  1,334 1,021 31% 1,240
Total cash costs ($/oz)b
967  1,284 859 49% 1,156
All-in sustaining costs ($/oz)b
970  1,291 871 48% 1,178
Bulyanhuluh
Gold produced (000s oz) 57  53  8% 178 44 304% 27
Cost of sales ($/oz) 956  1,073  (11%) 1,079 1,499 (28%) 1,207
Total cash costs ($/oz)b
567  724  (22%) 709 832 (15%) 676
All-in sustaining costs ($/oz)b
897  827  8% 891 895 0% 773
Kalgoorlie (50%)j
Gold produced (000s oz) 206
Cost of sales ($/oz) 1,062
Total cash costs ($/oz)b
873
All-in sustaining costs ($/oz)b
1,183
Total Attributable to Barrickk
Gold produced (000s oz) 1,203  1,092  10% 4,437  4,760 (7%) 5,465
Cost of sales ($/oz)l
1,075  1,122  (4%) 1,093  1,056 4% 1,005
Total cash costs ($/oz)b
715  739  (3%) 725  699 4% 671
All-in sustaining costs ($/oz)b
971  1,034  (6%) 1,026  967 6% 894
a.Represents the combined results of Cortez, Goldstrike (including our 60% share of South Arturo) and our 75% interest in Turquoise Ridge until June 30, 2019. Commencing July 1, 2019, the date Nevada Gold Mines was established, the results represent our 61.5% interest in Cortez, Carlin (including Goldstrike and NGM’s 60% interest in South Arturo up until May 30, 2021 and 100% interest thereafter), Turquoise Ridge (including Twin Creeks), Phoenix and Long Canyon.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.On July 1, 2019, Barrick's Goldstrike and Newmont's Carlin were contributed to Nevada Gold Mines and are now referred to as Carlin. As a result, the amounts presented represent Goldstrike on a 100% basis (including our 60% share of South Arturo) up until June 30, 2019, and the combined results of Carlin and Goldstrike (including our share of South Arturo) on a 61.5% basis thereafter. On September 7, 2021, Barrick announced NGM had entered into an Exchange Agreement with i-80 Gold to acquire the 40% interest in South Arturo that NGM did not already own in exchange for the Lone Tree and Buffalo Mountain properties and infrastructure. Operating results within our 61.5% interest in Carlin includes NGM’s 60% interest in South Arturo up until May 30, 2021, and 100% interest thereafter, reflecting the terms of the Exchange Agreement which closed on October 14, 2021.
d.On July 1, 2019, Cortez was contributed to Nevada Gold Mines, a joint venture with Newmont. As a result, the amounts presented are on a 100% basis up until June 30, 2019, and on a 61.5% basis thereafter. Starting in the first quarter of 2021, Goldrush is reported as part of Cortez as it is operated by Cortez management. Comparative periods have been restated to include Goldrush.
e.Barrick owned 75% of Turquoise Ridge through to the end of the second quarter of 2019, with our joint venture partner, Newmont, owning the remaining 25%. Turquoise Ridge was proportionately consolidated on the basis that the joint venture partners that have joint control have rights to the assets and obligations for the liabilities relating to the arrangement. The figures presented in this table are based on our 75% interest in Turquoise Ridge until June 30, 2019. On July 1, 2019, Barrick's 75% interest in Turquoise Ridge and Newmont's Twin Creeks and 25% interest in Turquoise Ridge were contributed to Nevada Gold Mines. Starting July 1, 2019, the results represent our 61.5% share of Turquoise Ridge and Twin Creeks, now referred to as Turquoise Ridge.
f.A 61.5% interest in these sites was acquired as a result of the formation of Nevada Gold Mines on July 1, 2019.
g.As Porgera was placed on care and maintenance on April 25, 2020, no operating data or per ounce data has been provided starting the third quarter of 2020.
h.Formerly part of Acacia Mining plc. On September 17, 2019, Barrick acquired all of the shares of Acacia it did not own. Operating results are included at 63.9% until September 30, 2019 (notwithstanding the completion of the Acacia transaction on September 17, 2019, we consolidated our interest in Acacia and recorded a non-controlling interest of 36.1% in the income statement for the entirety of the third quarter of 2019 as a matter of convenience), on a 100% basis from October 1, 2019, to December 31, 2019, and on an 84% basis thereafter as the GoT’s 16% free-carried interest was made effective from January 1, 2020.
i.With the end of mining at Buzwagi in the third quarter of 2021, as previously reported, we have ceased to include production or non-GAAP cost metrics for Buzwagi from October 1, 2021 onwards.
j.On November 28, 2019, we completed the sale of our 50% interest in Kalgoorlie in Western Australia to Saracen Mineral Holdings Limited for total cash consideration of $750 million. Accordingly, the amounts presented represent our 50% interest until November 28, 2019.
k.Excludes Pierina, Golden Sunlight starting in the third quarter of 2019, Morila (40%) starting in the third quarter of 2019 up until its divestiture in November 2020, Lagunas Norte starting in the fourth quarter of 2019 up until its divestiture in June 1, 2021 and Buzwagi starting in the fourth quarter of 2021. Some of these assets are producing incidental ounces while in closure or care and maintenance.
l.Gold cost of sales per ounce is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).
BARRICK YEAR-END 2021
48
MANAGEMENT’S DISCUSSION AND ANALYSIS

Production and Cost Summary - Copper
For the three months ended For the years ended
12/31/21 9/30/21 Change 12/31/21 12/31/20  Change 12/31/19
Lumwana
Copper production (millions lbs) 78  57  37% 242 276  (12%) 238 
Cost of sales ($/lb) 2.16  2.54  (15%) 2.25 2.01  12% 2.13 
C1 cash costs ($/lb)a
1.54  1.76  (13%) 1.62 1.56  4% 1.79 
All-in sustaining costs ($/lb)a
3.29  2.68  23% 2.80 2.43  15% 3.04 
Zaldívar (50%)
Copper production (millions lbs) 27  24  13% 97 106  (8%) 128 
Cost of sales ($/lb) 3.14  3.13  0% 3.19 2.46  30% 2.46 
C1 cash costs ($/lb)a
2.35  2.33  1% 2.38 1.79  33% 1.77 
All-in sustaining costs ($/lb)a
3.42  2.77  23% 2.94 2.25  31% 2.15 
Jabal Sayid (50%)
Copper production (millions lbs) 21  19  11% 76 75  1% 66 
Cost of sales ($/lb) 1.36  1.51  (10%) 1.38 1.42  (3%) 1.53 
C1 cash costs ($/lb)a
1.11  1.35  (18%) 1.18 1.11  6% 1.26 
All-in sustaining costs ($/lb)a
1.27  1.55  (18%) 1.33 1.24  7% 1.51 
Total Copper
Copper production (millions lbs) 126  100  26% 415 457 (9%) 432
Cost of sales ($/lb)b
2.21  2.57  (14%) 2.32 2.02 15% 2.14
C1 cash costs ($/lb)a
1.63  1.85  (12%) 1.72 1.54 12% 1.69
All-in sustaining costs ($/lb)a
2.92  2.60  12% 2.62 2.23 17% 2.52

a.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
b.Copper cost of sales per pound is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).


Operating Performance

Review of Operating Performance
Our presentation of reportable operating segments consists of nine gold mines (Carlin, Cortez, Turquoise Ridge, Pueblo Viejo, Loulo-Gounkoto, Kibali, Veladero, North Mara and Bulyanhulu). Starting in the first quarter of 2021, Goldrush was included as part of Cortez as management began reviewing the operating results and assessing performance on a combined level. The remaining operating segments, including our remaining gold mines, copper mines, and
project, have been grouped into an “other” category and will not be reported on individually. Segment performance is evaluated based on a number of measures including operating income before tax, production levels and unit production costs. Certain costs are managed on a consolidated basis and are therefore not reflected in segment income.


BARRICK YEAR-END 2021
49
MANAGEMENT’S DISCUSSION AND ANALYSIS

Nevada Gold Mines (61.5% basis)a, Nevada USA

Summary of Operating and Financial Data
For the three months ended  For the  years ended
  12/31/21 9/30/21 Change 12/31/21 12/31/20 Change 12/31/19
Total tonnes mined (000s) 45,593  48,494  (6)% 198,725  223,148  (11)% 189,456 
    Open pit ore 8,763  11,553  (24)% 37,670  36,305  4% 26,942 
    Open pit waste 35,468  35,616  0% 155,724  181,675  (14)% 157,868 
    Underground 1,362  1,325  3% 5,331  5,168  3% 4,646 
Average grade (grams/tonne)
    Open pit mined 0.65  0.69  (6)% 0.84  1.14  (26)% 0.93 
    Underground mined 9.86  9.28  6% 9.32  9.67  (4)% 10.52 
    Processed 1.90  1.50  27% 1.78  2.02  (12)% 2.29 
Ore tonnes processed (000s) 12,194  14,697  (17)% 49,232  43,174  14% 36,724 
    Oxide mill 3,054  2,991  2% 12,334  12,907  (4)% 8,338 
    Roaster 1,386  1,108  25% 4,866  5,222  (7)% 5,377 
    Autoclave 1,203  1,204  0% 4,683  5,418  (14)% 5,656 
    Heap leach 6,551  9,394  (30)% 27,349  19,627  39% 17,353 
Recovery rateb
80  % 80  % 0% 79  % 80  % (1)% 82  %
    Oxide Millb
75  % 79  % (5)% 77  % 73  % 5% 76  %
    Roaster 86  % 86  % 0% 86  % 86  % 0% 87  %
    Autoclave 68  % 69  % (1)% 69  % 71  % (3)% 74  %
Gold produced (000s oz) 604  495  22% 2,036  2,131  (4)% 2,218 
    Oxide mill 113  98  15% 364  300  21% 336 
    Roaster 308  214  44% 960  1,070  (10)% 1,070 
    Autoclave 102  102  0% 410  468  (12)% 547 
    Heap leach 81  81  0% 302  293  3% 265 
Gold sold (000s oz) 611  485  26% 2,039  2,134  (4)% 2,223 
Revenue ($ millions) 1,128  891  27% 3,773  3,867  (2)% 3,128 
Cost of sales ($ millions) 625  544  15% 2,186  2,186  0% 2,035 
Income ($ millions) 617  333  85% 1,675  1,636  2% 1,050 
EBITDA ($ millions)c
793  495  60% 2,305  2,232  3% 1,642 
EBITDA margind
70  % 56  % 27% 61  % 58  % 5% 52  %
Capital expenditures ($ millions)e
135  133  2% 555  583  (5)% 627 
    Minesite sustainingc
115  104  11% 458  459  0% 380 
    Projectc
20  29  (31)% 97  124  (22)% 247 
Cost of sales ($/oz) 1,023  1,123  (9)% 1,072  1,029  4% 924 
Total cash costs ($/oz)c
687  734  (6)% 705  702  0% 634 
All-in sustaining costs ($/oz)c
893  975  (8)% 949  941  1% 828 
All-in costs ($/oz)c
927  1,035  (10)% 997  998  0% 938 
a.Barrick is the operator of Nevada Gold Mines and owns 61.5% with Newmont Corporation owning the remaining 38.5%. Nevada Gold Mines is accounted for as a subsidiary with a 38.5% non-controlling interest. These results represent the combined results of Cortez, Goldstrike (including our 60% share of South Arturo) and our 75% interest in Turquoise Ridge until June 30, 2019. Commencing July 1, 2019, the date Nevada Gold Mines was established, the results represent our 61.5% interest in Cortez, Carlin, Turquoise Ridge (including Twin Creeks), Phoenix and Long Canyon. Carlin includes Goldstrike and our share of South Arturo. On September 7, 2021, Barrick announced NGM had entered into an Exchange Agreement with i-80 Gold to acquire the 40% interest in South Arturo that NGM did not already own in exchange for the Lone Tree and Buffalo Mountain properties and infrastructure. Operating results within our 61.5% interest in Carlin includes NGM’s 60% interest in South Arturo up until May 30, 2021, and 100% interest thereafter, reflecting the terms of the Exchange Agreement which closed on October 14, 2021.
b.Excludes the Gold Quarry (Mill 5) concentrator.
c.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
d.Represents EBITDA divided by revenue.
e.Amounts presented exclude capitalized interest.

Nevada Gold Mines includes Carlin, Cortez, Turquoise Ridge, Phoenix and Long Canyon. Barrick is the operator of the joint venture and owns 61.5%, with Newmont owning the remaining 38.5%. Refer to the following pages for a detailed discussion of each minesite’s results.

Regulatory Matters
Mining Education tax
The Nevada Legislative Session ended on May 31, 2021 with the passing of Assembly Bill 495, now named the Mining Education Tax, which is a new mining excise tax applied to gross proceeds. Importantly, the revenue generated by this new excise tax will be directed towards
BARRICK YEAR-END 2021
50
MANAGEMENT’S DISCUSSION AND ANALYSIS

education. This new tax became effective on July 1, 2021 and is a tiered tax, with the highest rate at 1.1%, the first payment of which is expected in April 2022. The bill was a negotiated alternative to the three resolutions that were passed in the special session that commenced on July 31, 2020, none of which passed a second approval in the legislative session ended on May 31, 2021. This was a positive outcome and the result of months of negotiation between Barrick, the Nevada Mining Association, legislators, the Nevada Governor’s office and other key stakeholders.
A number of rural Nevada counties and NGM had filed lawsuits in the Nevada District Court, challenging the constitutionality of the three resolutions from July 2020. These lawsuits were subsequently consolidated into one. On January 27, 2021, the Nevada District Court granted a summary judgment in favor of the Nevada Legislature, concluding that the matter is not yet ripe for adjudication. On February 24, 2021, NGM filed an appeal to this decision to the Nevada Supreme Court. The Nevada Supreme Court has ordered the appeal dismissed as moot and that the district court decision does not have precedential effect.
The tax does not take into consideration expenses or costs incurred to generate gross proceeds, therefore, it is treated as a gross receipts tax and not as a tax based on income subject to IAS 12. As a result, this new tax is reported as a component of cost of sales and not as an income tax expense.
Federal tax and royalty
In July 2021, the U.S. Congress began discussing proposed changes to the General Mining Law of 1872 (“General Mining Law”) which governs mining activities on federal land in the United States. The General Mining Law was designed to incentivize mining activity on federal lands by granting miners the right to prospect, explore, and mine while meeting all applicable environmental and other regulatory requirements, generating fees, taxable revenue, investment and employment benefiting the U.S. federal and state governments. Nevada Gold Mines conducts a portion of its mining activities on federal lands in Nevada pursuant to the General Mining Law.
The U.S. House version of the Build Back Better Act (the “Act”) contained provisions that would have amended the General Mining Law; however, the Act failed to reach a vote in the U.S. Senate. The Company was engaged in constructive discussions with legislators and affected stakeholders regarding the proposed changes to the General Mining Law that were included in the Act. The Company will continue to be engaged on any proposed changes to the General Mining Law and continues to support updates that will result in a more secure legal framework for Barrick and the U.S. hard rock mining industry as a whole.

BARRICK YEAR-END 2021
51
MANAGEMENT’S DISCUSSION AND ANALYSIS

Carlin (61.5% basis)a, Nevada USA

Summary of Operating and Financial Data
For the three months ended For the years ended
   12/31/21 9/30/21 Change 12/31/21 12/31/20 Change 12/31/19
Total tonnes mined (000s) 17,833  19,839  (10)% 75,207  72,820  3% 49,343 
Open pit ore 1,381  2,777  (50)% 6,472  6,054  7% 4,773 
Open pit waste 15,622  16,285  (4)% 65,507  63,579  3% 41,978 
Underground 830  777  7% 3,228  3,187  1% 2,592 
Average grade (grams/tonne)
Open pit mined 0.91  0.69  32% 0.78  2.08  (63)% 2.08 
Underground mined 9.23  8.98  3% 8.85  9.36  (5)% 9.09 
Processed 3.48  2.36  47% 2.97  3.69  (20)% 3.80 
Ore tonnes processed (000s) 3,373  4,627  (27)% 14,282  12,195  17% 10,467 
Oxide mill 671  629  7% 2,735  2,936  (7)% 1,368 
Roaster 1,029  817  26% 3,616  3,743  (3)% 3,627 
Autoclave 571  569  0% 2,221  3,071  (28)% 4,169 
Heap leach 1,102  2,612  (58)% 5,710  2,445  134% 1,303 
Recovery rateb
78  % 77  % 1% 77  % 79  % (3)% 75  %
Roaster 85  % 85  % 0% 85  % 86  % (1)% 86  %
Autoclave 47  % 48  % (2)% 46  % 57  % (19)% 59  %
Gold produced (000s oz) 295  209  41% 923  1,024  (10)% 968 
Oxide mill 23  12  92% 51  38  34% 25 
Roaster 229  164  40% 728  784  (7)% 694 
Autoclave 27  26  4% 102  161  (37)% 225 
Heap leach 16  129% 42  41  2% 24 
Gold sold (000s oz) 297  202  47% 922  1,024  (10)% 967 
Revenue ($ millions) 535  359  49% 1,653  1,812  (9)% 1,355 
Cost of sales ($ millions) 268  205  31% 893  999  (11)% 971 
Income ($ millions) 247  147  68% 733  795  (8)% 370 
EBITDA ($ millions)c
298  188  59% 903  983  (8)% 609 
EBITDA margind
56  % 52  % 8% 55  % 54  % 2% 45  %
Capital expenditures ($ millions)e
63  55  15% 260  231  13% 211 
    Minesite sustainingc
63  55  15% 260  231  13% 211 
    Projectc
0  0% 0  0%
Cost of sales ($/oz) 899  1,017  (12)% 968  976  (1)% 1,004 
Total cash costs ($/oz)c
728  814  (11)% 782  790  (1)% 746 
All-in sustaining costs ($/oz)c
950  1,124  (15)% 1,087  1,041  4% 984 
All-in costs ($/oz)c
950  1,124  (15)% 1,087  1,041  4% 984 
a.On July 1, 2019, Barrick's Goldstrike and Newmont's Carlin were contributed to Nevada Gold Mines and are now collectively referred to as Carlin. As a result, the amounts presented represent Goldstrike on a 100% basis (including our 60% share of South Arturo) up until June 30, 2019, and the combined results of Carlin and Goldstrike (including our share of South Arturo) on a 61.5% basis thereafter. On September 7, 2021, Barrick announced NGM had entered into an Exchange Agreement with i-80 Gold to acquire the 40% interest in South Arturo that NGM did not already own in exchange for the Lone Tree and Buffalo Mountain properties and infrastructure. Operating results within our 61.5% interest in Carlin includes NGM’s 60% interest in South Arturo up until May 30, 2021, and 100% interest thereafter, reflecting the terms of the Exchange Agreement which closed on October 14, 2021.
b.Excludes the Gold Quarry (Mill 5) concentrator.
c.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
d.Represents EBITDA divided by revenue.
e.Amounts presented exclude capitalized interest.

Safety and Environment
There were two lost time injuries (“LTI”) recorded at Carlin during the fourth quarter of 2021, which resulted in an LTIFR8 of 0.99, compared to 0.97 in the prior quarter. The TRIFR8 for the fourth quarter of 2021 was 3.47 per million hours worked, compared to 2.42 in the prior quarter.
There were 10 LTIs recorded in 2021, which resulted in an LTIFR8 of 1.19, compared to 1.06 in 2020. The TRIFR8 for 2021 was 3.08 per million hours worked,
compared to 3.48 in the prior year. No Class 19 environmental incidents occurred during 2021 or 2020.

Financial Results
Q4 2021 compared to Q3 2021
Carlin's income for the fourth quarter of 2021 was 68% higher than the prior quarter due to a significant increase in sales volume, a lower cost of sales per ounce7 and a higher realized gold price6.
BARRICK YEAR-END 2021
52
MANAGEMENT’S DISCUSSION AND ANALYSIS

Gold production in the fourth quarter of 2021 was 41% higher compared to the prior quarter, mainly resulting from higher roaster production due to the previously disclosed mechanical mill failure at the Goldstrike roaster on May 26, 2021, which resulted in a 40% reduction in throughput for the majority of the third quarter. Repairs were completed by the end of September, ahead of schedule. Mitigating actions taken in the third quarter of 2021 included the prioritization of ore with higher carbonaceous content for the majority of the quarter to take advantage of the extra retention time in the roasting circuit to deliver a higher recovery rate from this type of ore. Those actions allowed the complex to optimize roaster throughput and recoveries, which positively impacted the fourth quarter of 2021. Higher grade underground ore stockpiled through the roaster repair period, as described above, was processed in the fourth quarter of 2021. Total tonnes mined were 10% lower compared to the prior quarter, driven by the open pit. Open pit ore tonnes mined were 50% lower compared to the prior quarter, driven by a decrease in heap leach ore mined from the Gold Quarry and Gold Star open pits as planned. Average open pit mined grade was 32% higher than the prior quarter, due to a lower proportion of heap leach ore mined. Underground mined tonnes and grade were 7% and 3% higher, respectively, than the prior quarter due to mine sequencing across Carlin’s underground operations.
Cost of sales per ounce7 and total cash costs per ounce6 in the fourth quarter of 2021 were 12% and 11% lower, respectively, than the prior quarter due to continued cost discipline combined with the impact of higher sales volume. In the fourth quarter of 2021, all-in sustaining costs per ounce6 decreased by 15% compared to the prior quarter, primarily due to lower total cash costs per ounce6 and lower minesite sustaining capital expenditures6 on a per ounce basis.
Capital expenditures in the fourth quarter of 2021 increased by 15% compared to the prior quarter, due to an increase in waste tonnes from increased stripping at Goldstrike 5th NW and Gold Star Phase 3, partially offset by lower sustaining capital expenditures6 and underground capital development.

2021 compared to 2020
Carlin's income for the twelve month period ended December 31, 2021 was 8% lower than the same prior year period primarily due to a decrease in sales volume, partially offset by a slightly lower cost of sales per ounce7 and a higher realized gold price6.


INCOME AND EBITDA6,a

carlinincome.jpg

a The results represent Goldstrike on a 100% basis (including our 60% share of South Arturo) from January 1, 2019 to June 30, 2019 and the combined results of Carlin and Goldstrike (including NGM’s 60% interest in South Arturo up until May 30, 2021 and 100% interest thereafter) on a 61.5% basis from July 1, 2019 onwards.

Gold production for the twelve month period ended December 31, 2021 was 10% lower compared to the prior year, mainly due to the previously disclosed mechanical mill failure at the Goldstrike roaster, which negatively impacted production in the current year. In addition, lower production from the Goldstrike autoclave was mainly driven by the transition from acid to alkaline ore. As previously disclosed, the Goldstrike autoclave completed processing of acidic ore at the end of the third quarter of 2020. Total tonnes mined increased 3% compared to the same prior year period, mainly due to shorter hauls as the Goldstrike pit has transitioned from mining ore in the 4th NW layback to stripping of the 5th NW layback. Open pit ore tonnes mined increased by 7% compared to the same prior year period due to an increase in heap leach ore mined from the Gold Quarry and Gold Star open pits, offsetting the transition to stripping at the Goldstrike open pit as described above. Average open pit mined grade decreased by 63% due to the mining of a higher proportion of heap leach ore compared to the same prior year period. Underground tonnes mined were 1% higher compared to the same prior year period due to upgraded equipment and increased haulage capacity, while underground mined grade decreased by 5% driven by a change in the mix of ore sources across the different underground operations as per the mine plan.

PRODUCTIONa (thousands of ounces)

carlinprod.jpg
a The results include NGM’s 60% interest in South Arturo up until May 30, 2021 and 100% interest thereafter.
b Based on the midpoint of the guidance range.

Cost of sales per ounce7 and total cash costs per ounce6 for the twelve month period ended December 31, 2021 were slightly lower than the same prior year period, with operating cost discipline offsetting the impact of lower sales volume. For the twelve-month period December 31, 2021,
BARRICK YEAR-END 2021
53
MANAGEMENT’S DISCUSSION AND ANALYSIS

all-in sustaining costs per ounce6 was 4% higher than the prior year, primarily due to the impact of higher minesite sustaining capital expenditures6.

COST OF SALES7, TOTAL CASH COSTS6
AND ALL-IN SUSTAINING COSTS6 ($ per ounce)
carlinaisc.jpg

a Based on the midpoint of the guidance range.

Capital expenditures for the twelve month period ended December 31, 2021 increased by 13% from the prior year due to an increase in capitalized waste stripping and the purchase of an oxygen plant at the Goldstrike autoclave, which was previously owned by a third party and is expected to reduce operating costs going forward.

2021 compared to Guidance
Gold production for 2021 of 923 thousand ounces was below the guidance range of 940 to 1,000 thousand ounces as a result of the previously disclosed mechanical mill failure at the Goldstrike roaster on May 26, 2021 which was repaired in late September. Despite lower production and inflationary pressures, rigorous cost discipline resulted in all cost metrics coming in within guidance. Cost of sales per ounce7 of $968 was within the guidance range of $920 to $970 per ounce. Total cash costs per ounce6 and all-in sustaining costs per ounce6 of $782 and $1,087, respectively, were also within the guidance ranges of $740 to $790 per ounce, and $1,050 to $1,100 per ounce, respectively.
BARRICK YEAR-END 2021
54
MANAGEMENT’S DISCUSSION AND ANALYSIS

Cortez (61.5% basis)a, Nevada USA

Summary of Operating and Financial Data
For the three months ended For the years ended
   12/31/21 9/30/21 Change 12/31/21 12/31/20 Change 12/31/19
Total tonnes mined (000s) 17,996  17,515  3% 74,960  85,740  (13)% 105,949 
    Open pit ore 4,528  4,893  (7)% 15,456  11,392  36% 14,640 
    Open pit waste 13,136  12,295  7% 58,235  73,240  (20)% 90,029 
    Underground 332  327  2% 1,269  1,108  15% 1,280 
Average grade (grams/tonne)
    Open pit mined 0.62  0.63  (2)% 0.71  0.56  27% 0.67 
    Underground mined 10.96  9.40  17% 9.45  9.86  (4)% 10.66 
    Processed 1.28  1.01  27% 1.22  1.41  (13)% 1.60 
Ore tonnes processed (000s) 5,413  5,917  (9)% 18,333  13,019  41% 17,583 
    Oxide mill 673  667  1% 2,548  2,432  5% 3,462 
    Roaster 357  291  23% 1,250  1,479  (15)% 1,750 
    Autoclave 10  n/a n/a 10  n/a n/a n/a
    Heap leach 4,373  4,959  (12)% 14,525  9,108  59% 12,371 
Recovery rate 83  % 85  % (2)% 83  % 83  % 0% 86  %
    Oxide Mill 75  % 80  % (6)% 78  % 75  % 4% 78  %
    Roaster 90  % 89  % 1% 88  % 87  % 1% 87  %
    Autoclave 81  % n/a n/a 81  % n/a n/a n/a
Gold produced (000s oz) 169  130  30% 509  491  4% 801 
    Oxide mill 61  52  17% 192  129  49% 253 
    Roaster 79  50  58% 232  286  (19)% 376 
    Autoclave 1  n/a n/a 1  n/a n/a n/a
    Heap leach 28  28  0% 84  76  11% 172 
Gold sold (000s oz) 170  126  35% 508  491  3% 798 
Revenue ($ millions) 306  226  35% 913  865  6% 1,086 
Cost of sales ($ millions) 167  147  14% 570  470  21% 608 
Income ($ millions) 139  77  81% 337  385  (12)% 459 
EBITDA ($ millions)b
194  123  58% 518  523  (1)% 656 
EBITDA marginc
63  % 54  % 17% 57  % 60  % (5)% 60  %
Capital expenditures ($ millions)d
49  48  2% 177  235  (25)% 294 
    Minesite sustainingb
31  31  0% 118  145  (19)% 90 
    Projectb
18  17  6% 59  90  (34)% 204 
Cost of sales ($/oz) 984  1,164  (15)% 1,122  958  17% 762 
Total cash costs ($/oz)b
657  800  (18)% 763  678  13% 515 
All-in sustaining costs ($/oz)b
853  1,065  (20)% 1,013  998  2% 651 
All-in costs ($/oz)b
958  1,199  (20)% 1,129  1,179  (4)% 903 
a.On July 1, 2019, Cortez was contributed to Nevada Gold Mines, a joint venture with Newmont. As a result, the amounts presented are on a 100% basis up until June 30, 2019, and on a 61.5% basis thereafter. Starting in the first quarter of 2021, Goldrush is reported as part of Cortez as it is operated by Cortez management. Comparative periods have been restated to include Goldrush.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.Represents EBITDA divided by revenue.
d.Amounts presented exclude capitalized interest.

Safety and Environment
There were three LTIs recorded at Cortez during the fourth quarter of 2021, which resulted in a LTIFR8 of 3.21 per million hours worked, compared to 1.01 in the prior quarter. The TRIFR8 for the fourth quarter of 2021 was 3.21 per million hours worked, compared to 3.04 in the prior quarter.
There were seven LTIs recorded in 2021, which resulted in an LTIFR8 of 1.81 per million hours worked, compared to 0.24 in 2020. The TRIFR8 for 2021 was 2.85 per million hours worked, compared to 2.59 in the prior year. No Class 19 environmental incidents occurred during 2021 or 2020.
Financial Results
Q4 2021 compared to Q3 2021
Cortez’s income for the fourth quarter of 2021 was 81% higher than the prior quarter due to substantially higher sales volume, a lower cost of sales per ounce7 and a higher realized gold price6.
Gold production in the fourth quarter of 2021 was 30% higher compared to the prior quarter. This was primarily driven by higher grade refractory production at the Carlin roasters (including batch processing of trial Goldrush ore), following the previously disclosed mechanical mill failure at the Goldstrike roaster which impacted third quarter
BARRICK YEAR-END 2021
55
MANAGEMENT’S DISCUSSION AND ANALYSIS

production. Open pit ore tonnes mined were 7% lower compared to the prior quarter, driven primarily by the open pit mine sequence at Crossroads. Underground tonnes mined were 2% higher compared to the prior quarter due to higher underground tonnes mined from the Goldrush development project.
Cost of sales per ounce7 and total cash costs per ounce6 in the fourth quarter of 2021 were 15% and 18% lower, respectively, versus the prior quarter due to sales mix with a higher proportion from lower cost underground, production. In the fourth quarter of 2021, all-in sustaining costs per ounce6 were 20% lower than the prior quarter, driven by lower total cash costs per ounce6.
Capital expenditures in the fourth quarter of 2021 were 2% higher compared to the prior quarter due to higher project capital expenditures6. Minesite sustaining capital expenditure6 spend was comparable quarter-on-quarter.

2021 compared to 2020
Cortez’s income for the twelve month period ended December 31, 2021 was 12% lower than the same prior year period, primarily due to a higher cost of sales per ounce7, partially offset by the higher realized gold price6 and higher sales volume.

INCOME AND EBITDA6,a
cortezincome.jpg
a The results are on a 100% basis from January 1, 2019 to June 30, 2019 and on a 61.5% basis from July 1, 2019 onwards.

Gold production for the twelve month period ended December 31, 2021 was 4% higher than the same prior year period, mainly due to an increase in oxide mill and heap leach production, partially offset by a reduction in refractory ore processed at the Carlin roasters. The increase in oxide mill and heap leach production was due to higher grade ore and increased volumes mined from the Pipeline and Crossroads open pits. Lower refractory ore tonnes were processed at the Carlin roasters due to displacement by higher grade Carlin refractory ore. Open pit ore tonnes mined increased 36% over the same prior year period largely due to increased ore mined from the Crossroads open pit. Underground tonnes mined increased 15% over the same prior year period, mainly driven by increased underground development activity at Goldrush.


PRODUCTIONa (thousands of ounces)

cortezprod.jpg
a The results are on a 100% basis from January 1, 2019 to June 30, 2019 and on a 61.5% basis from July 1, 2019 onwards.
b Based on the midpoint of the guidance range.

Cost of sales per ounce7 and total cash costs per ounce6 for the twelve month period ended December 31, 2021 were 17% and 13% higher, respectively, than the same prior year period, mainly due to a higher proportion of higher cost open pit ounces, partially offset by the impact of higher sales volume. The higher cost of sales per ounce7 was also driven by higher depreciation expense. For the twelve month period ended December 31, 2021, all-in sustaining costs per ounce6 increased by 2% compared to the same prior year period, driven by higher total cash costs per ounce6, partially offset by lower minesite sustaining capital expenditures6.

COST OF SALES7, TOTAL CASH COSTS6
AND ALL-IN SUSTAINING COSTS6 ($ per ounce)
cortezaisc.jpg
a Based on the midpoint of the guidance range.

Capital expenditures for the twelve month period ended December 31, 2021 were 25% lower than the prior year due to both lower minesite sustaining6 and project capital expenditures6. Minesite sustaining capital expenditures6 were 19% lower compared to the same prior year period, primarily due to a decrease in capitalized waste stripping as relatively more mining activity occurred in operating phases of the Crossroads and Pipeline open pits. Lower project capital expenditures6 were due to lower cost development and exploration activities at Goldrush underground in the current period whereas in the same prior year period, activity mainly related to Goldrush twin decline development, Goldrush power infrastructure, and the Cortez Hills Rangefront Decline project.

2021 compared to Guidance
Gold production for 2021 of 509 thousand ounces was within the guidance range of 500 to 550 thousand ounces. Cost of sales per ounce7 for 2021 was $1,122, above the guidance range of $1,000 to $1,050 per ounce. Higher than expected open pit maintenance costs contributed to higher operating costs. Total cash costs per ounce6 of $763 was also above the guidance range of $700 to $750 per ounce, and all-in sustaining costs per ounce6 of $1,013 was higher than guidance of $940 to $990 per ounce due to higher sustaining capital expenditures6.
BARRICK YEAR-END 2021
56
MANAGEMENT’S DISCUSSION AND ANALYSIS

Turquoise Ridge (61.5%)a, Nevada USA

Summary of Operating and Financial Data
For the three months ended For the years ended
12/31/21 9/30/21 Change 12/31/21 12/31/20 Change 12/31/19
Total tonnes mined (000s) 235  1,581  (85)% 8,510  15,483  (45)% 9,001 
Open pit ore 35  785  (96)% 3,020  5,150  (41)% 1,340 
Open pit waste 0  575  (100)% 4,656  9,460  (51)% 6,887 
Underground 200  221  (10)% 834  873  (4)% 774 
Average grade (grams/tonne)
Open pit mined 1.72  1.36  26% 1.69  2.24  (25)% 1.37 
Underground mined 10.36  10.04  3% 10.69  10.44  2% 14.44 
Processed 4.12  2.94  40% 3.31  3.42  (3)% 5.62 
Ore tonnes processed (000s) 747  1,075  (31)% 3,793  3,613  5% 2,201 
Oxide Mill 125  105  19% 434  458  (5)% 221 
Autoclave 622  635  (2)% 2,452  2,346  5% 1,483 
Heap leach 0  335  (100)% 907  809  12% 497 
Recovery Rate 81  % 82  % (1)% 82  % 83  % (1)% 89  %
Oxide Mill 81  % 84  % (4)% 83  % 88  % (6)% 87  %
Autoclave 81  % 82  % (1)% 82  % 83  % (1)% 89  %
Gold produced (000s oz) 82  82  0% 334  330  1% 335 
Oxide Mill 4  0% 16  16  0%
Autoclave 74  76  (3)% 307  306  0% 321 
Heap leach 4  100% 11  38%
Gold sold (000s oz) 84  82  2% 337  332  2% 356 
Revenue ($ millions) 151  146  3% 607  589  3% 504 
Cost of sales ($ millions) 100  95  5% 378  353  7% 300 
Income ($ millions) 51  51  0% 229  229  0% 201 
EBITDA ($ millions)b
82  82  0% 352  342  3% 293 
EBITDA marginc
54  % 56  % (4)% 58  % 58  % 0% 58  %
Capital expenditures ($ millions) 19  21  (10)% 81  51  59% 85 
    Minesite sustainingb
14  12  17% 47  24  96% 50 
    Projectb
5  (44)% 34  27  26% 35 
Cost of sales ($/oz) 1,194  1,169  2% 1,122  1,064  5% 846 
Total cash costs ($/oz)b
819  788  4% 749  711  5% 585 
All-in sustaining costs ($/oz)b
996  943  6% 892  798  12% 732 
All-in costs ($/oz)b
1,061  1,053  1% 993  879  13% 834 
a.Prior to July 1, 2019, Barrick owned 75% of Turquoise Ridge with our joint venture partner, Newmont, owning the remaining 25%. Turquoise Ridge was proportionately consolidated on the basis that the joint venture partners that have joint control have rights to the assets and obligations for the liabilities relating to the arrangement. The figures presented in this table are based on our 75% interest in Turquoise Ridge until June 30, 2019. On July 1, 2019, Barrick's 75% interest in Turquoise Ridge and Newmont's 100% interest in Twin Creeks and 25% interest in Turquoise Ridge were contributed to Nevada Gold Mines. Starting July 1, 2019, the results represent our 61.5% share of Turquoise Ridge and Twin Creeks, now collectively referred to as Turquoise Ridge.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c. Represents EBITDA divided by revenue.

Safety and Environment
There were three LTIs recorded at Turquoise Ridge during the fourth quarter of 2021, which resulted in an LTIFR8 of 4.29 per million hours worked, compared to 5.81 in the prior quarter. The TRIFR8 for the fourth quarter of 2021 was 8.58 per million hours worked, compared to 4.36 in the prior quarter.
There were eight LTIs recorded in 2021, which resulted in an LTIFR8 of 2.85 per million hours worked compared to 2.51 million hours in 2020. The TRIFR8 for 2021 was 4.63 per million hours worked, compared to 4.31 in the prior year. No Class 19 environmental incidents occurred during 2021 or 2020.

Financial Results
Q4 2021 compared to Q3 2021
Turquoise Ridge's income for the fourth quarter of 2021 was in line with the prior quarter as higher sales volume and a higher realized gold price6 were offset by an increase in cost of sales per ounce7.
Gold production in the fourth quarter of 2021 was in line with the prior quarter. Total tonnes mined decreased by 85% compared to the prior quarter, driven by lower open pit production as the current phase of fresh ore mining ramped down and was completed in the fourth quarter of 2021 as expected and previously disclosed. We continue to expect open pit mining to resume in the medium-to-long term at Cut 40, with the analysis of an optimized restart currently under review. Underground tonnes mined
BARRICK YEAR-END 2021
57
MANAGEMENT’S DISCUSSION AND ANALYSIS

decreased by 10% compared to the prior quarter. Equipment issues continued to impact performance in the fourth quarter of 2021 including a battery fire in mid-October, which resulted in the loss of the electric truck fleet for the remainder of the fourth quarter at the direction of the Mine Safety and Health Administration (MSHA), pending a investigation into the cause of the fire. Once resolved, we expect to continue trialing battery-powered Sandvik haul trucks, together with the continued use of conventional mining equipment at Turquoise Ridge Underground.
Cost of sales per ounce7 and total cash costs per ounce6 in the fourth quarter of 2021 were 2% and 4% higher, respectively, than the prior quarter mainly due to the processing of a higher proportion of lower grade open pit ore (including ore stockpiled from prior quarters of the year) which carries a higher cost on a per ounce basis. All-in sustaining costs per ounce6 increased by 6% compared to the prior quarter, primarily reflecting higher total cash costs per ounce6 and higher sustaining capital expenditures6.
Capital expenditures in the fourth quarter of 2021 decreased by 10% compared to the prior quarter, primarily due to lower project capital expenditures6 on the Third Shaft project, partially offset by higher sustaining capital expenditures6. Project capital expenditures6 on the Third Shaft project was lower due to delays in shaft steel placement, while higher sustaining capital expenditures6 was related to the timing of underground equipment purchases.

