XML 23 R18.htm IDEA: XBRL DOCUMENT v2.4.0.8
COMMITMENTS AND CONTINGENCIES
9 Months Ended
Sep. 30, 2013
Statement [Line Items]  
Commitments and Contingencies Disclosure [Text Block]
COMMITMENTS AND CONTINGENCIES

Nuclear Insurance

Under Price-Anderson, SCE&G (for itself and on behalf of Santee Cooper, a one-third owner of Summer Station Unit 1) maintains agreements of indemnity with the NRC that, together with private insurance, cover third-party liability arising from any nuclear incident occurring at the Company's nuclear power plant. Price-Anderson provides funds up to $13.6 billion for public liability claims that could arise from a single nuclear incident. Each nuclear plant is insured against this liability to a maximum of $375 million by ANI with the remaining coverage provided by a mandatory program of deferred premiums that could be assessed, after a nuclear incident, against all owners of commercial nuclear reactors. Each reactor licensee is currently liable for up to $127.3 million per reactor owned for each nuclear incident occurring at any reactor in the United States, provided that not more than $18.9 million of the liability per reactor would be assessed per year.  SCE&G’s maximum assessment, based on its two-thirds ownership of Summer Station Unit 1, would be $84.8 million per incident, but not more than $12.6 million per year. Both the maximum assessment per reactor and the maximum yearly assessment are adjusted for inflation at least every five years.

SCE&G currently maintains insurance policies (for itself and on behalf of Santee Cooper) with NEIL.  The policies provide coverage to Summer Station Unit 1 for property damage and outage costs up to $2.75 billion resulting from an event of nuclear origin. In addition, a builder's risk insurance policy has been purchased from NEIL for the construction of the New Units. This policy provides the owners of the New Units up to $500 million in limits of accidental property damage occurring during construction. The NEIL policies, in the aggregate, are subject to a maximum loss of $2.75 billion for any single loss occurrence. All of the NEIL policies permit retrospective assessments under certain conditions to cover insurer’s losses.  Based on the current annual premium, SCE&G’s portion of the retrospective premium assessment would not exceed $40.6 million.
 
To the extent that insurable claims for property damage, decontamination, repair and replacement and other costs and expenses arising from a nuclear incident at Summer Station Unit 1 exceed the policy limits of insurance, or to the extent such insurance becomes unavailable in the future, and to the extent that SCE&G's rates would not recover the cost of any purchased replacement power or other costs and expenses, SCE&G will retain the risk of loss as a self-insurer.  SCE&G has no reason to anticipate a serious nuclear incident.  However, if such an incident were to occur, it likely would have a material impact on the Company’s results of operations, cash flows and financial position.

Environmental
 
As part of the President's Climate Action Plan and by Presidential Memorandum issued June 25, 2013, the EPA was directed to issue a revised carbon standard for new power plants by September 20, 2013, to be made final as soon as appropriate. Standards, regulations, or guidelines are also required for existing units by June 1, 2014, to be made final no later than June 1, 2015. On September 20, 2013, EPA re-proposed NSPS under the CAA for emissions of carbon dioxide from newly constructed fossil fuel-fired units.The Company is evaluating the proposed rule, but cannot predict when it will become final, if at all, or what conditions it may impose on the Company, if any. The Company also cannot predict when rules will become final for existing units, if at all, or what conditions they may impose on the Company, if any. The Company expects that any costs incurred to comply with GHG emission requirements will be recoverable through rates.

