XML 44 R27.htm IDEA: XBRL DOCUMENT v3.7.0.1
Commitments and Contingencies (Tables)
3 Months Ended
Mar. 31, 2017
Commitments and Contingencies [Abstract]  
Schedule of Planned Capital Expenditures
At March 31, 2017, estimated capital expenditures for the remainder of 2017 through 2021 for which applicable internal approvals (and also, if required, FPSC approvals for FPL or regulatory approvals for acquisitions) have been received were as follows:
 
Remainder of 2017
 
2018
 
2019
 
2020
 
2021
 
Total
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Generation:(a)
 
 
 
 
 
 
 
 
 
 
 
New(b)
$
935

 
$
660

 
$
475

 
$
35

 
$
5

 
$
2,110

Existing
790

 
755

 
615

 
655

 
510

 
3,325

Transmission and distribution
1,680

 
2,400

 
2,540

 
2,465

 
2,675

 
11,760

Nuclear fuel
45

 
190

 
170

 
210

 
120

 
735

General and other
370

 
275

 
250

 
220

 
250

 
1,365

Total
$
3,820

 
$
4,280

 
$
4,050

 
$
3,585

 
$
3,560

 
$
19,295

NEER:
 

 
 

 
 

 
 

 
 

 
 

Wind(c)
$
910

 
$
855

 
$
1,125

 
$
30

 
$
25

 
$
2,945

Solar(d)
190

 
10

 
5

 

 

 
205

Nuclear, including nuclear fuel
185

 
250

 
230

 
215

 
245

 
1,125

Natural gas pipelines(e)
450

 
850

 
40

 
35

 
10

 
1,385

Other
210

 
40

 
30

 
30

 
30

 
340

Total
$
1,945

 
$
2,005

 
$
1,430

 
$
310

 
$
310

 
$
6,000

Corporate and Other
$
40

 
$
60

 
$
90

 
$
50

 
$
40

 
$
280

———————————————
(a)
Includes AFUDC of approximately $69 million, $78 million, $44 million and $5 million for the remainder of 2017 through 2020, respectively.
(b)
Includes land, generation structures, transmission interconnection and integration and licensing.
(c)
Consists of capital expenditures for new wind projects, repowering of existing wind projects and related transmission totaling approximately 2,880 MW.
(d)
Includes capital expenditures for new solar projects and related transmission totaling approximately 140 MW.
(e)
Includes capital expenditures for construction of three natural gas pipelines, including equity contributions associated with equity investments in joint ventures for two pipelines and AFUDC associated with the third pipeline. The natural gas pipelines are subject to certain conditions. See Contracts below.

Required capacity and/or minimum payments under contracts
The required capacity and/or minimum payments under contracts, including those discussed above, as of March 31, 2017 were estimated as follows:
 
Remainder of 2017
 
2018
 
2019
 
2020
 
2021
 
Thereafter
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Capacity charges(a)
$
55

 
$
65

 
$
50

 
$
20

 
$
20

 
$
250

Minimum charges, at projected prices:(b)
 

 
 

 
 

 
 

 
 

 
 

Natural gas, including transportation and storage(c)
$
1,150

 
$
935

 
$
860

 
$
910

 
$
905

 
$
12,065

Coal, including transportation
$
105

 
$
5

 
$
5

 
$

 
$

 
$

NEER
$
1,440

 
$
1,020

 
$
140

 
$
105

 
$
75

 
$
295

Corporate and Other(d)(e)
$
60

 
$
20

 
$

 
$
5

 
$

 
$

———————————————
(a)
Capacity charges, substantially all of which are recoverable through the capacity clause, totaled approximately $20 million and $47 million for the three months ended March 31, 2017 and 2016, respectively. Energy charges, which are recoverable through the fuel clause, totaled approximately $16 million and $16 million for the three months ended March 31, 2017 and 2016, respectively.
(b)
Recoverable through the fuel clause.
(c)
Includes approximately $200 million, $295 million, $290 million, $360 million, $390 million and $7,495 million in 2017, 2018, 2019, 2020, 2021 and thereafter, respectively, of firm commitments, subject to certain conditions as noted above, related to the natural gas transportation agreements with Sabal Trail and Florida Southeast Connection.
(d)
Includes an approximately $30 million commitment to invest in clean power and technology businesses primarily in 2017.
(e)
Excludes approximately $445 million and $20 million in 2017 and 2018, respectively, of joint obligations of NEECH and NEER which are included in the NEER amounts above.