2021 compared to 2020
Turquoise Ridge’s income for the twelve month period ended December 31, 2021 was in line with the prior year, as higher sales volume and a higher realized gold price6 were offset by an increase in cost of sales per ounce7.

INCOME AND EBITDA6,a

trincome.jpg
a The results represent Turquoise Ridge on a 75% basis from January 1, 2019 to June 30, 2019 and the combined results of Turquoise Ridge and Twin Creeks on a 61.5% basis from July 1, 2019 onwards.

Gold production for the twelve month period ended December 31, 2021 was 1% higher compared to the prior year, primarily due to improved grades from Turquoise Ridge underground combined with improved throughput at the Sage autoclave, partially offset by lower underground tonnes mined. Total tonnes mined were lower by 45% relative to the same prior year period due to a decrease in open pit tonnes as the current phases of fresh ore mining were completed in the fourth quarter of 2021, as expected and previously disclosed. We continue to expect open pit mining to resume in the medium-to-long term at Cut 40, with the economics of an optimized restart currently under review. In addition, underground tonnes were lower by 4% relative to the same prior year period as higher operating
rates were more than offset by lower equipment availability and ventilation constraints.

PRODUCTIONa (thousands of ounces)
trprod.jpg
a The results represent Turquoise Ridge on a 75% basis from January 1, 2019 to June 30, 2019 and the combined results of Turquoise Ridge and Twin Creeks on a 61.5% basis from July 1, 2019 onwards.
b Based on the midpoint of the guidance range.

Cost of sales per ounce7 and total cash costs per ounce6 for the twelve month period ended December 31, 2021 were both 5% higher than the same prior year period due to the impact of lower grades processed, which was driven by a higher proportion of lower grade open pit ore versus the same prior year period. All-in sustaining costs per ounce6 increased by 12% compared to the prior year due to higher total cash costs per ounce6, and higher minesite sustaining capital expenditures6.

COST OF SALES7, TOTAL CASH COSTS6
AND ALL-IN SUSTAINING COSTS6 ($ per ounce)
traisc.jpg
a Based on the midpoint of the guidance range.

Capital expenditures for the twelve month period ended December 31, 2021 increased by 59% compared to the same prior year period, mainly due to an increase in minesite sustaining capital expenditures6 relating to underground equipment purchases and process efficiency related projects. This was combined with higher project capital expenditures6 related to the Third Shaft project.

2021 compared to Guidance
As expected and previously disclosed, gold production in 2021 of 334 thousand ounces was below the guidance range of 390 to 440 thousand ounces. This was mainly due to lower than planned underground equipment availability and utilization, as well as lower plant availability. Cost of sales per ounce7 and total cash costs per ounce6 of $1,122 and $749, respectively, were above the guidance ranges of $950 to $1,000 per ounce and $620 to $670 per ounce, respectively, mainly due to the impact of lower sales volumes which reflected this underperformance. All-in sustaining costs per ounce6 of $892 was above the guidance range of $810 to $860 per ounce for similar reasons.
BARRICK YEAR-END 2021
58
MANAGEMENT’S DISCUSSION AND ANALYSIS

Other Mines - Nevada Gold Mines

Summary of Operating and Financial Data
For the three months ended
12/31/21 9/30/21
Gold produced (000s oz) Cost of sales
($/oz)
Total cash costs
($/oz)
a
All-in sustaining costs
($/oz)
a
Capital Expend-ituresb
Gold produced (000s oz) Cost of sales
($/oz)
Total cash costs
($/oz)a
All-in sustaining costs
($/oz)a
Capital Expend-ituresb
Phoenix (61.5%)c
25 2,047  443  614  4  31 1,777  499  582 
Long Canyon (61.5%) 33 999  325  384  1  43 796  201  251 
a.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
b. Includes both minesite sustaining and project capital expenditures.
c.On September 7, 2021, NGM announced it had entered into an Exchange Agreement with i-80 Gold to acquire the 40% interest in South Arturo that NGM did not already own in exchange for the Lone Tree and Buffalo Mountain properties and infrastructure. Operating results within our 61.5% interest in Phoenix includes Lone Tree up until May 30, 2021, reflecting the terms of the Exchange Agreement which closed on October 14, 2021.

Phoenix (61.5%)
Gold production for Phoenix in the fourth quarter of 2021 was 19% lower compared to the prior quarter driven by the divestment of Lone Tree (part of the Phoenix operations) following the execution of the Exchange Agreement between NGM and i-80 Gold. Pursuant to this agreement, NGM exchanged Lone Tree and Buffalo Mountain for i-80 Gold’s 40% interest in South Arturo (included within the Carlin operations). This transaction closed in the fourth quarter of 2021 and had an effective date of June 1, 2021. Separately, a reduction in tonnes milled and lower mill recoveries also contributed to the decrease in quarter-on-quarter production.
Cost of sales per ounce7 in the fourth quarter of 2021 was 15% higher than the prior quarter, primarily due to lower sales volume. Total cash costs per ounce6 were 11% lower than the prior quarter primarily due to higher by- product credits, partially offset by lower sales volume. In the fourth quarter of 2021, all-in sustaining costs per ounce6 increased by 5% compared to the prior quarter, primarily due to higher minesite sustaining capital expenditures6, partially offset by lower total cash costs per ounce6.
Compared to our 2021 outlook, gold production of 109 thousand ounces was within the guidance range of 100 to 120 thousand ounces. Cost of sales per ounce7 of $1,922 was above the guidance range of $1,800 to $1,850 per ounce. Total cash costs per ounce6 and all-in sustaining costs per ounce6 of $398 and $533, respectively, were below the guidance ranges of $725 to $775 per ounce and $970 to $1,020 per ounce, respectively, mainly due to higher by-product credits driven by the increase in copper and silver prices.



Long Canyon (61.5%)
Gold production for Long Canyon in the fourth quarter of 2021 was 23% lower compared to the third quarter of 2021, primarily due to lower grade and a reduction in ore tonnes stacked, combined with a higher stacking height leading to a longer leach cycle. Cost of sales per ounce7 and total cash costs per ounce6 in the fourth quarter of 2021 were 26% and 62% higher than the prior quarter, respectively, primarily due to these same impacts. All-in sustaining costs per ounce6 increased by 53% compared to the prior quarter, primarily due to the same drivers described above as well as slightly higher sustaining capital expenditures6 resulting from haul truck refurbishments.
Compared to our 2021 outlook, gold production of 161 thousand ounces was above the top end of the guidance range of 140 to 160 thousand ounces. Cost of sales per ounce7 of $739 was well below the guidance range of $800 to $850 per ounce. Total cash costs per ounce6 and all-in sustaining costs per ounce6 of $188 and $238, respectively, were near or below the bottom end of the guidance ranges of $180 to $230 per ounce and $240 to $290 per ounce, respectively.
We continue to pursue sales of non-core assets that are not aligned with Barrick’s strategic investment filters. We will only proceed with transactions that make sense for the business, on terms we consider favorable to our shareholders. In this regard, we intend to initiate a process to explore the sale of Long Canyon in the first quarter of 2022.


















BARRICK YEAR-END 2021
59
MANAGEMENT’S DISCUSSION AND ANALYSIS

Pueblo Viejo (60% basis)a, Dominican Republic

Summary of Operating and Financial Data
For the three months ended For the years ended
  12/31/21 9/30/21 Change 12/31/21 12/31/20 Change 12/31/19
Open pit tonnes mined (000s) 5,626  5,926  (5)% 24,687  20,262  22% 24,732 
Open pit ore 1,489  2,464  (40)% 7,969  6,147  30% 8,085 
Open pit waste 4,137  3,462  19% 16,718  14,115  18% 16,647 
Average grade (grams/tonne)
Open pit mined 2.57  2.28  13% 2.41  2.57  (6)% 2.76 
Processed 2.83  3.07  (8)% 3.18  3.61  (12)% 3.91 
Autoclave ore tonnes processed (000s) 1,365  1,446  (6)% 5,466  5,297  3% 5,164 
Recovery rate 90  % 88  % 2% 88  % 89  % (1)% 89  %
Gold produced (000s oz) 107  127  (16)% 488  542  (10)% 590 
Gold sold (000s oz) 113  125  (10)% 497  541  (8)% 584 
Revenue ($ millions) 203  227  (11)% 898  954  (6)% 843 
Cost of sales ($ millions) 112  112  0% 445  443  0% 435 
Income ($ millions) 90  113  (20)% 445  508  (12)% 402 
EBITDA ($ millions)b
125  150  (17)% 587  644  (9)% 522 
EBITDA marginc
62  % 66  % (6)% 65  % 68  % (4)% 62  %
Capital expenditures ($ millions) 94  73  29% 311  134  132% 64 
    Minesite sustainingb
27  24  13% 96  79  22% 64 
    Projectb
67  49  37% 215  55  291%
Cost of sales ($/oz) 987  895  10% 896  819  9% 747 
Total cash costs ($/oz)b
612  521  17% 541  504  7% 471 
All-in sustaining costs ($/oz)b
858  728  18% 745  660  13% 592 
All-in costs ($/oz)b
1,453  1,117  30% 1,178  761  55% 600 
a.Barrick is the operator of Pueblo Viejo and owns 60% with Newmont Corporation owning the remaining 40%. Pueblo Viejo is accounted for as a subsidiary with a 40% non-controlling interest. The results in the table and the discussion that follows are based on our 60% share only.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.Represents EBITDA divided by revenue.

Safety and Environment
There were no LTIs recorded at Pueblo Viejo during the fourth quarter of 2021, which resulted in an LTIFR8 of 0.00 per million hours worked, a reduction from 0.30 LTIFR8 in the prior quarter. The TRIFR8 for the fourth quarter of 2021 was 0.46 per million hours worked, compared to 0.30 in the prior quarter.
There was one LTI recorded in 2021, which resulted in an LTIFR8 of 0.07 per million hours worked, compared to 0.10 in 2020. The TRIFR8 for 2021 was 0.50 per million hours worked, compared to 0.73 in the prior year. No Class 19 environmental incidents occurred during 2021 or 2020.

Financial Results
Q4 2021 compared to Q3 2021
Pueblo Viejo’s income for the fourth quarter of 2021 was 20% lower than the third quarter of 2021 due to lower sales volume and a higher cost of sales per ounce7, partially offset by a higher realized gold price6.
Gold production for the fourth quarter of 2021 was 16% lower than the prior quarter due to lower throughput driven by planned maintenance during the quarter, lower grades processed in line with the mine and stockpile processing plan and higher carbon-in-leach inventory accumulation. This was partially offset by higher recovery.
Cost of sales per ounce7 and total cash costs per ounce6 for the fourth quarter of 2021 were 10% and 17% higher, respectively, than the prior quarter primarily
reflecting the impact of planned maintenance and higher natural gas prices in the current quarter. This was partially offset by higher margins from third-party energy sales at the Quisqueya power plant driven by higher spot energy prices. The increase in cost of sales per ounce7 was also impacted by higher depreciation on a per ounce basis, resulting from the impact of lower sales volumes. For the fourth quarter of 2021, all-in sustaining costs per ounce6 increased by 18% compared to the prior quarter, reflecting higher total cash costs per ounce6 and higher minesite sustaining capital expenditures6.
Capital expenditures for the fourth quarter of 2021 increased by 29% compared to the prior quarter, primarily due to increased project capital expenditures6 incurred on the plant expansion and mine life extension project. This was combined with higher minesite sustaining capital expenditures6 related to the Llagal tailings storage facility and major maintenance at the Quisqueya power plant.

2021 compared to 2020
Pueblo Viejo’s income for 2021 was 12% lower than the prior year due to lower sales volume and a higher cost of sales per ounce7, partially offset by the higher realized gold price6.


BARRICK YEAR-END 2021
60
MANAGEMENT’S DISCUSSION AND ANALYSIS

INCOME AND EBITDA6

pvincome.jpg
Gold production for 2021 was 10% lower than the prior year, mainly due to lower grades processed in line with the mine and stockpile processing plan, partially offset by higher tonnes processed. Pueblo Viejo once again achieved record throughput in 2021 due to improved maintenance practices and increased tonnes per operating hour, with throughput 3% higher than the previous record set in 2020.

PRODUCTION (thousands of ounces)
pvprod.jpg
a Based on the midpoint of the guidance range.

Cost of sales per ounce7 and total cash costs per ounce6 for 2021 increased by 9% and 7%, respectively, compared to the prior year, primarily reflecting the impact of lower grades as described above, and higher natural gas prices. For 2021, all-in sustaining costs per ounce6 increased by 13% compared to the prior year, mainly reflecting higher total cash costs per ounce6 and higher minesite sustaining capital expenditures6.


COST OF SALES7, TOTAL CASH COSTS6
AND ALL-IN SUSTAINING COSTS6 ($ per ounce)
pvaisc.jpg
a Based on the midpoint of the guidance range.

Capital expenditures for 2021 increased by 132% compared to the prior year, primarily due to increased project capital expenditures6 for the plant expansion and mine life extension project. This was combined with higher minesite sustaining capital expenditures6 related to the Llagal tailings storage facility, higher capitalized stripping at the Montenegro open pit and major maintenance at the Quisqueya power plant. This was partially offset by the purchase of a new fleet for ore rehandling activities occurring in the prior year.

2021 compared to Guidance
Gold production in 2021 of 488 thousand ounces was within the guidance range of 470 to 510 thousand ounces. Cost of sales per ounce7 and total cash costs per ounce6 of $896 and $541, respectively, were within the guidance ranges of $880 to $930 per ounce and $520 to $570 per ounce, respectively, despite the impact of higher energy prices. All-in sustaining costs per ounce6 was $745, which was lower than the guidance range of $760 to $810 per ounce mainly driven by the deferral of sustaining capital at the existing tailings facility.

BARRICK YEAR-END 2021
61
MANAGEMENT’S DISCUSSION AND ANALYSIS

Loulo-Gounkoto (80% basis)a, Mali

Summary of Operating and Financial Data
For the three months ended For the years ended
   12/31/21 9/30/21 Change 12/31/21 12/31/20 Change 12/31/19
Total tonnes mined (000s) 7,766  8,131  (4)% 33,073  33,036  —% 32,192 
    Open pit ore 1,208  257  370% 1,808  1,698  6% 2,726 
    Open pit waste 5,999  7,319  (18)% 29,050  29,078  0% 27,183 
    Underground 559  555  1% 2,215  2,260  (2)% 2,283 
Average grade (grams/tonne)
    Open pit mined 3.47  2.63  32% 3.22  5.50  (41)% 4.83 
    Underground mined 4.34  4.65  (7)% 4.68  4.36  7% 4.67 
    Processed 4.25  4.63  (8)% 4.79  4.76  1% 4.90 
Ore tonnes processed (000s) 1,019  1,011  1% 4,015  3,916  3% 3,945 
Recovery rate 91  % 91  % 0% 91  % 91  % 0% 92  %
Gold produced (000s oz) 126  137  (8)% 560  544  3% 572 
Gold sold (000s oz) 128  134  (4)% 558  542  3% 575 
Revenue ($ millions) 228  239  (5)% 999  966  3% 806 
Cost of sales ($ millions) 145  149  (3)% 585  576  2% 601 
Income ($ millions) 74  84  (12)% 380  358  6% 190 
EBITDA ($ millions)b
132  137  (4)% 602  572  5% 426 
EBITDA marginc
58  % 57  % 2% 60  % 59  % 2% 53  %
Capital expenditures ($ millions) 50  59  (15)% 238  185  29% 136 
    Minesite sustainingb
13  42  (69)% 159  170  (6)% 133 
    Projectb
37  17  118% 79  15  427%
Cost of sales ($/oz) 1,139  1,109  3% 1,049  1,060  (1)% 1,044 
Total cash costs ($/oz)b
685  708  (3)% 650  666  (2)% 634 
All-in sustaining costs ($/oz)b
822  1,056  (22)% 970  1,006  (4)% 886 
All-in costs ($/oz)b
1,109  1,184  (6)% 1,111  1,034  7% 891 
a.Barrick owns 80% of Société des Mines de Loulo SA and Société des Mines de Gounkoto with the Republic of Mali owning 20%. Loulo-Gounkoto is accounted for as a subsidiary with a 20% non-controlling interest on the basis that Barrick controls the asset. The results in the table and the discussion that follows are based on our 80% share, inclusive of the impact of the purchase price allocation resulting from the Merger.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.Represents EBITDA divided by revenue.

Safety and Environment
There were zero LTIs recorded during the fourth quarter of 2021, which resulted in an LTIFR8 of 0.00 per million hours worked compared to 0.00 in the prior quarter. The TRIFR8 for the fourth quarter of 2021 was 0.35 per million hours worked, compared to 0.41 in the prior quarter.
There were two LTIs recorded in 2021, which resulted in an LTIFR8 of 0.11 per million hours worked compared to 0.07 in 2020. The TRIFR8 for 2021 was 0.92 per million hours worked, compared to 1.53 in the prior year. No Class 19 environmental incidents occurred during 2021 or 2020.

Financial Results
Q4 2021 compared to Q3 2021
Loulo-Gounkoto’s income for the fourth quarter of 2021 was 12% lower than the prior quarter, mainly due to lower sales volume and higher cost of sales per ounce7 partially offset by a higher realized gold price6.
Gold production for the fourth quarter of 2021 was 8% lower than the prior quarter, mainly due to lower grades processed, in line with the mine plan.
Cost of sales per ounce7 for the fourth quarter of 2021 was 3% higher than the prior quarter due to higher depreciation, partially offset by lower total cash costs per
ounce6. Total cash costs per ounce6 was 3% lower than the prior quarter due to more efficient power blends in both the underground mine and processing operations towards the end of the quarter, partially offset by the impact of lower grades. For the fourth quarter of 2021, all-in sustaining costs per ounce6 decreased by 22% compared to the prior quarter, primarily reflecting lower minesite sustaining capital expenditures6, as well as lower total cash costs per ounce6.
Capital expenditures for the fourth quarter of 2021 decreased by 15% compared to the prior quarter, primarily due to lower minesite sustaining capital expenditures6. This was partially offset by higher project capital expenditures6 relating to the continued development of Gounkoto underground and the expansion of power capacity.

2021 compared to 2020
Loulo-Gounkoto’s income for 2021 was 6% higher than the prior year, due to a higher realized gold price6, higher sales volume and lower cost of sales per ounce7.


BARRICK YEAR-END 2021
62
MANAGEMENT’S DISCUSSION AND ANALYSIS

INCOME AND EBITDA6

lgincome.jpg
Gold production in 2021 was 3% higher compared to the prior year, primarily due to higher plant throughput as well as higher grades processed.

PRODUCTION (thousands of ounces)
lgprod.jpg
a Based on the midpoint of the guidance range.

Cost of sales per ounce7 and total cash costs per ounce6 in 2021 were 1% and 2% lower, respectively, compared to the prior year, mainly due to the impact of higher grades as well as lower underground mining costs. For 2021, all-in sustaining costs6 were 4% lower compared to the prior year reflecting lower total cash costs per ounce6 and decreased minesite sustaining capital expenditures6.


COST OF SALES7, TOTAL CASH COSTS6
AND ALL-IN SUSTAINING COSTS6 ($ per ounce)
lgaisc.jpg
a Based on the midpoint of the guidance range.

Capital expenditures in 2021 were 29% higher compared to the prior year, primarily due to higher project capital expenditures6 from the development of Gounkoto underground and the expansion of power capacity. This was slightly offset by lower minesite sustaining capital expenditures6.

2021 compared to Guidance
Gold production in 2021 of 560 thousand ounces was at the top end of the guidance range of 510 to 560 thousand ounces. Cost of sales per ounce7 of $1,049 was above the guidance range of $980 to $1,030 per ounce, due to higher depreciation. Total cash costs per ounce6 and all-in sustaining costs per ounce6 of $650 and $970, respectively, were within the guidance ranges of $630 to $680 per ounce and $930 to $980 per ounce, respectively.


BARRICK YEAR-END 2021
63
MANAGEMENT’S DISCUSSION AND ANALYSIS

Kibali (45% basis)a, Democratic Republic of Congo

Summary of Operating and Financial Data
For the three months ended For the years ended
   12/31/21 9/30/21 Change 12/31/21 12/31/20 Change 12/31/19
Total tonnes mined (000s) 3,866  3,840  1% 14,657  13,308  10% 12,273 
    Open pit ore 330  361  (9)% 1,278  1,380  (7)% 1,693 
    Open pit waste 3,082  3,072  0% 11,610  10,091  15% 8,824 
    Underground 454  407  12% 1,769  1,837  (4)% 1,756 
Average grade (grams/tonne)
    Open pit mined 2.43  3.00  (19)% 2.71  2.22  22% 2.32 
    Underground mined 5.88  5.89  0% 5.63  5.20  8% 5.12 
    Processed 3.90  3.73  5% 3.62  3.68  (2)% 3.80 
Ore tonnes processed (000s) 841  872  (4)% 3,503  3,434  2% 3,381 
Recovery rate 89  % 90  % (1)% 90  % 90  % 0% 89  %
Gold produced (000s oz) 94  95  (1)% 366  364  1% 366 
Gold sold (000s oz) 95  93  2% 367  364  1% 363 
Revenue ($ millions) 172  166  4% 661  648  2% 505 
Cost of sales ($ millions) 93  92  1% 373  397  (6)% 403 
Income ($ millions) 71  74  (4)% 278  244  14% 108 
EBITDA ($ millions)b
108  110  (2)% 419  418  0% 304 
EBITDA marginc
63  % 66  % (5)% 63  % 65  % (3)% 60  %
Capital expenditures ($ millions) 19  19  0% 70  51  37% 43 
    Minesite sustainingb
12  11  9% 54  49  10% 41 
    Projectb
7  (13)% 16  700%
Cost of sales ($/oz) 979  987  (1)% 1,016  1,091  (7)% 1,111 
Total cash costs ($/oz)b
582  597  (3)% 627  608  3% 568 
All-in sustaining costs ($/oz)b
776  751  3% 818  778  5% 693 
All-in costs ($/oz)b
844  838  1% 861  782  10% 701 
a.Barrick owns 45% of Kibali Goldmines SA (Kibali) with the Democratic Republic of Congo ("DRC") and our joint venture partner, AngloGold Ashanti, owning 10% and 45%, respectively. Kibali is accounted for as an equity method investment on the basis that the joint venture partners that have joint control have rights to the net assets of the joint venture. The figures presented in this table and the discussion that follows are based on our 45% effective interest in Kibali, inclusive of the impact of the purchase price allocation resulting from the merger with Randgold.
b. Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c. Represents EBITDA divided by revenue.

Safety and Environment
There were no LTIs recorded during the fourth quarter of 2021, which resulted in an LTIFR8 of 0.00 per million hours worked, consistent with the prior quarter. The TRIFR8 for the fourth quarter of 2021 was 1.39 per million hours worked, an improvement from 1.88 in the prior quarter.
There were two LTIs recorded in 2021, which resulted in an LTIFR8 of 0.14 per million hours worked compared to 0.23 in 2020. The TRIFR8 for 2021 was 1.22 per million hours worked, compared to 1.59 in the prior year. No Class 19 environmental incidents occurred during 2021 or 2020.

Financial Results
Q4 2021 compared to Q3 2021
Kibali’s income for the fourth quarter of 2021 was 4% lower than the third quarter of 2021 as a result of foreign exchange payment fees incurred on dividend payments.
Gold production for the fourth quarter of 2021 was 1% lower than the prior quarter, due to fewer tonnes processed in line with the mine plan for the quarter, partially offset by higher grades processed. Gold sales for the fourth quarter of 2021 were 2% higher when compared to the prior quarter, due to the timing of sales.
Cost of sales per ounce7 for the fourth quarter of 2021 was in line with the prior quarter. Total cash costs per ounce6 was 3% below the prior quarter, with fewer stockpiled tonnes processed when compared to the previous quarter. All-in sustaining costs per ounce6 for the fourth quarter of 2021 ended 3% higher than the prior quarter, mainly due to higher minesite sustaining capital expenditures6, partially offset by lower total cash costs per ounce6.
Capital expenditures for the fourth quarter of 2021, were in line with the prior quarter. Slightly higher minesite sustaining capital expenditures7 were due to higher capitalized stripping relative to the prior quarter.

2021 compared to 2020
Kibali’s income for 2021 was 14% higher than the prior year due to a higher realized gold price6, lower cost of sales per ounce7 and slightly higher sales volume.





BARRICK YEAR-END 2021
64
MANAGEMENT’S DISCUSSION AND ANALYSIS

INCOME AND EBITDA6

kibaliincome.jpg

Gold production in 2021 was slightly higher compared to the prior year due to higher throughput, partially offset by lower grades processed.

PRODUCTION (thousands of ounces)
kibaliprod.jpg
a Based on the midpoint of the guidance range.

Cost of sales per ounce7 in 2021 decreased by 7% compared to the prior year due to lower depreciation expense, partially offset by higher total cash costs6. Total cash costs per ounce6 were 3% higher, mainly due to higher labor and logistics charges due to pandemic-related
travel restrictions. This was partially offset by lower energy costs driven by an improved hydro power blend in the first half of 2021 and relatively lower fuel prices. For 2021, all-in sustaining costs per ounce6 was 5% higher compared to the prior year, reflecting higher total cash costs per ounce6 and higher minesite sustaining capital expenditures6.

COST OF SALES7, TOTAL CASH COSTS6
AND ALL-IN SUSTAINING COSTS6 ($ per ounce)
kibaliaisc.jpg
a Based on the midpoint of the guidance range.

Capital expenditures in 2021 were 37% higher compared to the prior year, due to higher minesite sustaining capital expenditures6 related to a tailings dam raise, and project capital expenditures6 related to the advancement of the Kalimva/Ikamva and Pamao open pit projects.

2021 compared to Guidance
Attributable gold production in 2021 of 366 thousand ounces was near the midpoint of the guidance range of 350 to 380 thousand ounces. Cost of sales per ounce7 of $1,016 was within guidance range of $990 to $1,040 per ounce. Total cash costs per ounce6 of $627 were also within the guidance range of $590 to $640 per ounce, while all-in sustaining costs per ounce6 of $818 were at the lower end of the guidance range of $800 to $850 per ounce.

BARRICK YEAR-END 2021
65
MANAGEMENT’S DISCUSSION AND ANALYSIS

Veladero (50% basis)a, Argentina

Summary of Operating and Financial Data
For the three months ended  For the  years ended
  12/31/21 9/30/21 Change 12/31/21 12/31/20 Change 12/31/19
Open pit tonnes mined (000s) 8,997  8,837  % 37,787  29,108  30  % 36,758 
    Open pit ore 3,308  3,267  % 10,629  13,678  (22) % 16,048 
    Open pit waste 5,689  5,570  % 27,158  15,430  76  % 20,710 
Average grade (grams/tonne)
 Open pit mined 0.85  0.69  23  % 0.77  0.78  (1) % 0.71 
  Processed 0.81  0.71  14  % 0.77  0.84  (8) % 0.79 
Heap leach ore tonnes processed (000s) 3,442  3,126  10  % 11,114  12,017  (8) % 13,587 
Gold produced (000s oz) 61  48  27  % 172  226  (24) % 274 
Gold sold (000s oz) 83  44  89  % 206  186  11  % 271 
Revenue ($ millions) 153  81  89  % 382  333  15  % 386 
Cost of sales ($ millions) 109  58  88  % 262  213  23  % 323 
Income ($ millions) 43  24  79  % 118  114  % 57 
EBITDA ($ millions)b
80  41  95  % 203  183  11  % 172 
EBITDA marginc
52  % 51  % % 53  % 55  % (3) % 45  %
Capital expenditures ($ millions) 28  29  (3) % 142  113  26  % 106 
    Minesite sustainingb
22  29  (24) % 136  98  39  % 91 
    Projectb
6  100  % 6  15  (60) % 15 
Cost of sales ($/oz) 1,279  1,315  (3) % 1,256  1,151  % 1,188 
Total cash costs ($/oz)b
834  882  (5) % 816  748  % 734 
All-in sustaining costs ($/oz)b
1,113  1,571  (29) % 1,493  1,308  14  % 1,105 
All-in costs ($/oz)b
1,179  1,571  (25) % 1,520  1,390  % 1,162 
a.Barrick owns 50% of Veladero with our joint venture partner, Shandong Gold, owning the remaining 50%. Veladero is proportionately consolidated on the basis that the joint venture partners that have joint control have rights to the assets and obligations for the liabilities relating to the arrangement. The figures presented in this table and the discussion that follows are based on our 50% interest in Veladero inclusive of the impact of remeasurement of our interest in Veladero following the disposal of a 50% interest on June 30, 2017.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.Represents EBITDA divided by revenue.


Safety and Environment
There were no LTIs recorded at Veladero during the fourth quarter of 2021, which resulted in an LTIFR8 of 0.00 per million hours worked, consistent with the prior quarter. The TRIFR8 for the fourth quarter of 2021 was 0.00 per million hours worked, compared to 0.64 in the prior quarter.
There were three LTIs recorded in 2021, which resulted in an LTIFR8 of 0.28 per million hours worked compared to 0.31 in 2020. The TRIFR8 for 2021 was 0.48 per million hours worked, compared to 0.72 in the prior year. No Class 19 environmental incidents occurred during 2021 or 2020.
Minera Andina del Sol SRL, the joint venture company that operates the Veladero mine, is the subject of various regulatory proceedings related to operational incidents occurring in March 2017, September 2016 and September 2015. Refer to note 35 to the Financial Statements for more information regarding these and related matters.

Financial Results
Q4 2021 compared to Q3 2021
Veladero’s income for the fourth quarter of 2021 was 79% higher than the third quarter of 2021, primarily due to higher sales volume, lower cost of sales per ounce7 and a higher realized gold price6.
Gold production in the fourth quarter of 2021 was 27% higher than the prior quarter, primarily due to an
increase in recoverable ounces placed, combined with a successful strategy of processing material simultaneously from both Phases 1 to 5 and the recently commissioned Phase 6 leach pad. Gold sales were higher than production in the fourth quarter of 2021 due to the sale of a portion of built-up gold inventory as we continue to manage the timing of our sales to minimize our exposure to local currency devaluation.
Cost of sales per ounce7 and total cash costs per ounce6 in the fourth quarter of 2021 decreased by 3% and 5%, respectively, mainly due to the impact of higher sales volumes, partially offset by higher open pit mining and processing costs driven by maintenance and higher consumable prices. In the fourth quarter of 2021, all-in sustaining costs per ounce6 was 29% lower than the prior quarter, primarily attributable to lower minesite sustaining capital expenditures6, combined with lower total cash costs per ounce6.
Capital expenditures in the fourth quarter of 2021 decreased by 3% compared to the prior quarter due to lower minesite sustaining capital expenditures6 related to lower capitalized stripping and drilling. This was partially offset by increased project capital expenditures6 reflecting the commencement of construction for the Phase 7A leach pad after the winter season.

BARRICK YEAR-END 2021
66
MANAGEMENT’S DISCUSSION AND ANALYSIS

2021 compared to 2020
Veladero’s income for 2021 was 4% higher than the prior year, primarily due to a higher realized gold price6 and higher sales volume, partially offset by higher cost of sales per ounce7.

INCOME AND EBITDA6

veladeroincome.jpg

In 2021, gold production decreased by 24% compared to the prior year, primarily due to the construction and commissioning of the Phase 6 leach pad. As previously disclosed, heap leach processing operations at Veladero were reduced through the first half of 2021, while the mine transitioned to Phase 6. The Phase 6 leach pad expansion was successfully commissioned in the second quarter of 2021, in line with guidance. Gold sales were higher than production as we actively managed the timing of sales to minimize our exposure to local currency devaluation and support the payment of a $20 million dividend to the Veladero joint venture partners.

PRODUCTION (thousands of ounces)
veladeroprod.jpg
a Based on the midpoint of the guidance range.

In 2021, cost of sales per ounce7 and total cash costs per ounce6 both increased by 9% compared to the prior year period due to higher open pit costs driven by increased mining activity, combined with higher G&A expenditure related to Covid-19. Cost of sales per ounce7 was further impacted by higher depreciation expense. All-in sustaining costs per ounce6 in 2021 increased by 14% compared to the prior year, primarily due to the impact of higher total cash costs per ounce6 and higher minesite sustaining capital expenditures6.


COST OF SALES7, TOTAL CASH COSTS6
AND ALL-IN SUSTAINING COSTS6 ($ per ounce)
veladeroaisc.jpg
a Based on the midpoint of the guidance range.

In 2021, capital expenditures increased by 26% compared to the prior year, mainly due to higher sustaining capital expenditures6 resulting from the development of the Phase 6 leach pad expansion and higher capitalized stripping. Project capital expenditures were lower compared to the prior year, mainly due to a $15 million payment made for the funding of a power transmission line in Argentina following an agreement made with the Provincial Power Regulatory Body of San Juan ("EPRE") that occurred in the same prior year period.

2021 compared to Guidance
Gold production in 2021 of 172 thousand ounces was above the guidance range of 130 to 150 thousand ounces due to stronger performance from the additional stacking capacity of Phase 6, as well as the simultaneous processing of Phases 1 to 5 together with Phase 6. All cost metrics were below the guidance ranges. Cost of sales per ounce7 was $1,256 compared to the guidance range of $1,510 to $1,560 per ounce due to lower depreciation. Total cash costs per ounce6 and all-in sustaining costs per ounce6 were $816 and $1,493, respectively, compared to the guidance ranges of $820 to $870 per ounce and $1,720 to $1,770 per ounce, respectively. Lower total cash costs per ounce6 was driven by higher production. All-in sustaining costs per ounce6 was lower than guidance due to lower total cash costs per ounce6, lower capitalized stripping, and the postponement of truck purchases to 2023.

Regulatory matters
On September 1, 2019, the Argentine government issued Decree 609/2019 announcing currency restrictions in Argentina. Subsequently, the Central Bank of Argentina issued Communication “A” 6770 complementing this decree. As a result, all export proceeds are required to be converted into Argentine pesos. Dividend distributions and payments to foreign suppliers now require specific authorizations from the Central Bank. These currency restrictions have had limited impact on mining operations to date but we continue to optimize the timing of our gold sales to minimize our exposure to currency devaluation. During the fourth quarter of 2021, a dividend of $20 million was paid to the Veladero joint venture partners, in addition to a $17 million loan interest payment. Ongoing constructive discussions are still being held with the Central Bank on our rights to repatriate further profits.
Separately, on October 2, 2020, the Argentine government issued Decree 785/2020 that established the rate for mining export duties at 8%. On December 31, 2021, this decree was extended until December 31, 2023.
BARRICK YEAR-END 2021
67
MANAGEMENT’S DISCUSSION AND ANALYSIS

North Mara (84 basis)a, Tanzania

Summary of Operating and Financial Data
For the three months ended  For the  years ended
  12/31/21 9/30/21 Change 12/31/21 12/31/20 Change 12/31/19
Total tonnes mined (000s) 661  340  94% 1,603  3,758  (57)% 10,388 
    Open pit ore 116  n/a n/a 116  1,484  (92)% 3,987 
    Open pit waste 160  n/a n/a 160  1,197  (87)% 5,532 
    Underground 385  340  13% 1,327  1,077  23% 869 
Average grade (grams/tonne)
    Open pit mined 1.63  n/a n/a 1.63  2.14  (24)% 2.03 
    Underground mined 6.89  6.29  10% 5.58  6.19  (10)% 6.82 
Processed 3.57  3.25  10% 3.30  3.45  (4)% 4.50 
Ore tonnes processed (000s) 690  658  5% 2,703  2,546  6% 1,829 
Recovery rate 90  % 91  % (1)% 90  % 92  % (2)% 94  %
Gold produced (000s oz) 69  66  5% 260  261  0% 251 
Gold sold (000s oz) 70  65  8% 257  269  (4)% 248 
Revenue ($ millions) 126  116  9% 463  480  (4)% 350 
Cost of sales ($ millions) 59  64  (8)% 248  267  (7)% 236 
Income ($ millions) 68  52  31% 214  214  0% 112 
EBITDA ($ millions)b
80  64  25% 261  290  (10)% 187 
EBITDA marginc
63  % 55  % 15% 56  % 60  % (7)% 53  %
Capital expenditures ($ millions) 32  18  78% 79  87  (9)% 42 
    Minesite sustainingb
23  11  109% 52  57  (9)% 36 
    Projectb
9  29% 27  30  (10)%
Cost of sales ($/oz) 858  993  (14)% 966  992  (3)% 953 
Total cash costs ($/oz)b
679  796  (15)% 777  702  11% 646 
All-in sustaining costs ($/oz)b
1,033  985  5% 1,001  929  8% 802 
All-in costs ($/oz)b
1,150  1,105  4% 1,105  1,039  6% 824 
a.Formerly part of Acacia Mining plc. On September 17, 2019, Barrick acquired all of the shares of Acacia it did not already own. The results presented are on a 63.9% basis until September 30, 2019 (notwithstanding the completion of the Acacia transaction on September 17, 2019, we consolidated our interest in Acacia and recorded a non-controlling interest of 36.1% in the income statement for the entirety of the third quarter of 2019 as a matter of convenience); on a 100% basis from October 1, 2019 to December 31, 2019; and on a 84% basis starting January 1, 2020, the date the GoT’s 16% free carried interest was made effective. The results in the table and the discussion that follows are based on our share.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.Represents EBITDA divided by revenue.


Safety and Environment
There were no LTIs recorded at North Mara during the fourth quarter of 2021, which resulted in an LTIFR8 of 0.00 per million hours worked, consistent with the prior quarter. The TRIFR8 for the fourth quarter of 2021 was 1.04 per million hours worked, compared to 0.00 in the prior quarter.
There was one LTI recorded in 2021, resulting in an LTIFR8 of 0.13 per million hours worked, compared to 0.28 in 2020. The TRIFR8 for 2021 was 0.90 per million hours worked, compared to 1.96 in the prior year. No Class 19 environmental incidents occurred during 2021 or 2020.