In 2005, the EPA issued the CAIR, which required the District of Columbia and 28 states to reduce nitrogen oxide and sulfur dioxide emissions in order to attain mandated state levels.  CAIR set emission limits to be met in two phases beginning in 2009 and 2015, respectively, for nitrogen oxide and beginning in 2010 and 2015, respectively, for sulfur dioxide.  SCE&G and GENCO determined that additional air quality controls would be needed to meet the CAIR requirements.  On July 6, 2011 the EPA issued the CSAPR.  This rule replaced CAIR and the Clean Air Transport Rule proposed in July 2010 and is aimed at addressing power plant emissions that may contribute to air pollution in other states.  CSAPR requires states in the eastern United States to reduce power plant emissions, specifically sulfur dioxide and nitrogen oxide.  On December 30, 2011, the United States Court of Appeals for the District of Columbia issued an order staying CSAPR and reinstating CAIR pending resolution of an appeal of CSAPR. On August 21, 2012, the Court of Appeals vacated CSAPR and left CAIR in place. The EPA's petition for rehearing of the Court of Appeals' order was denied. In June, 2013, the U.S. Supreme Court agreed to review the Court of Appeals' decision and has scheduled oral arguments for December 10, 2013. Air quality control installations that SCE&G and GENCO have already completed have allowed the Company to comply with the reinstated CAIR. The Company will continue to pursue strategies to comply with all applicable environmental regulations.  Any costs incurred to comply with such regulations are expected to be recoverable through rates.

In April 2012, the EPA's rule containing new standards for mercury and other specified air pollutants became effective.  The rule provides up to four years for facilities to meet the standards, and the Company's evaluation of the rule is ongoing. The Company's decision in 2012 to retire certain coal-fired units or convert them to burn natural gas and its project to build the New Units (see Note 1) along with other actions are expected to result in the Company's compliance with the EPA's rule.  Any costs incurred to comply with this rule or other rules issued by the EPA in the future are expected to be recoverable through rates.

The EPA is conducting an enforcement initiative against the utilities industry related to the NSR provisions and the NSPS of the CAA. As part of the initiative, many utilities have received requests for information under Section 114 of the CAA. In addition, the DOJ, on behalf of the EPA, has taken civil enforcement action against several utilities. The primary basis for these actions is the assertion by the EPA that maintenance activities undertaken by the utilities at their coal-fired power plants constituted “major modifications” which required the installation of costly BACT. Some of the utilities subject to the actions have reached settlement. Though the Company cannot predict what action, if any, the EPA will initiate against it, any costs incurred are expected to be recoverable through rates.

The Company maintains an environmental assessment program to identify and evaluate its current and former operations sites that could require environmental clean-up.  As site assessments are initiated, estimates are made of the amount of expenditures, if any, deemed necessary to investigate and remediate each site.  Environmental liabilities are accrued when the criteria for loss contingencies are met. These estimates are refined as additional information becomes available; therefore, actual expenditures could differ significantly from the original estimates.  Amounts estimated and accrued to date for site assessments and clean-up relate solely to regulated operations.  Amounts expected to be recovered through rates are recorded in regulatory assets and, if applicable, amortized over approved amortization periods. Other environmental costs are recorded to expense.
 
SCE&G is responsible for four decommissioned MGP sites in South Carolina which contain residues of byproduct chemicals.  These sites are in various stages of investigation, remediation and monitoring under work plans approved by DHEC and the EPA.  SCE&G anticipates that major remediation activities at all these sites will continue until 2017 and will cost an additional $21.2 million, which is accrued in Other within Deferred Credits and Other Liabilities on the condensed consolidated balance sheet.  SCE&G expects to recover any cost arising from the remediation of MGP sites through rates.  At September 30, 2013, deferred amounts, net of amounts previously recovered through rates and insurance settlements, totaled $37.1 million and are included in regulatory assets.
 
PSNC Energy is responsible for environmental clean-up at five sites in North Carolina on which MGP residuals are present or suspected.  PSNC Energy’s actual remediation costs for these sites will depend on a number of factors, such as actual site conditions, third-party claims and recoveries from other PRPs.  PSNC Energy has recorded a liability and associated regulatory asset of approximately $2.9 million, the estimated remaining liability at September 30, 2013. PSNC Energy expects to recover through rates any cost allocable to PSNC Energy arising from the remediation of these sites.

New Nuclear Construction
 
SCE&G, on behalf of itself and as agent for Santee Cooper, has contracted with the Consortium for the design and construction of the New Units at the site of Summer Station.  SCE&G's share of the estimated cash outlays (future value, excluding AFC) totals approximately $5.7 billion for plant and related transmission infrastructure costs, and is projected based on historical one-year and five-year escalation rates as required by the SCPSC.

