Commitments and Contingencies
6 Months Ended
Jun. 30, 2022
Loss Contingencies [Line Items]  
Commitments and Contingencies Commitments and Contingencies
Construction Commitments

During the six-month period ended June 30, 2022, PacifiCorp entered into a procurement and construction services agreement for $849 million through 2024 for the construction of a key Energy Gateway Transmission segment extending between the Aeolus substation near Medicine Bow, Wyoming and the Clover substation near Mona, Utah.

Fuel Contracts

During the six-month period ended June 30, 2022, PacifiCorp entered into certain coal supply and transportation agreements totaling approximately $200 million through 2024.

Legal Matters

The Company is party to a variety of legal actions arising out of the normal course of business. Plaintiffs occasionally seek punitive or exemplary damages. The Company does not believe that such normal and routine litigation will have a material impact on its consolidated financial results. The Company is also involved in other kinds of legal actions, some of which assert or may assert claims or seek to impose fines, penalties and other costs in substantial amounts and are described below.
    
2020 Wildfires

In September 2020, a severe weather event resulting in high winds, low humidity and warm temperatures contributed to several major wildfires, real and personal property and natural resource damage, personal injuries and loss of life and widespread power outages in Oregon and Northern California. The wildfires spread across certain parts of PacifiCorp's service territory and surrounding areas across multiple counties in Oregon and California, including Siskiyou County, California; Jackson County, Oregon; Douglas County, Oregon; Marion County, Oregon; Lincoln County, Oregon; and Klamath County, Oregon burning over 500,000 acres in aggregate. Third party reports for these wildfires indicate over 2,000 structures destroyed, including residences; several structures damaged; multiple individuals injured; and several fatalities. Fire suppression costs estimated by various agencies total approximately $150 million. Investigations into the cause and origin of each wildfire are complex and ongoing and being conducted by various entities, including the United States Forest Service, the California Public Utilities Commission, the Oregon Department of Forestry, the Oregon Department of Justice, PacifiCorp and various experts engaged by PacifiCorp.

Multiple lawsuits have been filed in Oregon and California, including a putative class action complaint in Oregon, on behalf of citizens and businesses who suffered damages from fires allegedly caused by PacifiCorp. Additionally, several insurance carriers have filed subrogation complaints in Oregon and California with allegations similar to those made in the aforementioned lawsuits. The final determinations of liability, however, will only be made following comprehensive investigations and litigation processes.

In California, under inverse condemnation, courts have held that investor-owned utilities can be liable for real and personal property damages without the utility being found negligent and regardless of fault. California law also permits inverse condemnation plaintiffs to recover reasonable attorney fees and costs. In both Oregon and California, PacifiCorp has equipment in areas accessed through special use permits, easements or similar agreements that may contain provisions requiring it to pay for damages caused by its equipment regardless of fault. Even if inverse condemnation or other provisions do not apply, PacifiCorp could nevertheless be found liable for all damages proximately caused by negligence, including real and personal property and natural resource damage; fire suppression costs; personal injury and loss of life damages; and interest.
During the three-month period ended June 30, 2022, PacifiCorp accrued $64 million of losses net of expected insurance recoveries associated with the 2020 Wildfires resulting in an overall loss accrual net of expected insurance recoveries of $200 million as of June 30, 2022 compared to $136 million as of December 31, 2021. These accruals include PacifiCorp's estimate of losses for fire suppression costs, real and personal property damages, natural resource damages and noneconomic damages such as personal injury damages and loss of life damages that are considered probable of being incurred and that it is reasonably able to estimate at this time. For certain aspects of the 2020 Wildfires for which loss is considered probable, information necessary to reasonably estimate the potential losses, such as those related to natural resource damages, is not currently available. It is reasonably possible that PacifiCorp will incur additional losses beyond the amounts accrued; however, PacifiCorp is currently unable to estimate the range of possible additional losses that could be incurred due to the number of properties and parties involved and the variation in those types of properties and lack of available details. To the extent losses beyond the amounts accrued are incurred, additional insurance coverage is expected to be available to cover at least a portion of the losses. PacifiCorp's receivable for expected insurance recoveries was $277 million as of June 30, 2022.