Financial Results
Q4 2021 compared to Q3 2021
North Mara’s income for the fourth quarter of 2021 was 31% higher than the third quarter of 2021, mainly due to higher sales volumes, lower cost of sales per ounce7 and a higher realized gold price6.
In the fourth quarter of 2021, gold production was 5% higher than the prior quarter, mainly due to improved plant throughput combined with higher grade and tonnes from the underground. Open-pit mining resumed in the
fourth quarter of 2021 for the first time since the second quarter of 2020. The Rama pit is expected to be commissioned in the first quarter of 2022. Fleet replacement and an improvement in underground efficiency in 2021 has resulted in a record year for underground tonnes mined.
Cost of sales per ounce7 and total cash costs per ounce6 in the fourth quarter of 2021 were 14% and 15% lower, respectively, than the prior quarter, primarily due to the successful transition to grid power from diesel in the underground. This was combined with improved underground ore delivery, at a higher grade, after the delivery of new fleet purchased in prior quarters. All-in sustaining costs per ounce6 in the fourth quarter of 2021 was 5% higher than the prior quarter as a result of higher minesite sustaining capital expenditures6, partially offset by lower total cash costs per ounce6.
Capital expenditures in the fourth quarter of 2021 were 78% higher than the third quarter of 2021, driven by higher minesite sustaining capital expenditures6 as well as higher project capital expenditures6 predominantly relating to the initial capital spend on the restart of the open-pit mine, procurement of key underground equipment in line
BARRICK YEAR-END 2021
68
MANAGEMENT’S DISCUSSION AND ANALYSIS

with our automation and optimization plan, and completion of the brine treatment facility.

2021 compared to 2020
North Mara’s income for 2021 was in line with the prior year as lower sales volume was offset by a higher realized gold price6 and lower cost of sales per ounce7.

INCOME AND EBITDA6,a

nmincome.jpg

a The results are presented on a 63.9% basis from January 1, 2019 to September 30, 2019, on a 100% basis from October 1, 2019 to December 31, 2019 and on a 84% basis starting January 1, 2020, the date the GoT’s 16% free carried interest was made effective.

In 2021, gold production was largely in line with the prior year as higher throughput was offset by lower grades processed. Both mill throughput and underground tonnes mined reached annual records in 2021.

PRODUCTION (thousands of ounces)
nmprod.jpg
a Based on the midpoint of the guidance range.


Cost of sales per ounce7 in 2021 was 3% lower than the prior year, due to lower depreciation following the temporary cessation of open-pit mining in 2020, partially offset by higher total cash costs per ounce6. The increase in total cash costs per ounce6 of 11% was mainly due to increased royalty expense due to a higher realized gold price6, combined with higher operating costs related to the water treatment plant. All-in sustaining costs per ounce6 was 8% higher than the prior year, primarily due to higher total cash costs per ounce6, partially offset by a decrease in minesite sustaining capital expenditures6.

COST OF SALES7, TOTAL CASH COSTS6
AND ALL-IN SUSTAINING COSTS6 ($ per ounce)
nmaisc.jpg
a Based on the midpoint of the guidance range.

In 2021, capital expenditures decreased by 9% compared to the prior year, driven by lower minesite sustaining capital expenditures6 as well as lower project capital expenditures6, mainly due to investments in the prior year related to the tailings storage facility and other water management initiatives.

2021 compared to Guidance
Gold production in 2021 of 260 thousand ounces was in the upper end of the guidance range of 240 to 270 thousand ounces. Cost of sales per ounce7 of $966 was slightly below the guidance range of $970 to $1,020 per ounce. Total cash costs per ounce6 and and all-in sustaining costs per ounce6 of $777 and $1,001, respectively, were both within the guidance ranges of $740 to $790 per ounce and $960 to $1,100 per ounce, respectively.

 

BARRICK YEAR-END 2021
69
MANAGEMENT’S DISCUSSION AND ANALYSIS

Bulyanhulu (84% basis)a, Tanzania

Summary of Operating and Financial Data
For the three months ended  For the  years ended
  12/31/21 9/30/21 Change 12/31/21 12/31/20 Change 12/31/19
Underground tonnes mined (000s) 243  198  23  % 730  83  780  % n/a
Average grade (grams/tonne)
    Underground mined 8.86  9.91  (11) % 9.23  8.81  % n/a
Processed 8.18  9.82  (17) % 8.95  1.35  563  % 1.09 
Ore tonnes processed (000s) 234  179  31  % 661  1,618  (59) % 1,531 
Recovery rate 93  % 94  % (1) % 93  % 62  % 50  % 50  %
Gold produced (000s oz) 57  53  % 178  44  304  % 27 
Gold sold (000s oz) 53  49  % 166  103  61  % 27 
Revenue ($ millions) 101  91  11  % 303  202  50  % 39 
Cost of sales ($ millions) 50  53  (6) % 179  154  16  % 33 
Income ($ millions) 51  37  38  % 122  27  352  % (14)
EBITDA ($ millions)b
65  50  30  % 170  87  95  %
EBITDA marginc
64  % 55  % 16  % 56  % 43  % 30  % %
Capital expenditures ($ millions) 31  10  210  % 70  64  %
    Minesite sustainingb
17  240  % 29  383  %
    Projectb
14  180  % 41  58  (29) %
Cost of sales ($/oz) 956  1,073  (11) % 1,079  1,499  (28) % 1,207 
Total cash costs ($/oz)b
567  724  (22) % 709  832  (15) % 676 
All-in sustaining costs ($/oz)b
897  827  % 891  895  % 773 
All-in costs ($/oz)b
1,159  937  24  % 1,138  1,459  (22) % 850 
a.Formerly part of Acacia Mining plc. On September 17, 2019, Barrick acquired all of the shares of Acacia it did not already own. The results presented are on a 63.9% basis until September 30, 2019 (notwithstanding the completion of the Acacia transaction on September 17, 2019, we consolidated our interest in Acacia and recorded a non-controlling interest of 36.1% in the income statement for the entirety of the third quarter of 2019 as a matter of convenience); on a 100% basis from October 1, 2019 to December 31, 2019; and on a 84% basis starting January 1, 2020, the date the GoT’s 16% free carried interest was made effective. The results in the table and the discussion that follows are based on our share.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.Represents EBITDA divided by revenue.


Safety and Environment
There were two LTIs recorded at Bulyanhulu during the fourth quarter of 2021, which resulted in an LTIFR8 of 1.34 per million hours worked, versus 1.40 in the prior quarter. The TRIFR8 for the fourth quarter of 2021 was 2.69 per million hours worked, compared to 4.88 in the prior quarter.
There were four LTIs recorded at Bulyanhulu in 2021, which resulted in an LTIFR8 of 0.72 per million hours worked versus 0.32 in 2020. The TRIFR8 for 2021 was 2.90 per million hours worked, compared to 2.30 in the prior year. No Class 19 environmental incidents occurred during 2021 or 2020.

Financial Results
Q4 2021 compared to Q3 2021
Bulyanhulu’s income for the fourth quarter of 2021 was 38% higher than the third quarter of 2021, mainly due to higher sales volumes and lower cost of sales per ounce7 following the successful ramp-up of the underground operation into the fourth quarter of 2021, combined with a higher realized gold price6.
In the fourth quarter of 2021, gold production was 8% higher than the prior quarter. This increase was driven by the successful ramp-up of the underground operation, which achieved steady-state production during the quarter.
Cost of sales per ounce7 and total cash costs per ounce6 in the fourth quarter of 2021 were 11% and 22% lower, respectively, than the prior quarter mainly due to the
impact of higher production. All-in sustaining costs per ounce6 in the fourth quarter of 2021 was 8% higher than the prior quarter, mainly as a result of higher minesite sustaining capital expenditures6, partially offset by lower total cash costs per ounce6.
Capital expenditures in the fourth quarter of 2021 were 210% higher than the third quarter of 2021, mainly due to increased minesite sustaining capital expenditures6 related to the replacement of the underground mobile fleet. This was combined with higher project capital expenditures6 relating to the process plant optimization, capitalized drilling and life of mine design improvements identified during the underground re-start project.

2021 compared to 2020
Bulyanhulu’s income for 2021 was 352% higher than the prior year, primarily due to higher sales volumes related to the ramp-up of underground mining and processing operations, as described above. This was combined with lower cost of sales per ounce7 and a higher realized gold price6.


BARRICK YEAR-END 2021
70
MANAGEMENT’S DISCUSSION AND ANALYSIS

INCOME AND EBITDA6,a

bulyincome.jpg

a The results are presented on a 63.9% basis from January 1, 2019 to September 30, 2019, on a 100% basis from October 1, 2019 to December 31, 2019 and on a 84% basis starting January 1, 2020, the date the GoT’s 16% free carried interest was made effective.

In 2021, gold production was 304% higher than the prior year, primarily due to the ramp-up of underground mining and processing following the restart of underground mining operations at the end of the third quarter of 2020. For most of the prior year, Bulyanhulu was a tailings re-treatment operation.

PRODUCTION (thousands of ounces)
bulyprod.jpg
a Based on the midpoint of the guidance range.

Cost of sales per ounce7 and total cash costs per ounce6 in 2021 were 28% and 15% lower, respectively, than the prior year, mainly due to the impact of higher gold production following the successful ramp-up of underground mining and processing in 2021. All-in sustaining costs per ounce6 was in line with the prior year due to lower total cash costs per ounce6, largely offset by higher minesite sustaining capital expenditures6.
COST OF SALES7, TOTAL CASH COSTS6
AND ALL-IN SUSTAINING COSTS6 ($ per ounce)
bulyaisc.jpg
a Based on the midpoint of the guidance range.

In 2021, capital expenditures increased by 9% compared to the prior year, driven by higher minesite sustaining capital expenditures6 mainly from the replacement of the underground mobile fleet as well as capitalized drilling of the underground. This was partially offset by lower project capital expenditures6 as the mine transitioned to steady state.

2021 compared to Guidance
Gold production in 2021 of 178 thousand ounces was within the guidance range of 170 to 200 thousand ounces. Cost of sales per ounce7 and total cash costs per ounce6 of $1,079 and $709, respectively, were higher than the guidance ranges of $980 to $1,030 per ounce and $580 to $630 per ounce, respectively. All-in sustaining costs per ounce6 of $891 was also higher than the guidance range of $810 to $860 per ounce. All cost metrics were higher than the guidance ranges due to higher than expected dilution, additional drilling to improve grade control reconciliation, and the timing of concentrate sales resulting in lower copper by-product credits.
BARRICK YEAR-END 2021
71
MANAGEMENT’S DISCUSSION AND ANALYSIS

Other Mines - Gold
Summary of Operating and Financial Data For the three months ended
12/31/21 9/30/21
Gold produced (000s oz) Cost of sales
($/oz)
Total cash costs
($/oz)a
All-in sustaining costs
($/oz)a
Capital Expend-ituresb
Gold produced (000s oz) Cost of sales
($/oz)
Total cash costs
($/oz)a
All-in sustaining costs
($/oz)a
Capital Expend-ituresb
Tongon (89.7%) 50 1,494  1,205  1,301  2  41 1,579  1,139  1,329 
Hemlo 35 1,770  1,481  1,938  15  26 1,870  1,493  2,276  20 
Buzwagic (84%)
4 1,000  967  970 
Porgerad (47.5%)
        —  —  —  — 
a.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
b. Includes both minesite sustaining and project capital expenditures.
c.With the end of mining at Buzwagi in the third quarter of 2021, as previously reported, we have ceased to include production or non-GAAP cost metrics for Buzwagi from October 1, 2021 onwards.
d.As Porgera has been on care and maintenance since April 25, 2020, no operating data or per ounce data is provided.

Tongon (89.7% basis), Côte d'Ivoire
Gold production for Tongon in the fourth quarter of 2021 was 22% higher than the prior quarter, reflecting higher grades processed, throughput and recoveries. As previously disclosed, production in the third quarter of 2021 was impacted by a heavy rainy season. Cost of sales per ounce7 in the fourth quarter of 2021 was 5% lower than the prior quarter due to lower depreciation, partially offset by higher total cash costs per ounce6. Total cash costs per ounce6 were 6% higher than the prior quarter, primarily due to higher mill power consumption reflecting increased throughput. All-in sustaining costs per ounce6 in the fourth quarter of 2021 were lower than the prior quarter, due to lower minesite sustaining capital expenditures6, partially offset by the increase in total cash costs per ounce6 .
Gold production in 2021 of 187 thousand ounces was within the guidance range of 180 to 200 thousand ounces. Cost of sales per ounce7 of $1,504 was also within the guidance range of $1,470 to $1,520 per ounce. Total cash costs per ounce6 and all-in sustaining costs per ounce6 of $1,093 and $1,208, respectively, were both above the guidance ranges of $1,000 to $1,050 per ounce and $1,140 to $1,190 per ounce, respectively, driven by increased material mined and processed with lower grade and recoveries.

Hemlo, Ontario, Canada
Hemlo's gold production in the fourth quarter of 2021 was 35% higher than the prior quarter, primarily due to higher grades and higher ore tonnes mined due to improved underground performance. Cost of sales per ounce7 and total cash costs per ounce6 in the fourth quarter of 2021 were 5% and 1% lower, respectively, than the prior quarter due to the impact of higher sales volumes. All-in sustaining costs per ounce6 decreased by 15% compared to the prior quarter, primarily due to lower minesite sustaining capital expenditures6 and lower total cash costs per ounce6.
As expected and previously disclosed, gold production in 2021 of 150 thousand ounces was below the guidance range of 200 to 220 thousand ounces, which was due to lower underground productivity impacted by Covid-19 movement restrictions that slowed the ramp-up of underground development, temporary seismicity issues, and a mine shutdown following the tragic fatality in July 2021 of an employee from our underground mining contractor. Cost of sales per ounce7 of $1,693 and total cash costs per ounce6 of $1,388 were both above the guidance ranges of $1,200 to $1,250 per ounce and $950
to $1,000 per ounce, respectively. All-in sustaining costs per ounce6 of $1,970 was also higher than the guidance range of $1,280 to $1,330 per ounce. As expected and previously disclosed, per ounce cost metrics in 2021 were above guidance due to a significant increase in royalty expense from a higher realized gold price6 and mining in specific underground zones that incurred a higher net profit interest royalty burden. Costs were also impacted by lower production volumes as described above.
Porgera (47.5% basis), Papua New Guinea
On April 9, 2021, BNL signed a binding Framework Agreement with PNG and Kumul Minerals, a state-owned mining company, setting out the terms and conditions for the reopening of the Porgera mine. On February 3, 2022, the Framework Agreement was replaced by the Commencement Agreement. The Commencement Agreement was signed by PNG, Kumul Minerals, BNL and its affiliate Porgera (Jersey) Limited on October 15, 2021, and it became effective on February 3, 2022, following signature by Mineral Resources Enga Limited (“MRE”), the holder of the remaining 5% of the original Porgera joint venture. The Commencement Agreement reflects the commercial terms previously agreed to under the Framework Agreement, namely that PNG stakeholders will receive a 51% equity stake in the Porgera mine, with the remaining 49% to be held by BNL or an affiliate. BNL is jointly owned on a 50/50 basis by Barrick and Zijin Mining Group. Accordingly, following the implementation of the Commencement Agreement, Barrick’s current 47.5% interest in the Porgera mine is expected to be reduced to a 24.5% interest as reflected in Barrick’s reserve and resource estimates for Porgera. BNL will retain operatorship of the mine. The Commencement Agreement also provides that PNG stakeholders and BNL and its affiliates will share the economic benefits derived from the reopened Porgera Mine on a 53% and 47% basis over the remaining life of mine, respectively, and that the Government of PNG will retain the option to acquire BNL’s or its affiliate’s 49% equity participation at fair market value after 10 years.
The provisions of the Commencement Agreement will be implemented, and work to recommence full mine operations at Porgera will begin, following the execution of a number of definitive agreements and satisfaction of a number of conditions. These include a Shareholders Agreement among the shareholders of a new Porgera joint venture company, an Operatorship Agreement pursuant to which BNL will operate the Porgera mine, as well as a Mine
BARRICK YEAR-END 2021
72
MANAGEMENT’S DISCUSSION AND ANALYSIS

Development Contract to accompany the new SML that the new Porgera joint venture company will apply for following its incorporation. Under the terms of the Commencement Agreement, BNL will remain in possession of the site and maintain the mine on care and maintenance.
Porgera was excluded from our 2021 guidance and will also be excluded from our 2022 guidance. We expect to update our guidance following both the execution of all of the definitive agreements to implement the binding Commencement Agreement and the finalization of a timeline for the resumption of full mine operations. Refer to notes 21 and 35 to the Financial Statements for more information.
BARRICK YEAR-END 2021
73
MANAGEMENT’S DISCUSSION AND ANALYSIS

Other Mines - Copper
Summary of Operating and Financial Data For the three months ended
12/31/21 9/30/21
Copper production (millions of pounds) Cost of sales
($/lb)
C1 cash costs
($/lb)a
All-in sustaining costs
($/lb)a
Capital Expend-ituresb
Copper production (millions of pounds) Cost of sales
($/lb)
C1 cash costs
($/lb)
a
All-in sustaining costs
($/lb)
a
Capital Expend-ituresb
Lumwana 78 2.16  1.54  3.29  79  57 2.54  1.76  2.68  30 
Zaldívar (50%)
27 3.14  2.35  3.42  35  24 3.13  2.33  2.77  21 
Jabal Sayid (50%) 21 1.36  1.11  1.27  3  19 1.51  1.35  1.55 
a.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
b. Includes both minesite sustaining and project capital expenditures.

Lumwana, Zambia
Copper production for Lumwana in the fourth quarter of 2021 was 37% higher compared to the prior quarter, resulting from higher grades processed, improved recovery and a significant improvement in throughput driven by higher mill availability. Cost of sales per pound7 and C1 cash costs per pound6 in the fourth quarter of 2021 were 15% and 13% lower, respectively, than the prior quarter primarily due to higher capitalized stripping, partially offset by higher mining costs. Cost of sales per pound7 was further impacted by lower depreciation expense. In the fourth quarter of 2021, all-in sustaining costs per pound6 increased by 23% compared to the prior quarter, primarily due to higher minesite sustaining capital expenditures6 mainly related to new mining equipment and stripping, partially offset by lower C1 cash costs per pound6.
Copper production in 2021 of 242 million pounds was below the guidance range of 250 to 280 million pounds, mainly due to lower mill and equipment availability. A new fleet was commissioned in the fourth quarter of 2021, which improved availability and was a key driver in the significant increase in production quarter-on-quarter. Cost of sales per pound7 of $2.25 was above the guidance range of $1.85 to $2.05 per pound, while C1 cash costs per pound6 of $1.62 was within the guidance range of $1.45 to $1.65. All-in sustaining costs6 of $2.80 per pound were above the guidance range of $2.25 to $2.45 per pound, due to the timing of shipments. Higher cost metrics are mainly attributed to a higher realized copper price6, which resulted in a higher royalty expense, whereas the guidance ranges were based on a copper price of $2.75/lb as previously disclosed.

Zaldívar (50% basis), Chile
Copper production for Zaldívar in the fourth quarter of 2021 was 13% higher than the prior quarter, mainly due to higher grades processed. Cost of sales per pound7 and C1 cash costs per pound6 in the fourth quarter of 2021 were in line with the prior quarter. All-in sustaining costs per pound6 increased by 23% compared to the prior quarter, primarily due to higher minesite sustaining capital expenditures6 that were previously deferred as a result of Covid-19 movement restrictions earlier in the year.
Copper production in 2021 of 97 million pounds was within the guidance range of 90 to 110 million pounds. Cost metrics per pound were above the guidance ranges mainly due to cost overruns relating to site maintenance. Cost of sales per pound7 for 2021 was $3.19 compared to guidance of $2.30 to $2.50 per pound. C1 cash costs per pound6 was $2.38 compared to guidance of $1.65 to $1.85 per pound, and all-in sustaining costs per pound6 was $2.94 compared to guidance of $1.90 to $2.10 per pound.

Jabal Sayid (50% basis), Saudi Arabia
Jabal Sayid's copper production in the fourth quarter of 2021 was 11% higher compared to the prior quarter, mainly due to increased throughput. Cost of sales per pound7 and C1 cash costs per pound6 in the fourth quarter of 2021 were 10% and 18% lower, respectively, than the prior quarter mainly due to the impact of higher sales volume. All-in sustaining costs per pound6 in the fourth quarter of 2021 decreased by 18% when compared to the prior quarter, mainly due to the lower C1 cash costs per pound6, with minesite sustaining capital expenditures6 remaining consistent with the prior quarter.
Copper production in 2021 of 76 million pounds was near the midpoint of the guidance range of 70 to 80 million pounds, with the mine exceeding expectations on grade and the mill delivering across all quarters. Cost of sales per pound7 for 2021 was $1.38, finishing below the guidance range of $1.40 to $1.60 per pound. C1 cash costs per pound6 were $1.18, which was within the guidance range of $1.10 to $1.30 per pound. All-in sustaining costs per pound6 were $1.33, also within guidance of $1.30 to $1.50 per pound.

BARRICK YEAR-END 2021
74
MANAGEMENT’S DISCUSSION AND ANALYSIS

Growth Project Updates

Goldrush Project, Nevada, USA
Since the conclusion of the public scoping period in September 2021, the Bureau of Land Management’s (“BLM”) Environmental Impact Statement (“EIS”) contractor (Stantec) has completed the Draft EIS (“DEIS”) documents. The draft documents will be reviewed by the local, state, and federal BLM offices before being made available for public review and comment. We expect the public review period for the DEIS to begin in the first quarter of 2022, and it will last for 45 days. Public meetings will be held to gather comments and answer questions from the public. Comments gathered during the public review of the DEIS will then be addressed in the Final EIS (“FEIS”) documents. We continue to expect the issuance of a Record of Decision (“ROD”) in the second half of 2022, which is reflected in the current mine plan.
As the permitting process progresses, mine development has continued in the Red Hill mining zone at Goldrush. Development is currently focused on the upper portions of Red Hill, where dewatering of the ore body is not required. Additionally, the Multi-Purpose Drift (“MPD”) continues to be developed to the north over the top of the orebody. The MPD will serve as a platform for continued underground exploration drilling of the Red Hill and Crow mining zones. Test mining of underground longhole stopes commenced in November 2021. Test stoping will allow for the validation of mining rock mass conditions and increase the amount of ore available for bulk metallurgical testing through the Carlin roasters.
Capital purchases of mobile mining equipment continued in the fourth quarter of 2021. Assembly has begun on a modular dry facility just outside of the existing office/shop facility near the Cortez Hills Open Pit. Engineering work is progressing on Ventilation Raise #1 (“VR1”), the materials handling system, and the underground backfill system. The drilling of test wells for the first three dewatering wells is currently expected to begin in the third quarter of 2022.
The headcount ramp-up at Goldrush also continues, with 127 NGM employees on-site at year-end. Headcount is planned to increase to 233 over the course of 2022.
As at December 31, 2021, we have spent $290 million on a 100% basis (including $26 million in the fourth quarter of 2021) on the Goldrush project, inclusive of the exploration declines. This capital spent to date, together with the remaining expected pre-production capital (until commercial production begins in 2025), is anticipated to be slightly less than the $1 billion initial capital estimate previously disclosed for the Goldrush project (on a 100% basis).

Turquoise Ridge Third Shaft, Nevada, USA14
Construction of the Third Shaft at Turquoise Ridge, which has a hoisting capacity of 5,500 tonnes per day, continues to advance according to schedule and within budget. We continue to expect commissioning in late 2022. Together with increased hoisting capacity, the Third Shaft is expected to provide additional ventilation for underground mining operations as well as shorter haulage distances.
Construction activities continued in the fourth quarter of 2021, focusing on shaft steel installation. At the
end of the quarter, shaft steel equipping reached 28% completion as measured by steel weight. Furthermore, commissioning of the concrete/shotcrete slick line was successfully completed, construction on the 2280 level materials handling system restarted and surface construction of the additional main exhaust fan at the No. 1 Shaft began. Permanent conveyance deliveries have started and a contract is now in place for the construction of the change house facility, which will commence in 2022. The focus of the project will remain on shaft equipping for the first quarter of 2022, followed by final headframe refit.
As at December 31, 2021, we have spent $222 million (including $7 million in the fourth quarter of 2021) out of an estimated capital cost of approximately $300-$330 million (100% basis).

Pueblo Viejo Expansion, Dominican Republic15
The Pueblo Viejo plant expansion and mine life extension project is designed to increase throughput to 14 million tonnes per annum, allowing the operation to maintain minimum average annual gold production of approximately 800,000 ounces after 2022 (100% basis).
Engineering design of the plant expansion continued to progress during the fourth quarter of 2021 and is now essentially complete (from 97% as of the third quarter of 2021). 94% of the contracts and purchase orders have been placed. Steel fabrication is now complete and 91% of the manufactured steel required had been shipped at the end of the fourth quarter of 2021.
Construction for the plant expansion is now 26% complete (from 16% as of the third quarter of 2021). Earthworks were 75% and civil concrete works were 60% complete at the end of the fourth quarter of 2021. Steel and mechanical installation has started, and will ramp up through the first quarter of 2022 upon the arrival of materials. We expect completion of the plant expansion by the end of 2022.
The social, environmental, and technical studies for additional tailings and mine waste rock capacity continued to advance, including the review of alternative sites, in consultation with the government. Detailed design and engineering of these alternative sites is ongoing. We are continuing to engage with local stakeholders to review concerns and feedback.
As of December 31, 2021, we have incurred $450 million (including $112 million in the fourth quarter of 2021) on the project. As previously disclosed, the project has experienced logistical challenges and related delays primarily due to the impact of the Covid-19 pandemic on the global supply chain, and consequently the capital cost of the project is now estimated at approximately $1.4 billion (100% basis).

Bulyanhulu Re-Start and Optimization
During the fourth quarter of 2021, Bulyanhulu achieved record gold production of 68 thousand ounces (100% basis) since resuming mining operations, which is higher than the 2022 planned quarterly run-rate of 55 to 60 thousand ounces (100% basis). In addition, full commissioning of the grinding and gravity circuits has now been completed, enabling the plant to achieve steady throughput rates of
BARRICK YEAR-END 2021
75
MANAGEMENT’S DISCUSSION AND ANALYSIS

2,500 tonnes per day. As the construction phase of this project has been completed, it will no longer be separately reported in this section of the MD&A.
The internal feasibility study for Bulyanhulu delivered mineral reserve growth of 670 thousand ounces year on year (100% basis), net of 2021 depletion, as a direct result of the underground resource conversion drill program at Deep West. Accordingly, the updated mine plan is now expected to deliver an average of 240 thousand ounces (100% basis) per annum for the majority of the life of mine, in excess of 10 years. Furthermore, mineral reserve conversion drilling is planned to convert the lower half of the Deep West panel during 2022.

Zaldívar Chloride Leach Project, Chile
Zaldívar is jointly owned by Antofagasta and Barrick, and is operated by Antofagasta. In December 2019, the Board of Compañía Minera Zaldívar approved the Chloride Leach Project. The project contemplates the construction of a chloride dosing system, an upgrade of the solvent extraction plant and the construction of additional washing ponds.
During the fourth quarter of 2021, the fourth solvent extraction processing stream (Train D) was modified and recommissioned. Capital is trending in line with the approved budget. Construction of the project was substantially complete at the end of the fourth quarter of 2021 and subsequently completed in January 2022. Commissioning is expected in the first quarter of 2022.
Upon commissioning, the project is expected to increase copper recoveries by more than 10% through the addition of chlorides to the leach solution and with further potential upside in recoveries possible depending on the type of ore being processed. This process is based on a proprietary technology called CuproChlor® that was developed by Antofagasta at its Michilla operation, which had ore types similar to those that are processed at Zaldívar. Once in full operation, the project is expected to increase production at Zaldívar by approximately 10 to 15 thousand tonnes per annum at lower operating costs over the remaining life of mine.
As at December 31, 2021, we have spent $180 million (including $15 million in the fourth quarter of 2021)
out of an estimated capital cost of approximately $189 million (100% basis).

Veladero Phase 7 Leach Pad, Argentina
In November 2021, the board of Minera Andina del Sol approved the Phase 7A leach pad construction project. Construction of Phase 7B will commence following the completion of Phase 7A subject to approval by the Board. Construction on both phases will include sub-drainage and monitoring, leak collection and recirculation, impermeabilization, and pregnant leaching solution collection. Additionally, the north channel (non-contacted water management) will be extended along the leach pad facility.
Construction of Phase 7A commenced in November 2021. Overall project progress was at 20% completion at the end of the fourth quarter of 2021, slightly ahead of schedule. Completion is expected in mid-2022, in line with the mine plan.
As at December 31, 2021, we have spent $10 million out of an estimated capital cost of $75 million (100% basis). Subject to approval by the board of Minera Andina del Sol, construction of Phase 7B is expected to commence in the fourth quarter of 2022.

Veladero Power Transmission, Chile-Argentina
In 2019, we commenced construction of an extension to the existing Pascua-Lama power transmission line to connect to Veladero. Upon completion, the power transmission line will allow Veladero to convert to grid power exported from Chile and cease operating the current high-cost diesel generation power plant located at site. A power purchase price agreement was executed during the fourth quarter of 2019 to supply power from renewable energy that will significantly reduce Veladero’s carbon footprint. This is expected to reduce CO2 equivalent emissions by 100,000 tonnes per year upon commissioning.
We have now completed the construction of the Veladero Power Transmission project, which is expected to be energized in the first half of 2022, subject to final authorization. As of December 31, 2021, we have spent $52 million to complete the project (100% basis).

Exploration and Mineral Resource Management

The foundation of our exploration strategy starts with a deep organizational understanding that exploration is an investment and a value driver for the business - not a process. Our strategy has multiple elements that all need to be in balance to deliver on the Company's business plan for growth and long-term sustainability.
First, we seek to deliver projects of a short-to medium-term nature that will drive improvements in mine plans. Second, we seek to make new discoveries that add to Barrick's Tier One Gold Asset1 portfolio. Third, we seek to optimize the value of major undeveloped projects. Finally, we seek to identify emerging opportunities early in their value chain and secure them by an earn-in or outright acquisition, where appropriate.
Our exploration approach is to first understand the geological framework and ore controls. We then design exploration programs based upon that understanding,
instead of simply drilling for mineralized intervals. This has put us in good stead with robust results from multiple projects highlighted in the following section.

North America
Carlin, Nevada, USA16, 17
At North Leeville, results from the 2021 resource delineation program have delivered a maiden inferred resource of 1.9 million tonnes at 11.5 g/t for 0.70 million ounces (on a 100% basis). The bulk of high-grade mineralization occurs in a 200 meter by 135 meter area, with significant growth opportunity along prospective northwest and north-northeast structures. Additional assay results from hole NLX-00010 extend the previously reported 42.4 meters with a further 14.3 meters of high-grade mineralization, producing a final intercept of 56.7 meters at 28.39 g/t Au. A subsequent hole, NLX-00012, located
BARRICK YEAR-END 2021
76
MANAGEMENT’S DISCUSSION AND ANALYSIS

approximately 60 meters to the east returned two intercepts including 4.3 meters at 8.88 g/t Au and 7.8 meters at 26.03 g/t Au. The results confirm the continuity of mineralization along prominent low angle structural and stratigraphic controls in that direction. Resource delineation drilling will continue into 2022 to capture additional high-value ounces, while exploration drilling will test down-dip opportunities along interpreted feeder faults.
Exploration drifting continued from the south, with underground drilling successfully executing the drill program planned to infill the deposit along its southern extents. Overall, North Leeville is defined as a 1 by 1.2 kilometer zone of stratiform mineralization, primarily hosted at or near the contact of the Devonian Rodeo Creek and Popovich Formations, with high-grade centers focused on northwest and north-northeast structures, defining epicenters of high-value ounces within a rough 200 by 250 meter area, currently constrained only by drilling and open to the south and northeast.
Along the Post-Gen fault corridor beneath the southern margin of the Goldstrike stock, a final drill hole was completed at the Dogma target. While the hole intersected favorable breccia and alteration, the lithology was unfavorable and is expected to return only low-grade mineralization through the targeted zone. Focus along the fertile Post fault corridor has moved north of the Goldstrike stock, where down-dip extensions of several high-grade ore bodies remain open.
Resource delineation drilling at REN was completed in the fourth quarter of 2021, with the addition of a metallurgical core hole to increase the understanding of recoveries within the JB Zone. On a 100% basis, this program has delivered a maiden resource of 50 thousand ounces in the indicated category (0.11 million tonnes at 14.40 g/t Au) and 1.2 million ounces in the inferred category (5.2 million tonnes at 7.3 g/t Au), and has further expanded exploration upside potential. Drilling completed in the fourth quarter of 2021 targeted high upside potential areas outside the newly defined resource footprint and highlighted the potential for resource expansion both on the eastern side of the drift, south of the JB Zone (MRC-21015: 16.6 meters at 9.63 g/t Au, ~100m south of existing underground drilling) and, on the western side of the drift, highlighting the high-grade potential of the Corona Corridor (MRC-21001: 40.2 meters at 27.60 g/t Au in the north and MRC-21011: 16.8 meters at 7.03 g/t Au towards the south). Mineralization in the west remains open north, south and to the west. While on the east, mineralization remains unconstrained by drilling up to 800 meters to the south, at East Banshee.

Cortez, Nevada, USA18
At the Cortez Hills underground mine, drill testing of a fertile fault and inferred feeder below the mine referred to as the Hanson Footwall target was successful. To date, multiple intersections (16.9 meters at 11.24 g/t Au in the third quarter of 2021 and 22.6 meters at 23.07 g/t Au in the fourth quarter of 2021), provide encouragement for expansion along strike and down-dip. Follow-up step-out drill testing is planned to start in early 2022.
Follow-up drilling to grow the deposit westward at the Distal target intersected skarn alteration and quartz-sulfide veins that are associated with the previously encountered Distal mineralization. Further to the northwest, field mapping and sampling highlights additional potential associated with parallel structures containing strong
alteration, and surface gold mineralization. Mapping and sampling is ongoing with drilling planned for 2022 in this new area of the deposit.
Further west at Swift, an exploration earn-in joint venture for Nevada Gold Mines, geologic mapping in conjunction with soil and rock chip sampling was undertaken and has validated and expanded the extents of known surface anomalies. Drilling of a framework core hole was initiated to assess depth and alteration of favorable lower plate carbonate host rocks in an area of sparse drilling and strong surficial geochemistry.

Fourmile, Nevada, USA
At Fourmile, drilling northwest of the Dorothy breccia at the northern extents of known mineralization, returned a narrow interval of high-grade mineralization along with a thick interval of breccia that has anomalous pathfinder geochemistry. This anomalous breccia indicates proximity to mineralization and warrants follow-up work to vector to its source. Further north, mapping continues tracing the northward projection of known fertile faults and the northern margin of the premineral Mill Canyon stock where strong geochemical anomalies are focused. Framework drilling commenced during the fourth quarter of 2021, targeting the intersection of anomalous structures identified from mapping to assess the potential of this frontier area several kilometers north of Fourmile.

Turquoise Ridge, Nevada, USA14
Improvements in the understanding of the Turquoise Ridge district geology continues to be delivered from data mining, re-logging, and section work. Updates to the geologic model using the new interpretations continues to highlight opportunities in the camp and multiple targets have been developed.
Sphinx scout drilling results have all been received, intersecting gold mineralization and strong multi-element leakage along three primary structural corridors. Follow-up drilling to test the down-dip intersection of these fertile faults with favorable host rocks at depth is in progress. Additional reverse circulation (“RC”) drilling in the Fence Line target, towards the Mega Pit, is planned to define the extent of a newly recognized area of strong Carlin-type chemical anomalism. The program planned for 2022 is significantly larger than in recent years.

Hemlo, Canada
Infill drilling is ramping up through 2022 in the western extension (E-Zone). The E-Zone consists of fine grain visible gold associated with deformed quartz-carbonate veining and intense carbonate alteration. This varies from the typical C-Zone mineralization to the east, which is mainly associated with strong feldspathization, indicating the E-Zone might be a more distal ore zone to the main ore body. A second rig has been added and the E-Zone is on track to add a new mining area near surface, which will be accessible from the 9975 level.
The most significant reserve and resource material was added in the Lower C-Zone, with continuation of the Lower C-Zone high-grade ore shoots defined approximately 200 meters below current development.


BARRICK YEAR-END 2021
77
MANAGEMENT’S DISCUSSION AND ANALYSIS

Uchi Belt, Canada
In the second half of 2021, Barrick executed four exploration earn-in agreements to secure consolidated land packages totaling ~124,000 hectares of highly prospective and underexplored ground in the western Uchi Belt of northern Ontario. The properties cover over 130 kilometers of strike along prospective structural corridors within the belt, and are all early-stage greenfield projects with excellent discovery potential. Each of the option agreements allow Barrick a clear path, through various expenditure and milestone commitments, to earn a minimum 70% interest in the properties.
On the South Uchi option with Kenorland Minerals in the east of the belt, a property-wide till survey has been completed and partial results to date have identified an anomalous gold-arsenic train within the eastern half of the property package, coincident with the approximately 40 kilometer long arsenic anomaly identified from legacy lake sediment data. Multiple barren grid lines to the immediate northeast, in the up-ice flow direction from the anomalous area, suggests that the source is proximal.
A Lidar survey was flown over the three western properties in the fourth quarter of 2021, which will be used to map the geomorphology to understand the glaciation history ahead of till surveys when the weather permits in 2022.

Latin America & Asia Pacific
Pueblo Viejo, Dominican Republic15
Delineation work progressed at the Arroyo del Rey target, where mapping identified multiple silica alteration events and rock chip samples yielded mineralization at surface, extending the geochemical footprint of the target to 1.5 by 0.7 kilometers, along a northeast trend which is consistent with historical geophysics anomalies. An induced polarization survey is planned for the first quarter of 2022 to further define targets for drill testing later in the year. The first phase of drilling at the Zambrana Central target failed to intersect a significant system, but did add support to the concept of a blind target below the thrusted Hatillo limestones within the Pueblo Viejo corridor, where significant high chargeability and low magnetic anomalies are present.

Pascua-Lama Project Area, Argentina and Chile
At Pascua, the review of the incoming metallurgical results from the 5,537 meter metallurgical campaign is ongoing. Initial results from bottle roll tests are being reviewed, and variability in data is being correlated to the underlying geology models. Flotation variability testwork results are expected in the first quarter of 2022. Bottle roll tests are showing indicative results that portions of the orebody do recover well through direct cyanidation. As a result, we plan to initiate a small 3,000 meter campaign in the first half of 2022 to test for leachability of these ore types. This work continues in support of our effort to rebuild a geometallurgical model and processing optionality review from first principles data.
At Lama, we began a detailed review of the potential high-sulfidation epithermal targets in the immediate district that could tie into a greater Pascua- Lama project or optionality for Veladero. A drill program is being finalized and will be initiated with two rigs in the first half of 2022, with an objective of defining targets that
warrant future work, or elimination from ongoing optionality reviews.