The Consortium has experienced delays in the schedule for fabrication and delivery of sub-modules for the New Units. The fabrication and delivery of sub-modules are a focus area of the Consortium. The delivery schedule of sub-modules for structural module CA20, which is part of the auxiliary building, and CA01, which houses components inside the containment vessel, is now expected to support completion of on-site fabrication to allow them to be set on the nuclear island to the first New Unit during the first and third quarters of 2014, respectively. With this schedule, the Consortium continues to indicate that the substantial completion of the first New Unit is expected to be late 2017 or the first quarter of 2018 and that the substantial completion of the second New Unit is expected to be approximately twelve months after that of the first New Unit. The substantial completion dates currently approved by the SCPSC for the first and second New Units are March 15, 2017 and May 15, 2018, respectively. The SCPSC has also approved an 18-month contingency period beyond each of these dates. The preliminary expected new substantial completion dates are within the contingency periods. SCE&G cannot predict with certainty the extent to which the issue with the sub-modules or the delays in the substantial completion of the New Units will result in increased project costs. However, the preliminary estimate of the delay-related costs associated with SCE&G's share of the New Units is approximately $200 million. SCE&G has not accepted responsibility for any of these delay-related costs and expects to have further discussions with the Consortium regarding such responsibility. Additionally, the EPC Contract provides for liquidated damages in the event of a delay in the completion of the facility, which will also be included in discussions with the Consortium. SCE&G believes its responsibility for any portion of the $200 million estimate should ultimately be substantially less, once all of the relevant factors are considered.

In addition to the above-described project delays, SCE&G is also aware of financial difficulties at a supplier responsible for certain significant components of the project.  The Consortium is monitoring the potential for disruptions in such equipment fabrication and possible responses.   Any disruptions could impact the project's schedule or costs, and such impacts could be material.

Subject to a national megawatt capacity limitation, the electricity to be produced by the New Units (advanced nuclear units, as defined) is expected to qualify for nuclear production tax credits under Section 45J of the Internal Revenue Code. Following the pouring of safety-related concrete for each of the Units’ reactor buildings (March 2013 for the first New Unit and November 2013 for the second New Unit), the Company has applied to the IRS for its allocations of such national megawatt capacity limitation. The IRS will forward the applications to the United States Department of Energy for appropriate certification.
The parties to the EPC Contract have established both informal and formal dispute resolution procedures in order to resolve issues that arise during the course of constructing a project of this magnitude.  During the course of activities under the EPC Contract, issues have materialized that impact project budget and schedule. Claims specifically relating to COL delays,
design modifications of the shield building and certain pre-fabricated modules for the New Units and unanticipated rock
conditions at the site resulted in assertions of contractual entitlement to recover additional costs to be incurred. The resolution
of these specific claims is discussed in Note 2. SCE&G expects to resolve any disputes that arise in the future, including any which may arise with respect to the delay-related costs discussed above, through both the informal and formal procedures and anticipates that any additional costs that arise through such dispute resolution processes, as well as other costs identified from time to time, will be recoverable through rates.

When the NRC issued the COLs for the New Units, two of the conditions that it imposed were requiring inspection and testing of certain components of the New Units' passive cooling system, and requiring the development of strategies to respond to extreme natural events resulting in the loss of power at the New Units.  In addition, the NRC directed the Office of New Reactors to issue to SCE&G an order requiring enhanced, reliable spent fuel pool instrumentation, as well as a request for information related to emergency plant staffing.  These conditions and requirements are responsive to the NRC's Near-Term Task Force report titled “Recommendations for Enhancing Reactor Safety in the 21st Century.”  This report was prepared in the wake of the March 2011 earthquake-generated tsunami, which severely damaged several nuclear generating units and their back-up cooling systems in Japan.  SCE&G continues to evaluate the impact of these conditions and requirements that may be imposed on the construction and operation of the New Units, and SCE&G prepared and submitted an integrated response plan for the New Units to the NRC in August 2013.  SCE&G cannot predict what additional regulatory or other outcomes may be implemented in the United States, or how such initiatives would impact SCE&G's existing Summer Station or the construction or operation of the New Units.

