Commitments And Contingencies (Environmental Remediation Liability Composed) (Detail) - USD ($)
$ in Millions
Dec. 31, 2017
Dec. 31, 2016
Topock natural gas compressor station $ 334 $ 299
Hinkley natural gas compressor station 147 135
Former manufactured gas plant sites owned by the Utility or third parties 320 [1] 285
Utility-owned generation facilities (other than for fossil fuel-fired), other facilities, and third-party disposal sites 115 [2] 131
Fossil fuel-fired generation facilities and sites 123 [3] 108
Total environmental remediation liability $ 1,039 $ 958
[1] Primarily driven by the following sites: Vallejo, SF East Harbor, Napa, and SF North Beach
[2] Primarily driven by the Shell Pond site
[3] Primarily driven by the SF Potrero Power Plant site