We have financial commitments and obligations that arise in the ordinary course of our business. These include lease obligations, long-term debt, capital additions, purchase commitments for goods and services, and legal proceedings, all of which are discussed in Note 3, Leases; Note 10, Debt; and Note 19, Commitments, Guarantees, Indemnifications, and Legal Proceedings, of the Notes to Consolidated Financial Statements in "Part II, Item 8. Financial Statements and Supplementary Data" of our 2023 Annual Report on Form 10-K.

Guarantees and Indemnifications

We provide guarantees, indemnifications, and other assurances to third parties in the normal course of our business. These include tort indemnifications, environmental assurances, and representations and warranties in commercial agreements. At March 31, 2024, we are not aware of any material liabilities arising from any guarantee, indemnification, or financial assurance we have provided. If we determined such a liability was probable and subject to reasonable determination, we would accrue for it at that time.

DeRidder Mill Incident

On February 8, 2017, a tank located in the pulp mill at the Company's DeRidder, Louisiana facility exploded, resulting in three contractor fatalities and other injuries. The Company was served with multiple lawsuits involving the decedents and other allegedly injured parties, alleging negligence on the part of the Company and claiming compensatory and punitive damages. The Company believes that these suits are covered by its liability insurance policies, subject to an aggregate $1.0 million deductible. The majority of these lawsuits were settled by the Company and its insurers. The Company has not paid any losses in excess of its insurance deductible in connection with these settlements, and its insurance deductible has been satisfied in full. To date, all settlements in excess of the deductible have been paid out by one of the Company’s insurers. The Company is vigorously defending the remaining lawsuit, which involves nine plaintiffs and was tried in the U.S. District Court for the Middle District of Louisiana in April 2024. On April 24, 2024, a jury awarded these plaintiffs approximately $91.8 million in compensatory damages. The verdict is subject to prejudgment interest. The amount of the verdict with interest is within the remaining limits of the Company's liability insurance policies. The matter is in the post-trial stage, and the Company intends to appeal the decision. While the Company cannot predict the outcome of the appeal and the ultimate outcome of this matter, the Company believes that it has sufficient insurance to cover the verdict and prejudgment interest. At March 31, 2024, the Company recorded an accrual of $123.7 million including the compensatory damages as well as interest of $31.9 million in “Accrued liabilities” in the Consolidated Balance Sheets. Additionally, a receivable of $123.7 million for the insurance recovery was recorded in “Prepaids and other current assets” in the Consolidated Balance Sheets.

In May 2017, the EPA conducted an on-site inspection of the DeRidder facility to assess compliance with the Clean Air Act, Risk Management Program (“RMP”). The Company provided additional information to the EPA promptly after the inspection to address certain areas of concern (“AOCs”) observed during the inspection. Since the inspection in 2017, PCA performed several voluntary activities to address the AOCs presented in the EPA's inspection report and has removed the RMP covered process from the facility. In January 2021, the EPA and U.S. Department of Justice (“DOJ”) initiated civil judicial enforcement discussions with PCA. During the third quarter of 2022, we reached a settlement with the agencies, resulting in an agreed civil penalty of $2.5 million. The Company did not admit liability for violation of the Clean Air Act in connection with the settlement. The settlement was approved by the federal district court for the Western District of Louisiana in December 2022, and the agreed civil penalty was paid out in January 2023.

Legal Proceedings

We are also a party to various legal actions arising in the ordinary course of our business. These legal actions include commercial liability claims, premises liability claims, and employment-related claims, among others. As of the date of this filing, we believe it is not reasonably possible that any of the legal actions against us will, either individually or in the aggregate, have a material adverse effect on our financial condition, results of operations, or cash flows.