SCE&G understands that Santee Cooper continues to evaluate reduction of its level of participation in the New Units through potential sales of portions of its interest therein to third parties. SCE&G is unable to predict whether any change in Santee Cooper's ownership interest or the addition of new joint owners will increase project costs or delay the substantial completion dates of the New Units.  Any such project cost increase or delay could be material.
SCEG
 
Statement [Line Items]  
Commitments and Contingencies Disclosure [Text Block]
COMMITMENTS AND CONTINGENCIES

 Nuclear Insurance

Under Price-Anderson, SCE&G (for itself and on behalf of Santee Cooper, a one-third owner of Summer Station Unit 1) maintains agreements of indemnity with the NRC that, together with private insurance, cover third-party liability arising from any nuclear incident occurring at the Company's nuclear power plant. Price-Anderson provides funds up to $13.6 billion for public liability claims that could arise from a single nuclear incident. Each nuclear plant is insured against this liability to a maximum of $375 million by ANI with the remaining coverage provided by a mandatory program of deferred premiums that could be assessed, after a nuclear incident, against all owners of commercial nuclear reactors. Each reactor licensee is currently liable for up to $127.3 million per reactor owned for each nuclear incident occurring at any reactor in the United States, provided that not more than $18.9 million of the liability per reactor would be assessed per year.  SCE&G’s maximum assessment, based on its two-thirds ownership of Summer Station Unit 1, would be $84.8 million per incident, but not more than $12.6 million per year. Both the maximum assessment per reactor and the maximum yearly assessment are adjusted for inflation at least every five years.
 
SCE&G currently maintains insurance policies (for itself and on behalf of Santee Cooper) with NEIL.  The policies provide coverage to Summer Station Unit 1 for property damage and outage costs up to $2.75 billion resulting from an event of nuclear origin. In addition, a builder's risk insurance policy has been purchased from NEIL for the construction of the New Units. This policy provides the owners of the New Units up to $500 million in limits of accidental property damage occurring during construction. The NEIL policies, in the aggregate, are subject to a maximum loss of $2.75 billion for any single loss occurrence. All of the NEIL policies permit retrospective assessments under certain conditions to cover insurer’s losses.  Based on the current annual premium, SCE&G’s portion of the retrospective premium assessment would not exceed $40.6 million.
 
To the extent that insurable claims for property damage, decontamination, repair and replacement and other costs and expenses arising from a nuclear incident at Summer Station Unit 1 exceed the policy limits of insurance, or to the extent such insurance becomes unavailable in the future, and to the extent that SCE&G's rates would not recover the cost of any purchased replacement power or other cost and expenses, SCE&G will retain the risk of loss as a self-insurer.  SCE&G has no reason to anticipate a serious nuclear incident.  However, if such an incident were to occur, it likely would have a material impact on the Company’s results of operations, cash flows and financial position.

Environmental
 
As part of the President's Climate Action Plan and by Presidential Memorandum issued June 25, 2013, the EPA was directed to issue a revised carbon standard for new power plants by September 20, 2013, to be made final as soon as appropriate. Standards, regulations, or guidelines are also required for existing units by June 1, 2014, to be made final no later than June 1, 2015. On September 20, 2013, EPA re-proposed NSPS under the CAA for emissions of carbon dioxide from newly constructed fossil fuel-fired units. Consolidated SCE&G is evaluating the proposed rule, but cannot predict when it will become final, if at all, or what conditions it may impose on the Company, if any. Consolidated SCE&G also cannot predict when rules will become final for existing units, if at all, or what conditions they may impose on Consolidated SCE&G, if any. Consolidated SCE&G expects that any costs incurred to comply with GHG emission requirements will be recoverable through rates.

