XML 67 R51.htm IDEA: XBRL DOCUMENT v2.4.0.8
Commitments and Contingencies (Long-term Purchase Commitment) (Details) (USD $)
3 Months Ended 6 Months Ended 6 Months Ended 0 Months Ended
Jun. 30, 2014
Corporate and Other [Member]
Jun. 30, 2014
NextEra Energy Resources [Member]
Jun. 30, 2014
NextEra Energy Resources [Member]
Contract Group 1 [Member]
Jun. 30, 2014
FPL [Member]
Jun. 30, 2013
FPL [Member]
Jun. 30, 2014
FPL [Member]
Jun. 30, 2013
FPL [Member]
Jun. 30, 2014
FPL [Member]
Jea And Southern Subsidiaries Contract Range 1 [Member]
MW
Jun. 30, 2014
FPL [Member]
Jea And Southern Subsidiaries Contract Range 2 [Member]
MW
Jun. 30, 2014
FPL [Member]
Qualifying Facilities Contracts [Member]
MW
Jun. 30, 2014
FPL [Member]
Natural Gas, Coal, And Oil, Including Transportation And Storage [Member]
Jun. 30, 2014
FPL [Member]
Qualifying Facilities Capacity Payments [Member]
Jun. 30, 2014
FPL [Member]
Jea And Southern Subsidiaries Capacity Payments [Member]
Jun. 30, 2014
FPL [Member]
Natural Gas, Including Transportation And Storage, Contract Minimum Payments [Member]
Jun. 30, 2014
FPL [Member]
Coal Contract Minimum Payments [Member]
Jun. 30, 2014
Minimum [Member]
NextEra Energy Resources [Member]
Contract Group 1 [Member]
Jun. 30, 2014
Minimum [Member]
NextEra Energy Resources [Member]
Contract Group 2 [Member]
Jun. 30, 2014
Maximum [Member]
NextEra Energy Resources [Member]
Contract Group 1 [Member]
Jun. 30, 2014
Maximum [Member]
NextEra Energy Resources [Member]
Contract Group 2 [Member]
May 01, 2017
Scenario, Forecast [Member]
FPL [Member]
Sabal Trail and Florida Southeast Connection [Member]
Jun. 30, 2014
Sabal Trail Transmission, LLC [Member]
Corporate and Other [Member]
Jun. 30, 2014
Sabal Trail and Florida Southeast Connection [Member]
FPL [Member]
Natural Gas, Including Transportation And Storage, Contract Minimum Payments [Member]
Jun. 30, 2014
Sabal Trail Transmission, LLC [Member]
Natural Gas Expenditures [Member]
Corporate and Other [Member]
Long-term Commitment (Excluding Unconditional Purchase Obligation) [Abstract]                                              
Minimum annual purchase commitments (in megawatts)               1,330 375                            
Time period under contracts                                       25 years      
Minimum total purchase commitments (in megawatts)                   705                          
Expiration dates of purchase commitments               through 2015 through 2021 2024 through 2034 through 2036         August 2014 August 2014 2030 2033        
Equity Method Investment, Ownership Percentage                                         33.00%    
Long Term Purchase Commiment, Initial Quantity Per Day                                       400,000      
Long Term Purchase Commitment, Increased Volume Required                                       600,000      
Commitment amount included in capital expenditures     $ 3,000,000,000                                        
Required capacity and/or minimum payments [Abstract]                                              
Remainder of 2014 95,000,000 [1],[2] 1,430,000,000                   140,000,000 [3] 110,000,000 [3] 995,000,000 [4],[5] 35,000,000 [4]                
2015 250,000,000 [1],[2] 1,085,000,000                   290,000,000 [3] 195,000,000 [3] 1,045,000,000 [4],[5] 40,000,000 [4]                
2016 510,000,000 [1],[2] 480,000,000                   250,000,000 [3] 70,000,000 [3] 685,000,000 [4],[5] 20,000,000 [4]                
2017 50,000,000 [1],[2] 115,000,000                   255,000,000 [3] 50,000,000 [3] 745,000,000 [4],[5] 0 [4]             200,000,000  
2018 25,000,000 [1],[2] 120,000,000                   260,000,000 [3] 10,000,000 [3] 825,000,000 [4],[5] 0 [4]             295,000,000  
Thereafter 70,000,000 [1],[2] 475,000,000                   1,965,000,000 [3] 5,000,000 [3] 14,520,000,000 [4],[5] 0 [4]             8,535,000,000  
Capacity payments       123,000,000 119,000,000 246,000,000 244,000,000                                
Energy payments       75,000,000 86,000,000 132,000,000 109,000,000                                
Commitment to invest 50,000,000                                            
Joint Obligations of NEECH and NEER Included in NEER Amounts, remainder of current year 195,000,000                                            
Joint Obligations Of NEECH and NEER included NEER Amounts due in the second year 200,000,000                                            
commitment to invest in pipeline                                             $ 900,000,000
[1] Excludes approximately $195 million and $200 million in 2014 and 2015, respectively, of joint obligations of NEECH and NEER which are included in the NEER amounts above.
[2] Includes an approximately $50 million commitment to invest in clean power and technology businesses through 2021.
[3] Capacity charges under these contracts, substantially all of which are recoverable through the capacity cost recovery clause, totaled approximately $123 million and $119 million for the three months ended June 30, 2014 and 2013, respectively, and approximately $246 million and $244 million for the six months ended June 30, 2014 and 2013, respectively. Energy charges under these contracts, which are recoverable through the fuel clause, totaled approximately $75 million and $86 million for the three months ended June 30, 2014 and 2013, respectively
[4] Recoverable through the fuel clause.
[5] Includes approximately $200 million, $295 million and $8,535 million in 2017, 2018 and thereafter, respectively, of firm commitments, subject to certain conditions as noted above, related to the natural gas transportation agreements with Sabal Trail and Florida Southeast Connection.