Environmental        
Goal For Reduced Carbon Dioxide Emissions From 2005 Levels By 2030 Under Clean Air Act 32.00%      
NPDES permit renewal permit period five      
Nuclear Generation        
Forecasted Incremental Capital Costs Associated With Schedule Delays, 2015 Petition $ 539,000      
EPC Contract Amendment, New Nuclear Construction Completion Bonus 151,000      
EPC Contract Amendment, Payment and Performance Bonds $ 45,000      
EPC Contract Amendment, Payment And Performance Bonds, Percentage of Billing 15.00%      
EPC Contract Amendment, Payment And Performance Bonds, Maximum Aggregate Nominal Coverage $ 100,000      
Dispute Review Board Resolution Without Recourse less than $5 million      
Dispute Review Board Resolution Subject To Litigation greater than $5 million      
SCEG        
Commitments and contingencies        
Storm Damage Provision $ 2,000      
Nuclear Insurance        
Maximum liability assessment per reactor for each nuclear incident 127,300      
Maximum Insurance Coverage For Each Nuclear Plant by ANI 375,000      
Federal Limit on Public Liability Claims from Nuclear Incident Approximate 13,400,000      
Maximum Federal Limit on Public Liability Claims Per Reactor for Each Year 18,900      
Maximum Federal Limit on Public Liability Claims per Reactor for each Nuclear Incident at 2/3 84,800      
Maximum Federal Limit on Public Liability Claims Per Incident for Each Year $ 12,600      
Inflation adjustment period for nuclear insurance 5      
Maximum loss for a single nuclear incident $ 2,750,000      
NEIL Maximum Insurance Coverage of Accidental Property Damage 500,000      
NEIL Maximum Insurance Coverage To Nuclear Facility For Property Damage And Outage Costs From Non-Nuclear Event 2,330,000      
EMANI Maximum Retrospective Premium Assessment 1,800      
EMANI Maximum Insurance Coverage for Summer Station Unit 1 For Property Damage And Outage Costs From Non-Nuclear Event 415,000      
NEIL Maximum Prosepective Insurance Premium Per Nuclear Incident 45,800      
NEIL Maximum Insurance Coverage to Nuclear Facility for Property Damage and Outage Costs 2,750,000      
Environmental        
Environmental Remediation Costs Recognized in Regulatory Assets $ 26,000      
Number of MGP decommissioned sites that contain residues of byproduct chemicals 4      
Number Of States Required To Reduce Emissions Under CSAPR 28      
Site Contingency MGP Estimated Environmental Remediation Costs $ 10,300      
Nuclear Generation        
EPC Contract Amendment, Increase In Fixed Component Of Contract Price 165,000      
EPC Contract Amendment, Credit Applied To Target Component Of New Units Contract Price 27,000      
EPC Contract Amendment, Cap On Delay Oriented Liquidated Damages Per New Nuclear Unit 255,000      
EPC Contract Amendment, Revised Construction Milestone Payment Schedule, Per Month 55,000      
EPC Contract Amendment, Payment and Performance Bonds 25,000      
EPC Contract Amendment, Payment And Performance Bonds, Maximum Aggregate Nominal Coverage 55,000      
Transmission Capital Costs Forecast WIthdrawn 4,300      
Total New Nuclear Project Cost Approved By SCPSC In September 2015 6,800,000      
EPC Contract Amendment, Total New Nuclear Project Cost Including Amendment Increase $ 7,200,000      
SCEG        
Nuclear Insurance        
Jointly Owned Utility Plant, Proportionate Ownership Share 5.00%      
Nuclear Generation        
EPC Contract Amendment, Cap On Delay Oriented Liquidated Damages Per New Nuclear Unit $ 186,000      
EPC Contract Amendment, New Nuclear Construction Completion Bonus 83,000      
EPC Contract Amendment, Fixed Price Option, Price For New Nuclear Construction After June 2015 3,345,000      
EPC Contract Amendment, Increase In Fixed Component Of Contract Price, Payments 103,100      
EPC Contract Amendment, Revised Construction Milestone Payment Schedule, Payments $ 512,000      
Summer Station New Units [Domain]        
Nuclear Insurance        
Jointly Owned Utility Plant, Proportionate Ownership Share 55.00%      
Jointly Owned Utility Plant, Ownership Amount of Construction Work in Progress $ 4,200,000      
Nuclear Generation        
jointly owned utility plant ownership, construction financing cost 3,200,000      
EPC Contract Amendment, Increase In Fixed Component Of Contract Price 300,000      
EPC Contract Amendment, Credit Applied To Target Component Of New Units Contract Price 50,000      
EPC Contract Amendment, Cap On Delay Oriented Liquidated Damages Per New Nuclear Unit 463,000      
EPC Contract Amendment, Fixed Price Option, New Nuclear Construction Completion Bonus 150,000      
EPC Contract Amendment, New Nuclear Construction Completion Bonus 275,000      
EPC Contract Amendment, Revised Construction Milestone Payment Schedule, Per Month 100,000      
Nuclear Production Tax Credits $ 1,400,000      
Nuclear Production Tax Credit realization period 8      
EPC Contract Amendment, Fixed Price Option, Price For New Nuclear Construction After June 2015 $ 6,082,000      
EPC Contract Amendment, Fixed Price Option, Cap On Delay Oriented Liquidated Damages Per New Nuclear Unit 338,000      
EPC Contract Amendment, Increase In Fixed Component Of Contract Price, Payments 188,000      
EPC Contract Amendment, Revised Construction Milestone Payment Schedule, Payments 930,000      
Capital costs, owners [Domain]        
Nuclear Generation        
Forecasted incremental capital costs, 2015 petition 245,000      
Forecasted Total Capital Costs, 2015 Petition 5,200,000      
Forecasted Gross Capital Costs, 2015 Petition 6,800,000      
Capital costs, Other [Domain] [Domain]        
Nuclear Generation        
Forecasted incremental capital costs, 2015 petition 453,000      
Scenario, Forecast [Member] | SCEG        
Nuclear Generation        
Additional ownership in new units   2.00% 2.00% 1.00%
Maximum [Member] | SCEG        
Nuclear Generation        
Additional ownership in new units, dollars $ 850,000