In 2005, the EPA issued the CAIR, which required the District of Columbia and 28 states to reduce nitrogen oxide and sulfur dioxide emissions in order to attain mandated state levels.  CAIR set emission limits to be met in two phases beginning in 2009 and 2015, respectively, for nitrogen oxide and beginning in 2010 and 2015, respectively, for sulfur dioxide.  SCE&G and GENCO determined that additional air quality controls would be needed to meet the CAIR requirements. On July 6, 2011 the EPA issued the CSAPR.  This rule replaced CAIR and the Clean Air Transport Rule proposed in July 2010 and is aimed at addressing power plant emissions that may contribute to air pollution in other states.  CSAPR requires states in the eastern United States to reduce power plant emissions, specifically sulfur dioxide and nitrogen oxide.  On December 30, 2011, the United States Court of Appeals for the District of Columbia issued an order staying CSAPR and reinstating CAIR pending resolution of an appeal of CSAPR. On August 21, 2012, the Court of Appeals vacated CSAPR and left CAIR in place. The EPA's petition for rehearing of the Court of Appeals' order was denied. In June, 2013, the U.S. Supreme Court agreed to review the Court of Appeals' decision and has scheduled oral arguments for December 10, 2013. Air quality control installations that SCE&G and GENCO have already completed have allowed Consolidated SCE&G to comply with the reinstated CAIR.  Consolidated SCE&G will continue to pursue strategies to comply with all applicable environmental regulations.  Any costs incurred to comply with such regulations are expected to be recoverable through rates.

In April 2012, the EPA's rule containing new standards for mercury and other specified air pollutants became effective.  The rule provides up to four years for facilities to meet the standards, and Consolidated SCE&G's evaluation of the rule is ongoing. Consolidated SCE&G's decision in 2012 to retire certain coal-fired units or convert them to burn natural gas and its project to build the New Units (see Note 1) along with other actions are expected to result in Consolidated SCE&G's compliance with the EPA's rule.  Any costs incurred to comply with this rule or other rules issued by the EPA in the future are expected to be recoverable through rates.

The EPA is conducting an enforcement initiative against the utilities industry related to the NSR provisions and the NSPS of the CAA. As part of the initiative, many utilities have received requests for information under Section 114 of the CAA. In addition, the DOJ, on behalf of the EPA, has taken civil enforcement action against several utilities. The primary basis for these actions is the assertion by the EPA that maintenance activities undertaken by the utilities at their coal-fired power plants constituted “major modifications” which required the installation of costly BACT. Some of the utilities subject to the actions have reached settlement. Though Consolidated SCE&G cannot predict what action, if any, the EPA will initiate against it, any costs incurred are expected to be recoverable through rates.

Consolidated SCE&G maintains an environmental assessment program to identify and evaluate its current and former operations sites that could require environmental clean-up.  As site assessments are initiated, estimates are made of the amount of expenditures, if any, deemed necessary to investigate and remediate each site.  Environmental liabilities are accrued when the criteria for loss contingencies are met. These estimates are refined as additional information becomes available; therefore, actual expenditures could differ significantly from the original estimates.  Amounts estimated and accrued to date for site assessments and clean-up relate solely to regulated operations.  Amounts expected to be recovered through rates are recorded in regulatory assets and, if applicable, amortized over approved amortization periods. Other environmental costs are recorded to expense.
 
SCE&G is responsible for four decommissioned MGP sites in South Carolina which contain residues of byproduct chemicals.  These sites are in various stages of investigation, remediation and monitoring under work plans approved by DHEC and the EPA.  SCE&G anticipates that major remediation activities at all these sites will continue until 2017 and will cost an additional $21.2 million, which is accrued in Other within Deferred Credits and Other Liabilities on the condensed consolidated balance sheet.  SCE&G expects to recover any cost arising from the remediation of MGP sites through rates.  At September 30, 2013, deferred amounts, net of amounts previously recovered through rates and insurance settlements, totaled $37.1 million and are included in regulatory assets.
 
New Nuclear Construction

SCE&G, on behalf of itself and as agent for Santee Cooper, has contracted with the Consortium for the design and construction of the New Units at the site of Summer Station.  SCE&G's share of the estimated cash outlays (future value, excluding AFC) totals approximately $5.7 billion for plant and related transmission infrastructure costs, and is projected based on historical one-year and five-year escalation rates as required by the SCPSC.