El Indio Belt, Argentina and Chile
The El Indio Belt spans for over 120 kilometers along the Chile-Argentina border in the high Andes, from Alturas-Del Carmen at the southern end to El Encierro in the north. Barrick controls significant ground over this highly productive and prospective belt. Our exploration efforts have been focused on delineating targets with potential to deliver value, including drill testing in nine different targets during 2021, with an additional six targets at drill-ready stage planned for 2022. Generative work has delivered seven additional targets for delineation, which are expected to represent additional exploration opportunities.
At Alturas-Del Carmen, work in the fourth quarter of 2021 was focused on a drilling campaign at Alturas, to test structural controls within the system that could yield higher-grade controls and preferred ore continuity, within the larger framework of the deposit. Drilling at the Del Carmen targets is expected to resume in the first quarter of 2022.
Two holes drilled at Carmen Norte, located immediately to the north of the Rojo Grande mineralization in Del Carmen, confirmed the presence of porphyry style mineralization, associated with reduced high-sulfidation mineralization in the upper part of the drill holes. However, grades are expected to be weak and a decision on further work will be made when results are received.
A geophysical survey consisting of induced polarization and ground magnetics was completed at the Tayta target in Bañitos identifying a strong conductive area related to a large mineralized stockwork surrounded by a high chargeability anomaly, interpreted to be part of the quartz-sericite-pyrite halo of a sizeable gold-copper porphyry system. One framework drillhole was completed during the fourth quarter of 2021, which intersected intense quartz-pyrite-molybdenite and chalcopyrite mineralization in a favorable, strongly magnetized and altered microdioritic host rock. These observations support the potential for a previously unexplored porphyry target at Tayta and further drilling is being planned.
In Chile, drilling started at the Azufreras target in the El Indio Camp, where three drillholes successfully intercepted high-sulfidation style alteration, associated with different styles of phreatomagmatic breccias below a cover of 250 to 300 meters of a fresh or weakly altered tuff, which creates challenges for the economic potential of the target. Upon the completion of two additional holes that are underway to test for shallower concepts in the target, a decision on further work will be made.

Veladero District, Argentina
At Cerro Pelado, work continued through the fourth quarter of 2021 to consolidate recent drill results into the greater Veladero 3D geological model. The updated model will be drill tested in the first quarter of 2022, with the objective of defining a viable project for inclusion in the Veladero life of mine plan.
Delineation work was carried out at Zancarron, located 39 kilometers to the south of Veladero, in an area containing structurally controlled high-sulphidation veins. Two drillholes were subsequently completed at Zancarron, intersecting several intervals of vuggy silica and silicification that is often associated with high grade in the system.
BARRICK YEAR-END 2021
78
MANAGEMENT’S DISCUSSION AND ANALYSIS

Assays are pending. Additionally, ongoing work shows potential for continuity of the Zancarron system under cover to the southeast, where geochemical results from talus sampling has revealed a 400 meter long gold and copper anomaly associated with alteration, that may represent the upper parts of a high-sulfidation system.

El Quevar, Argentina
Results received from an extensive talus fines sampling campaign at El Quevar has defined five areas for follow-up work within the large (greater than 570 square kilometer) mining property. Consistent pathfinder anomalies (arsenic, antimony, bismuth) of a large, high-sulphidation system have been defined and are coincident with significant structures. This information supports the presence of a fully preserved target.
A controlled-source audio-frequency geophysical survey was completed during the fourth quarter of 2021, and drilling is scheduled to start in the first quarter of 2022.

Porgera, Papua New Guinea
As discussed on page 37 , Porgera is currently on temporary care and maintenance and consequently, all exploration activities have ceased.

Japan Gold Strategic Alliance, Japan
Regional scale geochemical sampling programs along with geophysical gravity surveys have been completed and interpreted over the majority of the portfolio and have led to the identification of a number of exciting target areas for further work. The Japan Gold and Barrick teams are working collaboratively to prioritize these areas of interest and define the follow-up work programs.

Makapa Project, Guyana
Systematic geological and geochemical screening along a 60 kilometer zone of the Makapa-Kuribrong Shear Zone is supporting the interpretation of prospectivity beneath post-mineral sand cover. A wide-spaced air-core drilling program is in progress and low-level gold and pathfinder anomalism in the southeastern extents of the project is coincident with and potentially controlled by a newly interpreted truncated fold closure. Drilling along the shear zone is ongoing.

Reunion Gold Strategic Alliance, Guiana Shield
Drilling commenced on the NW Extension project in Suriname late in the fourth quarter of 2021, and 10 drill holes have been completed to date. The purpose of the program is to geologically and geochemically screen the projection of interpreted structural corridors, similar to those associated with gold mineralization at the Rosebel gold deposit located 70 kilometers to the southeast. Post-mineral cover on average has been less than or equal to 30 meters thick to date and bedrock comprised of volcanics and sediments is broadly consistent with the interpreted geology. Analytical results are pending and the drilling program will continue through the first quarter of 2022.

Africa & Middle East
Bambadji, Senegal
At Bambadji, in addition to doubling our land position over the prospective Faleme Volcanics Domain, further data integration continued to upgrade the geology models, while
geochemistry has generated additional robust anomalies to be tested in the next field season.
Kabewest continues to emerge as a new discovery and further modeling undertaken in the fourth quarter of 2021 supports potential for significant upside. The next phase of drilling is planned to define the down-dip extent of the system and target potentially blind mineralization along strike.
At Soya, a new soil sampling program has already delineated four kilometers of high tenor anomalies to the north with a prospective north-northwest corridor emerging along strike from Gounkoto on the eastern margin of the albitite. An RC drilling program is being designed to test this area and the potential strike extension of the Gounkoto domain boundary into the Bambadji permit.
At Baqata Ridge, additional rock sampling was undertaken to assess the tenor of mineralization in the host sandstone between already defined high-grade quartz-carbonate-hematite-pyrite vein arrays. This new sampling returned values from hematite altered sandstone supporting the high-grade potential of this target. Further mapping and drilling are planned to rapidly progress this Gara-style deposit (an underground mine at Loulo-Gounkoto).

Loulo-Gounkoto, Mali19
At Yalea Ridge, Phase 2 drilling continues with the aim of further defining the extents and footprint of the system, while providing detailed geological information to enable the building of the first integrated 3D geological model of the target. In the fourth quarter of 2021, drilling successfully intersected the system at 400 meters vertical depth with results including: 3.20 meters at 15.53 g/t Au, 12.40 meters at 3.33 g/t Au and 5.23 meters at 9.54 g/t Au. To date, the highest gold grades are associated with sheeted quartz veinlets and hematite-quartz shear veins.
Along strike to the north from Yalea Ridge, at Sansamba West, first pass aircore drilling over previously defined auger anomalies returned encouraging results in a similar geological setting to Yalea Ridge. Intersections associated with hematite alteration included 3.00 meters at 3.05 g/t Au, 6.00 meters at 2.89 g/t Au, including 2.00 meters at 7.36 g/t Au and 8.00 meters at 3.57 g/t Au, including 4.00 meters at 5.77 g/t. This confirms continuity of the system over at least a 1.20 kilometer strike length beyond Yalea Ridge, highlighting the continued prospectivity of this trend.
At Loulo 1-2 Complex (Yalea Structure), the stratigraphic framework has been resolved with recent diamond drilling and historical reverse circulation and diamond drill holes have been relogged within this framework. Next steps are to incorporate the relogged structural architecture and assess complexities that may influence grade and shoot distribution. The outcomes from this model update will dictate subsequent drill planning.
At the Faraba Complex, drilling through 2021 was aimed to assess the continuity of mineralization through this entire complex and figure out the potential for merging two resources into one mineralized system. Drilling has confirmed the continuation of Faraba Main mineralization (footwall zones 1 and 2) 300 meters to the north into Faraba Gap, and main zone 2 mineralization has been traced 280 meters south from Faraba North into Faraba Gap. In addition, the possibility for a high-grade horizontal shoot within the Dip Domain Boundary Structure, beneath the current optimized pit shell has been identified. Overall,
BARRICK YEAR-END 2021
79
MANAGEMENT’S DISCUSSION AND ANALYSIS

results are very encouraging for building a continuous resource through this area. Further infill drilling is required and will be designed and planned for commencement in the first quarter of 2022.
At Gounkoto DB1, located two kilometers to the south of Gounkoto, drill results within the overall DB structure have been weak. However, drilling did intersect 39 meters of high-grade footwall zone mineralization which indicates potential for Gounkoto-style mineralization. Geological modeling is ongoing with further drilling planned for early in the first quarter of 2022.

Tongon, Côte d'Ivoire20
At Seydou North, step-out drilling is confirming an additional 90 meters down-plunge continuity of mineralization at depth. Results include 16.13 meters at 2.32 g/t Au and 10.90 meters at 2.27 g/t Au. Infill resource conversion drilling has returned better than expected results including 35 meters at 8.99 g/t Au and 28 meters at 6.24 g/t Au. Geotechnical drilling to support an updated pit design commenced in January 2022.
Building on auger results along the fertile Stabilo trend from the second quarter of 2021, ten targets were identified, ranked and drill tested in the fourth quarter of 2021. New potential zones of mineralization have been identified at multiple targets with initial results including 15 meters at 3.54 g/t Au from the Koro A2 target and 10 meters at 0.96 g/t Au from the Koro A1 target. Additional high priority targets are Jubula Main and Jubula West. A second phase of drilling to test these targets will commence in 2022.

Regional Exploration, Côte d'Ivoire
At Fonondara on the Boundiali permit, results from two deep diamond drillholes confirmed the extension of mineralization for more than 75 vertical meters and infill drilling to assess satellite potential to Tongon is currently being planned.

Kibali, Democratic Republic of Congo21
At KCD, the third hole and final hole of the deep drilling program was completed, testing 500 meters down plunge of the 9000 and 12000 lode systems. The targeted lodes and related banded iron formation (“BIF”) were not intersected; however, a 150 meter wide zone of alteration with anomalous mineralization was intersected at the 9000 lode targeted depth. Analysis of the data suggests the BIF and lodes have swung slightly to the southeast. The next phase of exploration will commence after additional infill drilling up plunge more clearly defines the trend of these lodes.
Also at KCD, three underground conversion drillholes targeting the high-grade 3106 lode were extended by exploration, to test for opportunities to the northwest of the main KCD system. All holes intersected a new BIF with alteration and anomalous mineralization. This indicates exploration potential to the northwest of the main KCD system between KCD and the Gorumbwa and Kombokolo deposits, opening a kilometer scale exploration play that is very sparsely tested. Additional drilling is being planned.
At Kalimva, the first hole of a 19 hole follow -st the down-plunge continuation of high-grade shoots and to assess the continuity of mineralization between shoots along the structure. This hole was located on the expected edge of the system and confirmed lithologies, structure,
alteration and anomalous mineralization. Remaining holes in this program will continue to be drilled in early 2022.
At Kolapi, the first phase of drilling commenced to test open-pit potential along a 1.6 kilometer section of the prolific KZ structure between the Oere and Mofu pits. Significant results thus far include 4 meters at 3.8 g/t Au, including 1 meter at 6.27 g/t Au. This open-pit opportunity is close to mine infrastructure including the Ikamva-Kalimva-Oere haul road.
At Makoro, fieldwork aims to build geological understanding behind stream sediment and soil anomalies. Observations and results indicate a shear zone system comprising a number of sub parallel structures that extend over two kilometers. Exploration is just commencing but lithosamples and pit groove samples are returning encouraging results. The shear zone remains open along strike towards the northwest and southeast. Exploration and construction of the geology model is ongoing.

North Mara and Bulyanhulu, Tanzania
Building upon work reported in the third quarter of 2021, mapping and rock chip sampling continued at North Mara with a 1,020 square kilometer area completed during the fourth quarter of 2021. This has delivered four new areas of interest over priority targets showing key indicators for mineralization including host rocks, structure, alteration and geochemical pathfinders.
At the Ochuna target, located 45 kilometers west of the Rama deposit, the structural review to update the geology mode has concluded. This work shows several east-northeast and west-northwest zones of higher-grade mineralization, controlled by lithologic contacts and increased vein intensity. Intervening rock between the higher-grade mineralization contains broad halos of lower-grade disseminated pyrite, which increases mineralization continuity in the system. Resource estimation and pit optimization activities are planned for early 2022 to further evaluate this target as a potential new satellite opportunity
At Bulyanhulu, detailed regolith mapping shows prospective geology and mineralized trends are largely covered by lake sediments and river alluvium, preserving the exploration potential of the district. Results from recent geochemical drilling through this cover have generated several priority targets in the northeast of the mining license. Two of these targets are drill-ready for the first quarter of 2022. Program objectives are to discover additional resources that will increase our inventory and introduce open-pit flexibility into the mine plan.

Regional Exploration, Tanzania
After the successful granting of 2,600 square kilometers of new regional permits earlier in 2021, reconnaissance field programs and exploration planning intensified during the fourth quarter of 2021. In the Ndalilo and Maji-Moto districts, over 330 kilometers of traverses were completed leading to the delivery of six priority areas of interest and two new structural corridors with over 10 kilometers of prospective strike (combined) for advancement in the first half of 2022.
Delivering on our strategy of increased investment in new growth opportunities, in partnership with the Government of Tanzania, we have entered into a binding agreement with Tembo Gold Corporation for the acquisition of six highly prospective prospecting licenses adjacent to
BARRICK YEAR-END 2021
80
MANAGEMENT’S DISCUSSION AND ANALYSIS

the Bulyanhulu mining permit. These licenses contain extensions to prospective structures and geology and have the potential to add mineral reserves to Barrick’s asset base in Tanzania. This transaction is subject to customary regulatory approvals, which are expected to be complete in the first quarter of 2022. Reconnaissance programs are currently being designed for implementation as soon as approvals are complete.

Egypt, Regional Exploration
In Egypt, the administrative and technical setup in-country is progressing. Field visits to the four licenses areas were undertaken in the fourth quarter of 2021. Field observations validate regional spectral interpretation from satellite imagery. Detailed alteration, lithological and structural mapping is underway using high-resolution, multi-spectral satellite imagery to aid rapid testing of ground and targets during the first year field program in 2022.


Jabal Sayid, Kingdom of Saudi Arabia22
At Jabal Sayid Lode 1, exploration drilling intersected significant copper mineralization of 135.7 meters at 1.93% Cu, indicating strong potential to grow the Lode 1 resource along strike and down-plunge to the southwest. Geological observations from this part of the deposit continue to support the presence of a conceptual feeder at depth, with infill drilling planned for the first half of 2022.
Ongoing exploration continues to identify multiple new opportunities along the target palaeosurface along strike from Lode 4. A key exploration focus is the North Gossan target located 500 meters north of Lode 4. Multiple zones of VMS-style alteration within the favorable rhyolite host stratigraphy was observed in exploration drilling in the fourth quarter of 2021. Additional gaps, including around known lodes and possible new mineralization along strike to the south-southwest will be advanced in 2022, including the South Gossan and Wadi Ghafara targets.


BARRICK YEAR-END 2021
81
MANAGEMENT’S DISCUSSION AND ANALYSIS

REVIEW OF FINANCIAL RESULTS

Revenue
($ millions, except per ounce/pound data in dollars) For the three months ended For the years ended
   12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Gold
000s oz solda
1,234  1,071  4,468  4,879  5,467 
000s oz produceda
1,203  1,092  4,437  4,760  5,465 
Market price
($/oz)
1,795  1,790  1,799  1,770  1,393 
Realized price ($/oz)b
1,793  1,771  1,790  1,778  1,396 
Revenue
2,977  2,531  10,738  11,670  9,186 
Copper
millions lbs solda
113  101  423  457  355 
millions lbs produceda
126  100  415  457  432 
Market price
($/lb)
4.40  4.25  4.23  2.80  2.72 
Realized price ($/lb)b
4.63  3.98  4.32  2.92  2.77 
Revenue
263  209  962  697  393 
Other sales 70  86  285  228  138 
Total revenue 3,310  2,826  11,985  12,595  9,717 
a.On an attributable basis.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.

Both 2021 gold and copper production of 4.44 million ounces and 415 million pounds, respectively, were within the guidance ranges of 4.4 to 4.7 million ounces and 410 to 460 million pounds, respectively.

Q4 2021 compared to Q3 2021
In the fourth quarter of 2021, gold revenues increased by 18% compared to the third quarter of 2021 primarily due to higher sales volume, combined with a higher realized gold price4. The average market price for the three month period ended December 31, 2021 was $1,795 per ounce versus $1,790 per ounce for the prior quarter. During the fourth quarter of 2021, the gold price ranged from $1,746 per ounce to $1,877 per ounce and closed the quarter at $1,806 per ounce. Gold prices in the fourth quarter of 2021 continued to be volatile as a result of impacts relating to the Covid-19 pandemic, including the progress of vaccine distribution and emergence of variants, as well as growing concerns about increased levels of inflation and expectations for continued economic recovery that are forecast to lead to increases in benchmark interest rates in the near future.









ATTRIBUTABLE GOLD PRODUCTION VARIANCE (000s oz)
Q4 2021 compared to Q3 2021

q4vq3proda.jpg

In the fourth quarter of 2021, attributable gold production was 111 thousand ounces higher than the prior quarter, primarily due to the strong performance from Carlin and Cortez following the repair of the Goldstrike roaster completed at the end of the third quarter of 2021, which allowed for increased processing of material mined from both sites. Gold sales volume also benefited as Veladero sold a portion of its built-up gold inventory.
Copper revenues in the fourth quarter of 2021 increased by 26% compared to the prior quarter, primarily due to a higher realized copper price6, combined with higher copper sales volume. The average market price in the fourth quarter of 2021 was $4.40 per pound versus $4.25 per pound in the prior quarter. In the fourth quarter of 2021, the realized copper price6 was higher than the market copper price due to the impact of positive provisional pricing adjustments, whereas a negative provisional pricing adjustment was recorded in the prior quarter. During the fourth quarter of 2021, the copper price ranged from $4.10 per pound to $4.66 per pound and closed the quarter at $4.40 per pound. Copper prices in the fourth quarter of 2021 were positively influenced by economic optimism following the lifting of some pandemic related restrictions, supply constraints and low copper stockpiles.
Attributable copper production in the fourth quarter of 2021 increased by 26 million pounds compared to the prior quarter, primarily at Lumwana due to increased throughput levels. Copper sales were lower than production, primarily due to the timing of shipments at Lumwana.

2021 compared to 2020
In 2021, gold revenues decreased by 8% compared to the prior year, primarily due to a decrease in sales volumes, partially offset by an increase in the realized gold price6.
BARRICK YEAR-END 2021
82
MANAGEMENT’S DISCUSSION AND ANALYSIS

The average market gold price for 2021 was $1,799 per ounce versus $1,770 per ounce in the prior year.
In 2021, attributable gold production was 4,437 thousand ounces, or 323 thousand ounces lower than the prior year, mainly due to the mechanical mill failure at Carlin’s Goldstrike roaster, Porgera being placed on care and maintenance on April 25, 2020, lower underground productivity related to Covid-19 restrictions that slowed the ramp-up of underground development at Hemlo, and lower grades and throughput at Tongon reflecting the change in the mine plan related to the previously disclosed mine life extension to 2023. This was combined with reduced heap leach processing operations at Veladero through the first half of 2021 due to Covid-19 related delays in the commissioning of Phase 6 of the leach pad and lower grades processed in line with the mine and stockpile processing plan at Pueblo Viejo. These impacts were partially offset by increased production at Bulyanhulu following the ramp-up of underground mining and processing operations starting near the end of 2020. Gold sales were higher than gold production in 2021 as Veladero sold a portion of its built-up gold inventory. In 2020, gold sales were higher than gold production following the re-commencement of exports of concentrate stockpiled in Tanzania, which was completed in the third quarter of 2020.

ATTRIBUTABLE GOLD PRODUCTION VARIANCE (000s oz)
Year ended December 31, 2021
ytdprod.jpg
*Other consists primarily of Porgera, Tongon, Hemlo and Buzwagi.

Copper revenues for 2021 were up 38% compared to the prior year due to a higher realized copper price6, partially offset by lower copper sales volume. In both 2021 and 2020, the realized copper price6 was higher than the market copper price as a result of positive provisional pricing adjustments to copper sales that were subject to finalization at the end of each year.
Attributable copper production for 2021 was 42 million pounds lower than the prior year, mainly due to lower grades processed and lower throughput at Lumwana.

Production Costs
($ millions, except per ounce/pound data in dollars) For the three months ended For the years ended
   12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Gold
Site operating costs 1,157  1,025  4,218  4,421  4,274
Depreciation 512  475  1,889  1,975  1,902
Royalty expense 93  93  371  410  308
Community relations 9  26  26  30
Cost of sales 1,771  1,601  6,504  6,832  6,514
Cost of sales
($/oz)a
1,075  1,122  1,093  1,056  1,005
Total cash costs ($/oz)b
715  739  725  699  671
All-in sustaining costs ($/oz)b
971  1,034  1,026  967  894
Copper
Site operating costs 63  73  266  292  224
Depreciation 43  60  197  208  100
Royalty expense 28  27  103  54  34
Community relations 0  3  3
Cost of sales 134  162  569  556  361
Cost of sales
($/lb)a
2.21  2.57  2.32  2.02  2.14
C1 cash costs ($/lb)b
1.63  1.85  1.72  1.54  1.69
All-in sustaining costs ($/lb)b
2.92  2.60  2.62  2.23  2.52
a.Gold cost of sales per ounce is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share). Copper cost of sales per pound is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.

Q4 2021 compared to Q3 2021
In the fourth quarter of 2021, cost of sales applicable to gold was 11% higher compared to the third quarter of 2021, primarily as a result of higher sales volume. Our 45% interest in Kibali is equity accounted and we therefore do not include its cost of sales in our consolidated gold cost of sales. On a per ounce basis, cost of sales applicable to gold7 and total cash costs6, after including our proportionate share of cost of sales at our equity method investees, were 4% and 3% lower, respectively, than the prior quarter, primarily at Cortez due to sales mix with a higher proportion from lower cost underground production and at Carlin resulting from continued cost discipline, offset by the impact of planned maintenance and higher natural gas prices at Pueblo Viejo.
In the fourth quarter of 2021, gold all-in sustaining costs4 decreased by 6% on a per ounce basis compared to the prior quarter, primarily due to lower total cash costs per
BARRICK YEAR-END 2021
83
MANAGEMENT’S DISCUSSION AND ANALYSIS

ounce6 as discussed above, combined with lower minesite sustaining capital expenditures6 on a per ounce basis.
In the fourth quarter of 2021, cost of sales applicable to copper was 17% lower than the prior quarter, primarily due to lower depreciation and higher capitalized stripping, partially offset by higher mining costs at Lumwana. Our 50% interests in Zaldívar and Jabal Sayid are equity accounted and therefore we do not include their cost of sales in our consolidated copper cost of sales. On a per pound basis, cost of sales applicable to copper7 and C1 cash costs6, after including our proportionate share of cost of sales at our equity method investees, decreased by 14% and 12%, respectively, compared to the prior quarter primarily due to higher capitalized stripping, partially offset by higher mining costs at Lumwana. Cost of sales per pound was further impacted by lower depreciation expense at Lumwana.
In the fourth quarter of 2021, copper all-in sustaining costs6, which have been adjusted to include our proportionate share of equity method investees, were 12% higher per pound than the prior quarter, primarily reflecting higher minesite sustaining capital expenditures6 at Lumwana mainly related to new mining equipment and stripping, partially offset by lower C1 cash costs per pound4.

2021 compared to 2020
In 2021, cost of sales applicable to gold was 5% lower than the prior year primarily due to lower sales volume. On a per ounce basis, cost of sales applicable to gold7, after including our proportionate share of cost of sales at our equity method investees, and total cash costs per ounce6 were both 4% higher than the prior year, primarily due to the impact of lower grades, mainly at Tongon and North Mara.
In 2021, gold all-in sustaining costs per ounce6 increased by 6% compared to the prior year primarily due to higher total cash costs per ounce6, combined with higher minesite sustaining capital expenditures6.
In 2021, cost of sales applicable to copper was 2% higher than the prior year, primarily due to higher royalties at Lumwana, which is a function of a higher realized copper price6. Our 50% interests in Zaldívar and Jabal Sayid are equity accounted and therefore we do not include their cost of sales in our consolidated copper cost of sales. On a per pound basis, cost of sales applicable to copper7 and C1 cash costs6, after including our proportionate share of cost of sales at our equity method investees, increased by 15% and 12%, respectively, compared to the prior year, primarily due to higher royalty expense as a result of a higher realized copper price6 and the impact of lower sales volume.
Copper all-in sustaining costs per pound6 was 17% higher than the prior year, primarily reflecting the higher total C1 cash costs per pound6, combined with higher minesite sustaining capital expenditures6.

2021 compared to Guidance
2021 cost of sales applicable to gold7 was $1,093 per ounce, slightly higher than our guidance range of $1,020 to $1,070 per ounce. Gold total cash costs6 for 2021 of $725 per ounce was at the higher end of the guidance range of $680 to $730, while all-in sustaining costs6 for 2021 of $1,026 per ounce was slightly higher than the guidance range of $970 to $1,020 per ounce. The higher gold cost metrics are mainly driven by the Nevada Mining Education
Tax, which became effective on July 1, 2021 and therefore was not factored into our guidance for the year (refer to page 50 ), as well as higher royalty expense due to a higher realized gold price6 .
2021 cost of sales applicable to copper7 and C1 cash costs6 were $2.32 per pound and $1.72 per pound, respectively, higher than our guidance ranges of $1.90 to $2.10 per pound and $1.40 to $1.60 per pound, respectively. 2021 copper all-in sustaining costs6 of $2.62 per pound was also higher than our guidance range of $2.00 to $2.20 per pound. All copper cost metrics for the year were above guidance due to the impact of lower production, higher maintenance costs at Zaldívar and higher royalty expense driven by a higher realized copper price6.

Capital Expendituresa
($ millions) For the three months ended For the years ended
   12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Minesite sustainingb,c
431  386  1,673 1,559  1,320 
Project capital expendituresb,d
234  179  747 471  370 
Capitalized interest 4  15 24  11 
Total consolidated capital expenditures 669  569  2,435 2,054  1,701 
Attributable capital expenditurese
552  456  1,951 1,651  1,512 
2021 Attributable capital expenditures guidancee
$1,800
to
$2,100
a.These amounts are presented on a cash basis.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.Includes both minesite sustaining and mine development.
d.Project capital expenditures are included in our calculation of all-in costs, but not included in our calculation of all-in sustaining costs.
e.These amounts are presented on the same basis as our guidance on page 41 .

Q4 2021 compared to Q3 2021
In the fourth quarter of 2021, total consolidated capital expenditures on a cash basis were 18% higher than the third quarter of 2021, due to an increase in both minesite sustaining capital expenditures6 and project capital expenditures6. Minesite sustaining capital expenditures6 increased by 12% compared to the prior quarter, primarily at Lumwana due to new mining equipment and stripping, at North Mara from the initial capital spend on the restart of the open-pit mine, and at Bulyanhulu mainly for the long-term underground fleet. Project capital expenditures6 increased by 30% primarily due to the plant expansion and mine life extension project at Pueblo Viejo, the development of the third underground mine and expansion of power capacity at Loulo-Gounkoto, and the commencement of construction for the Phase 7A leach pad at Veladero.

2021 compared to 2020
In 2021, total consolidated capital expenditures on a cash basis increased by 19% compared to the prior year. This was primarily due to a 59% increase in project capital
BARRICK YEAR-END 2021
84
MANAGEMENT’S DISCUSSION AND ANALYSIS

expenditures6 mainly attributable to the Pueblo Viejo plant expansion and mine life extension project, as well as the development of the third underground mine and expansion of power capacity at Loulo-Gounkoto. This was partially offset by a decrease at Cortez due to lower cost development and exploration activities at Goldrush underground. The increase in project capital expenditures6 was combined with higher minesite sustaining capital expenditures6 of 7%, mainly resulting from the Phase 6 leach pad expansion at Veladero, and at Carlin due to an increase in capitalized waste stripping and the purchase of an oxygen plant at the Goldstrike autoclave. This was combined with an increase at Turquoise Ridge relating to underground equipment purchases and process efficiency related projects.

2021 compared to Guidance
Attributable capital expenditures for 2021 of $1,951 million was at the lower end of the guidance range of $1,800 to $2,100 million.

General and Administrative Expenses 
($ millions) For the three months ended For the years ended 
   12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Corporate administrationa
32  23  118 118  148 
Share-based compensationb
7  33 67  37 
Tanzaniac
0  0 27 
General & administrative expenses 39  27  151 185  212 
2021 General & administrative expenses guidance ~$190
a.For the three months and year ended December 31, 2021, corporate administration costs include approximately $nil and $nil, respectively, of severance costs (September 30, 2021: $nil; 2020 $nil; 2019: $18 million).
b.Based on US$19.00 share price as at December 31, 2021 (September 30, 2021: US$18.24; 2020: US$22.78; 2019: $18.59) and excludes share-based compensation relating to Tanzania.
c.Formerly known as Acacia Mining plc.

Q4 2021 compared to Q3 2021
In the fourth quarter of 2021, general and administrative expenses increased by $12 million compared to the third quarter of 2021, primarily due to higher spend on external services.

2021 compared to 2020
General and administrative expenses decreased by $34 million compared to the prior year due to lower share-based compensation expense as a result of our lower share price in the current period compared to an increase in the same prior year period.

2021 compared to Guidance
General and administrative expenses were lower than guidance of ~$190 million. Corporate administration expenses of $118 million were below our guidance of ~$130 million, highlighting the continued benefit of our cost reduction activities, while share-based compensation expense of $33 million was lower than our guidance of ~$60 million, resulting from a decrease in our share price.
Exploration, Evaluation and Project Costs
($ millions) For the three months ended For the years ended
   12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Global exploration and evaluation 35  26  122 143  143 
Project costs:
Pascua-Lama 16  46 37  49 
   Other 11  39 27  20 
Corporate development 8  16 51 
Business improvement and innovation 0  0 10 
Global exploration and evaluation and project expense 70  47  223 216  273 
Minesite exploration and evaluation 12  20  64 79  69 
Total exploration, evaluation and project expenses 82  67  287 295  342 
2021 total E&E and project expenses guidance $280
to
$320

Q4 2021 compared to Q3 2021
Exploration, evaluation and project expenses for the fourth quarter of 2021 increased by $15 million compared to the prior quarter. This was primarily due to higher project costs at Pascua-Lama and higher global exploration and evaluation costs mainly at Nevada Gold Mines due to increased drilling. This was partially offset by lower minesite exploration and evaluation costs, primarily at Carlin.

2021 compared to 2020
Exploration, evaluation and project costs for 2021 decreased by $8 million compared to the prior year, primarily due to lower global exploration and evaluation costs at Fourmile and lower minesite exploration and evaluation costs, mainly at Carlin due to lower drill and crew availability. This was partially offset by higher project costs across various projects.

2021 compared to Guidance
Exploration, evaluation and project expenses for 2021 of $287 million were within the guidance range of $280 to $320 million. Exploration and evaluation costs of $223 million were slightly lower than the guidance range of $230 million to $250 million and project expenses of $64 million were in the middle of the guidance range of $50 million to $70 million.

BARRICK YEAR-END 2021
85
MANAGEMENT’S DISCUSSION AND ANALYSIS

Finance Costs, Net
($ millions) For the three months ended For the years ended
   12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Interest expensea
90  94  357 342  435
Accretion 10  13  48 41  75
Loss on debt extinguishment 0  0 15  3
Interest capitalized (5) (4) (16) (24) (14)
Other finance costs 1  8 1
Finance income (12) (10) (42) (28) (31)
Finance costs, net 84  93  355 347  469
2021 finance costs, net guidance $330
to
$370
a.For the three months and year ended December 31, 2021, interest expense includes approximately $9 million and $35 million, respectively, of non-cash interest expense relating to the gold and silver streaming agreements with Wheaton and Royal Gold, Inc. (September 30, 2021: $8 million; 2020: $34 million; 2019: $103 million).

Q4 2021 compared to Q3 2021
In the fourth quarter of 2021, finance costs, net decreased by 10% compared to the prior quarter, mainly due to minor decreases in both interest expense and accretion, combined with marginally higher finance income.

2021 compared to 2020
In 2021, finance costs, net were 2% higher than the prior year, primarily due to higher interest expense, combined with higher accretion resulting from an increase in market interest rates. This was partially offset by a loss on debt extinguishment of $15 million occurring in the same prior year period. The loss on debt extinguishment in the prior year was due to the make-whole repurchase of the outstanding $337 million of principal of our 3.85% notes due 2022.

2021 compared to Guidance
Finance costs, net for 2021 of $355 million were within the guidance range of $330 to $370 million.


Additional Significant Statement of Income Items
($ millions) For the three months ended For the years ended
   12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Impairment charges (reversals) 14  10  (63) (269) (1,423)
Loss on currency translation 13  29  50  109 
Other (income) expense (130) 18  (67) (178) (3,100)

Impairment Charges (Reversals)
($ millions) For the three months ended For the years ended
   12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
   Post-tax
(our share)
Post-tax
(our
share)
Post-tax
(our
share)
Post-tax
(our
share)
Post-tax
(our
share)
Asset impairments (reversals)
Lagunas Norte 0  (86) 12 
Pueblo Viejo 0  (2) (277)
Golden Sunlight 12  12 
Hemlo 0  4 
Tanzania (1) 3  (91)
Pascua-Lama 0  1  296 
Nevada Gold Mines 0  0  48 
Lumwana 0  0  (663)
Veladero 0  0 
Other (2) 10  4  15  14 
Total asset impairment charges (reversals) 9  10  (64) (68) (568)
Tax effects and NCI 5  1  (201) (855)
Total impairment charges (reversals) 14  10  (63) (269) (1,423)

Impairment Charges (Reversals)
Q4 2021 compared to Q3 2021
In the fourth quarter of 2021, net impairment charges were $9 million (net of tax and non-controlling interests) compared to $10 million (net of tax and non-controlling interests) in the prior quarter. The net impairment charge in
both the current quarter and prior quarter relate to miscellaneous assets.

2021 compared to 2020
In 2021, we recognized $64 million (net of tax and non-controlling interests) of net impairment reversals for non-current assets. This was mainly due to the impairment reversal at Lagunas Norte of $86 million (net of tax) resulting from the agreement to sell our 100% interest to Boroo. This compares to net impairment reversals of $68 million (net of tax and non-controlling interests) in 2020 mainly from our Tanzanian assets as the agreement with the Government of Tanzania was made effective in the first quarter of 2020.
Refer to note 21 to the Financial Statements for a full description of impairment charges, including pre-tax amounts and sensitivity analysis.

Loss on Currency Translation
Q4 2021 compared to Q3 2021
Loss on currency translation in the fourth quarter of 2021 was $13 million compared to $5 million in the prior quarter. The losses in both quarters mainly relate to unrealized foreign currency translation losses from the depreciation of the Argentine peso. The current quarter was also impacted by the depreciation of the Zambian kwacha, whereas in the prior quarter the appreciation of the Zambian kwacha partially offset the losses on the Argentine peso.
BARRICK YEAR-END 2021
86
MANAGEMENT’S DISCUSSION AND ANALYSIS

Fluctuations in these currencies versus the US dollar revalue our peso and kwacha denominated value-added tax receivable balances.

2021 compared to 2020
Loss on currency translation for 2021 was $29 million compared to $50 million in the prior year. The losses in both years mainly relate to unrealized foreign currency losses from the Argentine peso and the Zambian kwacha, however the rate of depreciation of the Argentine peso moderated compared to the same prior year period. Fluctuations in these currencies versus the US dollar revalue our peso and kwacha denominated value-added tax receivable balances.

Other Expense (Income)
Q4 2021 compared to Q3 2021
In the fourth quarter of 2021, other income was $130 million compared to other expense of $18 million in the prior quarter. Other income in the fourth quarter of 2021 mainly relates to a gain on the sale of Lone Tree of $205 million (refer to note 4 to the Financial Statements for more information), partially offset by a $25 million litigation settlement, $21 million of supplies obsolescence at Buzwagi, and care and maintenance expenses at Porgera. In the prior quarter, other expense primarily relates to care and maintenance expenses at Porgera and losses on the revaluation of warrant investments.

2021 compared to 2020
Other income was $67 million in 2021 compared to $178 million in the prior year. In 2021, we recognized a gain on the sale of Lone Tree of $205 million, partially offset by care and maintenance expenses at Porgera of $51 million, a $25 million litigation settlement and supplies obsolescence at Buzwagi of $21 million. In 2020, other income mainly relates to gains of $180 million reflecting gains on the sale of Eskay Creek ($59 million), Massawa ($54 million), Morila ($27 million), and Bullfrog ($22 million). Refer to note 4 to the Financial Statements for more information. This was combined with a gain of $104 million on the remeasurement of the residual cash liability relating to our silver sale agreement with Wheaton. This was partially offset by care and maintenance expenses at Porgera of $51 million and donations made to our host communities relating to the Covid-19 pandemic.
For a further breakdown of other expense (income), refer to note 9 to the Financial Statements.

Income Tax Expense
Income tax expense was $1,344 million in 2021. The unadjusted effective income tax rate for 2021 was 29% of the income before income taxes.
The underlying effective income tax rate on ordinary income for 2021 was 27% after adjusting for the impact of net impairment reversals; the impact of deferred taxes at Hemlo; the impact of the sale of long-lived assets; the impact of the settlement of the Massawa Senegalese Tax Dispute; the impact of tax reform measures in Argentina; the impact of foreign currency translation gains and losses on tax balances; the impact of non-deductible foreign exchange losses; the impact of the Porgera mine being placed on care and maintenance; the impact of the recognition and de-recognition of deferred tax assets; and the impact of other expense adjustments.
We record deferred tax charges or credits if changes in facts or circumstances affect the estimated tax basis of assets and therefore, the expectations in our ability to realize deferred tax assets. The interpretation of tax regulations and legislation as well as their application to our business is complex and subject to change. We have significant amounts of deferred tax assets, including tax loss carry forwards, and also deferred tax liabilities. We also have significant amounts of unrecognized deferred tax assets (e.g. for tax losses in Canada). Potential changes in any of these amounts, as well as our ability to realize deferred tax assets, could significantly affect net income or cash flow in future periods. For further details on income tax expense, refer to note 12 to the Financial Statements.

Reconciliation to Canadian Statutory Rate
For the years ended 12/31/21 12/31/20
At 26.5% statutory rate 1,228  1,311 
Increase (decrease) due to:
Allowances and special tax deductionsa
(138) (151)
Impact of foreign tax ratesb
(84) (32)
Expenses not tax deductible 118  154 
Taxable gains on sales of long-lived assets 24 
Net currency translation (gains) losses on current and deferred tax balances 23  (19)
Tax impact from pass-through entities and equity accounted investments (330) (309)
Current year tax gains not recognized (18) (9)
Recognition and de-recognition of deferred tax assets (31) (61)
Adjustments in respect of prior years 24  (53)
Increase to income tax related contingent liabilities 19  42 
Impact of tax rate changes 66 
Withholding taxes 110  100 
Mining taxes 323  383 
Tax impact of amounts recognized within accumulated OCI 8  (21)
Other items 2  (4)
Income tax expense 1,344  1,332 
a.We are able to claim certain allowances, incentives and tax deductions unique to extractive industries that result in a lower effective tax rate.
b.We operate in multiple foreign tax jurisdictions that have tax rates different than the Canadian statutory rate.