Environmental Laws and Regulations

The Company is subject to federal, state, local and foreign laws and regulations regarding climate change, renewable portfolio standards, air and water quality, emissions performance standards, coal combustion byproduct disposal, hazardous and solid waste disposal, protected species and other environmental matters that have the potential to impact the Company's current and future operations. The Company believes it is in material compliance with all applicable laws and regulations.

Hydroelectric Relicensing

PacifiCorp is a party to the 2016 amended Klamath Hydroelectric Settlement Agreement ("KHSA"), which is intended to resolve disputes surrounding PacifiCorp's efforts to relicense the Klamath Hydroelectric Project. The KHSA establishes a process for PacifiCorp, the states of Oregon and California ("States") and other stakeholders to assess whether dam removal can occur consistent with the settlement's terms. For PacifiCorp, the key elements of the settlement include: (1) a contribution from PacifiCorp's Oregon and California customers capped at $200 million plus $250 million in California bond funds; (2) complete indemnification from harms associated with dam removal; (3) transfer of the FERC license to a third-party dam removal entity, the Klamath River Renewal Corporation ("KRRC"), who would conduct dam removal; and (4) ability for PacifiCorp to operate the facilities for the benefit of customers until dam removal commences.

In September 2016, the KRRC and PacifiCorp filed a joint application with the FERC to transfer the license for the four mainstem Klamath dams from PacifiCorp to the KRRC. The FERC approved partial transfer of the Klamath license in a July 2020 order, subject to the condition that PacifiCorp remains co-licensee. Under the amended KHSA, PacifiCorp did not agree to remain co-licensee during the surrender and removal process given concerns about liability protections for PacifiCorp and its customers. In November 2020, PacifiCorp entered a memorandum of agreement (the "MOA") with the KRRC, the Karuk Tribe, the Yurok Tribe and the States to continue implementation of the KHSA. The agreement required the States, PacifiCorp and KRRC to file a new license transfer application to remove PacifiCorp from the license for the Klamath Hydroelectric Project and add the States and KRRC as co-licensees for the purposes of surrender. In addition, the MOA provides for additional contingency funding of $45 million, equally split between PacifiCorp and the States, and for PacifiCorp and the States to equally share in any additional cost overruns in the unlikely event that dam removal costs exceed the $450 million in funding to ensure dam removal is complete. The MOA also requires PacifiCorp to cover the costs associated with certain pre-existing environmental conditions. In June 2021, the FERC approved transfer of the four mainstem Klamath dams from PacifiCorp to the KRRC and the States as co-licensees. In July 2021, the Oregon, Wyoming, Idaho and California state public utility commissions conditionally approved the required property transfer applications. In August 2021, PacifiCorp notified the Public Service Commission of Utah of the property transfer, however no formal approval is required in Utah. The transfer will be effective within 30 days following the issuance of a license surrender from the FERC for the project, which remains pending. In February 2022, the FERC staff issued a draft environmental impact statement for the project, concluding that dam removal is the preferred alternative. A final environmental impact statement is expected later in 2022.

Guarantees

The Company has entered into guarantees as part of the normal course of business and the sale of certain assets. These guarantees are not expected to have a material impact on the Company's consolidated financial results.
PAC  
Loss Contingencies [Line Items]  
Commitments and Contingencies Commitments and Contingencies
Construction Commitments

During the six-month period ended June 30, 2022, PacifiCorp entered into a procurement and construction services agreement for $849 million through 2024 for the construction of a key Energy Gateway Transmission segment extending between the Aeolus substation near Medicine Bow, Wyoming and the Clover substation near Mona, Utah.

Fuel Contracts

During the six-month period ended June 30, 2022, PacifiCorp entered into certain coal supply and transportation agreements totaling approximately $200 million through 2024.