The Consortium has experienced delays in the schedule for fabrication and delivery of sub-modules for the New Units. The fabrication and delivery of sub-modules are a focus area of the Consortium. The delivery schedule of sub-modules for structural module CA20, which is part of the auxiliary building, and CA01, which houses components inside the containment vessel, is now expected to support completion of on-site fabrication to allow them to be set on the nuclear island for the first New Unit during the first and third quarters of 2014, respectively. With this schedule, the Consortium continues to indicate that the substantial completion of the first New Unit is expected to be late 2017 or the first quarter of 2018 and that the substantial completion of the second New Unit is expected to be approximately twelve months after that of the first New Unit. The substantial completion dates currently approved by the SCPSC for the first and second New Units are March 15, 2017 and May 15, 2018, respectively. The SCPSC has also approved an 18-month contingency period beyond each of these dates. The preliminary expected new substantial completion dates are within the contingency periods. SCE&G cannot predict with certainty the extent to which the issue with the sub-modules or the delays in the substantial completion of the New Units will result in increased project costs. However, the preliminary estimate of the delay-related costs associated with SCE&G's share of the New Units is approximately $200 million. SCE&G has not accepted responsibility for any of these delay-related costs and expects to have further discussions with the Consortium regarding such responsibility. Additionally, the EPC Contract provides for liquidated damages in the event of a delay in the completion of the facility, which will also be included in discussions with the Consortium. SCE&G believes its responsibility for any portion of the $200 million estimate should ultimately be substantially less, once all of the relevant factors are considered.

In addition to the above-described project delays, SCE&G is also aware of financial difficulties at a supplier responsible for certain significant components of the project.  The Consortium is monitoring the potential for disruptions in such equipment fabrication and possible responses.   Any disruptions could impact the project's schedule or costs, and such impacts could be material.

Subject to a national megawatt capacity limitation, the electricity to be produced by the New Units (advanced nuclear units, as defined) is expected to qualify for nuclear production tax credits under Section 45J of the Internal Revenue Code. Following the pouring of safety-related concrete for each of the Units’ reactor buildings (March 2013 for the first New Unit and November 2013 for the second New Unit), the Company has applied to the IRS for its allocations of such national megawatt capacity limitation. The IRS will forward the applications to the United States Department of Energy for appropriate certification.
The parties to the EPC Contract have established both informal and formal dispute resolution procedures in order to resolve issues that arise during the course of constructing a project of this magnitude.  During the course of activities under the EPC Contract, issues have materialized that impact project budget and schedule. Claims specifically relating to COL delays,
design modifications of the shield building and certain pre-fabricated modules for the New Units and unanticipated rock
conditions at the site resulted in assertions of contractual entitlement to recover additional costs to be incurred. The resolution
of these specific claims is discussed in Note 2. SCE&G expects to resolve any disputes that arise in the future, including any which may arise with respect to the delay-related costs discussed above, through both the informal and formal procedures and anticipates that any additional costs that arise through such dispute resolution processes, as well as other costs identified from time to time, will be recoverable through rates.
    
When the NRC issued the COLs for the New Units, two of the conditions that it imposed were requiring inspection and testing of certain components of the New Units' passive cooling system, and requiring the development of strategies to respond to extreme natural events resulting in the loss of power at the New Units.  In addition, the NRC directed the Office of New Reactors to issue to SCE&G an order requiring enhanced, reliable spent fuel pool instrumentation, as well as a request for information related to emergency plant staffing.  These conditions and requirements are responsive to the NRC's Near-Term Task Force report titled “Recommendations for Enhancing Reactor Safety in the 21st Century.”  This report was prepared in the wake of the March 2011 earthquake-generated tsunami, which severely damaged several nuclear generating units and their back-up cooling systems in Japan. SCE&G continues to evaluate the impact of these conditions and requirements that may be imposed on the construction and operation of the New Units, and SCE&G prepared and submitted an integrated response plan for the New Units to the NRC in August 2013.  SCE&G cannot predict what additional regulatory or other outcomes may be implemented in the United States, or how such initiatives would impact SCE&G's existing Summer Station or the construction or operation of the New Units.

SCE&G understands that Santee Cooper continues to evaluate reduction of its level of participation in the New Units through potential sales of portions of its interest therein to third parties. SCE&G is unable to predict whether any change in Santee Cooper's ownership interest or the addition of new joint owners will increase project costs or delay the substantial completion dates of the New Units.  Any such project cost increase or delay could be material.