The more significant items impacting income tax expense in 2021 and 2020 include the following:

Currency Translation
Current and deferred tax balances are subject to remeasurement for changes in currency exchange rates each period. This is required in countries where tax is paid in local currency and the subsidiary has a different functional currency (e.g. US dollars). The most significant balances relate to Argentine and Malian tax liabilities.
In 2021, a tax expense of $23 million arose from translation losses on tax balances, mainly due to the weakening of the Argentine peso and the West African CFA franc against the US dollar. In 2020, a tax recovery of $19 million arose from translation losses and gains on tax balances due to the weakening of the Argentine peso and strengthening of the West African CFA franc, respectively,
BARRICK YEAR-END 2021
87
MANAGEMENT’S DISCUSSION AND ANALYSIS

against the US dollar. These net translation losses (gains) are included within income tax expense (recovery).

Withholding Taxes
In 2021, we have recorded $66 million of dividend withholding taxes related to the undistributed earnings of our subsidiaries in Argentina, Côte d'Ivoire, Saudi Arabia and the United States. We have also recorded $33 million (2020: $87 million, related to Côte d’Ivoire, Tanzania and the United States) of dividend withholding taxes related to the distributed earnings of our subsidiaries in Argentina, Saudi Arabia and the United States.

Accounting for Joint Ventures and Associates
Nevada Gold Mines is a limited liability company treated as a flow through partnership for US tax purposes. The partnership is not subject to federal income tax directly, but
each of its partners is liable for tax on its share of the profits of the partnership. As such, Barrick accounts for its current and deferred income tax associated with the investment (61.5% share) following the principles in IAS 12.

Mining Taxes
Nevada Gold Mines is subject to a Net Proceeds of Minerals tax in Nevada at a rate of 5% and the tax expense recorded in 2021 was $136 million (2020: $149 million). Other significant mining taxes include the Dominican Republic’s Net Profits Interest tax, which is determined based on cash flows as defined by the Pueblo Viejo Special Lease Agreement. A tax expense of $180 million (2020: $212 million) was recorded for this in 2021. Both taxes are included on a consolidated basis in the Company's consolidated statements of income.


Financial Condition Review      
Summary Balance Sheet and Key Financial Ratios    
($ millions, except ratios and share amounts)
As at December 31 2021  2020  2019 
Total cash and equivalents 5,280  5,188  3,314 
Current assets 2,969  2,955  3,573 
Non-current assets 38,641  38,363  37,505 
Total Assets 46,890  46,506  44,392 
Current liabilities excluding short-term debt 2,071  2,200  2,001 
Non-current liabilities excluding long-term debta
7,362  7,441  7,028 
Debt (current and long-term) 5,150  5,155  5,536 
Total Liabilities 14,583  14,796  14,565 
Total shareholders’ equity 23,857  23,341  21,432 
Non-controlling interests 8,450  8,369  8,395 
Total Equity 32,307  31,710  29,827 
Total common shares outstanding (millions of shares) 1,779  1,778  1,778 
Key Financial Ratios:      
   Current ratiob
3.95:1 3.67:1 2.90:1
  Debt-to-equityc
0.16:1 0.16:1 0.19:1
a.Non-current financial liabilities as at December 31, 2021 were $5,578 million (2020: $5,486 million; 2019: $5,559 million).
b.Represents current assets (excluding assets held-for-sale) divided by current liabilities (including short-term debt and excluding liabilities held-for-sale) as at December 31, 2021, December 31, 2020 and December 31, 2019.
c.Represents debt divided by total shareholders’ equity (including minority interest) as at December 31, 2021, December 31, 2020, and December 31, 2019.


Balance Sheet Review
Total assets were $46.9 billion at December 31, 2021, slightly higher than total assets at December 31, 2020.
Our asset base is primarily comprised of non-current assets such as property, plant and equipment and goodwill, reflecting the capital-intensive nature of the mining business and our history of growth through acquisitions. Other significant assets include production inventories, indirect taxes recoverable and receivable, concentrate sales receivables, other government transaction and joint venture related receivables, and cash and equivalents.
Total liabilities at December 31, 2021 were $14.6 billion, slightly lower than total liabilities at December 31, 2020. Our liabilities are primarily comprised of debt, other non-current liabilities such as provisions and deferred income tax liabilities, and accounts payable.
Shareholders’ Equity
February 8, 2022 Number of shares
Common shares 1,779,331,037 
Stock options — 

Financial Position and Liquidity
We believe we have sufficient financial resources to meet our business requirements for the foreseeable future, including capital expenditures, working capital requirements, interest payments, share buybacks and dividends. To date, we have not experienced significant negative impacts to liquidity as a result of the Covid-19 pandemic. During 2021, our cash balance benefited from strong cash flow from operating activities and cash exceeded debt as at December 31, 2021, for the second
BARRICK YEAR-END 2021
88
MANAGEMENT’S DISCUSSION AND ANALYSIS

year in a row, despite a record $1.4 billion in cash returns paid to shareholders in 2021, inclusive of a $750 million return of capital distribution.
Total cash and cash equivalents as at December 31, 2021 were $5.3 billion. This cash and cash equivalents balance does not include cash held by our equity method investments, including approximately $500 million (our share) at Kibali. The cash and cash equivalents held at Kibali are subject to various steps before they can be distributed to the joint venture shareholders and are held across three banks in the Democratic Republic of Congo, including two domestic banks. Our capital structure comprises a mix of debt, non-controlling interest (primarily at Nevada Gold Mines) and shareholders’ equity. As at December 31, 2021, our total debt was $5.2 billion (debt net of cash and equivalents was negative $130 million) and our debt-to-equity ratio was 0.16:1. This compares to debt as at December 31, 2020 of $5.2 billion (debt, net of cash and cash equivalents was negative $33 million), and a debt-to-equity ratio of 0.16:1.
In 2022, we have capital commitments of $425 million and expect to incur attributable sustaining and project capital expenditures6 of approximately $1,900 to $2,200 million in 2022 based on our guidance range on page 40 . In 2022, we have $308 million in interest payments and other amounts as detailed in the table on page 91 . In addition, we have contractual obligations and commitments of $658 million in purchase obligations for supplies and consumables. We expect to fund these commitments through operating cash flow, which is our primary source of liquidity, as well as existing cash balances.
Our operating cash flow is dependent on the ability of our operations to deliver projected future cash flows. The market prices of gold, and to a lesser extent copper, are the primary drivers of our operating cash flow. Other options to enhance liquidity include further portfolio optimization and the creation of new joint ventures and partnerships; issuance of equity securities in the public markets or to private investors, which could be undertaken for liquidity enhancement and/or in connection with establishing a strategic partnership; issuance of long-term debt securities in the public markets or to private investors (Moody’s and S&P currently rate Barrick’s outstanding long-term debt as investment grade, with ratings of Baa1 and BBB, respectively); and drawing on the $3.0 billion available under our undrawn Credit Facility (subject to compliance with covenants and the making of certain representations and warranties, this facility is available for drawdown as a source of financing). In May 2021, we amended the credit and guarantee agreement (the “Credit Facility”) with certain Lenders, which requires such Lenders to make available to us a credit facility of $3.0 billion or the equivalent amount in Canadian dollars. The Credit Facility, which is unsecured, currently has an interest rate of London Interbank Offered Rate (“LIBOR”) plus 1.125% on drawn amounts, and a standby rate of 0.11% on undrawn amounts. The Credit Facility also includes terms to replace LIBOR with a suitable replacement once that matter is resolved. As part of the amendment, the termination date of the Credit Facility was extended from January 2025 to May 2026. The Credit Facility was undrawn as at December 31, 2021. The key financial covenant in our undrawn credit facility requires Barrick to maintain a net debt to total capitalization ratio of less than 0.60:1. Barrick’s net debt to total capitalization
ratio was 0.00:1 as at December 31, 2021 (0.00:1 as at December 31, 2020).

Summary of Cash Inflow (Outflow)
($ millions) For the three months ended For the years ended
  12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Net cash provided by operating activities 1,387  1,050  4,378  5,417  2,833 
Investing activities
Capital expenditures (669) (569) (2,435) (2,054) (1,701)
Investment (purchases) sales (46) (46) 220 
Cash acquired in Merger 0  0  751 
Divestitures 8  27  283  750 
Dividends received from equity method investments 306  53  520  141  217 
Other 14  17  37  124  33 
Total investing (outflows) inflows (387) (499) (1,897) (1,286) 50 
Financing activities
Net change in debta
(5) (5) (27) (379) (309)
Dividendsb
(159) (158) (634) (547) (548)
Return of Capital (250) (250) (750)
Net disbursements to non-controlling interests (363) (270) (1,092) (1,356) (281)
Other 14  37  115  28  (1)
Total financing outflows (763) (646) (2,388) (2,254) (1,139)
Effect of exchange rate 0  (1) (3) (1)
Increase (decrease) in cash and equivalents 237  (95) 92  1,874  1,743 
a.The difference between the net change in debt on a cash basis and the net change on the balance sheet is due to changes in non-cash charges, specifically the unwinding of discounts and amortization of debt issue costs.
b.For the three months and year ended December 31, 2021, we declared and paid dividends per share in US dollars totaling $0.09 and $0.36, respectively (September 30, 2021: declared and paid $0.09; 2020: declared and paid $0.31; 2019: declared $0.13 and paid $0.20, and also paid $2.69 per share to Randgold shareholders).

Q4 2021 compared to Q3 2021
In the fourth quarter of 2021, we generated $1,387 million in operating cash flow, compared to $1,050 million in the prior quarter. The increase of $337 million was primarily due to lower cash taxes paid, combined with an increase in realized gold and copper prices6 as well as higher gold and copper sales volumes. Operating cash flow was further impacted by lower cost of sales per ounce/pound7. These impacts were partially offset by an unfavorable movement in working capital, mainly in other current assets and
BARRICK YEAR-END 2021
89
MANAGEMENT’S DISCUSSION AND ANALYSIS

receivables, which was partially offset by a favorable movement in inventory.
Cash outflows from investing activities in the fourth quarter of 2021 were $387 million, compared to $499 million in the prior quarter. The decreased outflow was primarily due to an increase in dividends from our equity method investments, partially offset by an increase in capital expenditures. Cash outflows from investing activities was further impacted by the purchase of i-80 Gold shares by NGM pursuant to the Exchange Agreement to acquire the 40% interest in South Arturo that NGM did not already own in exchange for the Lone Tree and Buffalo Mountain properties and infrastructure.
Net financing cash outflows for the fourth quarter of 2021 amounted to $763 million, compared to $646 million in the prior quarter. The increase of $117 million is primarily due to an increase in disbursements to non-controlling interests, primarily to Newmont in relation to their interest in Nevada Gold Mines.

2021 compared to 2020
In 2021, we generated $4,378 million in operating cash flow, compared to $5,417 million in the prior year. The decrease of $1,039 million was primarily due to higher cash taxes paid, lower gold and copper sales volumes and higher cost of sales per ounce/pound7. This was partially offset by higher realized gold and copper prices6.
Cash outflows from investing activities for 2021 were $1,897 million compared to $1,286 million in the prior year. The increased outflow of $611 million was primarily due to an increase in capital expenditures, namely the Pueblo Viejo plant expansion and mine life extension project, as well as the development of the third underground mine and expansion of power capacity at Loulo-Gounkoto. This was combined with cash proceeds of $283 million from the sale of Massawa as well as net investment sales of $220 million mainly from the sale of shares in Shandong Gold, both occurring in the prior year. These impacts were partially offset by higher dividends received from our equity method investments, specifically Jabal Sayid, Zaldívar and Kibali, in the current year.
Net financing cash outflows for 2021 amounted to $2,388 million, compared to $2,254 million in the prior year. The higher outflow of $134 million is primarily due to the payment of the $750 million return of capital distribution in 2021 and higher dividends paid, reflecting Barrick's continued strong financial performance. This was partially offset by the make-whole repurchase of the outstanding $337 million of principal of our 3.85% notes due 2022 in January 2020 and a decrease in disbursements to non-controlling interests, primarily to Newmont in relation to their interest in Nevada Gold Mines, in the current year.


Summary of Financial Instrumentsa
As at December 31, 2021
Financial Instrument Principal/Notional Amount
 Associated  Risks
n  Interest rate
Cash and equivalents $5,280  million
n   Credit
       
n   Credit
Accounts receivable $623  million
n   Market
       
n  Market
Other investments $414  million
n   Liquidity
Accounts payable   $1,448  million
n   Liquidity
Debt   $5,176  million
n  Interest rate
Restricted share units   $31  million
n   Market
Deferred share units   $13  million
n   Market
a.Refer to notes 25, 26 and 28 to the Financial Statements for more information regarding financial instruments, fair value measurements and financial risk management, respectively.

BARRICK YEAR-END 2021
90
MANAGEMENT’S DISCUSSION AND ANALYSIS

Commitments and Contingencies

Litigation and Claims
We are currently subject to various litigation proceedings as disclosed in note 35 to the Financial Statements, and we may be involved in disputes with other parties in the future that may result in litigation. If we are unable to resolve these disputes favorably, it may have a material adverse impact on our financial condition, cash flow and results of operations.
Contractual Obligations and Commitments
In the normal course of business, we enter into contracts that give rise to commitments for future minimum payments. The following table summarizes the remaining contractual maturities of our financial liabilities and operating and capital commitments shown on an undiscounted basis:
 
($ millions) Payments due as at December 31, 2021
   2022 2023 2024 2025 2026 2027 and thereafter Total
Debta
Repayment of principal 12  47  5,050  5,109 
Capital leases 15  12  27  67 
Interest 308  307  306  306  304  3,836  5,367 
Provisions for environmental rehabilitationb
254  155  101  96  96  1,927  2,629 
Restricted share units 24  31 
Pension benefits and other post-retirement benefits 41  61 
Minimum royalty paymentsc
10 
Purchase obligations for supplies and consumablesd
658  188  149  139  134  450  1,718 
Capital commitmentse
425  18  443 
Social development costsf
14  12  10  10  64  119 
Other obligationsg
17  17  17  17  348  425 
Total 1,712  722  594  591  616  11,744  15,979 
a.Debt and Interest - Our debt obligations do not include any subjective acceleration clauses or other clauses that enable the holder of the debt to call for early repayment, except in the event that we breach any of the terms and conditions of the debt or for other customary events of default. We are not required to post any collateral under any debt obligations. Projected interest payments on variable rate debt were based on interest rates in effect at December 31, 2021. Interest is calculated on our long-term debt obligations using both fixed and variable rates.
b.Provisions for environmental rehabilitation - Amounts presented in the table represent the undiscounted uninflated future payments for the expected cost of provisions for environmental rehabilitation.
c.Minimum royalty payments are related to continuing operations and are presented net of recoverable amounts.
d.Purchase obligations for supplies and consumables - Includes commitments related to new purchase obligations to secure supply of acid, tires and cyanide for our production process.
e.Capital commitments - Purchase obligations for capital expenditures include only those items where binding commitments have been entered into.    
f.Social development costs - Includes a commitment of $14 million in 2027 and thereafter related to the funding of a power transmission line in Argentina.
g.Other obligations includes the Pueblo Viejo JV partner shareholder loan and the deposit on the Pascua-Lama silver sale agreement with Wheaton.
BARRICK YEAR-END 2021
91
MANAGEMENT’S DISCUSSION AND ANALYSIS

Review of Quarterly Results

Quarterly Informationa
   2021 2020
($ millions, except where indicated) Q4 Q3 Q2 Q1 Q4 Q3 Q2 Q1
Revenues 3,310  2,826  2,893  2,956  3,279  3,540  3,055  2,721 
Realized price per ounce – goldb
1,793  1,771  1,820  1,777  1,871  1,926  1,725  1,589 
Realized price per pound – copperb
4.63  3.98  4.57  4.12  3.39  3.28  2.79  2.23 
Cost of sales 1,905  1,768  1,704  1,712  1,814  1,927  1,900  1,776 
Net earnings 726  347  411  538  685  882  357  400 
     Per share (dollars)c
0.41  0.20  0.23  0.30  0.39  0.50  0.20  0.22 
Adjusted net earningsb
626  419  513  507  616  726  415  285 
     Per share (dollars)b,c
0.35  0.24  0.29  0.29  0.35  0.41  0.23  0.16 
Operating cash flow 1,387  1,050  639  1,302  1,638  1,859  1,031  889 
Cash consolidated capital expendituresd
669  569  658  539  546  548  509  451 
Free cash flowb
718  481  (19) 763  1,092  1,311  522  438 
a.Sum of all the quarters may not add up to the annual total due to rounding.
b.Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
c.Calculated using weighted average number of shares outstanding under the basic method of earnings per share.
d. Amounts presented on a consolidated cash basis.
 
Our recent financial results reflect our emphasis on cost discipline, an agile management structure that empowers our site based leadership teams and a portfolio of Tier One Gold Assets1. This, combined with rising gold and copper prices, has resulted in stronger operating cash flows. The positive free cash flow6 generated, together with the proceeds from various divestitures, have allowed us to continue to strengthen our balance sheet over the past two years and to increase returns to shareholders.
These same fundamentals have also driven higher net earnings in recent quarters. Net earnings has also been impacted by the following items in each quarter
which have been excluded from adjusted net earnings6. In the fourth quarter of 2021, we recorded a gain of $118 million (net of tax and non-controlling interest) related to the disposition of Lone Tree. In the first quarter of 2021, we recorded a net impairment reversal of $86 million (no tax impact) at Lagunas Norte resulting from the agreement to sell our 100% interest of the mine to Boroo. In the first quarter of 2020, we recorded a net impairment reversal of $115 million (net of tax effects), resulting from the agreement with the Government of Tanzania being signed and made effective in that quarter.


BARRICK YEAR-END 2021
92
MANAGEMENT’S DISCUSSION AND ANALYSIS

Internal Control Over Financial Reporting and Disclosure Controls and Procedures

Management is responsible for establishing and maintaining adequate internal control over financial reporting and disclosure controls and procedures. Internal control over financial reporting is a framework designed to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with IFRS. The Company’s internal control over financial reporting framework includes those policies and procedures that (i) pertain to the maintenance of records that, in reasonable detail, accurately and fairly reflect the transactions and dispositions of the assets of the Company; (ii) provide reasonable assurance that transactions are recorded as necessary to permit preparation of financial statements in accordance with IFRS, and that receipts and expenditures of the Company are being made only in accordance with authorizations of management and directors of the Company; and (iii) provide reasonable assurance regarding prevention or timely detection of unauthorized acquisition, use or disposition of the Company’s assets that could have a material effect on the Company’s consolidated financial statements.
Disclosure controls and procedures form a broader framework designed to provide reasonable assurance that other financial information disclosed publicly fairly presents in all material respects the financial condition, results of operations and cash flows of the Company for the periods presented in this MD&A and Barrick’s Annual Report. The Company’s disclosure controls and procedures framework includes processes designed to ensure that material information relating to the Company, including its consolidated subsidiaries, is made known to management by others within those entities to allow timely decisions regarding required disclosure.

Together, the internal control over financial reporting and disclosure controls and procedures frameworks provide internal control over financial reporting and disclosure. Due to its inherent limitations, internal control over financial reporting and disclosure may not prevent or detect all misstatements. Further, the effectiveness of internal control is subject to the risk that controls may become inadequate because of changes in conditions, or that the degree of compliance with policies or procedures may change.
There were no changes in the Company’s internal control over financial reporting during the year ended December 31, 2021 that have materially affected, or are reasonably likely to materially affect, the Company’s internal control over financial reporting.
The management of Barrick, at the direction of our President and Chief Executive Officer and Senior Executive Vice-President, Chief Financial Officer, evaluated the effectiveness of the design and operation of internal control over financial reporting as of the end of the period covered by this report based on the framework and criteria established in Internal Control – Integrated Framework (2013) as issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). Based on that evaluation, management concluded that the Company’s internal control over financial reporting was effective as at December 31, 2021.
Barrick’s annual management report on internal control over financial reporting and the integrated audit report of Barrick’s auditors for the year ended December 31, 2021 will be included in Barrick’s 2021 Annual Report and its 2021 Form 40-F/Annual Information Form on file with the US Securities and Exchange Commission and Canadian provincial securities regulatory authorities.


IFRS Critical Accounting Policies and Accounting Estimates

Management has discussed the development and selection of our critical accounting estimates with the Audit & Risk Committee of the Board of Directors, and the Audit & Risk Committee has reviewed the disclosure relating to such estimates in conjunction with its review of this MD&A. The accounting policies and methods we utilize determine how we report our financial condition and results of operations, and they may require Management to make estimates or rely on assumptions about matters that are inherently uncertain. The consolidated financial statements have been prepared in accordance with IFRS as issued by the International Accounting Standards Board (“IASB”) under the historical cost convention, as modified by revaluation of certain financial assets, derivative contracts and post-retirement assets. Our significant accounting policies are disclosed in note 2 to the Financial Statements, including a summary of current and future changes in accounting policies.


Critical Accounting Estimates and Judgments
Certain accounting estimates have been identified as being “critical” to the presentation of our financial condition and results of operations because they require us to make subjective and/or complex judgments about matters that are inherently uncertain; or there is a reasonable likelihood that materially different amounts could be reported under different conditions or using different assumptions and estimates. Our significant accounting judgments, estimates and assumptions are disclosed in note 3 to the accompanying Financial Statements.
BARRICK YEAR-END 2021
93
MANAGEMENT’S DISCUSSION AND ANALYSIS

Non-GAAP Financial Performance Measures

Adjusted Net Earnings and Adjusted Net Earnings per Share
Adjusted net earnings is a non-GAAP financial measure which excludes the following from net earnings:
Impairment charges (reversals) related to intangibles, goodwill, property, plant and equipment, and investments;
Acquisition/disposition gains/losses;
Foreign currency translation gains/losses;
Significant tax adjustments; and
Tax effect and non-controlling interest of the above items.
Management uses this measure internally to evaluate our underlying operating performance for the reporting periods presented and to assist with the planning and forecasting of future operating results. Management believes that adjusted net earnings is a useful measure of our performance because impairment charges, acquisition/disposition gains/losses and significant tax adjustments do not reflect the underlying operating performance of our core mining business and are not necessarily indicative of future operating results. Furthermore, foreign currency translation gains/losses are not necessarily reflective of the underlying operating results for the reporting periods presented. The tax effect and non-controlling interest of the adjusting items
are also excluded to reconcile the amounts to Barrick’s share on a post-tax basis, consistent with net earnings.
As noted, we use this measure for internal purposes. Management’s internal budgets and forecasts and public guidance do not reflect the types of items we adjust for. Consequently, the presentation of adjusted net earnings enables investors and analysts to better understand the underlying operating performance of our core mining business through the eyes of management. Management periodically evaluates the components of adjusted net earnings based on an internal assessment of performance measures that are useful for evaluating the operating performance of our business segments and a review of the non-GAAP financial measures used by mining industry analysts and other mining companies.
Adjusted net earnings is intended to provide additional information only and does not have any standardized definition under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The measures are not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate these measures differently. The following table reconciles these non-GAAP financial measures to the most directly comparable IFRS measure.


Reconciliation of Net Earnings to Net Earnings per Share, Adjusted Net Earnings and Adjusted Net Earnings per Share
 
For the three months ended For the years ended
($ millions, except per share amounts in dollars) 12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Net earnings attributable to equity holders of the Company 726  347  2,022  2,324  3,969 
Impairment charges (reversals) related to long-lived assetsa
14  10  (63) (269) (1,423)
Acquisition/disposition gainsb
(198) (5) (213) (180) (2,327)
Loss on currency translation 13  29  50  109 
Significant tax adjustmentsc
(29) 45  125  (119) 34 
Other expense (income) adjustmentsd
36  12  73  71  (687)
Tax effect and non-controlling intereste
64  92  165  1,227 
Adjusted net earnings 626  419  2,065  2,042  902 
Net earnings per sharef
0.41  0.20  1.14  1.31  2.26 
Adjusted net earnings per sharef
0.35  0.24  1.16  1.15  0.51 
a.Net impairment reversals primarily relate to non-current asset reversals at Lagunas Norte in the current year and primarily relate to our Tanzanian assets in the prior year.
b.Acquisition/disposition gains for the current year primarily relate to the gain on the sale of Lone Tree in the fourth quarter of 2021, while the prior year mainly relates to the gains on the sale of Eskay Creek, Massawa, Morila and Bullfrog.
c.Significant tax adjustments in the current year primarily relate to deferred tax expense as a result of tax reform measures in Argentina, the foreign exchange impact on current tax expense in Peru and the remeasurement of current and deferred tax balances, the acquisition of the 40% interest in South Arturo that NGM did not already own, the sale of Lagunas Norte, the settlement of the Massawa Senegalese tax dispute and the recognition/derecognition of our deferred taxes in various jurisdictions. In 2020, significant tax adjustments primarily relate to deferred tax recoveries as a result of tax reform measures in Argentina and adjustments made in recognition of the net settlement of all outstanding disputes with the Government of Tanzania.
d.Other expense adjustments for both the current and prior year primarily relate to care and maintenance expenses at Porgera. The current year periods were also impacted by a $25 million litigation settlement. The prior year was further impacted by the impact of changes in the discount rate assumptions on our closed mine rehabilitation provision and donations related to Covid-19, partially offset by the gain on the remeasurement of the residual cash liability relating to our silver sale agreement with Wheaton.
e.Tax effect and non-controlling interest for the current year primarily relates to acquisition/disposition gains.
f.Calculated using weighted average number of shares outstanding under the basic method of earnings per share.

BARRICK YEAR-END 2021
94
MANAGEMENT’S DISCUSSION AND ANALYSIS


Free Cash Flow
Free cash flow is a non-GAAP financial measure that deducts capital expenditures from net cash provided by operating activities. Management believes this to be a useful indicator of our ability to operate without reliance on additional borrowing or usage of existing cash.
Free cash flow is intended to provide additional information only and does not have any standardized definition under IFRS, and should not be considered in
isolation or as a substitute for measures of performance prepared in accordance with IFRS. The measure is not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate this measure differently. The following table reconciles this non-GAAP financial measure to the most directly comparable IFRS measure.

Reconciliation of Net Cash Provided by Operating Activities to Free Cash Flow 
For the three months ended For the years ended
  ($ millions) 12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Net cash provided by operating activities 1,387  1,050  4,378  5,417  2,833 
Capital expenditures (669) (569) (2,435) (2,054) (1,701)
Free cash flow 718  481  1,943  3,363  1,132 
 


Capital Expenditures
Starting with this MD&A, we have included minesite sustaining capital expenditures and project capital expenditures as non-GAAP financial measures. Capital expenditures are classified into minesite sustaining capital expenditures or project capital expenditures depending on the nature of the expenditure. Minesite sustaining capital expenditures is the capital spending required to support current production levels. Project capital expenditures represent the capital spending at new projects and major, discrete projects at existing operations intended to increase net present value through higher production or longer mine life. Management believes this to be a useful indicator of
the purpose of capital expenditures and this distinction is an input into the calculation of all-in sustaining costs per ounce and all-in costs per ounce.
Classifying capital expenditures is intended to provide additional information only and does not have any standardized definition under IFRS, and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. Other companies may calculate these measures differently. The following table reconciles these non-GAAP financial measures to the most directly comparable IFRS measure.

Reconciliation of the Classification of Capital Expenditures 
For the three months ended For the years ended
  ($ millions) 12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Minesite sustaining capital expenditures 431  386  1,673  1,559  1,320 
Project capital expenditures 234  179  747  471  370 
Capitalized interest 4  15  24  11 
Total consolidated capital expenditures 669   569  2,435   2,054  1,701 
BARRICK YEAR-END 2021
95
MANAGEMENT’S DISCUSSION AND ANALYSIS


Total cash costs per ounce, All-in sustaining costs per ounce, All-in costs per ounce, C1 cash costs per pound and All-in sustaining costs per pound

Total cash costs per ounce, all-in sustaining costs per ounce and all-in costs per ounce are non-GAAP financial measures which are calculated based on the definition published by the World Gold Council (a market development organization for the gold industry comprised of and funded by gold mining companies from around the world, including Barrick, the “WGC”). The WGC is not a regulatory organization. Management uses these measures to monitor the performance of our gold mining operations and its ability to generate positive cash flow, both on an individual site basis and an overall company basis.
Total cash costs start with our cost of sales related to gold production and removes depreciation, the non-controlling interest of cost of sales and includes by-product credits. All-in sustaining costs start with total cash costs and includes minesite sustaining capital expenditures, sustaining leases, general and administrative costs, minesite exploration and evaluation costs and reclamation cost accretion and amortization. These additional costs reflect the expenditures made to maintain current production levels.
All-in costs starts with all-in sustaining costs and adds additional costs that reflect the varying costs of producing gold over the life-cycle of a mine, including: project capital expenditures (capital spending at new projects and major, discrete projects at existing operations intended to increase net present value through higher production or longer mine life) and other non-sustaining costs (primarily non-sustaining leases, exploration and evaluation costs, community relations costs and general and administrative costs that are not associated with current operations). These definitions recognize that there are different costs associated with the life-cycle of a mine, and that it is therefore appropriate to distinguish between sustaining and non-sustaining costs.
We believe that our use of total cash costs, all-in sustaining costs and all-in costs will assist analysts, investors and other stakeholders of Barrick in understanding the costs associated with producing gold, understanding the economics of gold mining, assessing our operating performance and also our ability to generate free cash flow from current operations and to generate free cash flow on an overall company basis. Due to the capital-intensive nature of the industry and the long useful lives over which these items are depreciated, there can be a significant timing difference between net earnings
calculated in accordance with IFRS and the amount of free cash flow that is being generated by a mine and therefore we believe these measures are useful non-GAAP operating metrics and supplement our IFRS disclosures. These measures are not representative of all of our cash expenditures as they do not include income tax payments, interest costs or dividend payments. These measures do not include depreciation or amortization.
Total cash costs per ounce, all-in sustaining costs and all-in costs are intended to provide additional information only and do not have standardized definitions under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures are not equivalent to net income or cash flow from operations as determined under IFRS. Although the WGC has published a standardized definition, other companies may calculate these measures differently.
In addition to presenting these metrics on a by-product basis, we have calculated these metrics on a co-product basis. Our co-product metrics remove the impact of other metal sales that are produced as a by-product of our gold production from cost per ounce calculations but does not reflect a reduction in costs for costs associated with other metal sales.
C1 cash costs per pound and all-in sustaining costs per pound are non-GAAP financial measures related to our copper mine operations. We believe that C1 cash costs per pound enables investors to better understand the performance of our copper operations in comparison to other copper producers who present results on a similar basis. C1 cash costs per pound excludes royalties and production taxes and non-routine charges as they are not direct production costs. All-in sustaining costs per pound is similar to the gold all-in sustaining costs metric and management uses this to better evaluate the costs of copper production. We believe this measure enables investors to better understand the operating performance of our copper mines as this measure reflects all of the sustaining expenditures incurred in order to produce copper. All-in sustaining costs per pound includes C1 cash costs, sustaining capital expenditures, sustaining leases, general and administrative costs, minesite exploration and evaluation costs, royalties and production taxes, reclamation cost accretion and amortization and write-downs taken on inventory to net realizable value.


BARRICK YEAR-END 2021
96
MANAGEMENT’S DISCUSSION AND ANALYSIS

Reconciliation of Gold Cost of Sales to Total cash costs, All-in sustaining costs and All-in costs, including on a per ounce basis
  For the three months ended For the years ended
  ($ millions, except per ounce information in dollars)  Footnote 12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Cost of sales applicable to gold production 1,771  1,601  6,504  6,832  6,514 
 Depreciation (512) (475) (1,889) (1,975) (1,902)
Cash cost of sales applicable to equity method investments
52  51  217  222  226 
By-product credits
(70) (86) (285) (228) (138)
Realized losses on hedge and non-hedge derivatives a 0  0 
Non-recurring items
b 0  0  (55)
Other
c (7) 14  (48) (129) (102)
Non-controlling interests
d (351) (314) (1,261) (1,312) (878)
Total cash costs
  883  791  3,238  3,411  3,666 
  General  & administrative costs 39  27  151  185  212 
Minesite exploration and evaluation costs
e 12  20  64  79  69 
Minesite sustaining capital expenditures
f 431  386  1,673  1,559  1,320 
Sustaining leases
13  41  31  27 
Rehabilitation - accretion and amortization (operating sites)
g 12  14  50  46  65 
Non-controlling interest, copper operations and other
h (191) (140) (636) (594) (470)
  All-in sustaining costs
  1,199  1,107  4,581  4,717  4,889 
Global exploration and evaluation and project expense e 70  47  223  216  273 
Community relations costs not related to current operations
0  0 
Project capital expenditures
f 234  179  747  471  370 
Non-sustaining leases 0  0 
Rehabilitation - accretion and amortization (non-operating sites)
g 2  13  10  22 
Non-controlling interest and copper operations and other
h (71) (53) (240) (157) (105)
All-in costs   1,434  1,284  5,324  5,262  5,451 
Ounces sold - equity basis (000s ounces) i 1,234  1,071  4,468  4,879  5,467 
Cost of sales per ounce j,k 1,075  1,122  1,093  1,056  1,005 
Total cash costs per ounce k 715  739  725  699  671 
Total cash costs per ounce (on a co-product basis) k,l 753  794  765  727  689 
All-in sustaining costs per ounce k 971  1,034  1,026  967  894 
All-in sustaining costs per ounce (on a co-product basis) k,l 1,009  1,089  1,066  995  912 
All-in costs per ounce k 1,162  1,199  1,192  1,079  996 
All-in costs per ounce (on a co-product basis) k,l 1,200  1,254  1,232  1,107  1,014 

a.Realized losses on hedge and non-hedge derivatives
Includes realized hedge losses of $nil and $nil for the three months and year ended December 31, 2021, respectively (September 30, 2021: $nil; 2020: $nil; 2019: $nil), and realized non-hedge losses of $nil and $nil for the three months and year ended December 31, 2021, respectively (September 30, 2021: $nil; 2020: $nil; 2019: $1 million). Refer to note 5 to the Financial Statements for further information.

b.Non-recurring items
These costs are not indicative of our cost of production and have been excluded from the calculation of total cash costs. Non-recurring items in 2019 relate to organizational restructuring.

c.Other
Other adjustments for the three months and year ended December 31, 2021 include the removal of total cash costs and by-product credits associated with Pierina, Golden Sunlight starting in the third quarter of 2019, Morila starting in the third quarter of 2019 up until its divestiture in November 2020, Lagunas Norte starting in the fourth quarter of 2019 up until its divestiture in June 2021 and Buzwagi starting in the fourth quarter of 2021, which are producing incidental ounces, of $7 million and $51 million, respectively (September 30, 2021: $6 million; 2020: $104 million; 2019: $92 million).

d.Non-controlling interests
Non-controlling interests include non-controlling interests related to gold production of $527 million and $1,923 million, respectively, for the three months and year ended December 31, 2021 (September 30, 2021: $481 million; 2020: $1,959 million; 2019: $1,306 million). Non-controlling interests include Nevada Gold Mines from July 1, 2019, Pueblo Viejo, Loulo-Gounkoto, Tongon; North Mara, Bulyanhulu and Buzwagi (until September 30, 2019, notwithstanding the completion of the Acacia transaction on September 17, 2019, we consolidated our interest in Acacia and recorded a non-controlling interest of 36.1% in the income statement for the entirety of the third quarter of 2019 as a matter of convenience; and from January 1, 2020 onwards, the date the GoT’s 16% free carried interest was made effective). Refer to note 5 to the Financial Statements for further information.
BARRICK YEAR-END 2021
97
MANAGEMENT’S DISCUSSION AND ANALYSIS


e.Exploration and evaluation costs
Exploration, evaluation and project expenses are presented as minesite if it supports current mine operations and project if it relates to future projects. Refer to page 85 of this MD&A.

f.Capital expenditures
Capital expenditures are related to our gold sites only and are split between minesite sustaining and project capital expenditures. Project capital expenditures are capital spending at new projects and major, discrete projects at existing operations intended to increase net present value through higher production or longer mine life. Significant projects in the current year are the expansion project at Pueblo Viejo, construction of the Third Shaft at Turquoise Ridge, the development of the Gounkoto underground and the Veladero Phase 7 expansion. Refer to page 84 of this MD&A.

g.Rehabilitation - accretion and amortization
Includes depreciation on the assets related to rehabilitation provisions of our gold operations and accretion on the rehabilitation provisions of our gold operations, split between operating and non-operating sites.

h.Non-controlling interest and copper operations
Removes general & administrative costs related to non-controlling interests and copper based on a percentage allocation of revenue. Also removes exploration, evaluation and project expenses, rehabilitation costs and capital expenditures incurred by our copper sites and the non-controlling interest of Nevada Gold Mines (including South Arturo) from July 1, 2019, Pueblo Viejo, Loulo-Gounkoto, Tongon; North Mara, Bulyanhulu and Buzwagi (until September 30, 2019 notwithstanding the completion of the Acacia transaction on September 17, 2019, we consolidated our interest in Acacia and recorded a non-controlling interest of 36.1% in the income statement for the entirety of the third quarter of 2019 as a matter of convenience; and from January 1, 2020 onwards, the date the GoT’s 16% free carried interest was made effective). It also includes capital expenditures applicable to our equity method investment in Kibali. Figures remove the impact of Pierina, Golden Sunlight starting in the third quarter of 2019, Morila starting in the third quarter of 2019 up until its divestiture in November 2020, Lagunas Norte starting in the fourth quarter of 2019 up until its divestiture in June 2021 and Buzwagi starting in the fourth quarter of 2021. The impact is summarized as the following:
($ millions)
For the three months ended For the years ended
   Non-controlling interest, copper operations and other 12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
    General & administrative costs
(4) (4) (21) (25) (58)
Minesite exploration and evaluation costs
(2) (7) (19) (25) (16)
Rehabilitation - accretion and amortization (operating sites)
(3) (4) (14) (14) (13)
   Minesite sustaining capital expenditures (182) (125) (582) (530) (383)
   All-in sustaining costs total
(191) (140) (636) (594) (470)
   Global exploration and evaluation and project costs (6) (4) (19) (25) (54)
Project capital expenditures
(65) (49) (221) (132) (51)
   All-in costs total
(71) (53) (240) (157) (105)

i.Ounces sold - equity basis
Figures remove the impact of Pierina, Golden Sunlight starting in the third quarter of 2019, Morila starting in the third quarter of 2019 up until its divestiture in November 2020, Lagunas Norte starting in the fourth quarter of 2019 up until its divestiture in June 2021 and Buzwagi starting in the fourth quarter of 2021. Some of these assets are producing incidental ounces while in closure or care and maintenance.

j.Cost of sales per ounce
Figures remove the cost of sales impact of Pierina of $7 million and $20 million, respectively, for the three months and year ended December 31, 2021 (September 30, 2021: $6 million; 2020: $18 million; 2019: $113 million); starting in the third quarter of 2019, Golden Sunlight of $nil and $nil, respectively, for the three months and year ended December 31, 2021 (September 30, 2021: $nil; 2020: $nil; 2019: $1 million); starting in the third quarter of 2019 up until its divestiture in November 2020, Morila of $nil and $nil, respectively, for the three months and year ended December 31, 2021 (September 30, 2021: $nil; 2020: $22 million; 2019: $23 million); and starting in the fourth quarter of 2019 up until its divestiture in June 2021, Lagunas Norte of $nil and $37 million, respectively, for the three months and year ended December 31, 2021 (September 30, 2021: $nil; 2020: $92 million; 2019: $26 million), and Buzwagi of $nil and $nil, respectively, for the three months and year ended December 31, 2021 (September 30, 2021: $nil; 2020: $nil; 2019: $nil), which are producing incidental ounces. Gold cost of sales per ounce is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).

