XML 118 R38.htm IDEA: XBRL DOCUMENT v2.4.0.6
Commitments and Contingencies (Tables)
12 Months Ended
Dec. 31, 2012
Commitments and Contingencies [Abstract]  
Schedule of Planned Capital Expenditures
At December 31, 2012, estimated capital expenditures for 2013 through 2017 were as follows:

 
2013
 
2014
 
2015
 
2016
 
2017
 
Total
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Generation:(a)
 
 
 
 
 
 
 
 
 
 
 
New(b)(c)
$
915

 
$
760

 
$
295

 
$
130

 
$

 
$
2,100

Existing
645

 
710

 
675

 
580

 
555

 
3,165

Transmission and distribution
745

 
795

 
745

 
770

 
795

 
3,850

Nuclear fuel
125

 
175

 
245

 
245

 
260

 
1,050

General and other
155

 
145

 
105

 
125

 
120

 
650

Total
$
2,585

 
$
2,585

 
$
2,065

 
$
1,850

 
$
1,730

 
$
10,815

NEER:
 

 
 

 
 

 
 

 
 

 
 

Wind(d)
$
385

 
$
45

 
$
5

 
$
5

 
$
5

 
$
445

Solar(e)
830

 
175

 
5

 

 

 
1,010

Nuclear(f)
280

 
310

 
310

 
330

 
280

 
1,510

Other(g)
310

 
45

 
115

 
50

 
50

 
570

Total
$
1,805

 
$
575

 
$
435

 
$
385

 
$
335

 
$
3,535

Corporate and Other(h)
$
175

 
$
75

 
$
70

 
$
70

 
$
70

 
$
460

______________________
(a)
Includes AFUDC of approximately $85 million, $52 million, $47 million and $27 million for 2013 through 2016, respectively.
(b)
Includes land, generating structures, transmission interconnection and integration and licensing.
(c)
Consists of projects that have received FPSC approval.  Includes pre-construction costs and carrying charges (equal to a fixed pretax AFUDC rate) on construction costs recoverable through the capacity clause of approximately $42 million and $12 million in 2013 and 2014, respectively.  Excludes capital expenditures for the construction costs for the two additional nuclear units at FPL's Turkey Point site beyond what is required to receive an NRC license for each unit.  
(d)
Consists of capital expenditures for new wind projects and related transmission totaling approximately 300 mw, including approximately 125 mw in Canada, that have received applicable internal approvals.  Excludes new Canadian wind projects requiring internal approvals with generation totaling approximately 470 mw in 2014 and 2015, with an estimated cost of approximately $1.3 billion to $1.5 billion.
(e)
Consists of capital expenditures for new solar projects and related transmission totaling 645 mw that have received applicable internal approvals, including equity contributions associated with a 50% equity investment in a 550 mw solar project.  Excludes solar projects requiring internal approvals with generation totaling 250 mw with an estimated cost of approximately $600 million to $800 million.
(f)
Includes nuclear fuel.
(g)
Consists of capital expenditures that have received applicable internal approvals. 
(h)
Consists of capital expenditures that have received applicable internal approvals and includes AFUDC related to Lone Star of approximately $21 million in 2013.
Required Capacity and/or Minimum Payments
The required capacity and/or minimum payments under the contracts discussed above as of December 31, 2012 were estimated as follows:

 
2013
 
2014
 
2015
 
2016
 
2017
 
Thereafter
 
(millions)
FPL:
 
 
 
 
 
 
 
 
 
 
 
Capacity charges:(a)
 
 
 
 
 
 
 
 
 
 
 
Qualifying facilities
$
270

 
$
275

 
$
280

 
$
245

 
$
250

 
$
2,165

JEA and Southern subsidiaries
$
230

 
$
220

 
$
195

 
$
70

 
$
40

 
$
115

Minimum charges, at projected prices:
 
 
 
 
 
 
 
 
 
 
 
Natural gas, including transportation and storage(b)
$
1,995

 
$
1,310

 
$
570

 
$
535

 
$
530

 
$
6,405

Coal(b)
$
95

 
$
35

 
$
5

 
$
5

 
$

 
$

NEER
$
860

 
$
325

 
$
95

 
$
110

 
$
65

 
$
580

Corporate and Other(c)
$
45

 
$
10

 
$
15

 
$
10

 
$
10

 
$
10

______________________
(a)
Capacity charges under these contracts, substantially all of which are recoverable through the capacity clause, totaled approximately $523 million, $511 million and $537 million for the years ended December 31, 2012, 2011 and 2010, respectively.  Energy charges under these contracts, which are recoverable through the fuel clause, totaled approximately $276 million, $403 million and $434 million for the years ended December 31, 2012, 2011 and 2010, respectively.
(b)
Recoverable through the fuel clause.
(c)
Includes an approximately $68 million commitment to invest in clean power and technology businesses through 2021.