Legal Matters

PacifiCorp is party to a variety of legal actions arising out of the normal course of business. Plaintiffs occasionally seek punitive or exemplary damages. PacifiCorp does not believe that such normal and routine litigation will have a material impact on its consolidated financial results. PacifiCorp is also involved in other kinds of legal actions, some of which assert or may assert claims or seek to impose fines, penalties and other costs in substantial amounts and are described below.
2020 Wildfires

In September 2020, a severe weather event resulting in high winds, low humidity and warm temperatures contributed to several major wildfires, real and personal property and natural resource damage, personal injuries and loss of life and widespread power outages in Oregon and Northern California. The wildfires spread across certain parts of PacifiCorp's service territory and surrounding areas across multiple counties in Oregon and California, including Siskiyou County, California; Jackson County, Oregon; Douglas County, Oregon; Marion County, Oregon; Lincoln County, Oregon; and Klamath County, Oregon burning over 500,000 acres in aggregate. Third party reports for these wildfires indicate over 2,000 structures destroyed, including residences; several structures damaged; multiple individuals injured; and several fatalities. Fire suppression costs estimated by various agencies total approximately $150 million. Investigations into the cause and origin of each wildfire are complex and ongoing and being conducted by various entities, including the United States Forest Service, the California Public Utilities Commission, the Oregon Department of Forestry, the Oregon Department of Justice, PacifiCorp and various experts engaged by PacifiCorp.

Multiple lawsuits have been filed in Oregon and California, including a putative class action complaint in Oregon, on behalf of citizens and businesses who suffered damages from fires allegedly caused by PacifiCorp. Additionally, several insurance carriers have filed subrogation complaints in Oregon and California with allegations similar to those made in the aforementioned lawsuits. The final determinations of liability, however, will only be made following comprehensive investigations and litigation processes.

In California, under inverse condemnation, courts have held that investor-owned utilities can be liable for real and personal property damages without the utility being found negligent and regardless of fault. California law also permits inverse condemnation plaintiffs to recover reasonable attorney fees and costs. In both Oregon and California, PacifiCorp has equipment in areas accessed through special use permits, easements or similar agreements that may contain provisions requiring it to pay for damages caused by its equipment regardless of fault. Even if inverse condemnation or other provisions do not apply, PacifiCorp could nevertheless be found liable for all damages proximately caused by negligence, including real and personal property and natural resource damage; fire suppression costs; personal injury and loss of life damages; and interest.

During the three-month period ended June 30, 2022, PacifiCorp accrued $64 million of losses net of expected insurance recoveries associated with the 2020 Wildfires resulting in an overall loss accrual net of expected insurance recoveries of $200 million as of June 30, 2022 compared to $136 million as of December 31, 2021. These accruals include PacifiCorp's estimate of losses for fire suppression costs, real and personal property damages, natural resource damages and noneconomic damages such as personal injury damages and loss of life damages that are considered probable of being incurred and that it is reasonably able to estimate at this time. For certain aspects of the 2020 Wildfires for which loss is considered probable, information necessary to reasonably estimate the potential losses, such as those related to natural resource damages, is not currently available. It is reasonably possible that PacifiCorp will incur additional losses beyond the amounts accrued; however, PacifiCorp is currently unable to estimate the range of possible additional losses that could be incurred due to the number of properties and parties involved and the variation in those types of properties and lack of available details. To the extent losses beyond the amounts accrued are incurred, additional insurance coverage is expected to be available to cover at least a portion of the losses. PacifiCorp's receivable for expected insurance recoveries was $277 million as of June 30, 2022.

Environmental Laws and Regulations

PacifiCorp is subject to federal, state and local laws and regulations regarding air and water quality, renewable portfolio standards, emissions performance standards, climate change, coal combustion byproduct disposal, hazardous and solid waste disposal, protected species and other environmental matters that have the potential to impact PacifiCorp's current and future operations. PacifiCorp believes it is in material compliance with all applicable laws and regulations.