k.Per ounce figures
Cost of sales per ounce, cash costs per ounce, all-in sustaining costs per ounce and all-in costs per ounce may not calculate based on amounts presented in this table due to rounding.

l.Co-product costs per ounce
Cash costs per ounce, all-in sustaining costs per ounce and all-in costs per ounce presented on a co-product basis remove the impact of by-product credits of our gold production (net of non-controlling interest) calculated as:
($ millions)
For the three months ended For the years ended
  
12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
   By-product credits
70  86  285  228  138 
   Non-controlling interest
(25) (27) (108) (92) (48)
   By-product credits (net of non-controlling interest)
45  59  177  136  90 




BARRICK YEAR-END 2021
98
MANAGEMENT’S DISCUSSION AND ANALYSIS

Reconciliation of Gold Cost of Sales to Total cash costs, All-in sustaining costs and All-in costs, including on a per ounce basis, by operating segment
($ millions, except per ounce information in dollars) For the three months ended 12/31/21
   Footnote
Carlin a
Cortez b
Turquoise Ridgec
Long Canyond
Phoenix d
Nevada Gold Minese
Hemlo North America
Cost of sales applicable to gold production 434  271  163  54  87  1,009  60  1,069 
Depreciation (82) (89) (51) (37) (21) (280) (9) (289)
   By-product credits 0  (1) (1) 0  (47) (49) 0  (49)
   Non-recurring items f 0  0  0  0  0  0  0  0 
Other 0  0  0  0  1  1  0  1 
Non-controlling interests (135) (70) (43) (6) (8) (262) 0  (262)
Total cash costs 217  111  68  11  12  419  51  470 
General & administrative costs 0  0  0  0  0  0  0  0 
Minesite exploration and evaluation costs g 4  2  0  1  1  11  0  11 
Minesite sustaining capital expenditures h 99  50  23  3  6  188  15  203 
Sustaining capital leases 2  0  0  0  0  2  0  2 
Rehabilitation - accretion and amortization (operating sites) i 3  3  1  0  0  7  0  7 
Non-controlling interests (42) (22) (9) (2) (3) (81) 0  (81)
All-in sustaining costs 283  144  83  13  16  546  66  612 
Project exploration and evaluation and project costs g 0  0  0  0  0  0  0  0 
Project capital expenditures h 0  29  9  0  0  33  0  33 
Non-controlling interests 0  (11) (4) 0  0  (13) 0  (13)
All-in costs 283  162  88  13  16  566  66  632 
Ounces sold - equity basis (000s ounces) 297  170  84  34  26  611  34  645 
Cost of sales per ounce j,k 899  984  1,194  999  2,047  1,023  1,770  1,063 
Total cash costs per ounce k 728  657  819  325  443  687  1,481  729 
Total cash costs per ounce (on a co-product basis) k,l 729  661  821  326  1,533  736  1,487  775 
All-in sustaining costs per ounce k 950  853  996  384  614  893  1,938  948 
All-in sustaining costs per ounce (on a co-product basis) k,l 951  857  998  385  1,704  942  1,944  994 
All-in costs per ounce k 950  958  1,061  384  614  927  1,939  980 
All-in costs per ounce (on a co-product basis) k,l 951  962  1,063  385  1,704  976  1,945  1,026 







BARRICK YEAR-END 2021
99
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the three months ended 12/31/21
   Footnote Pueblo Viejo Veladero Latin America & Asia Pacific
Cost of sales applicable to gold production 185  109  294 
Depreciation (57) (37) (94)
   By-product credits (12) (1) (13)
   Non-recurring items f 0  0  0 
Other 0  0  0 
   Non-controlling interests (47) 0  (47)
Total cash costs 69  71  140 
General & administrative costs 0  0  0 
Minesite exploration and evaluation costs g 1  0  1 
Minesite sustaining capital expenditures h 45  22  67 
Sustaining capital leases 0  0  0 
Rehabilitation - accretion and amortization (operating sites) i 2  1  3 
Non-controlling interests (20) 0  (20)
All-in sustaining costs 97  94  191 
Project exploration and evaluation and project costs g 1  0  1 
Project capital expenditures h 112  6  118 
Non-controlling interests (46) 0  (46)
All-in costs 164  100  264 
Ounces sold - equity basis (000s ounces) 113  83  196 
Cost of sales per ounce j,k 987  1,279  1,131 
Total cash costs per ounce k 612  834  707 
Total cash costs per ounce (on a co-product basis) k,l 677  852  752 
All-in sustaining costs per ounce k 858  1,113  964 
All-in sustaining costs per ounce (on a co-product basis) k,l 923  1,131  1,009 
All-in costs per ounce k 1,453  1,179  1,332 
All-in costs per ounce (on a co-product basis) k,l 1,518  1,197  1,377 

























BARRICK YEAR-END 2021
100
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the three months ended 12/31/21
   Footnote Loulo-Gounkoto Kibali
North Mara m
Tongon
Bulyanhulu m
Buzwagi m,n
Africa & Middle East
Cost of sales applicable to gold production 181  93  72  79  59  484 
Depreciation (72) (37) (15) (15) (17) (156)
By-product credits 0  (1) 0  (1) (6) (8)
Non-recurring items f 0  0  0  0  0  0 
Other 0  0  0  0  0  0 
Non-controlling interests (21) 0  (9) (6) (6) (42)
Total cash costs 88  55  48  57  30  278 
General & administrative costs 0  0  0  0  0  0 
Minesite exploration and evaluation costs g 4  3  0  0  0  7 
Minesite sustaining capital expenditures h 17  12  28  3  20  80 
Sustaining capital leases 0  3  0  1  0  4 
Rehabilitation - accretion and amortization (operating sites) i 1  0  1  1  0  3 
Non-controlling interests (4) 0  (5) (1) (3) (13)
All-in sustaining costs 106  73  72  61  47  359 
Project exploration and evaluation and project costs g 0  0  0  0  0  0 
Project capital expenditures h 46  7  10  0  17  80 
Non-controlling interests (9) 0  (1) 0  (3) (13)
All-in costs 143  80  81  61  61  426 
Ounces sold - equity basis (000s ounces) 128  95  70  47  53  393 
Cost of sales per ounce j,k 1,139  979  858  1,494  956  1,067 
Total cash costs per ounce k 685  582  679  1,205  567  705 
Total cash costs per ounce (on a co-product basis) k,l 686  586  688  1,209  678  723 
All-in sustaining costs per ounce k 822  776  1,033  1,301  897  915 
All-in sustaining costs per ounce (on a co-product basis) k,l 823  780  1,042  1,305  1,008  933 
All-in costs per ounce k 1,109  844  1,150  1,278  1,159  1,078 
All-in costs per ounce (on a co-product basis) k,l 1,110  848  1,159  1,282  1,270  1,096 













BARRICK YEAR-END 2021
101
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the three months ended 9/30/21
   Footnote
Carlin a
Cortez b
Turquoise Ridgec
Long Canyond
Phoenix d
Nevada Gold Minese
Hemlo North America
Cost of sales applicable to gold production 335  240  155  55  95  880  54  934 
Depreciation (67) (75) (50) (41) (26) (259) (11) (270)
By-product credits (1) (51) (52) (1) (53)
Non-recurring items f
Other
Non-controlling interests (104) (63) (40) (6) (10) (223) (223)
Total cash costs 164  101  65  16  354  42  396 
General & administrative costs
Minesite exploration and evaluation costs g 13  14 
Minesite sustaining capital expenditures h 91  51  20  171  20  191 
Sustaining capital leases
Rehabilitation - accretion and amortization (operating sites) i
Non-controlling interests (38) (23) (8) (1) (1) (73) (73)
All-in sustaining costs 227  135  78  10  19  472  65  537 
Project exploration and evaluation and project costs g
Project capital expenditures h 28  15  48  48 
Non-controlling interests (11) (6) (19) (19)
All-in costs 227  152  87  10  19  501  65  566 
Ounces sold - equity basis (000s ounces) 202  126  82  42  33  485  29  514 
Cost of sales per ounce j,k 1,017  1,164  1,169  796  1,777  1,123  1,870  1,165 
Total cash costs per ounce k 814  800  788  201  499  734  1,493  776 
Total cash costs per ounce (on a co-product basis) k,l 815  803  792  201  1,299  790  1,498  829 
All-in sustaining costs per ounce k 1,124  1,065  943  251  582  975  2,276  1,047 
All-in sustaining costs per ounce (on a co-product basis) k,l 1,125  1,068  947  251  1,382  1,031  2,281  1,100 
All-in costs per ounce k 1,124  1,199  1,053  251  582  1,035  2,277  1,103 
All-in costs per ounce (on a co-product basis) k,l 1,125  1,202  1,057  251  1,382  1,091  2,282  1,156 







BARRICK YEAR-END 2021
102
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the three months ended 9/30/21
   Footnote Pueblo Viejo Veladero Latin America & Asia Pacific
Cost of sales applicable to gold production 186  58  244 
Depreciation (61) (17) (78)
By-product credits (16) (2) (18)
Non-recurring items f
Other
Non-controlling interests (43) (43)
Total cash costs 66  39  105 
General & administrative costs
Minesite exploration and evaluation costs g
Minesite sustaining capital expenditures h 40  29  69 
Sustaining capital leases
Rehabilitation - accretion and amortization (operating sites) i
Non-controlling interests (18) (18)
All-in sustaining costs 91  70  161 
Project exploration and evaluation and project costs g
Project capital expenditures h 81  81 
Non-controlling interests (32) (32)
All-in costs 140  70  210 
Ounces sold - equity basis (000s ounces) 125  44  169 
Cost of sales per ounce j,k 895  1,315  1,038 
Total cash costs per ounce k 521  882  616 
Total cash costs per ounce (on a co-product basis) k,l 600  922  685 
All-in sustaining costs per ounce k 728  1,571  960 
All-in sustaining costs per ounce (on a co-product basis) k,l 807  1,611  1,029 
All-in costs per ounce k 1,117  1,571  1,247 
All-in costs per ounce (on a co-product basis) k,l 1,196  1,611  1,316 













BARRICK YEAR-END 2021
103
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the three months ended 9/30/21
   Footnote Loulo-Gounkoto Kibali
North Mara m
Tongon
Bulyanhulu m
Buzwagi m,n
Africa & Middle East
Cost of sales applicable to gold production 188  92  76  72  62  496 
Depreciation (68) (36) (14) (20) (15) (153)
By-product credits (1) (5) (6)
Non-recurring items f
Other
Non-controlling interests (25) (10) (6) (6) (1) (48)
Total cash costs 95  56  51  46  36  289 
General & administrative costs
Minesite exploration and evaluation costs g
Minesite sustaining capital expenditures h 52  11  13  91 
Sustaining capital leases
Rehabilitation - accretion and amortization (operating sites) i
Non-controlling interests (11) (2) (1) (1) (15)
All-in sustaining costs 142  70  64  55  41  377 
Project exploration and evaluation and project costs g
Project capital expenditures h 21  45 
Non-controlling interests (4) (2) (1) (7)
All-in costs 159  78  71  56  46  415 
Ounces sold - equity basis (000s ounces) 134  93  65  41  49  388 
Cost of sales per ounce j,k 1,109  987  993  1,579  1,073  1,000  1,104 
Total cash costs per ounce k 708  597  796  1,139  724  967  747 
Total cash costs per ounce (on a co-product basis) k,l 708  601  803  1,143  806  976  760 
All-in sustaining costs per ounce k 1,056  751  985  1,329  827  970  970 
All-in sustaining costs per ounce (on a co-product basis) k,l 1,056  755  992  1,333  909  979  983 
All-in costs per ounce k 1,184  838  1,105  1,344  937  970  1,071 
All-in costs per ounce (on a co-product basis) k,l 1,184  842  1,112  1,348  1,019  979  1,084 













BARRICK YEAR-END 2021
104
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the year ended 12/31/2021
   Footnote
Carlin a
Cortez b
Turquoise Ridgec
Long Canyond
Phoenix d
Nevada Gold Minese
Hemlo North America
Cost of sales applicable to gold production 1,451  927  615  193  346  3,532  257  3,789 
Depreciation (276) (294) (200) (144) (89) (1,003) (45) (1,048)
By-product credits (2) (3) (5) 0  (194) (204) (1) (205)
Non-recurring items f 0  0  0  0  0  0  0  0 
Other 0  0  0  0  9  9  0  9 
Non-controlling interests (451) (243) (158) (19) (28) (899) 0  (899)
Total cash costs 722  387  252  30  44  1,435  211  1,646 
General & administrative costs 0  0  0  0  0  0  0  0 
Minesite exploration and evaluation costs g 22  10  1  4  1  41  2  43 
Minesite sustaining capital expenditures h 424  192  77  8  20  746  82  828 
Sustaining capital leases 2  0  0  0  1  5  2  7 
Rehabilitation - accretion and amortization (operating sites) i 10  11  1  1  2  25  2  27 
Non-controlling interests (177) (86) (30) (5) (9) (318) 0  (318)
All-in sustaining costs 1,003  514  301  38  59  1,934  299  2,233 
Project exploration and evaluation and project costs g 0  0  0  0  0  0  0  0 
Project capital expenditures h 0  96  56  0  0  158  0  158 
Non-controlling interests 0  (37) (22) 0  0  (61) 0  (61)
All-in costs 1,003  573  335  38  59  2,031  299  2,330 
Ounces sold - equity basis (000s ounces) 922  508  337  161  111  2,039  152  2,191 
Cost of sales per ounce j,k 968  1,122  1,122  739  1,922  1,072  1,693  1,115 
Total cash costs per ounce k 782  763  749  188  398  705  1,388  752 
Total cash costs per ounce (on a co-product basis) k,l 784  767  757  188  1,428  764  1,394  807 
All-in sustaining costs per ounce k 1,087  1,013  892  238  533  949  1,970  1,020 
All-in sustaining costs per ounce (on a co-product basis) k,l 1,089  1,017  900  238  1,563  1,008  1,976  1,075 
All-in costs per ounce k 1,087  1,129  993  238  533  997  1,970  1,064 
All-in costs per ounce (on a co-product basis) k,l 1,089  1,133  1,001  238  1,563  1,056  1,976  1,119 
















BARRICK YEAR-END 2021
105
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the year ended 12/31/2021
   Footnote Pueblo Viejo Veladero Latin America & Asia Pacific
Cost of sales applicable to gold production 739  262  1,001 
Depreciation (234) (85) (319)
By-product credits (58) (7) (65)
Non-recurring items 0  0  0 
Other f 0  0  0 
Non-controlling interests (178) 0  (178)
Total cash costs 269  170  439 
General & administrative costs 0  0  0 
Minesite exploration and evaluation costs g 4  1  5 
Minesite sustaining capital expenditures h 160  136  296 
Sustaining capital leases 0  1  1 
Rehabilitation - accretion and amortization (operating sites) i 8  2  10 
Non-controlling interests (71) 0  (71)
All-in sustaining costs 370  310  680 
Project exploration and evaluation and project costs g 1  0  1 
Project capital expenditures h 358  6  364 
Non-controlling interests (144) 0  (144)
All-in costs 585  316  901 
Ounces sold - equity basis (000s ounces) 497  206  703 
Cost of sales per ounce j,k 896  1,256  1,028 
Total cash costs per ounce k 541  816  622 
Total cash costs per ounce (on a co-product basis) k,l 610  850  680 
All-in sustaining costs per ounce k 745  1,493  969 
All-in sustaining costs per ounce (on a co-product basis) k,l 814  1,527  1,027 
All-in costs per ounce k 1,178  1,520  1,282 
All-in costs per ounce (on a co-product basis) k,l 1,247  1,554  1,340 














BARRICK YEAR-END 2021
106
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the year ended 12/31/2021
   Footnote Loulo-Gounkoto Kibali
North Mara m
Tongon
Bulyanhulu m
Buzwagi m,n
Africa & Middle East
Cost of sales applicable to gold production 732  373  296  310  212  65  1,988 
Depreciation (278) (141) (56) (84) (57) (2) (618)
By-product credits 0  (2) (2) (1) (15) 0  (20)
Non-recurring items f 0  0  0  0  0  0  0 
Other 0  0  0  0  0  0  0 
Non-controlling interests (91) 0  (38) (23) (22) (10) (184)
Total cash costs 363  230  200  202  118  53  1,166 
General & administrative costs 0  0  0  0  0  0  0 
Minesite exploration and evaluation costs g 18  5  0  3  0  0  26 
Minesite sustaining capital expenditures h 199  54  62  18  34  0  367 
Sustaining capital leases 2  10  0  2  0  0  14 
Rehabilitation - accretion and amortization (operating sites) i 4  1  6  1  1  0  13 
Non-controlling interests (44) 0  (11) (3) (5) 0  (63)
All-in sustaining costs 542  300  257  223  148  53  1,523 
Project exploration and evaluation and project costs g 0  0  0  0  0  0  0 
Project capital expenditures h 98  16  32  0  49  0  195 
Non-controlling interests (19) 0  (5) 0  (8) 0  (32)
All-in costs 621  316  284  223  189  53  1,686 
Ounces sold - equity basis (000s ounces) 558  367  257  185  166  41  1,574 
Cost of sales per ounce j,k 1,049  1,016  966  1,504  1,079  1,334  1,092 
Total cash costs per ounce k 650  627  777  1,093  709  1,284  740 
Total cash costs per ounce (on a co-product basis) k,l 650  631  784  1,096  787  1,277  751 
All-in sustaining costs per ounce k 970  818  1,001  1,208  891  1,291  968 
All-in sustaining costs per ounce (on a co-product basis) k,l 970  822  1,008  1,211  969  1,284  979 
All-in costs per ounce k 1,111  861  1,105  1,206  1,138  1,291  1,070 
All-in costs per ounce (on a co-product basis) k,l 1,111  865  1,112  1,209  1,216  1,284  1,081 
















BARRICK YEAR-END 2021
107
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the year ended 12/31/2020
   Footnote
Carlin a
Cortez b
Turquoise Ridgec
Long Canyond
Phoenix d
Nevada Gold Minese
Hemlo North America
Cost of sales applicable to gold production 1,624  764  575  227  365  3,555  281  3,836 
Depreciation (306) (221) (184) (165) (94) (970) (44) (1,014)
By-product credits (2) (2) (7) (137) (148) (1) (149)
Non-recurring items f
Other
Non-controlling interests (507) (208) (148) (24) (51) (938) (938)
Total cash costs 809  333  236  38  83  1,499  236  1,735 
General & administrative costs
Minesite exploration and evaluation costs g 30  52  53 
Minesite sustaining capital expenditures h 381  235  39  35  29  748  79  827 
Sustaining capital leases
Rehabilitation - accretion and amortization (operating sites) i 13  26  27 
Non-controlling interests (163) (98) (18) (17) (13) (321) (321)
All-in sustaining costs 1,066  490  264  66  103  2,008  317  2,325 
Project exploration and evaluation and project costs g
Project capital expenditures h 146  44  200  200 
Non-controlling interests (56) (17) (76) (76)
All-in costs 1,066  580  291  66  103  2,132  317  2,449 
Ounces sold - equity basis (000s ounces) 1,024  491  332  161  126  2,134  224  2,358 
Cost of sales per ounce j,k 976  958  1,064  869  1,772  1,029  1,256  1,050 
Total cash costs per ounce k 790  678  711  236  649  702  1,056  735 
Total cash costs per ounce (on a co-product basis) k,l 791  680  723  238  1,315  745  1,060  774 
All-in sustaining costs per ounce k 1,041  998  798  405  814  941  1,423  987 
All-in sustaining costs per ounce (on a co-product basis) k,l 1,042  1,000  810  407  1,480  984  1,427  1,026 
All-in costs per ounce k 1,041  1,179  879  405  814  998  1,424  1,039 
All-in costs per ounce (on a co-product basis) k,l 1,042  1,181  891  407  1,480  1,041  1,428  1,078 


















BARRICK YEAR-END 2021
108
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the year ended 12/31/2020
   Footnote Pueblo Viejo Veladero
Porgera o
Latin America & Asia Pacific
Cost of sales applicable to gold production 735  213  106  1,054 
Depreciation (224) (69) (25) (318)
By-product credits (57) (5) (1) (63)
Non-recurring items f
Other
Non-controlling interests (182) (182)
Total cash costs 272  139  80  491 
General & administrative costs
Minesite exploration and evaluation costs g
Minesite sustaining capital expenditures h 132  98  11  241 
Sustaining capital leases
Rehabilitation - accretion and amortization (operating sites) i 10 
Non-controlling interests (56) (56)
All-in sustaining costs 357  243  96  696 
Project exploration and evaluation and project costs g
Project capital expenditures h 91  15  106 
Non-controlling interests (37) (37)
All-in costs 412  258  96  766 
Ounces sold - equity basis (000s ounces) 541  186  87  814 
Cost of sales per ounce j,k 819  1,151  1,225  938 
Total cash costs per ounce k 504  748  928  604 
Total cash costs per ounce (on a co-product basis) k,l 568  777  934  654 
All-in sustaining costs per ounce k 660  1,308  1,115  856 
All-in sustaining costs per ounce (on a co-product basis) k,l 724  1,337  1,121  906 
All-in costs per ounce k 761  1,390  1,116  942 
All-in costs per ounce (on a co-product basis) k,l 825  1,419  1,122  992 











BARRICK YEAR-END 2021
109
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the year ended 12/31/2020
   Footnote Loulo-Gounkoto Kibali
North Mara m
Tongon
Bulyanhulu m
Buzwagi m,n
Africa & Middle East
Cost of sales applicable to gold production 719  397  318  380  184  211  2,209 
Depreciation (267) (174) (91) (167) (72) (11) (782)
By-product credits (1) (2) (10) (22) (35)
Non-recurring items f
Other
Non-controlling interests (90) (36) (22) (16) (28) (192)
Total cash costs 362  222  189  191  86  150  1,200 
General & administrative costs
Minesite exploration and evaluation costs g 11  16 
Minesite sustaining capital expenditures h 213  49  68  346 
Sustaining capital leases 15 
Rehabilitation - accretion and amortization (operating sites) i
Non-controlling interests (46) (12) (1) (1) (60)
All-in sustaining costs 546  283  249  203  93  152  1,526 
Project exploration and evaluation and project costs g
Project capital expenditures h 19  35  69  125 
Non-controlling interests (4) (5) (11) (20)
All-in costs 561  285  279  203  151  152  1,631 
Ounces sold - equity basis (000s ounces) 542  364  269  255  103  174  1,707 
Cost of sales per ounce j,k 1,060  1,091  992  1,334  1,499  1,021  1,119 
Total cash costs per ounce k 666  608  702  747  832  859  701 
Total cash costs per ounce (on a co-product basis) k,l 666  612  709  748  913  968  719 
All-in sustaining costs per ounce k 1,006  778  929  791  895  871  893 
All-in sustaining costs per ounce (on a co-product basis) k,l 1,006  782  936  792  976  980  911 
All-in costs per ounce k 1,034  782  1,039  791  1,459  871  954 
All-in costs per ounce (on a co-product basis) k,l 1,034  786  1,046  792  1,540  980  972 













BARRICK YEAR-END 2021
110
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the year ended 12/31/2019
   Footnote
Carlin a
Cortez b
Turquoise Ridgec
Long Canyond
Phoenix d
Nevada Gold Minese
Hemlo North America
Cost of sales applicable to gold production 1,310  751  425  101  154  2,741  247  2,988 
Depreciation (312) (240) (140) (70) (36) (798) (27) (825)
By-product credits (1) (1) (2) (48) (52) (1) (53)
Non-recurring items f (10) (10) (23) (33)
Other
Non-controlling interests (266) (99) (75) (12) (27) (479) (479)
Total cash costs 721  411  208  19  43  1,402  196  1,598 
General & administrative costs
Minesite exploration and evaluation costs g 17  36  37 
Minesite sustaining capital expenditures h 307  129  70  26  22  554  47  601 
Sustaining capital leases
Rehabilitation - accretion and amortization (operating sites) i 10  16  30  32 
Non-controlling interests (102) (44) (21) (12) (10) (189) (189)
All-in sustaining costs 953  520  264  39  58  1,834  247  2,081 
Project exploration and evaluation and project costs g
Project capital expenditures h 332  45  295  295 
Non-controlling interests (128) (10) (48) (48)
All-in costs 953  724  299  39  58  2,081  247  2,328 
Ounces sold - equity basis (000s ounces) 967  798  356  57  45  2,223  217  2,440 
Cost of sales per ounce j,k 1,004  762  846  1,088  2,093  924  1,137  943 
Total cash costs per ounce k 746  515  585  333  947  634  904  655 
Total cash costs per ounce (on a co-product basis) k,l 747  516  588  335  1,600  657  907  677 
All-in sustaining costs per ounce k 984  651  732  681  1,282  828  1,140  851 
All-in sustaining costs per ounce (on a co-product basis) k,l 985  652  735  683  1,935  851  1,143  873 
All-in costs per ounce k 984  903  834  681  1,282  938  1,141  953 
All-in costs per ounce (on a co-product basis) k,l 985  904  837  683  1,935  961  1,144  975 

















BARRICK YEAR-END 2021
111
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the year ended 12/31/2019
   Footnote Pueblo Viejo Veladero
Porgera o
Kalgoorlie p
Latin America & Asia Pacific
Cost of sales applicable to gold production 721  323  284  223  1,551 
Depreciation (196) (115) (42) (38) (391)
By-product credits (61) (8) (3) (1) (73)
Non-recurring items f (2) (1) (3)
Other
Non-controlling interests (187) (187)
Total cash costs 275  199  239  184  897 
General & administrative costs
Minesite exploration and evaluation costs g 11 
Minesite sustaining capital expenditures h 107  91  45  52  295 
Sustaining capital leases
Rehabilitation - accretion and amortization (operating sites) i 10  (2) 16 
Non-controlling interests (47) (47)
All-in sustaining costs 345  300  287  249  1,181 
Project exploration and evaluation and project costs g
Project capital expenditures h 15  15 
Non-controlling interests (3) (3)
All-in costs 350  315  287  249  1,201 
Ounces sold - equity basis (000s ounces) 584  271  285  210  1,350 
Cost of sales per ounce j,k 747  1,188  994  1,062  937 
Total cash costs per ounce k 471  734  838  873  664 
Total cash costs per ounce (on a co-product basis) k,l 536  759  848  876  716 
All-in sustaining costs per ounce k 592  1,105  1,003  1,183  874 
All-in sustaining costs per ounce (on a co-product basis) k,l 657  1,130  1,013  1,186  926 
All-in costs per ounce k 600  1,162  1,003  1,183  885 
All-in costs per ounce (on a co-product basis) k,l 665  1,187  1,013  1,186  937 














BARRICK YEAR-END 2021
112
MANAGEMENT’S DISCUSSION AND ANALYSIS

($ millions, except per ounce information in dollars) For the year ended 12/31/2019
   Footnote Loulo-Gounkoto Kibali
North Mara m
Tongon
Bulyanhulu m
Buzwagi m,n
Africa & Middle East
Cost of sales applicable to gold production 751  403  310  402  45  138  2,049 
Depreciation (295) (196) (97) (186) (19) (8) (801)
By-product credits (1) (2) (1) (1) (1) (6)
Non-recurring items f
Other
Non-controlling interests (91) (51) (23) (7) (36) (208)
Total cash costs 365  206  160  192  18  93  1,034 
General & administrative costs
Minesite exploration and evaluation costs g 12  18 
Minesite sustaining capital expenditures h 165  41  48  11  267 
Sustaining capital leases
Rehabilitation - accretion and amortization (operating sites) i
Non-controlling interests (37) (13) (2) (1) (53)
All-in sustaining costs 509  251  198  206  20  95  1,279 
Project exploration and evaluation and project costs g
Project capital expenditures h 18 
Non-controlling interests (1) (3) (1) (5)
All-in costs 512  253  204  206  22  95  1,292 
Ounces sold - equity basis (000s ounces) 575  363  248  245  27  81  1,539 
Cost of sales per ounce j,k 1,044  1,111  953  1,469  1,207  1,240  1,126 
Total cash costs per ounce k 634  568  646  787  676  1,156  673 
Total cash costs per ounce (on a co-product basis) k,l 634  571  654  789  709  1,166  677 
All-in sustaining costs per ounce k 886  693  802  844  773  1,178  834 
All-in sustaining costs per ounce (on a co-product basis) k,l 886  696  810  846  806  1,188  838 
All-in costs per ounce k 891  701  824  846  840  1,178  842 
All-in costs per ounce (on a co-product basis) k,l 891  704  832  848  873  1,188  846 
a.On July 1, 2019, Barrick's Goldstrike and Newmont's Carlin were contributed to Nevada Gold Mines and are now collectively referred to as Carlin. As a result, the amounts presented represent Goldstrike on a 100% basis (including our 60% share of South Arturo) up until June 30, 2019, and the combined results of Carlin and Goldstrike (including our share of South Arturo) on a 61.5% basis thereafter. On September 7, 2021, Barrick announced NGM had entered into an Exchange Agreement with i-80 Gold to acquire the 40% interest in South Arturo that NGM did not already own in exchange for the Lone Tree and Buffalo Mountain properties and infrastructure. Operating results within our 61.5% interest in Carlin includes NGM’s 60% interest in South Arturo up until May 30, 2021, and 100% interest thereafter, reflecting the terms of the Exchange Agreement which closed on October 14, 2021.

b.On July 1, 2019, Cortez was contributed to Nevada Gold Mines, a joint venture with Newmont. As a result, the amounts presented are on a 100% basis up until June 30, 2019, and on a 61.5% basis thereafter. Starting in the first quarter of 2021, Goldrush is reported as part of Cortez as it is operated by Cortez management. Comparative periods have been restated to include Goldrush.

c.Barrick owned 75% of Turquoise Ridge through to the end of the second quarter of 2019, with our joint venture partner, Newmont, owning the remaining 25%. Turquoise Ridge was proportionately consolidated on the basis that the joint venture partners that have joint control have rights to the assets and obligations for the liabilities relating to the arrangement. The figures presented in this table are based on our 75% interest in Turquoise Ridge until June 30, 2019. On July 1, 2019, Barrick's 75% interest in Turquoise Ridge and Newmont's Twin Creeks and 25% interest in Turquoise Ridge were contributed to Nevada Gold Mines. Starting July 1, 2019, the results represent our 61.5% share of Turquoise Ridge and Twin Creeks, now referred to as Turquoise Ridge.

d.A 61.5% interest in these sites was acquired as a result of the formation of Nevada Gold Mines on July 1, 2019.

e.Represents the combined results of Cortez, Goldstrike (including our 60% share of South Arturo) and our 75% interest in Turquoise Ridge until June 30, 2019. Commencing July 1, 2019, the date Nevada Gold Mines was established, the results represent our 61.5% interest in Cortez, Carlin (including Goldstrike and NGM’s 60% interest in South Arturo up until May 30, 2021 and 100% interest thereafter), Turquoise Ridge (including Twin Creeks), Phoenix and Long Canyon.

f.Non-recurring items 
Non-recurring items in 2019 relate to organizational restructuring. These costs are not indicative of our cost of production and have been excluded from the calculation of total cash costs.


BARRICK YEAR-END 2021
113
MANAGEMENT’S DISCUSSION AND ANALYSIS

g.Exploration and evaluation costs
Exploration, evaluation and project expenses are presented as minesite sustaining if it supports current mine operations and project if it relates to future projects. Refer to page 85 of this MD&A.

h. Capital expenditures  
Capital expenditures are related to our gold sites only and are split between minesite sustaining and project capital expenditures. Project capital expenditures are capital spending at new projects and major, discrete projects at existing operations intended to increase net present value through higher production or longer mine life. Significant projects in the current year are the expansion project at Pueblo Viejo, construction of the Third Shaft at Turquoise Ridge, the development of the Gounkoto underground and the Veladero Phase 7 expansion. Refer to page 84 of this MD&A.

i.Rehabilitation - accretion and amortization  
Includes depreciation on the assets related to rehabilitation provisions of our gold operations and accretion on the rehabilitation provision of our gold operations, split between operating and non-operating sites.

j.Cost of sales per ounce
Gold cost of sales per ounce is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share).

k. Per ounce figures    
Cost of sales per ounce, total cash costs per ounce, all-in sustaining costs per ounce and all-in costs per ounce may not calculate based on amounts presented in this table due to rounding.

l.Co-product costs per ounce   
Total cash costs per ounce, all-in sustaining costs per ounce and all-in costs per ounce presented on a co-product basis removes the impact of by-product credits of our gold production (net of non-controlling interest) calculated as:
($ millions) For the three months ended 12/31/21
  
Carlin a
Cortez b
Turquoise Ridgec
Long Canyond
Phoenix d
Nevada Gold Minese
Hemlo Pueblo Viejo
By-product credits 0  1  1  0  47  49  0  12 
Non-controlling interest 0  0  0  0  (18) (18) 0  (5)
By-product credits (net of non-controlling interest) 0  1  1  0  29  31  0  7 
($ millions) For the three months ended 12/31/21
   Veladero Loulo-Gounkoto Kibali
North Mara m
Tongon
Bulyanhulu m
Buzwagi m,n
By-product credits 1  0 1  0  1  6 
Non-controlling interest 0  0 0  0  0  (1)
By-product credits (net of non-controlling interest) 1  0 1  0  1  5 
($ millions) For the three months ended 9/30/21
  
Carlin a
Cortez b
Turquoise Ridgec
Long Canyond
Phoenix d
Nevada Gold Minese
Hemlo Pueblo Viejo
By-product credits 51  52  16 
Non-controlling interest  (1) (20) (21) (6)
By-product credits (net of non-controlling interest) 31  31  10 
($ millions) For the three months ended 9/30/21
   Veladero Loulo-Gounkoto Kibali
North Mara m
Tongon
Bulyanhulu m
Buzwagi m,n
By-product credits
Non-controlling interest 
By-product credits (net of non-controlling interest)
 
BARRICK YEAR-END 2021
114
MANAGEMENT’S DISCUSSION AND ANALYSIS

   For the year ended 12/31/21
  
Carlin a
Cortez b
Turquoise Ridgec
Long Canyond
Phoenix d
Nevada Gold Minese
Hemlo
Pueblo Viejo
By-product credits 2  3  5  0  194  204  1  58 
Non-controlling interest  (1) (1) (2) 0  (75) (79) 0  (23)
By-product credits (net of non-controlling interest) 1  2  3  0  119  125  1  35 
   For the year ended 12/31/21
  
Veladero
Loulo-Gounkoto
Kibali
North Mara m
Tongon
Bulyanhulu m
Buzwagi m,n
By-product credits 7  0  2  2  1  15  0 
Non-controlling interest  0  0  0  0  0  (2) 0 
By-product credits (net of non-controlling interest) 7  0  2  2  1  13  0 
   For the year ended 12/31/20
  
Carlin a
Cortez b
Turquoise Ridgec
Long Canyond
Phoenix d
Nevada Gold Minese
Hemlo Pueblo Viejo
By-product credits 137  148  57 
Non-controlling interest  (1) (1) (3) (53) (57) (23)
By-product credits (net of non-controlling interest) 84  91  34 
   For the year ended 12/31/20
   Veladero
Porgera n
Loulo-Gounkoto Kibali
North Mara m
Tongon
Bulyanhulu m
Buzwagi m,n
By-product credits 10  22 
Non-controlling interest  (2) (4)
By-product credits (net of non-controlling interest) 18 

   For the year ended 12/31/19
  
Carlin a
Cortez b
Turquoise Ridgec
Long Canyond
Phoenix d
Nevada Gold Minese
Hemlo Pueblo Viejo
By-product credits 48  52  61 
Non-controlling interest  (1) (18) (19) (24)
By-product credits (net of non-controlling interest) 30  33  37 
   For the year ended 12/31/19
   Veladero
Porgera o
Kalgoorlie p
Loulo-Gounkoto Kibali
North Mara m
Tongon
Bulyanhulu m
Buzwagi m,n
By-product credits
Non-controlling interest 
By-product credits (net of non-controlling interest)

m.Formerly part of Acacia Mining plc. On September 17, 2019, Barrick acquired all of the shares of Acacia it did not already own. The results presented are on a 63.9% basis until September 30, 2019 (notwithstanding the completion of the Acacia transaction on September 17, 2019, we consolidated our interest in Acacia and recorded a non-controlling interest of 36.1% in the income statement for the entirety of the third quarter of 2019 as a matter of convenience); on a 100% basis from October 1, 2019 to December 31, 2019; and on a 84% basis starting January 1, 2020, the date the GoT’s 16% free carried interest was made effective. The results in the table and the discussion that follows are based on our share.

n.With the end of mining at Buzwagi in the third quarter of 2021, as previously reported, we have ceased to include production or non-GAAP cost metrics for Buzwagi from October 1, 2021 onwards.

o.As Porgera was placed on care and maintenance on April 25, 2020, no operating data or per ounce data was provided for the three month periods ended December 31, 2021 and September 30, 2021 and the year ended December 31, 2021.

p. On November 28, 2019, we completed the sale of our 50% interest in Kalgoorlie in Western Australia to Saracen Mineral Holdings Limited for total cash consideration of $750 million. The transaction resulted in a gain of $408 million for the year ended December 31, 2019. The operating results reported for Kalgoorlie reflect the Company’s attributable share of Kalgoorlie’s results until the date of divestiture.
BARRICK YEAR-END 2021
115
MANAGEMENT’S DISCUSSION AND ANALYSIS


Reconciliation of Copper Cost of Sales to C1 cash costs and All-in sustaining costs, including on a per pound basis
 
For the three months ended For the years ended
($ millions, except per pound information in dollars) 12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
 Cost of sales 134  162  569  556  361 
Depreciation/amortization (43) (60) (197) (208) (100)
Treatment and refinement charges 39  42  161  157  99 
Cash cost of sales applicable to equity method investments 88  74  313  267  288 
Less: royalties and production taxesa
(28) (27) (103) (54) (35)
By-product credits (6) (2) (15) (15) (9)
Other 0  0  (5)
 C1 cash cost of sales
184  189  728  703  599 
General & administrative costs 5  17  18  19 
Rehabilitation - accretion and amortization 2  6  15 
Royalties and production taxes 28  27  103  54  35 
Minesite exploration and evaluation costs 5  14 
Minesite sustaining capital expenditures 104  40  234  223  215 
Sustaining leases 3  9 
Inventory write-downs 0  0 
 All-in sustaining costs
331  265  1,111  1,020  894 
 Pounds sold - consolidated basis (millions pounds) 113  101  423  457  355 
 Cost of sales per poundb,c
2.21  2.57  2.32  2.02  2.14 
 C1 cash costs per poundb
1.63  1.85  1.72  1.54  1.69 
 All-in sustaining costs per poundb
2.92  2.60  2.62  2.23  2.52 
a.For the three months and year ended December 31, 2021, royalties and production taxes include royalties of $28 million and $103 million, respectively (September 30, 2021: $27 million, 2020: $54 million and 2019: $34 million).
b.Cost of sales per pound, C1 cash costs per pound and all-in sustaining costs per pound may not calculate based on amounts presented in this table due to rounding.
c.Copper cost of sales per pound is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).


