XML 97 R77.htm IDEA: XBRL DOCUMENT v3.22.1
OTHER CONTINGENCIES AND COMMITMENTS (Environmental Remediation Contingencies Narrative) (Details)
$ in Millions
Mar. 31, 2022
USD ($)
Long-term Purchase Commitment [Line Items]  
Amount of environmental loss accrual expected to be recovered $ 984
Topock Site  
Long-term Purchase Commitment [Line Items]  
Utility undiscounted future costs $ 230
Topock Site | Pacific Gas & Electric Co (Utility)  
Long-term Purchase Commitment [Line Items]  
Remediation cost recovery percentage 90.00%
Hinkley Natural Gas Compressor Station  
Long-term Purchase Commitment [Line Items]  
Utility undiscounted future costs $ 138
Former Manufactured Gas Plant  
Long-term Purchase Commitment [Line Items]  
Utility undiscounted future costs $ 475
Former Manufactured Gas Plant | Pacific Gas & Electric Co (Utility)  
Long-term Purchase Commitment [Line Items]  
Remediation cost recovery percentage 90.00%
Utility Owned Generation Facilities and Third Party Disposal Sites  
Long-term Purchase Commitment [Line Items]  
Utility undiscounted future costs $ 50
Utility Owned Generation Facilities and Third Party Disposal Sites | Pacific Gas & Electric Co (Utility)  
Long-term Purchase Commitment [Line Items]  
Remediation cost recovery percentage 90.00%
Fossil Fuel Fired Generation  
Long-term Purchase Commitment [Line Items]  
Utility undiscounted future costs $ 43