Hydroelectric Relicensing

PacifiCorp is a party to the 2016 amended Klamath Hydroelectric Settlement Agreement ("KHSA"), which is intended to resolve disputes surrounding PacifiCorp's efforts to relicense the Klamath Hydroelectric Project. The KHSA establishes a process for PacifiCorp, the states of Oregon and California ("States") and other stakeholders to assess whether dam removal can occur consistent with the settlement's terms. For PacifiCorp, the key elements of the settlement include: (1) a contribution from PacifiCorp's Oregon and California customers capped at $200 million plus $250 million in California bond funds; (2) complete indemnification from harms associated with dam removal; (3) transfer of the Federal Energy Regulatory Commission ("FERC") license to a third-party dam removal entity, the Klamath River Renewal Corporation ("KRRC"), who would conduct dam removal; and (4) ability for PacifiCorp to operate the facilities for the benefit of customers until dam removal commences.
In September 2016, the KRRC and PacifiCorp filed a joint application with the FERC to transfer the license for the four mainstem Klamath dams from PacifiCorp to the KRRC. The FERC approved partial transfer of the Klamath license in a July 2020 order, subject to the condition that PacifiCorp remains co-licensee. Under the amended KHSA, PacifiCorp did not agree to remain co-licensee during the surrender and removal process given concerns about liability protections for PacifiCorp and its customers. In November 2020, PacifiCorp entered a memorandum of agreement (the "MOA") with the KRRC, the Karuk Tribe, the Yurok Tribe and the States to continue implementation of the KHSA. The agreement required the States, PacifiCorp and KRRC to file a new license transfer application to remove PacifiCorp from the license for the Klamath Hydroelectric Project and add the States and KRRC as co-licensees for the purposes of surrender. In addition, the MOA provides for additional contingency funding of $45 million, equally split between PacifiCorp and the States, and for PacifiCorp and the States to equally share in any additional cost overruns in the unlikely event that dam removal costs exceed the $450 million in funding to ensure dam removal is complete. The MOA also requires PacifiCorp to cover the costs associated with certain pre-existing environmental conditions. In June 2021, the FERC approved transfer of the four mainstem Klamath dams from PacifiCorp to the KRRC and the States as co-licensees. In July 2021, the Oregon, Wyoming, Idaho and California state public utility commissions conditionally approved the required property transfer applications. In August 2021, PacifiCorp notified the Public Service Commission of Utah of the property transfer, however no formal approval is required in Utah. The transfer will be effective within 30 days following the issuance of a license surrender from the FERC for the project, which remains pending. In February 2022, the FERC staff issued a draft environmental impact statement for the project, concluding that dam removal is the preferred alternative. A final environmental impact statement is expected later in 2022.

Guarantees

PacifiCorp has entered into guarantees as part of the normal course of business and the sale or transfer of certain assets. These guarantees are not expected to have a material impact on PacifiCorp's consolidated financial results.
MEC  
Loss Contingencies [Line Items]  
Commitments and Contingencies Commitments and Contingencies
Legal Matters

MidAmerican Energy is party to a variety of legal actions arising out of the normal course of business. Plaintiffs occasionally seek punitive or exemplary damages. MidAmerican Energy does not believe that such normal and routine litigation will have a material impact on its financial results.

Environmental Laws and Regulations

MidAmerican Energy is subject to federal, state and local laws and regulations regarding climate change, renewable portfolio standards, air and water quality, emissions performance standards, coal combustion byproduct disposal, hazardous and solid waste disposal, protected species and other environmental matters that have the potential to impact its current and future operations. MidAmerican Energy believes it is in material compliance with all applicable laws and regulations.