BARRICK YEAR-END 2021
116
MANAGEMENT’S DISCUSSION AND ANALYSIS

Reconciliation of Copper Cost of Sales to C1 cash costs and All-in sustaining costs, including on a per pound basis, by operating site
For the three months ended
($ millions, except per pound information in dollars) 12/31/21 9/30/21
   Zaldívar Lumwana Jabal Sayid Zaldívar Lumwana Jabal Sayid
Cost of sales 84  134  33  79  162  19 
Depreciation/amortization (21) (43) (8) (20) (60) (4)
Treatment and refinement charges 0  31  8  38 
Less: royalties and production taxesa
0  (28) 0  (27)
By-product credits 0  0  (6) (2)
Other 0  0  0 
C1 cash cost of sales
63  94  27  59  113  17 
Rehabilitation - accretion and amortization 1  1  0 
Royalties and production taxesa
0  28  0  27 
Minesite exploration and evaluation costs 4  0  1 
Minesite sustaining capital expenditures 22  79  3  30 
Sustaining leases 1  1  1 
Inventory write-downs 0  0  0 
All-in sustaining costs
91  203  32  71  172  19 
Pounds sold - consolidated basis (millions pounds) 26  62  25  25  64  12 
Cost of sales per poundb,c
3.14  2.16  1.36  3.13  2.54  1.51 
C1 cash costs per poundb
2.35  1.54  1.11  2.33  1.76  1.35 
All-in sustaining costs per poundb
3.42  3.29  1.27  2.77  2.68  1.55 
($ millions, except per pound information in dollars) For the years ended December 31
12/31/21 12/31/20 12/31/19
   Zaldívar Lumwana Jabal Sayid Zaldívar Lumwana Jabal Sayid Zaldívar Lumwana Jabal Sayid
Cost of sales 314  569  99  262  556  104  307  361  93 
Depreciation/amortization (79) (197) (21) (72) (208) (27) (86) (100) (27)
Treatment and refinement charges 0  140  21  137  19  80  19 
Less: royalties and production taxesa
0  (103) 0  (54) (35)
By-product credits 0  0  (15) (15) (9)
Other 0  0  0  (5)
C1 cash cost of sales 235  409  84  191  431  81  221  301  76 
Rehabilitation - accretion and amortization 1  5  0  10 
Royalties and production taxesa
0  103  0  54  35 
Minesite exploration and evaluation costs 13  0  1 
Minesite sustaining capital expenditures 37  189  8  39  175  34  166  15 
Sustaining leases 4  3  2 
Inventory write-downs 0  0  0 
All-in sustaining costs 290  709  95  239  672  91  269  514  91 
Pounds sold - consolidated basis (millions pounds) 98  253  72  106  277  74  125  169  61 
Cost of sales per poundb,c
3.19  2.25  1.38  2.46  2.01  1.42  2.46  2.13  1.53 
C1 cash costs per poundb
2.38  1.62  1.18  1.79  1.56  1.11  1.77  1.79  1.26 
All-in sustaining costs per poundb
2.94  2.80  1.33  2.25  2.43  1.24  2.15  3.04  1.51 
a.For the three months and year ended December 31, 2021, royalties and production taxes include royalties of $28 million and $103 million, respectively (September 30, 2021: $27 million, 2020: $54 million and 2019: $34 million).
b.Cost of sales per pound, C1 cash costs per pound and all-in sustaining costs per pound may not calculate based on amounts presented in this table due to rounding.
c.Copper cost of sales per pound is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).
BARRICK YEAR-END 2021
117
MANAGEMENT’S DISCUSSION AND ANALYSIS

EBITDA and Adjusted EBITDA
EBITDA is a non-GAAP financial measure, which excludes the following from net earnings:
Income tax expense;
Finance costs;
Finance income; and
Depreciation.

Management believes that EBITDA is a valuable indicator of our ability to generate liquidity by producing operating cash flow to fund working capital needs, service debt obligations, and fund capital expenditures. Management uses EBITDA for this purpose. EBITDA is also frequently used by investors and analysts for valuation purposes whereby EBITDA is multiplied by a factor or “EBITDA multiple” that is based on an observed or inferred relationship between EBITDA and market values to determine the approximate total enterprise value of a company.
Adjusted EBITDA removes the effect of impairment charges; acquisition/disposition gains/losses; foreign currency translation gains/losses; and other expense adjustments. We also remove the impact of the income tax expense, finance costs, finance income and depreciation incurred in our equity method accounted investments. We believe these items provide a greater level of consistency with the adjusting items included in our
adjusted net earnings reconciliation, with the exception that these amounts are adjusted to remove any impact on finance costs/income, income tax expense and/or depreciation as they do not affect EBITDA. We believe this additional information will assist analysts, investors and other stakeholders of Barrick in better understanding our ability to generate liquidity from our full business, including equity method investments, by excluding these amounts from the calculation as they are not indicative of the performance of our core mining business and do not necessarily reflect the underlying operating results for the periods presented.
EBITDA and adjusted EBITDA are intended to provide additional information to investors and analysts and do not have any standardized definition under IFRS, and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. EBITDA and adjusted EBITDA exclude the impact of cash costs of financing activities and taxes, and the effects of changes in operating working capital balances, and therefore are not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate EBITDA and adjusted EBITDA differently.


Reconciliation of Net Earnings to EBITDA and Adjusted EBITDA
For the three months ended For the years ended
  ($ millions) 12/31/21 9/30/21 12/31/21 12/31/20 12/31/19
Net earnings 1,152  612  3,288  3,614  4,574 
   Income tax expense 304  323  1,344  1,332  1,783 
   Finance costs, neta
74  80  307  306  394 
   Depreciation 557  538  2,102  2,208  2,032 
EBITDA 2,087  1,553  7,041  7,460  8,783 
Impairment charges (reversals) of long-lived assetsb
14  10  (63) (269) (1,423)
Acquisition/disposition gainsc
(198) (5) (213) (180) (2,327)
Loss on currency translation 13  29  50  109 
Other expense (income) adjustmentsd
36  12  73  71  (687)
Income tax expense, net finance costsa, and depreciation from equity investees
118  94  391  360  378 
Adjusted EBITDA 2,070  1,669  7,258  7,492  4,833 
a.Finance costs exclude accretion.
b.Net impairment reversals primarily relate to non-current asset reversals at Lagunas Norte in the current year and primarily relate to our Tanzanian assets in the prior year.
c.Acquisition/disposition gains for the current year primarily relate to the gain on the sale of Lone Tree in the fourth quarter of 2021, while the prior year mainly relates to the gains on the sale of Eskay Creek, Massawa, Morila and Bullfrog.
d.Other expense adjustments for both the current and prior year primarily relate to care and maintenance expenses at Porgera. The current year periods were also impacted by a $25 million litigation settlement. The prior year was further impacted by the impact of changes in the discount rate assumptions on our closed mine rehabilitation provision and donations related to Covid-19, partially offset by the gain on the remeasurement of the residual cash liability relating to our silver sale agreement with Wheaton.

BARRICK YEAR-END 2021
118
MANAGEMENT’S DISCUSSION AND ANALYSIS

Reconciliation of Segment Income to Segment EBITDA
($ millions) For the three months ended 12/31/21
  
Carlin a (61.5%)
Cortez b (61.5%)
Turquoise Ridgec (61.5%)
Nevada Gold Minesd (61.5%)
Pueblo Viejo (60%) Loulo-Gounkoto (80%) Kibali (45%) Veladero (50%)
North Mara e (84%)
Bulyanhulu e (84%)
Income 247  139  51  617  90  74  71  43  68  51 
Depreciation 51  55  31  176  35  58  37  37  12  14 
EBITDA 298  194  82  793  125  132  108  80  80  65 
For the three months ended 9/30/21
  
Carlin a (61.5%)
Cortez b (61.5%)
Turquoise Ridgec (61.5%)
Nevada Gold Minesd (61.5%)
Pueblo Viejo (60%) Loulo-Gounkoto (80%) Kibali (45%) Veladero (50%)
North Mara e (84%)
Bulyanhulu e (84%)
Income 147  77  51  333  113  84  74  24  52  37 
Depreciation 41  46  31  162  37  53  36  17  12  13 
EBITDA 188  123  82  495  150  137  110  41  64  50 
For the year ended 12/31/21
  
Carlin a (61.5%)
Cortez b (61.5%)
Turquoise Ridgec (61.5%)
Nevada Gold Minesd (61.5%)
Pueblo Viejo (60%) Loulo-Gounkoto (80%) Kibali (45%) Veladero (50%)
North Mara e (84%)
Bulyanhulu e (84%)
Income 733  337  229  1,675  445  380  278  118  214  122 
Depreciation 170  181  123  630  142  222  141  85  47  48 
EBITDA 903  518  352  2,305  587  602  419  203  261  170
   For the year ended 12/31/20
  
Carlin a (61.5%)
Cortez b (61.5%)
Turquoise Ridgec (61.5%)
Nevada Gold Minesd (61.5%)
Pueblo Viejo (60%) Loulo-Gounkoto (80%) Kibali (45%) Veladero (50%)
North Mara e (84%)
Bulyanhulu e (84%)
Income 795  385  229  1,636  508  358  244  114  214  27 
Depreciation 188  138  113  596  136  214  174  69  76  60 
EBITDA 983  523  342  2,232  644  572  418  183  290  87 
For the year ended 12/31/19
  
Carlin a (61.5%)
Cortez b (61.5%)
Turquoise Ridgec (61.5%)
Nevada Gold Minesd (61.5%)
Pueblo Viejo (60%) Loulo-Gounkoto (80%) Kibali (45%) Veladero (50%)
North Mara e (84%)
Bulyanhulu e (84%)
Income 370  459  201  1,050  402  190  108  57  112  (14)
Depreciation 239  197  92  592  120  236  196  115  75  14 
EBITDA 609  656  293  1,642  522  426  304  172  187 
a.On July 1, 2019, Barrick's Goldstrike and Newmont's Carlin were contributed to Nevada Gold Mines and are now referred to as Carlin. As a result, the amounts presented represent Goldstrike on a 100% basis (including our 60% share of South Arturo) up until June 30, 2019, and the combined results of Carlin and Goldstrike (including our share of South Arturo) on a 61.5% basis thereafter. On September 7, 2021, Barrick announced NGM had entered into an Exchange Agreement with i-80 Gold to acquire the 40% interest in South Arturo that NGM did not already own in exchange for the Lone Tree and Buffalo Mountain properties and infrastructure. Operating results within our 61.5% interest in Carlin includes NGM’s 60% interest in South Arturo up until May 30, 2021, and 100% interest thereafter, reflecting the terms of the Exchange Agreement which closed on October 14, 2021.
b.On July 1, 2019, Cortez was contributed to Nevada Gold Mines, a joint venture with Newmont. As a result, the amounts presented are on a 100% basis up until June 30, 2019, and on a 61.5% basis thereafter. Starting in the first quarter of 2021, Goldrush is reported as part of Cortez as it is operated by Cortez management. Comparative periods have been restated to include Goldrush.
c.Barrick owned 75% of Turquoise Ridge through to the end of the second quarter of 2019, with our joint venture partner, Newmont, owning the remaining 25%. Turquoise Ridge was proportionately consolidated on the basis that the joint venture partners that have joint control have rights to the assets and obligations for the liabilities relating to the arrangement. The figures presented in this table are based on our 75% interest in Turquoise Ridge until June 30, 2019. On July 1, 2019, Barrick's 75% interest in Turquoise Ridge and Newmont's Twin Creeks and 25% interest in Turquoise Ridge were contributed to Nevada Gold Mines. Starting July 1, 2019, the results represent our 61.5% share of Turquoise Ridge and Twin Creeks, now referred to as Turquoise Ridge.
d.Represents the combined results of Cortez, Goldstrike (including our 60% share of South Arturo) and our 75% interest in Turquoise Ridge until June 30, 2019. Commencing July 1, 2019, the date Nevada Gold Mines was established, the results represent our 61.5% interest in Cortez, Carlin (including Goldstrike and NGM’s 60% interest in South Arturo up until May 30, 2021 and 100% interest thereafter), Turquoise Ridge (including Twin Creeks), Phoenix and Long Canyon.
e.Formerly part of Acacia Mining plc. On September 17, 2019, Barrick acquired all of the shares of Acacia it did not own. Operating results are included at 63.9% until September 30, 2019 (notwithstanding the completion of the Acacia transaction on September 17, 2019, we consolidated our interest in Acacia and recorded a non-controlling interest of 36.1% in the income statement for the entirety of the third quarter of 2019 as a matter of convenience), on a 100% basis from October 1, 2019, to December 31, 2019, and on an 84% basis thereafter as the GoT’s 16% free-carried interest was made effective from January 1, 2020.


BARRICK YEAR-END 2021
119
MANAGEMENT’S DISCUSSION AND ANALYSIS

Realized Price
Realized price is a non-GAAP financial measure which excludes from sales:
Unrealized gains and losses on non-hedge derivative contracts;
Unrealized mark-to-market gains and losses on provisional pricing from copper and gold sales contracts;
Sales attributable to ore purchase arrangements;
Treatment and refining charges; and
Cumulative catch-up adjustment to revenue relating to our streaming arrangements.

This measure is intended to enable Management to better understand the price realized in each reporting period for gold and copper sales because unrealized mark-to-market values of non-hedge gold and copper derivatives are subject to change each period due to changes in market factors such as spot and forward gold and copper prices, so that prices ultimately realized may differ from those recorded. The exclusion of such unrealized mark-to-market gains and losses from the presentation of this performance measure enables investors to understand performance based on the realized proceeds of selling gold and copper production.
The gains and losses on non-hedge derivatives and receivable balances relate to instruments/balances that mature in future periods, at which time the gains and losses will become realized. The amounts of these gains and losses reflect fair values based on market valuation assumptions at the end of each period and do not necessarily represent the amounts that will become realized on maturity. We believe this provides investors and analysts with a more accurate measure with which to compare to market gold prices and to assess our gold sales performance. For those reasons, management believes that this measure provides a more accurate reflection of our Company’s past performance and is a better indicator of its expected performance in future periods.
The realized price measure is intended to provide additional information, and does not have any standardized definition under IFRS and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The measure is not necessarily indicative of sales as determined under IFRS. Other companies may calculate this measure differently. The following table reconciles realized prices to the most directly comparable IFRS measure.
 
Reconciliation of Sales to Realized Price per ounce/pound
For the three  months ended For the years ended
($ millions, except per ounce/pound information in dollars) Gold Copper Gold Copper
   12/31/21 9/30/21 12/31/21 9/30/21 12/31/21 12/31/20 12/31/19 12/31/21 12/31/20 12/31/19
Sales 2,977  2,531  263  209  10,738  11,670  9,186  962   697  393 
Sales applicable to non-controlling interests (931) (799) 0  (3,323) (3,494) (1,981) 0 
Sales applicable to equity method investmentsa,b
172  166  222  154  660  648  543  707  483  492 
Realized non-hedge gold/copper derivative gains 0  0  0  0 
Sales applicable to sites in care and maintenancec
(8) (11) 0  (88) (170) (140) 0 
Treatment and refining charges 1  39  42  10  161  157  99 
Otherd
2  0  2  13  22  0 
Revenues – as adjusted 2,213  1,896  524  405  7,999  8,674  7,631  1,830   1,337  984 
Ounces/pounds sold (000s ounces/millions pounds)c
1,234  1,071  113  101  4,468  4,879  5,467  423   457  355 
Realized gold/copper price per ounce/pounde
1,793  1,771  4.63  3.98  1,790  1,778  1,396  4.32  2.92  2.77 
a.Represents sales of $172 million and $661 million, respectively, for the three months and year ended December 31, 2021 (September 30, 2021: $166 million; 2020: $648 million; 2019: $505 million) applicable to our 45% equity method investment in Kibali and $nil and $nil, respectively (September 30, 2021: $nil; 2020: $nil; 2019: $39 million) applicable to our 40% equity method investment in Morila for gold. Represents sales of $119 million and $423 million, respectively, for the three months and year ended December 31, 2021 (September 30, 2021: $108 million; 2020: $298 million; 2019: $343 million) applicable to our 50% equity method investment in Zaldívar and $111 million and $305 million, respectively (September 30, 2021: $50 million; 2020: $204 million; 2019: $168 million) applicable to our 50% equity method investment in Jabal Sayid.
b. Sales applicable to equity method investments are net of treatment and refinement charges.
c.Figures exclude Pierina, Golden Sunlight starting in the third quarter of 2019, Morila starting in the third quarter of 2019 up until its divestiture in November 2020, Lagunas Norte starting in the fourth quarter of 2019, and Buzwagi starting in the fourth quarter of 2021 up until its divestiture in June 2021 from the calculation of realized price per ounce. Some of these assets are producing incidental ounces while in closure or care and maintenance.
d.Represents cumulative catch-up adjustment to revenue relating to our streaming arrangements. Refer to note 2f to the Financial Statements for more information.
e.Realized price per ounce/pound may not calculate based on amounts presented in this table due to rounding.
BARRICK YEAR-END 2021
120
MANAGEMENT’S DISCUSSION AND ANALYSIS

Technical Information

The scientific and technical information contained in this MD&A has been reviewed and approved by Craig Fiddes, SME-RM, Manager – Resource Modeling, Nevada Gold Mines; Chad Yuhasz, P.Geo, Mineral Resource Manager, Latin America & Asia Pacific; Simon Bottoms, CGeol, MGeol, FGS, FAusIMM, Mineral Resources Manager: Africa & Middle East; Rodney Quick, MSc, Pr. Sci.Nat, Mineral Resource Management and Evaluation Executive; John Steele, CIM, Metallurgy, Engineering and Capital Projects
Executive; and Rob Krcmarov, FAusIMM, Technical Advisor to Barrick – each a “Qualified Person” as defined in National Instrument 43-101 – Standards of Disclosure for Mineral Projects.
All mineral reserve and mineral resource estimates are estimated in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects. Unless otherwise noted, such mineral reserve and mineral resource estimates are as of December 31, 2021.

Endnotes 

1A Tier One Gold Asset is an asset with a reserve potential to deliver a minimum 10-year life, annual production of at least 500,000 ounces of gold and total cash costs per ounce over the mine life that are in the lower half of the industry cost curve.
2A Tier Two Gold Asset is an asset with a reserve potential to deliver a minimum 10-year life, annual production of at least 250,000 ounces of gold and total cash costs per ounce over the mine life that are in the lower half of the industry cost curve.
3A Tier One Copper Asset is an asset with a reserve potential of greater than five million tonnes of contained copper and C1 cash costs per pound over the mine life that are in the lower half of the industry cost curve.
4A Strategic Asset is an asset which in the opinion of Barrick, has the potential to deliver significant unrealized value in the future.
5Currently consists of Barrick’s Lumwana mine and Zaldívar and Jabal Sayid copper joint ventures.
6Further information on these non-GAAP financial measures, including detailed reconciliations, is included on pages 94 to 120 of this MD&A.
7Gold cost of sales per ounce is calculated as cost of sales across our gold operations (excluding sites in closure or care and maintenance) divided by ounces sold (both on an attributable basis using Barrick’s ownership share). Copper cost of sales per pound is calculated as cost of sales across our copper operations divided by pounds sold (both on an attributable basis using Barrick’s ownership share).
8Total reportable incident frequency rate (“TRIFR”) is a ratio calculated as follows: number of reportable injuries x 1,000,000 hours divided by the total number of hours worked. Reportable injuries include fatalities, lost time injuries, restricted duty injuries, and medically treated injuries. Lost time injury frequency rate (“LTIFR”) is a ratio calculated as follows: number of lost time injuries x 1,000,000 hours divided by the total number of hours worked.
9Class 1 - High Significance is defined as an incident that causes significant negative impacts on human health or the environment or an incident that extends
onto publicly accessible land and has the potential to cause significant adverse impact to surrounding communities, livestock or wildlife.
10Preliminary figures and subject to external assurance.
11All mineral resource and mineral reserve estimates of tonnes, Au oz, Ag oz and Cu lb are reported to the second significant digit. All measured and indicated mineral resource estimates of grade and all proven and probable mineral reserve estimates of grade for Au g/t, Ag g/t and Cu % are reported to two decimal places. All inferred mineral resource estimates of grade for Au g/t, Ag g/t and Cu % are reported to one decimal place. 2021 polymetallic mineral resources and mineral reserves are estimated using the combined value of gold, copper & silver and accordingly are reported as Gold, Copper & Silver mineral resources and mineral reserves.
12Estimated in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects as required by Canadian securities regulatory authorities. Estimates are as of December 31, 2021, unless otherwise noted. Proven reserves of 240 tonnes grading 2.20 g/t, representing 17 million ounces of gold, and 380 million tonnes grading 0.41%, representing 3,400 million pounds of copper. Probable reserves of 1,000 tonnes grading 1.60 g/t, representing 53 million ounces of gold, and 1,100 million tonnes grading 0.37%, representing 8,800 million pounds of copper. Measured resources of 490 tonnes grading 2.05 g/t, representing 32 million ounces of gold, and 680 million tonnes grading 0.38%, representing 5,700 million pounds of copper. Indicated resources of 2,800 tonnes grading 1.40 g/t, representing 130 million ounces of gold, and 2,500 million tonnes grading 0.34%, representing 19,000 million pounds of copper. Inferred resources of 1,000 tonnes grading 1.3 g/t, representing 42 million ounces of gold, and 450 million tonnes grading 0.2%, representing 2,100 million pounds of copper. Complete mineral reserve and mineral resource data for all mines and projects referenced in this MD&A, including tonnes, grades, and ounces, can be found on pages 129-137 of Barrick’s Fourth Quarter and Year-End 2021 Report.
BARRICK YEAR-END 2021
121
MANAGEMENT’S DISCUSSION AND ANALYSIS

13Estimated in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects as required by Canadian securities regulatory authorities. Estimates are as of December 31, 2020, unless otherwise noted. Proven reserves of 280 million tonnes grading 2.37 g/t, representing 21 million ounces of gold, and 350 million tonnes grading 0.39%, representing 3,000 million pounds of copper. Probable reserves of 990 million tonnes grading 1.46 g/t, representing 47 million ounces of gold, and 1,100 million tonnes grading 0.39%, representing 9,700 million pounds of copper. Measured resources of 530 million tonnes grading 2.11 g/t, representing 36 million ounces of gold, and 600 million tonnes grading 0.36%, representing 4,800 million pounds of copper. Indicated resources of 2,800 million tonnes grading 1.41 g/t, representing 130 million ounces of gold, and 2,500 million tonnes grading 0.36%, representing 20,000 million pounds of copper. Inferred resources of 980 million tonnes grading 1.4 g/t, representing 43 million ounces of
gold, and 440 million tonnes grading 0.2%, representing 2,200 million pounds of copper. Complete 2020 mineral reserve and mineral resource data for all mines and projects referenced in this MD&A, including tonnes, grades, and ounces, can be found on pages 34-47 of Barrick’s Annual Information Form/Form 40-F for the year ended December 31, 2020 on file with Canadian provincial securities regulatory authorities and the U.S. Securities and Exchange Commission.
14See the Technical Report on the Turquoise Ridge mine, dated March 25, 2020, and filed on SEDAR at www.sedar.com and EDGAR at www.sec.gov on March 25, 2020.
15See the Technical Report on the Pueblo Viejo mine, Sanchez Ramirez Province, Dominican Republic, dated March 19, 2018, and filed on SEDAR at www.sedar.com and EDGAR at www.sec.gov on March 23, 2018.
16North Leeville Significant Interceptsa
Drill Results from Q4 2021
Drill Holeb
Azimuth Dip Interval (m)
Width (m)c
Au (g/t)
NLX-00009 23 (79) 822.3 - 833.9 11.6 12.00
NLX-00010 117 (72) 791.6 - 848.3 56.7 28.39
826.9 - 831.2 4.3 8.88
NLX-00012 305 -79 837.3 - 845.1 7.8 26.03
CGX-21086 90 -81 773.6 - 778.8 5.2 24.50
a.All intercepts calculated using a 3.4 g/t Au cutoff and are uncapped; minimum intercept width is 3.0 m; internal dilution is less than 20% total width.
b.Carlin Trend drill hole nomenclature: Project area (NLX - North Leeville, CGX - Leeville) followed by hole number.
c.True widths of intercepts are uncertain at this stage.
The drilling results for the Carlin Trend contained in this MD&A have been prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects. All drill hole assay information has been manually reviewed and approved by staff geologists and re-checked by the project manager. Sample preparation and analyses are conducted by an independent laboratory, ALS Minerals. Procedures are employed to ensure security of samples during their delivery from the drill rig to the laboratory. The quality assurance procedures, data verification and assay protocols used in connection with drilling and sampling on North Leeville conform to industry accepted quality control methods.
17    REN Significant Interceptsa
Drill Results from Q4 2021
Drill Holeb
Azimuth Dip Interval (m)
Width (m)c
True Width (m)c
Au (g/t)
273.7 - 313.9 40.2 15.8 27.6
MRC-21001 301 (28) 329.2 - 341.4 12.2 12.9 13.78
235 - 260.3 25.3 15.9 16.94
266.9 - 276.1 9.3 13.1 24.75
MRC-21010 239 (22) 299.6 - 307.2 7.6 9.1 5.11
347.5 - 351.7 4.3 9.1 5.25
MRC-21011 262 (27) 413.9 - 430.7 16.8 12.2 7.03
MRC-21014 80 (29) 286.8 - 298.1 11.3 7.6 17.49
96 (20) 242.2 - 258.8 16.6 12.2 9.63
MRC-21015 80 (20) 274 - 293.5 19.5 14.0 5.25
a.All intercepts calculated using a 3.4 g/t Au cutoff and are uncapped; minimum intercept width is 3.0 m; internal dilution is less than 20% total width.
b.Carlin Trend drill hole nomenclature: Project area (MRC - Ren) followed by hole number.
c.True widths of intercepts are uncertain at this stage.
BARRICK YEAR-END 2021
122
MANAGEMENT’S DISCUSSION AND ANALYSIS

The drilling results for REN contained in this MD&A have been prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects. All drill hole assay information has been manually reviewed and approved by staff geologists and re-checked by the project manager. Sample preparation and analyses are conducted by an independent laboratory, ALS Minerals. Procedures are employed to ensure security of samples during their delivery from the drill rig to the laboratory. The quality assurance procedures, data verification and assay protocols used in connection with drilling and sampling on REN conform to industry accepted quality control methods.
18    CHUG Hanson Footwall Significant Interceptsa
Drill Results from Q4 2021
Drill Holeb
Azimuth Dip Interval (m)
Width (m)c
Au (g/t)
479.6 - 499.5 16.9 11.24
CMX-21012 217 42 564.4 - 577
No Significant Interceptd
CMX-21008 093 55
No Significant Interceptd
CMX-21025 228 47 584.4 - 608.1 22.6 23.07
a.All intercepts calculated using a 4.2 g/t Au cutoff and are uncapped; minimum intercept width is 2.5 m; internal dilution is less than 20% total width.
b.Cortez drill hole nomenclature: Project (CMX - CHUG Minex) followed by the year (21 for 2021) then hole number.
c.True widths of intercepts are uncertain at this stage.
d.Sub-grade intercepts in drillhole CMX-21012 of 12.6 m at 2.59 g/t and CMX-21008 of 5.2 m at 2.75 g/t and 5.1 m at 1.91 g/t using a 1.0 g/t cutoff uncapped; minimum intercept width is 2.5 m; internal dilution is less than 20% total width, have been listed in previous reports for the purpose of showing the presence of the mineral system.

The drilling results for Cortez contained in this MD&A have been prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects. All drill hole assay information has been manually reviewed and approved by staff geologists and re-checked by the project manager. Sample preparation and analyses are conducted by an independent laboratory, ALS Minerals. Procedures are employed to ensure security of samples during their delivery from the drill rig to the laboratory. The quality assurance procedures, data verification and assay protocols used in connection with drilling and sampling at Cortez conform to industry accepted quality control methods.
19    Loulo-Gounkoto Significant Interceptsa
Drill Results from Q4 2021
Including d
Drill Holeb
Azimuth Dip Interval (m)
Width (m)c
Au (g/t) Interval (m)
Width (m)c
Au (g/t)
336.8-340 3.20 15.53      
346.03-348.67 2.64 1.30      
YRDH024 229.26 (56.48) 371.65-377.45 5.80 0.76      
131.1-138.5 7.40 6.03      
139.1-141.7 2.60 6.64      
YRDH027 230.26 (56.16) 156.5-162.4 5.90 2.89      
296.8-299.9 3.10 0.77      
YRDH029 225.00 (55.00) 300.9-303.45 2.55 2.41      
312.7-315.15 2.45 0.64      
YRDH030 225.00 (55.00) 320.5-324.8 4.30 0.92      
312-324.4 12.40 3.33      
337.17-342.4 5.23 9.54      
YRDH031 230.00 (55.00) 343.2-345.6 2.40 1.72      
27-30 3.00 3.05      
YRAC0015 270.00 (60.00) 42-48 6.00 2.89 42-44 2.00 7.36
YRAC0017 270.00 (60.00) 13-18 5.00 0.52      
57-59 2.00 0.69      
YRAC0029 270.00 (60.00) 63-66 3.00 1.02      
2-13 11.00 0.96      
YRAC0030 270.00 (60.00) 15-22 7.00 1.26      
YRAC0031 270.00 (60.00) 7-10 3.00 0.58      
YRAC0045 270.00 (60.00) 30-32 2.00 1.21      
YRAC0047 270.00 (60.00) 13-15 2.00 1.94      
YRAC0048 270.00 (60.00) 27-35 8.00 3.57 28-32 4.00 5.77

BARRICK YEAR-END 2021
123
MANAGEMENT’S DISCUSSION AND ANALYSIS

a.All intercepts calculated using a 0.5 g/t Au cutoff and are uncapped; minimum intercept width is 2 m; internal dilution is equal to or less than 2 m total width.
b.Loulo – Gounkoto drill hole nomenclature: prospect initial YR (Yalea Ridge and Sansamba West), followed by type of drilling AC (Air Core), RC (Reverse Circulation), DH (Diamond Drilling) RCDH (RC/Diamond Tail).
c.True widths uncertain at this stage.
d.All intercepts calculated using a 3.0 g/t Au cutoff and are uncapped; minimum intercept width is 2 m; internal dilution is equal to or less than 2 m total width.
The drilling results for the Loulo-Gounkoto property contained in this MD&A have been prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects. All drill hole assay information has been manually reviewed and approved by staff geologists and re-checked by the project manager. Sample preparation and analyses are conducted by SGS Laboratories, an independent laboratory. Industry accepted best practices for preparation and fire assaying procedures are utilized to determine gold content. Procedures are employed to ensure security of samples during their delivery from the drill rig to the laboratory. The quality assurance procedures, data verification and assay protocols used in connection with drilling and sampling on the Loulo property conform to industry accepted quality control methods.
20    Nielle Significant Interceptsa
Drill Results from Q4 2021
Drill Holeb
Azimuth Dip Interval (m)
Width (m)c
Au (g/t)
144.00-146.00 2.00 2.90
169.00-175.00 6.00 1.43
183.00-186.00 3.00 1.15
213.00-215.00 2.00 2.63
219.00-223.00 4.00 1.29
SNRC052 119 (51) 225.00-233.00 8.00 4.52
140.00-142.00 2.00 1.01
188.00-205.00 17.00 2.87
208.00-210.00 2.00 2.07
SNRC053 117 (53) 219.00-222.00 3.00 11.77
254.00-262.00 8.00 1.91
263.00-274.70 11.70 5.17
277.26-284.00 6.74 2.11
286.40-293.08 6.68 5.20
372.00-374.00 2.00 0.56
SNRCDH001 121 (50) 384.50-387.20 2.70 1.54
202.00-206.00 4.00 2.29
SNRCDH002 115 (52) 225.00-228.00 3.00 1.31
198.00-200.00 2.00 0.90
208.00-210.00 2.00 2.69
222.00-225.00 3.00 0.75
SNRCDH003 117 (50) 236.00-240.00 4.00 0.92
SNRCDH004 120 (54) 350.07-366.20 16.13 2.32
SNRCDH005 120 (53) 346.80-349.95 3.15 2.96
286.80-291.32 4.52 1.36
SNRCDH006 114 (58) 296.18-300.96 4.78 2.20
303.00-306.00 3.00 0.88
311.00-314.00 3.00 2.16
317.70-323.00 5.30 2.20
SNRCDH007 117 (53) 328.85-332.90 4.05 1.49
294.00-300.10 6.10 0.87
317.35-322.55 5.20 4.30
SNRCDH008 298 (53) 324.40-331.00 6.60 1.60
335.37-338.61 3.24 1.56
355.90-361.90 6.00 4.79
SNRCDH009 300 (53) 387.10-390.80 3.70 1.65
38.00-42.00 4.00 8.24
43.00-48.00 5.00 1.25
SNRC057 117 (50) 52.00-54.00 2.00 0.58
BARRICK YEAR-END 2021
124
MANAGEMENT’S DISCUSSION AND ANALYSIS

189.00-191.00 2.00 0.50
207.00-209.00 2.00 0.59
SNRC060 120 (51) 217.00-230.00 13.00 2.08
50.00-64.00 14.00 12.01
SNRC103 119 (49) 66.00-68.00 2.00 1.19
90.00-102.00 12.00 1.95
SNRC105 125 (49) 109.00-120.00 11.00 10.47
26.00-61.00 35.00 8.99
65.00-69.00 4.00 1.32
SNRC106 115 (52) 74.00-76.00 2.00 0.53
0.00-5.00 5.00 21.46
SNRC108 120 (50) 9.00-12.00 3.00 0.93
SNRC114 128 (53) 73.00-76.00 3.00 6.62
SNRC115 126 (51) 29.00-38.00 9.00 2.60
SNRC118 119 (54) 115.00-122.00 7.00 4.94
73.00-76.00 3.00 0.70
SNRC119 114 (51) 85.00-90.00 5.00 12.54
43.00-51.00 8.00 3.39
SNRC120 126 (47) 67.00-69.00 2.00 0.96
117.00-122.00 5.00 1.08
SNRC122 118 (48) 123.00-132.00 9.00 4.20
88.00-90.00 2.00 1.28
SNRC123 117 (50) 96.00-106.00 10.00 6.23
8.00-11.00 3.00 4.44
14.00-25.00 11.00 7.22
SNRC125 120 (50) 26.00-28.00 2.00 0.99
91.00-106.00 15.00 1.92
SNRC127 125 (51) 107.00-117.00 10.00 5.37
56.00-58.00 2.00 1.67
SNRC128 123 (51) 61.00-84.00 23.00 7.03
SNRC129 120 (50) 21.00-33.00 12.00 4.53
73.00-78.00 5.00 2.09
83.00-85.00 2.00 1.51
91.00-93.00 2.00 0.90
SNRC131 120 (52) 95.00-115.00 20.00 4.59
8.00-10.00 2.00 1.04
36.00-38.00 2.00 0.58
SNRC132 120 (50) 40.00-68.00 28.00 6.24
SNRC133 120 (50) 6.00-20.00 14.00 3.59
SNRC134 125 (51) 161.00-176.00 15.00 5.91
93.00-102.00 9.00 2.22
104.00-109.00 5.00 2.97
120.00-124.00 4.00 0.93
SNRC135 125 (49) 126.00-137.00 11.00 1.98
65.00-72.00 7.00 3.04
79.00-91.00 12.00 12.80
94.00-96.00 2.00 0.79
SNRC136 121 (53) 101.00-114.00 13.00 7.91
25.00-27.00 2.00 6.50
38.00-41.00 3.00 3.59
43.00-45.00 2.00 20.75
54.00-66.00 12.00 3.00
SNRC137 122 (51) 68.00-70.00 2.00 0.58
SNRC138 120 (50) 17.00-22.00 5.00 1.76
SNRC139 123 (50) 179.00-182.00 3.00 1.08
BARRICK YEAR-END 2021
125
MANAGEMENT’S DISCUSSION AND ANALYSIS

SNRC158 120 (50) 52.00-57.00 5.00 4.42
SNRC160 121 (51) 48.00-51.00 3.00 3.26
50.00-57.00 7.00 1.04
60.00-63.00 3.00 3.64
66.00-70.00 4.00 2.37
74.00-80.00 6.00 2.87
SNRC161 131 (50) 83.00-101.00 18.00 8.91
SNRC162 120 (50) 8.00-18.00 10.00 4.84
SNRC164 120 (50) 25.00-28.00 3.00 1.31
275.42-284.00 8.58 0.79
321.10-332.00 10.90 2.27
338.00-343.00 5.00 1.23
SNDDH003A 295 (52) 351.10-354.20 3.10 2.29
138.00-140.00 2.00 2.23
148.00-152.00 4.00 2.07
164.00-166.00 2.00 2.46
177.00-179.00 2.00 1.69
SNRC073A 121 (50) 190.00-203.00 13.00 4.06
KORAC001 120 (50) 87.00-92.00 5.00 0.69
KORAC002 120 (50) 12.00-23.00 11.00 0.88
KORAC009 120 (50) 50.00-60.00 10.00 0.96
KORAC021 120 (50) 29.00-32.00 3.00 1.22
41.00-48.00 7.00 1.05
KORAC022 120 (50) 51.00-66.00 15.00 3.54
a.All intercepts calculated using a 0.5 g/t Au cutoff and are uncapped; minimum intercept width is 2 m; internal dilution is equal to or less than 2 m width.
b.Nielle drill hole nomenclature: prospect initial SN (Seydou North), KOR (Koro), followed by type of drilling RC (Reverse Circulation), DDH (Diamond Drilling), RCDH (RC pre-collar with Diamond Tail), or AC (Air Core).
c.True widths are uncertain at this stage.
The drilling results for the Nielle property contained in this MD&A have been prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects. All drill hole assay information has been manually reviewed and approved by staff geologists and re-checked by the project manager. Sample preparation and analyses are conducted by SGS, an independent laboratory. Procedures are employed to ensure security of samples during their delivery from the drill rig to the laboratory. The quality assurance procedures, data verification and assay protocols used in connection with drilling and sampling on the Nielle property conform to industry accepted quality control methods.
21    Kibali Significant Interceptsa
Drill Results from Q4 2021
Including d
Drill Holeb
Azimuth Dip Interval (m)
Width (m)c
Au (g/t) Interval (m) Width (m) Au (g/t)
KPRC0001 290 (60) 100.00-104.00 4.00 3.80 101.00 - 102.00 1.00 6.27
KPRC0002 290 (60) 26.00-30.00 4.00 0.83
a.All intercepts calculated using a 0.5 g/t Au cutoff and are uncapped; minimum intercept width is 2 m; internal dilution is equal to or less than 25% total width.
b.Kibali drill hole nomenclature: prospect initial KP (Kolapi) followed by type of drilling RC (Reverse Circulation) with no designation of the year.
c.True width of intercepts uncertain at this stage.
d.All including intercepts, calculated using a 0.5 g/t Au cutoff and are uncapped, minimum intercept width is 1m, no internal dilution, with grade significantly above (>40%) the overall intercept grade.
The drilling results for the Kibali property contained in this MD&A have been prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects. All drill hole assay information has been manually reviewed and approved by staff geologists and re-checked by the project manager. Sample preparation and analyses are conducted by SGS, an independent laboratory. Procedures are employed to ensure security of samples during their delivery from the drill rig to the laboratory. The quality assurance procedures, data verification and assay protocols used in connection with drilling and sampling on the Kibali property conform to industry accepted quality control methods.
BARRICK YEAR-END 2021
126
MANAGEMENT’S DISCUSSION AND ANALYSIS