Transmission Rates

MidAmerican Energy's wholesale transmission rates are set annually using Federal Energy Regulatory Commission ("FERC")-approved formula rates subject to true-up for actual cost of service. MidAmerican Energy is authorized by the FERC to include a 0.50% adder beyond the approved base return on equity ("ROE") effective January 2015. Prior to September 2016, the rates in effect were based on a 12.38% ROE. In November 2013 and February 2015, a coalition of intervenors filed successive complaints with the FERC requesting that the 12.38% ROE no longer be found just and reasonable and sought to reduce the base ROE to 9.15% and 8.67%, respectively. In September 2016, the FERC issued an order for the first complaint, which reduces the base ROE to 10.32% and required refunds, plus interest, for the period from November 2013 through February 2015. Customer refunds relative to the first complaint occurred in February 2017. In November 2019, the FERC issued an order addressing the second complaint and issues on appeal in the first complaint. The order established a ROE of 9.88% (10.38% including the 0.50% adder) for the 15-month refund period of the first complaint and prospectively from September 2016 forward. In May 2020, the FERC issued an order on rehearing of the November 2019 order. The May 2020 order affirmed the FERC's prior decision to dismiss the second complaint and established an ROE of 10.02% (10.52% including the 0.50% adder) for the 15-month refund period of the first complaint and prospectively from September 2016 to the date of the May 2020 order. These orders continue to be subject to judicial appeal. MidAmerican Energy cannot predict the ultimate outcome of these matters and, as of June 30, 2022, has accrued an $8 million liability for refunds of amounts collected under the higher ROE during the periods covered by both complaints.
MidAmerican Funding, LLC  
Loss Contingencies [Line Items]  
Commitments and Contingencies Commitments and ContingenciesMidAmerican Funding is party to a variety of legal actions arising out of the normal course of business. Plaintiffs occasionally seek punitive or exemplary damages. MidAmerican Funding does not believe that such normal and routine litigation will have a material impact on its consolidated financial results. Refer to Note 8 of MidAmerican Energy's Notes to Financial Statements.
NPC  
Loss Contingencies [Line Items]  
Commitments and Contingencies Commitments and Contingencies
Legal Matters

Nevada Power is party to a variety of legal actions arising out of the normal course of business. Plaintiffs occasionally seek punitive or exemplary damages. Nevada Power does not believe that such normal and routine litigation will have a material impact on its consolidated financial results.

Environmental Laws and Regulations

Nevada Power is subject to federal, state and local laws and regulations regarding climate change, renewable portfolio standards, air and water quality, emissions performance standards, coal combustion byproduct disposal, hazardous and solid waste disposal, protected species and other environmental matters that have the potential to impact Nevada Power's current and future operations. Nevada Power believes it is in material compliance with all applicable laws and regulations.
SPPC  
Loss Contingencies [Line Items]  
Commitments and Contingencies Commitments and Contingencies
Legal Matters

Sierra Pacific is party to a variety of legal actions arising out of the normal course of business. Plaintiffs occasionally seek punitive or exemplary damages. Sierra Pacific does not believe that such normal and routine litigation will have a material impact on its consolidated financial results.

Environmental Laws and Regulations

Sierra Pacific is subject to federal, state and local laws and regulations regarding climate change, renewable portfolio standards, air and water quality, emissions performance standards, coal combustion byproduct disposal, hazardous and solid waste disposal, protected species and other environmental matters that have the potential to impact Sierra Pacific's current and future operations. Sierra Pacific believes it is in material compliance with all applicable laws and regulations.
EEGH  
Loss Contingencies [Line Items]  
Commitments and Contingencies Commitments and Contingencies
Legal Matters

Eastern Energy Gas is party to a variety of legal actions arising out of the normal course of business. Plaintiffs occasionally seek punitive or exemplary damages. Eastern Energy Gas does not believe that such normal and routine litigation will have a material impact on its consolidated financial results.

Environmental Laws and Regulations

Eastern Energy Gas is subject to federal, state and local laws and regulations regarding climate change, renewable portfolio standards, air and water quality, emissions performance standards, hazardous and solid waste disposal, protected species and other environmental matters that have the potential to impact Eastern Energy Gas' current and future operations. Eastern Energy Gas believes it is in material compliance with all applicable laws and regulations.