22    Jabal Sayid Significant Interceptsa
Drill Results from Q4 2021
Drill Holeb
Azimuth Dip Interval (m)
Width (m)c
Cu (%)
BDH1153 273 (75) 375.20-510.90 135.70 1.93
BDH4084 21 (52) 5.00-11.00 6.00 0.78
a.All intercepts calculated using a 0.5% Cu cutoff and are uncapped; minimum intercept width is 2 m; internal dilution is equal to or less than 5 m total width.
b.Jabal Sayid drill hole nomenclature: BDH (surface diamond hole) followed by lode and hole number.
c.True widths uncertain at this stage.
The drilling results for the Jabal Sayid property contained in this MD&A have been prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects. All drill hole assay information has been manually reviewed and approved by staff geologists and re-checked by the project manager. Sample preparation and analyses are conducted by ALS Jeddah, an independent laboratory. Procedures are employed to ensure security of samples during their delivery from the drill rig to the laboratory. The quality assurance procedures, data verification and assay protocols used in connection with drilling and sampling on the Jabal Sayid property conform to industry accepted quality control methods.
BARRICK YEAR-END 2021
127
MANAGEMENT’S DISCUSSION AND ANALYSIS

Glossary of Technical Terms
 
ALL-IN SUSTAINING COSTS: A non-GAAP measure of cost per ounce/pound for gold/copper. Refer to page 96 of this MD&A for further information and a reconciliation of the measure.
AUTOCLAVE: Oxidation process in which high temperatures and pressures are applied to convert refractory sulfide mineralization into amenable oxide ore.
BY-PRODUCT: A secondary metal or mineral product recovered in the milling process such as silver.
C1 CASH COSTS: A non-GAAP measure of cost per pound for copper. Refer to page 116 of this MD&A for further information and a reconciliation of the measure.
CONCENTRATE: A very fine, powder-like product containing the valuable ore mineral from which most of the waste mineral has been eliminated.
CONTAINED OUNCES: Represents ounces in the ground before loss of ounces not able to be recovered by the applicable metallurgical processing process.
DEVELOPMENT: Work carried out for the purpose of gaining access to an ore body. In an underground mine, this includes shaft sinking, crosscutting, drifting and raising. In an open-pit mine, development includes the removal of overburden (more commonly referred to as stripping in an open pit).
DILUTION: The effect of waste or low-grade ore which is unavoidably extracted and comingled with the ore mined thereby lowering the recovered grade from what was planned to be mined.
DORÉ: Unrefined gold and silver bullion bars usually consisting of approximately 90 percent precious metals that will be further refined to almost pure metal.
DRILLING:
Core: drilling with a hollow bit with a diamond cutting rim to produce a cylindrical core that is used for geological study and assays.
Reverse circulation: drilling that uses a rotating cutting bit within a double-walled drill pipe and produces rock chips rather than core. Air or water is circulated down to the bit between the inner and outer wall of the drill pipe. The chips are forced to the surface through the center of the drill pipe and are collected, examined and assayed.
In-fill: drilling closer spaced holes in between existing holes, used to provide greater geological detail and to help upgrade resource estimates to reserve estimates.
Step-out: drilling to intersect a mineralized horizon or structure along strike or down-dip.
EXPLORATION: Prospecting, sampling, mapping, drilling and other work involved in searching for minerals.
FREE CASH FLOW: A non-GAAP measure that reflects our ability to generate cash flow. Refer to page 95 of this MD&A for a definition.
GRADE: The amount of metal in each tonne of ore, expressed as grams per tonne (g/t) for precious metals and as a percentage for most other metals.
Cut-off grade: the minimum metal grade at which an ore body can be economically mined (used in the calculation of ore reserves).
Mill-head grade: metal content per tonne of ore going into a mill for processing.
Reserve grade: estimated metal content of an ore body, based on reserve calculations.
HEAP LEACHING: A process whereby gold/copper is extracted by “heaping” broken ore on sloping impermeable pads and continually applying to the heaps a weak cyanide solution/sulfuric acid which dissolves the contained gold/copper. The gold/copper-laden solution is then collected for gold/copper recovery.
HEAP LEACH PAD: A large impermeable foundation or pad used as a base for stacking ore for the purpose of heap leaching.
MILL: A processing facility where ore is finely ground and thereafter undergoes physical or chemical treatment to extract the valuable metals.
MINERAL RESERVE: See pages 129 to 137 – Summary Gold/Copper Mineral Reserves and Mineral Resources.
MINERAL RESOURCE: See pages 129 to 137 – Summary Gold/Copper Mineral Reserves and Mineral Resources.
OPEN PIT: A mine where the minerals are mined entirely from the surface.
ORE: Rock, generally containing metallic or non-metallic minerals, which can be mined and processed at a profit.
ORE BODY: A sufficiently large amount of ore that can be mined economically.
OUNCES: Troy ounce is a unit of measure used for weighing gold at 999.9 parts per thousand purity and is equivalent to 31.1035g.
RECLAMATION: The process by which lands disturbed as a result of mining activity are modified to support future beneficial land use. Reclamation activity may include the removal of buildings, equipment, machinery and other physical remnants of mining, closure of tailings storage facilities, leach pads and other mine features, and contouring, covering and re-vegetation of waste rock dumps and other disturbed areas.
RECOVERY RATE: A term used in process metallurgy to indicate the proportion of valuable material physically recovered in the processing of ore. It is generally stated as a percentage of the valuable material recovered compared to the total material originally contained in the ore.
REFINING: The final stage of metal production in which impurities are removed through heating to extract the pure metal.
ROASTING: The treatment of sulfide ore by heat and air, or oxygen enriched air, in order to oxidize sulfides and remove other elements (carbon, antimony or arsenic).
STRIPPING: Removal of overburden or waste rock overlying an ore body in preparation for mining by open-pit methods.
TAILINGS: The material that remains after all economically and technically recoverable precious metals have been removed from the ore during processing.
TOTAL CASH COSTS: A non-GAAP measure of cost per ounce for gold. Refer to page 96 of this MD&A for further information and a reconciliation of the measure.

BARRICK YEAR-END 2021
128
MANAGEMENT’S DISCUSSION AND ANALYSIS

Mineral Reserves and Mineral Resources

The tables on the next seven pages set forth Barrick’s interest in the total proven and probable gold, silver and copper reserves and in the total measured, indicated and inferred gold, silver and copper resources and certain related information at each property. For further details of proven and probable mineral reserves and measured, indicated and inferred mineral resources by category, metal and property, see pages 130 to 137 .
The Company has carefully prepared and verified the mineral reserve and mineral resource figures and believes that its method of estimating mineral reserves has been verified by mining experience. These figures are estimates, however, and no assurance can be given that the indicated quantities of metal will be produced. Metal price fluctuations may render mineral reserves containing relatively lower grades of mineralization uneconomic. Moreover, short-term operating factors relating to the mineral reserves, such as the need for orderly development of ore bodies or the processing of new or different ore grades, could affect the Company’s profitability in any particular accounting period.

Definitions
A mineral resource is a concentration or occurrence of diamonds, natural solid inorganic material, or natural solid fossilized organic material including base and precious metals, coal, and industrial minerals in or on the Earth’s crust in such form and quantity and of such a grade or quality that it has reasonable prospects for economic extraction. The location, quantity, grade, geological characteristics and continuity of a mineral resource are known, estimated or interpreted from specific geological evidence and knowledge. Mineral resources are sub-divided, in order of increasing geological confidence, into inferred, indicated and measured categories.
An inferred mineral resource is that part of a mineral resource for which quantity and grade or quality can be estimated on the basis of geological evidence and limited sampling and reasonably assumed, but not verified, geological and grade continuity. The estimate is based on limited information and sampling gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes.
An indicated mineral resource is that part of a mineral resource for which quantity, grade or quality, densities, shape and physical characteristics can be estimated with a level of confidence sufficient to allow the appropriate application of technical and economic
parameters, to support mine planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough for geological and grade continuity to be reasonably assumed.
A measured mineral resource is that part of a mineral resource for which quantity, grade or quality, densities, shape and physical characteristics are so well established that they can be estimated with confidence sufficient to allow the appropriate application of technical and economic parameters, to support production planning and evaluation of the economic viability of the deposit. The estimate is based on detailed and reliable exploration, sampling and testing information gathered through appropriate techniques from locations such as outcrops, trenches, pits, workings and drill holes that are spaced closely enough to confirm both geological and grade continuity.
Mineral resources, which are not mineral reserves, do not have demonstrated economic viability.
A mineral reserve is the economically mineable part of a measured or indicated mineral resource demonstrated by at least a preliminary feasibility study. This study must include adequate information on mining, processing, metallurgical, economic and other relevant factors that demonstrate, at the time of reporting, that economic extraction can be justified.
A mineral reserve includes diluting materials and allowances for losses that may occur when the material is mined. Mineral reserves are sub-divided in order of increasing confidence into probable mineral reserves and proven mineral reserves. A probable mineral reserve is the economically mineable part of an indicated and, in some circumstances, a measured mineral resource demonstrated by at least a preliminary feasibility study. This study must include adequate information on mining, processing, metallurgical, economic and other relevant factors that demonstrate, at the time of reporting, that economic extraction can be justified.
A proven mineral reserve is the economically mineable part of a measured mineral resource demonstrated by at least a preliminary feasibility study. This study must include adequate information on mining, processing, metallurgical, economic and other relevant factors that demonstrate, at the time of reporting, that economic extraction is justified.


BARRICK YEAR-END 2021
129
RESERVES AND RESOURCES


Gold Mineral Reserves1,2,3
As at December 31, 2021 PROVEN PROBABLE TOTAL
Tonnes Grade Contained ozs Tonnes Grade Contained ozs Tonnes Grade Contained ozs
Based on attributable ounces (Mt) (g/t) (Moz) (Mt) (g/t) (Moz) (Mt) (g/t) (Moz)
AFRICA AND MIDDLE EAST
Bulyanhulu surface 0.00010 10.42 0.000035 0.00010 10.42 0.000035
Bulyanhulu underground 10 7.76 2.5 10 7.76 2.5
Bulyanhulu (84.00%) total 10 7.76 2.5 10 7.76 2.5
Jabal Sayid surface 0.072 0.34 0.00079 0.072 0.34 0.00079
Jabal Sayid underground 6.3 0.19 0.039 6.7 0.33 0.071 13  0.26 0.11
Jabal Sayid (50.00%) total 6.4 0.19 0.040 6.7 0.33 0.071 13 0.26 0.11
Kibali surface 5.0 2.31 0.37 12 2.51 0.95 17 2.45 1.3
Kibali underground 9.4 4.54 1.4 11 4.54 1.6 21 4.54 3.0
Kibali (45.00%) total 14 3.76 1.7 23 3.50 2.6 37 3.60 4.3
Loulo-Gounkoto surface 9.6 2.62 0.81 12 3.26 1.3 22 2.98 2.1
Loulo-Gounkoto underground 8.4 4.45 1.2 21 5.03 3.4 29 4.86 4.6
Loulo-Gounkoto (80.00%) total 18 3.48 2.0 33 4.38 4.7 51 4.06 6.7
North Mara surface 0.66 1.73 0.037 37 1.73 2.1 38 1.73 2.1
North Mara underground 0.90 5.56 0.16 5.9 3.12 0.59 6.8 3.44 0.75
North Mara (84.00%) total 1.6 3.93 0.20 43 1.92 2.6 44 1.99 2.8
Tongon surface (89.70%) 2.0 1.51 0.095 5.9 1.99 0.38 7.9 1.87 0.47
AFRICA AND MIDDLE EAST TOTAL 42 3.00 4.1 120 3.29 13 160 3.22 17
LATIN AMERICA AND ASIA PACIFIC
Norte Abierto surface (50.00%) 110 0.65 2.4 480 0.59 9.2 600 0.60 12
Porgera surface4
4.8 3.66 0.56 4.8 3.66 0.56
Porgera underground4
0.58 6.79 0.13 2.6 6.25 0.53 3.2 6.34 0.66
 Porgera (24.50%) total4
0.58 6.79 0.13 7.4 4.59 1.1 8.0 4.75 1.2
Pueblo Viejo surface (60.00%) 7.5 2.20 0.53 68 2.22 4.9 76 2.22 5.4
Veladero surface (50.00%) 9.8 0.41 0.13 80 0.82 2.1 90 0.77 2.2
LATIN AMERICA AND ASIA PACIFIC TOTAL 130 0.74 3.2 640 0.84 17 770 0.83 21
NORTH AMERICA
Carlin surface 11 2.58 0.95 73 2.18 5.1 84 2.23 6.0
Carlin underground 12 9.25 3.6 7.0 8.18 1.8 19 8.86 5.4
Carlin (61.50%) total5
24 6.01 4.5 80 2.70 6.9 100 3.46 11
Cortez surface 1.4 2.13 0.095 37 1.66 2.0 39 1.68 2.1
Cortez underground6
0.78 8.57 0.21 26 7.77 6.5 27 7.79 6.7
Cortez (61.50%) total 2.2 4.43 0.31 63 4.16 8.5 65 4.17 8.8
Hemlo surface 0.018 0.32 0.00018 0.018 0.32 0.00018
Hemlo underground 0.34 5.02 0.055 6.1 5.19 1.0 6.4 5.18 1.1
Hemlo (100%) total 0.36 4.79 0.055 6.1 5.19 1.0 6.4 5.16 1.1
Long Canyon surface (61.50%) 0.21 1.43 0.0097 0.40 1.06 0.013 0.61 1.18 0.023
Phoenix surface (61.50%) 8.3 0.72 0.19 96 0.59 1.8 100 0.60 2.0
Turquoise Ridge surface 18 2.13 1.2 8.3 1.90 0.51 26 2.05 1.7
Turquoise Ridge underground 8.8 11.05 3.1 12 9.89 3.7 21 10.39 6.9
Turquoise Ridge (61.50%) total 26 5.09 4.3 20 6.59 4.3 46 5.74 8.6
NORTH AMERICA TOTAL
61 4.81 9.4 270 2.64 23 330 3.04 32
TOTAL
240 2.20 17 1,000 1.60 53 1,300 1.71 69
See “Mineral Reserves and Resources Endnotes”.
BARRICK YEAR-END 2021
130
RESERVES AND RESOURCES


Copper Mineral Reserves1,2,3,7
As at December 31, 2021 PROVEN PROBABLE TOTAL
Tonnes Cu Grade Contained Cu Tonnes Cu Grade Contained Cu Tonnes Cu Grade Contained Cu
Based on attributable pounds (Mt) (%) (Mlb) (Mt) (%) (Mlb) (Mt) (%) (Mlb)
AFRICA AND MIDDLE EAST
Bulyanhulu surface —  —  —  0.00010 0.61 0.0014 0.00010 0.61 0.0014
Bulyanhulu underground —  —  —  10 0.37 82 10 0.37 82
Bulyanhulu (84.00%) total —  —  —  10 0.37 82 10 0.37 82
Jabal Sayid surface 0.072 3.06 4.9 —  —  —  0.072 3.06 4.9
Jabal Sayid underground 6.3 2.30 320 6.7 2.24 330 13 2.27 650
Jabal Sayid (50.00%) total 6.4 2.31 330 6.7 2.24 330 13 2.27 650
Lumwana surface (100%) 68 0.51 770 410 0.58 5,200 470 0.57 6,000
AFRICA AND MIDDLE EAST TOTAL
75 0.67 1,100 420 0.60 5,600 500 0.61 6,700
LATIN AMERICA AND ASIA PACIFIC
Norte Abierto surface (50.00%) 110 0.19 480 480 0.23 2,400 600 0.22 2,900
Zaldívar surface (50.00%) 180 0.45 1800 42 0.34 320 230 0.43 2,100
LATIN AMERICA AND ASIA PACIFIC TOTAL
300 0.35 2,300 530 0.24 2,700 820 0.28 5,000
NORTH AMERICA
Phoenix surface (61.50%) 11 0.17 40 130 0.17 470 140 0.17 510
NORTH AMERICA TOTAL
11 0.17 40 130 0.17 470 140 0.17 510
TOTAL
380 0.41 3,400 1,100 0.37 8,800 1,500 0.38 12,000
See “Mineral Reserves and Resources Endnotes”.
Silver Mineral Reserves1,2,3,7
As at December 31, 2021 PROVEN PROBABLE TOTAL
Tonnes Ag Grade Contained Ag Tonnes Ag Grade Contained Ag Tonnes Ag Grade Contained Ag
Based on attributable ounces (Mt) (g/t) (Moz) (Mt) (g/t) (Moz) (Mt) (g/t) (Moz)
AFRICA AND MIDDLE EAST
Bulyanhulu surface —  —  —  0.00010 4.32 0.000014 0.00010 4.32 0.000014
Bulyanhulu underground —  —  —  10 6.92 2.3 10 6.92 2.3
Bulyanhulu (84.00%) total —  —  —  10 6.92 2.3 10 6.92 2.3
AFRICA AND MIDDLE EAST TOTAL
—  —  —  10 6.92 2.3 10 6.92 2.3
LATIN AMERICA AND ASIA PACIFIC
Norte Abierto surface (50.00%) 110 1.91 7.0 480 1.43 22 600 1.52 29
Pueblo Viejo surface (60.00%) 7.5 11.18 2.7 68 14.85 33 76 14.49 35
Veladero surface (50.00%) 9.8 12.41 3.9 80 14.78 38 90 14.52 42
LATIN AMERICA AND ASIA PACIFIC TOTAL
130 3.21 14 630 4.58 93 760 4.34 110
NORTH AMERICA
Phoenix surface (61.50%) 8.3 7.40 2.0 96 6.35 20 100 6.43 22
NORTH AMERICA TOTAL
8.3 7.40 2.0 96 6.35 20 100 6.43 22
TOTAL
140 3.46 16 740 4.84 120 880 4.62 130
See “Mineral Reserves and Resources Endnotes”.

BARRICK YEAR-END 2021
131
RESERVES AND RESOURCES


Gold Mineral Resources1,2,3,8,9
As at December 31, 2021
MEASURED (M)10
INDICATED (I)10
(M) + (I)10
INFERRED 11
Tonnes Grade Contained ozs Tonnes Grade Contained ozs Contained ozs Tonnes Grade Contained ozs
Based on attributable ounces (Mt) (g/t) (Moz) (Mt) (g/t) (Moz) (Moz) (Mt) (g/t) (Moz)
AFRICA AND MIDDLE EAST
Bulyanhulu surface —  —  —  0.00010 10.42 0.000035 0.000035 —  —  — 
Bulyanhulu underground —  —  —  17 8.92 4.8 4.8 24 8.0 6.2
Bulyanhulu (84.00%) total —  —  —  17 8.92 4.8 4.8 24 8.0 6.2
Jabal Sayid surface 0.072 0.34 0.00079 —  —  —  0.00079 —  —  — 
Jabal Sayid underground 6.8 0.22 0.049 7.9 0.37 0.092 0.14 1.3 0.6 0.022
Jabal Sayid (50.00%) total 6.9 0.23 0.050 7.9 0.37 0.092 0.14 1.3 0.6 0.022
Kibali surface 7.1 2.26 0.52 20 2.25 1.5 2.0 3.7 2.1 0.25
Kibali underground 14 4.63 2.1 22 4.06 2.8 5.0 6.6 3.0 0.64
Kibali (45.00%) total 21 3.84 2.6 42 3.18 4.3 6.9 10 2.7 0.89
Loulo-Gounkoto surface 9.5 2.57 0.79 14 3.31 1.5 2.3 3.2 2.1 0.22
Loulo-Gounkoto underground 16 4.57 2.3 30 4.94 4.8 7.1 8.3 3.1 0.82
Loulo-Gounkoto (80.00%) total 25 3.82 3.1 44 4.42 6.2 9.3 12 2.8 1.0
North Mara surface 13 2.54 1.0 40 1.41 1.8 2.8 5.0 1.1 0.18
North Mara underground 0.64 3.56 0.073 18 2.04 1.2 1.3 7.8 1.8 0.46
North Mara (84.00%) total 13 2.59 1.1 58 1.61 3.0 4.1 13 1.6 0.65
Tongon surface (89.70%) 2.8 1.79 0.16 7.8 2.21 0.55 0.71 3.5 2.7 0.30
AFRICA AND MIDDLE EAST TOTAL
70 3.15 7.1 180 3.34 19 26 64 4.5 9.1
LATIN AMERICA AND ASIA PACIFIC
Alturas surface (100%) —  —  —  —  —  —  —  260 1.1 8.9
Norte Abierto surface (50.00%) 190 0.63 3.9 1,100 0.53 19 22 370 0.4 4.4
Pascua Lama surface (100%) 43 1.86 2.6 390 1.49 19 21 15 1.7 0.86
Porgera surface4
—  —  —  10 3.21 1.0 1.0 3.9 2.5 0.31
Porgera underground4
0.64 6.66 0.14 4.2 6.20 0.84 0.98 1.3 6.5 0.28
Porgera (24.50%) total4
0.64 6.66 0.14 14 4.09 1.9 2.0 5.3 3.5 0.59
Pueblo Viejo surface (60.00%) 63 2.03 4.1 150 2.04 10 14 38 1.7 2.1
Veladero surface (50.00%) 11 0.39 0.14 130 0.71 2.9 3.0 18 0.7 0.39
LATIN AMERICA AND ASIA PACIFIC TOTAL12
310 1.09 11 1,800 0.92 52 63 710 0.8 17
See “Mineral Reserves and Resources Endnotes”.
BARRICK YEAR-END 2021
132
RESERVES AND RESOURCES


Gold Mineral Resources1,2,3,8,9
As at December 31, 2021
MEASURED (M)10
INDICATED (I)10
(M) + (I)10
INFERRED 11
Tonnes Grade Contained ozs Tonnes Grade Contained ozs Contained ozs Tonnes Grade Contained ozs
Based on attributable ounces (Mt) (g/t) (Moz) (Mt) (g/t) (Moz) (Moz) (Mt) (g/t) (Moz)
NORTH AMERICA
Carlin surface 28 2.33 2.1 150 1.82 9.0 11 58 1.2 2.2
Carlin underground 23 7.53 5.6 12 6.97 2.7 8.4 10.0 7.5 2.4
Carlin (61.50%) total5
51 4.68 7.8 170 2.20 12 19 68 2.1 4.6
Cortez surface 1.4 2.12 0.096 92 1.07 3.2 3.3 62 0.5 1.1
Cortez underground6
1.2 8.06 0.32 32 7.40 7.7 8.0 15 5.9 2.8
Cortez (61.50%) total 2.6 4.88 0.41 120 2.71 11 11 76 1.6 3.9
Donlin surface (50.00%) 3.9 2.52 0.31 270 2.24 19 20 46 2.0 3.0
Fourmile underground (100%) —  —  —  1.00 10.90 0.35 0.35 6.4 10.6 2.2
Hemlo surface 0.024 0.48 0.00037 27 0.90 0.78 0.78 5.4 0.9 0.15
Hemlo underground 0.66 4.64 0.098 11 4.73 1.7 1.8 3.7 5.6 0.67
Hemlo (100%) total 0.68 4.50 0.099 38 2.03 2.5 2.6 9.1 2.8 0.82
Long Canyon surface 0.54 2.66 0.046 5.3 2.45 0.42 0.47 1.1 0.8 0.029
Long Canyon underground —  —  —  1.1 10.68 0.38 0.38 0.53 9.1 0.16
Long Canyon (61.50%) total 0.54 2.66 0.046 6.5 3.87 0.80 0.85 1.6 3.6 0.19
Phoenix surface (61.50%) 13 0.65 0.27 230 0.51 3.7 4.0 30 0.4 0.36
Turquoise Ridge surface 25 2.12 1.7 23 2.00 1.5 3.2 10 1.8 0.60
Turquoise Ridge underground 11 10.28 3.5 18 8.84 5.2 8.7 0.68 6.2 0.14
Turquoise Ridge (61.50%) total 36 4.57 5.3 41 5.05 6.6 12 11 2.0 0.74
NORTH AMERICA TOTAL
110 4.08 14 870 1.99 56 70 250 2.0 16
TOTAL
490 2.05 32 2,800 1.40 130 160 1,000 1.3 42
See “Mineral Reserves and Resources Endnotes”.
BARRICK YEAR-END 2021
133
RESERVES AND RESOURCES


Copper Mineral Resources1,3,7,8,9
As at December 31, 2021
MEASURED (M)10
INDICATED (I)10
(M) + (I)10
INFERRED 11
Tonnes Grade Contained lbs Tonnes Grade Contained lbs Contained lbs Tonnes Grade Contained lbs
Based on attributable pounds (Mt) (%) (Mlb) (Mt) (%) (Mlb) (Mlb) (Mt) (%) (Mlb)
AFRICA AND MIDDLE EAST
Bulyanhulu surface —  —  —  0.00010 0.61 0.0014 0.0014 —  —  — 
Bulyanhulu underground —  —  —  17 0.41 150 150 24 0.4 200
Bulyanhulu (84.00%) total —  —  —  17 0.41 150 150 24 0.4 200
Jabal Sayid surface 0.072 3.06 4.9 —  —  —  4.9 —  —  — 
Jabal Sayid underground 6.8 2.60 390 7.9 2.22 380 770 1.3 1.4 38
Jabal Sayid (50.00%) total 6.9 2.60 390 7.9 2.22 380 780 1.3 1.4 38
Lumwana surface (100%) 93 0.51 1,000 880 0.54 10,000 11,000 7.6 0.6 93
AFRICA AND MIDDLE EAST TOTAL
99 0.65 1,400 910 0.55 11,000 12,000 33 0.4 330
LATIN AMERICA AND ASIA PACIFIC
Norte Abierto surface (50.00%) 170 0.21 790 1,000 0.21 4,700 5,500 360 0.2 1,400
Zaldívar surface (50.00%) 390 0.40 3,400 240 0.36 1,900 5,300 26 0.3 190
LATIN AMERICA AND ASIA PACIFIC TOTAL 560 0.34 4,200 1,300 0.24 6,600 11,000 390 0.2 1,600
NORTH AMERICA
Phoenix surface (61.50%) 16 0.16 55 310 0.15 1,000 1,100 32 0.1 90
NORTH AMERICA TOTAL
16 0.16 55 310 0.15 1,000 1,100 32 0.1 90
TOTAL
680 0.38 5,700 2,500 0.34 19,000 24,000 450 0.2 2,100
See “Mineral Reserves and Resources Endnotes”.
BARRICK YEAR-END 2021
134
RESERVES AND RESOURCES


Silver Mineral Resources1,3,7,8,9
As at December 31, 2021
MEASURED (M)10
INDICATED (I)10
(M) + (I)10
INFERRED 11
Tonnes Ag Grade Contained Ag Tonnes Ag Grade Contained Ag Contained Ag Tonnes Ag Grade Contained Ag
Based on attributable ounces (Mt) (g/t) (Moz) (Mt) (g/t) (Moz) (Moz) (Mt) (g/t) (Moz)
AFRICA AND MIDDLE EAST
Bulyanhulu surface —  —  —  0.00010 4.32 0.000014 0.000014 —  —  — 
Bulyanhulu underground —  —  —  17 7.31 3.9 3.9 24 6.3 4.9
Bulyanhulu (84.00%) total —  —  —  17 7.31 3.9 3.9 24 6.3 4.9
AFRICA AND MIDDLE EAST TOTAL
—  —  —  17 7.31 3.9 3.9 24 6.3 4.9
LATIN AMERICA AND ASIA PACIFIC
Norte Abierto surface (50.00%) 190 1.62 10 1,100 1.23 43 53 370 1.0 11
Pascua-Lama surface (100%) 43 57.21 79 390 52.22 660 740 15 17.8 8.8
Pueblo Viejo surface (60.00%) 63 11.47 23 150 12.63 63 86 38 9.0 11
Veladero surface (50.00%) 11 11.35 4.0 130 14.19 58 62 18 13.8 8.1
LATIN AMERICA AND ASIA PACIFIC TOTAL 310 11.68 120 1,800  14.56 820 940 440 2.8 39
NORTH AMERICA
Phoenix surface (61.50%) 13 6.74 2.8 230  5.88 43 46 30 5.6 5.4
NORTH AMERICA TOTAL
13 6.74 2.8 230 5.88 43 46 30 5.6 5.4
TOTAL
320 11.48 120 2,000 13.50 870 990 500 3.1 50
See “Mineral Reserves and Resources Endnotes”.


BARRICK YEAR-END 2021
135
RESERVES AND RESOURCES


Summary Gold Mineral Reserves1,2,3
For the years ended December 31 2021 2020
Ownership Tonnes Grade Ounces Ownership Tonnes Grade Ounces
Based on attributable ounces % (Mt) (g/t) (Moz) % (Mt) (g/t) (Moz)
AFRICA AND MIDDLE EAST
Bulyanhulu surface 84.00% 0.00010 10.42 0.000035 84.00% —  — 
Bulyanhulu underground 84.00% 10  7.76 2.5  84.00% 6.9  8.92 2.0 
Bulyanhulu Total 84.00% 10  7.76 2.5  84.00% 6.9  8.92 2.0 
Buzwagi surface 84.00% —  —  84.00% 1.7  0.76 0.042 
Jabal Sayid surface 50.00% 0.072 0.34 0.00079 50.00% —  — 
Jabal Sayid underground 50.00% 13 0.26 0.11 50.00% —  — 
Jabal Sayid Total 50.00% 13 0.26 0.11 50.00% 12  0.23 0.090 
Kibali surface 45.00% 17 2.45 1.3 45.00% 14  2.47 1.1 
Kibali underground 45.00% 21 4.54 3.0 45.00% 20  4.81 3.1 
Kibali Total
45.00% 37 3.60 4.3 45.00% 34  3.84 4.2 
Loulo-Gounkoto surface
80.00% 22 2.98 2.1 80.00% 17  3.21 1.7 
Loulo-Gounkoto underground 80.00% 29 4.86 4.6 80.00% 31  4.93 5.0 
Loulo-Gounkoto Total 80.00% 51 4.06 6.7 80.00% 48  4.33 6.7 
North Mara surface 84.00% 38 1.73 2.1 84.00% 18  1.44 0.85 
North Mara underground 84.00% 6.8 3.44 0.75 84.00% 7.3  5.01 1.2 
North Mara Total 84.00% 44 1.99 2.8 84.00% 26  2.46 2.0 
Tongon surface 89.70% 7.9 1.87 0.47 89.70% 9.3  1.92 0.57 
AFRICA AND MIDDLE EAST TOTAL
160 3.22 17 140  3.52 16 
LATIN AMERICA AND ASIA PACIFIC
Norte Abierto surface 50.00% 600 0.60 12 50.00% 600  0.60  12
Porgera surface4
24.50% 4.8 3.66 0.56 47.50% 9.2  3.66  1.1
Porgera underground4
24.50% 3.2 6.34 0.66 47.50% 6.3  6.34  1.3
Porgera Total4
24.50% 8.0 4.75 1.2 47.50% 15  4.75  2.4
Pueblo Viejo surface 60.00% 76 2.22 5.4 60.00% 83  2.31  6.2
Veladero surface 50.00% 90 0.77 2.2 50.00% 110  0.75  2.6
LATIN AMERICA AND ASIA PACIFIC TOTAL
770 0.83 21 810  0.88  23
NORTH AMERICA
Carlin surface 61.50% 84 2.23 6.0 61.50% 91  2.21  6.5
Carlin underground 61.50% 19 8.86 5.4 61.50% 19  9.17  5.6
Carlin Total5
61.50% 100 3.46 11 61.50% 110  3.42  12
Cortez surface 61.50% 39 1.68 2.1 61.50% 52  1.52  2.6
Cortez underground6
61.50% 27 7.79 6.7 61.50% 11  9.38  3.4
Cortez Total 61.50% 65 4.17 8.8 61.50% 64  2.92  6.0
Hemlo surface 100% 0.018 0.32 0.00018 100% 0.57  0.77  0.014
Hemlo underground 100% 6.4 5.18 1.1 100% 9.0  5.08  1.5
Hemlo Total 100% 6.4 5.16 1.1 100% 9.6  4.82  1.5
Long Canyon surface 61.50% 0.61 1.18 0.023 61.50% 3.1  2.21  0.22
Phoenix surface 61.50% 100  0.60  2.0  61.50% 95  0.58  1.8
Turquoise Ridge surface 61.50% 26 2.05 1.7 61.50% 26  2.03  1.7
Turquoise Ridge underground 61.50% 21 10.39 6.9 61.50% 17  10.92  6.0
Turquoise Ridge Total 61.50% 46 5.74 8.6 61.50% 43  5.58  7.7
NORTH AMERICA TOTAL
330 3.04 32 320  2.80  29
TOTAL
1,300 1.71 69 1,300  1.66  68
See “Mineral Reserves and Resources Endnotes”.

BARRICK YEAR-END 2021
136
RESERVES AND RESOURCES


Mineral Reserves and Resources Endnotes
1.Mineral reserves (“reserves”) and mineral resources (“resources”) have been estimated as at December 31, 2021 (unless otherwise noted) in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects (“NI 43-101”) as required by Canadian securities regulatory authorities. For United States reporting purposes, the SEC has adopted amendments to its disclosure rules to modernize the mineral property disclosure requirements for issuers whose securities are registered with the SEC under the Securities and Exchange Act of 1934, as amended (the “Exchange Act”). These amendments became effective February 25, 2019 (the “SEC Modernization Rules”) with compliance required for the first fiscal year beginning on or after January 1, 2021. The SEC Modernization Rules replace the historical property disclosure requirements for mining registrants that were included in SEC Industry Guide 7, which will be rescinded from and after the required compliance date of the SEC Modernization Rules. As a result of the adoption of the SEC Modernization Rules, the SEC now recognizes estimates of “measured”, “indicated” and “inferred” mineral resources. In addition, the SEC has amended its definitions of “proven mineral reserves” and “probable mineral reserves” to be substantially similar to the corresponding Canadian Institute of Mining, Metallurgy and Petroleum definitions, as required by NI 43-101. U.S. investors should understand that “inferred” mineral resources have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. In addition, U.S. investors are cautioned not to assume that any part or all of Barrick’s mineral resources constitute or will be converted into reserves. Mineral resource and mineral reserve estimations have been prepared by employees of Barrick, its joint venture partners or its joint venture operating companies, as applicable, under the supervision of regional Mineral Resource Managers Simon Bottoms, Africa & Middle East Mineral Resource Manager and Chad Yuhasz, Latin America & Australia Pacific Mineral Resource Manager, Craig Fiddes, North America Resource Modeling Manager and reviewed by Rodney Quick, Barrick’s Mineral Resource Management and Evaluation Executive. Reserves have been estimated based on an assumed gold price of US$1,200 per ounce, an assumed silver price of US$16.50 per ounce, and an assumed copper price of US$2.75 per pound and long-term average exchange rates of 1.30 CAD/US$, except at Zaldívar, where mineral reserves for 2020 and 2021 were calculating using Antofagasta guidance and an assumed copper price of US$3.10 per pound. Reserve estimates incorporate current and/or expected mine plans and cost levels at each property. Varying cut-off grades have been used depending on the mine and type of ore contained in the reserves. Barrick’s normal data verification procedures have been employed in connection with the calculations. Verification procedures include industry-standard quality control practices. Resources as at December 31, 2021 have been estimated using varying cut-off grades, depending on both the type of mine or project, its maturity and ore types at each property.
2.In confirming our annual reserves for each of our mineral properties, projects, and operations, we conduct a reserve test on December 31 of each year to verify that the future undiscounted cash flow from reserves is positive. The cash flow ignores all sunk costs and only considers future operating and closure expenses as well as any future capital costs.
3.All mineral resource and mineral reserve estimates of tonnes, Au oz, Ag oz and Cu lb are reported to the second significant digit.
4.Porgera mineral reserves and mineral resources are reported on a 24.5% interest basis, reflecting Barrick’s expected ownership interest following the implementation of the binding Commencement Agreement entered into by Barrick Niugini Limited (“BNL”), its affiliate Porgera (Jersey) Limited, the Government of Papua New Guinea (“PNG”), Kumul Minerals Holdings Limited, a state-owned mining company, and Mineral Resources Enga Limited, effective February 3, 2022. The Commencement Agreement replaced the Framework Agreement signed in April 2021 and provides, among other things, for ownership of Porgera to be held in a new joint venture owned 51% by PNG stakeholders and 49% by BNL or an affiliate. BNL is jointly owned on a 50/50 basis by Barrick and Zijin Mining Group and will retain operatorship of the mine under the terms of the Commencement Agreement. Efforts are ongoing to execute definitive agreements to implement the Commencement Agreement and finalize a timeline for the reopening of the Porgera mine and resumption of full mine operations. For additional information, see page 37 of Barrick’s Fourth Quarter and Year End Report 2021.
5.On October 14, 2021, NGM acquired the 40% interest in South Arturo that NGM did not already own from i-80 Gold Corp. Accordingly, Carlin mineral reserve and resource estimates include South Arturo on a 36.9% basis as at December 31, 2020, and on a 61.5% basis as at December 31, 2021. For additional information, see page 37 of Barrick’s Fourth Quarter and Year End Report 2021.
6.Cortez underground includes 20 million tonnes at 7.29 g/t for 4.8 million ounces of probable reserves, 23 million tonnes at 7.07 g/t for 5.2 million ounces of indicated resources and 14 million tonnes at 6.0 g/t for 2.8 million ounces of inferred resources related to Goldrush. As noted in endnote #9, mineral resources are reported on an inclusive basis.
7.2021 polymetallic mineral resources and mineral reserves are estimated using the combined value of gold, copper & silver and accordingly are reported as gold, copper and silver mineral resources and mineral reserves.
8.Mineral resources which are not mineral reserves do not have demonstrated economic viability.
9.Mineral resources are reported inclusive of mineral reserves.
10.All measured and indicated mineral resource estimates of grade and all proven and probable mineral reserve estimates of grade for Au g/t, Ag g/t and Cu % are reported to two decimal places.
11.All inferred mineral resource estimates of grade for Au g/t, Ag g/t and Cu % are reported to one decimal place.
12.On June 1, 2021, Barrick sold its 100% interest in the Lagunas Norte gold mine to Boroo Pte Ltd. For additional information, see page 37 of Barrick’s Fourth Quarter and Year End Report 2021.
BARRICK YEAR-END 2021
137
RESERVES AND RESOURCES