Commitments and Contingencies, Planned Capital Expenditures (Details) (USD $)
In Millions, unless otherwise specified
9 Months Ended
Sep. 30, 2012
MW
FPL [Member]
 
Planned Capital Expenditures [Line Items]  
2012 $ 1,020
2013 2,420
2014 2,440
2015 1,830
2016 1,595
Total 9,305
FPL [Member] | New Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 500 [1],[2],[3]
2013 770 [1],[2],[3]
2014 770 [1],[2],[3]
2015 295 [1],[2],[3]
2016 120 [1],[2],[3]
Total 2,455 [1],[2],[3]
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 2012 24
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 2013 42
Pre-construction costs and carrying charges (equal to a pretax AFUDC rate) - 2014 12
FPL [Member] | Existing Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 190 [1]
2013 645 [1]
2014 655 [1]
2015 550 [1]
2016 440 [1]
Total 2,480 [1]
FPL [Member] | Transmission And Distribution Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 215
2013 690
2014 690
2015 660
2016 705
Total 2,960
FPL [Member] | Nuclear Fuel Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 70
2013 125
2014 205
2015 245
2016 245
Total 890
FPL [Member] | General And Other Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 45
2013 190
2014 120
2015 80
2016 85
Total 520
FPL [Member] | Generation Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
Allowance for funds used during construction (AFUDC) - 2012 24
Allowance for funds used during construction (AFUDC) - 2013 82
Allowance for funds used during construction (AFUDC) - 2014 53
Allowance for funds used during construction (AFUDC) - 2015 48
Allowance for funds used during construction (AFUDC) - 2016 27
NextEra Energy Resources [Member]
 
Planned Capital Expenditures [Line Items]  
2012 1,310
2013 1,470
2014 585
2015 430
2016 390
Total 4,185
NextEra Energy Resources [Member] | Nuclear Fuel Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 95 [4]
2013 315 [4]
2014 280 [4]
2015 285 [4]
2016 325 [4]
Total 1,300 [4]
NextEra Energy Resources [Member] | Wind Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 740 [5]
2013 285 [5]
2014 25 [5]
2015 5 [5]
2016 5 [5]
Total 1,060 [5]
Planned New Wind Generation To Be Added over 5 Years 1,500
Planned New Canadian Wind With Internal Approvals 150
Planned New Canadian Wind Generation Requiring Internal Approvals MW 470
Expected Cost of New Wind Projects Requiring Internal Approvals - Low End of Range 1,300
Expected Costs of New Wind Projects Requiring Internal Approvals - High End of Range 1,500
NextEra Energy Resources [Member] | Solar Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 390 [6]
2013 670 [6]
2014 160 [6]
2015 5 [6]
2016 0 [6]
Total 1,225 [6]
Planned new solar generation over 5 year period (in megawatts) 625
Planned New Solar Capacity of Equity Method Investment 550
Planned new solar capacity of projects requiring internal approvals 270
Expected cost of new solar projects requiring internal approals - Low End of Range 600
Expected Costs of New Solar Projects Requiring Internal Approval - High End of Range 800
NextEra Energy Resources [Member] | Other Expenditures [Member]
 
Planned Capital Expenditures [Line Items]  
2012 85 [7]
2013 200 [7]
2014 120 [7]
2015 135 [7]
2016 60 [7]
Total 600 [7]
Corporate and Other [Member]
 
Planned Capital Expenditures [Line Items]  
2012 115 [8]
2013 115 [8]
2014 45 [8]
2015 45 [8]
2016 45 [8]
Total 365 [8]
Allowance for funds used during construction (AFUDC) - 2012 9
Allowance for funds used during construction (AFUDC) - 2013 $ 14
[1] Includes allowance for funds used during construction (AFUDC) of approximately $24 million, $82 million, $53 million, $48 million and $27 million in 2012 to 2016, respectively.
[2] Consists of projects that have received FPSC approval. Includes pre-construction costs and carrying charges (equal to a pretax AFUDC rate) on construction costs recoverable through the capacity clause of approximately $24 million, $42 million and $12 million in 2012 to 2014, respectively. Excludes capital expenditures for the construction costs for the two additional nuclear units at FPL's Turkey Point site beyond what is required to receive an NRC license for each unit.
[3] Includes land, generating structures, transmission interconnection and integration and licensing.
[4] Includes nuclear fuel.
[5] Consists of capital expenditures for planned new wind projects and related transmission totaling approximately 1,500 mw, including approximately 150 mw in Canada, that have received applicable internal approvals. Excludes new Canadian wind projects requiring internal approvals with generation totaling approximately 470 mw in 2014 and 2015, with an estimated cost of approximately $1.3 billion to $1.5 billion.
[6] Consists of capital expenditures for planned new solar projects and related transmission totaling 625 mw that have received applicable internal approvals, including equity contributions associated with a 50% equity method investment in a 550 mw solar project. Excludes solar projects requiring internal approvals with generation totaling 270 mw with an estimated cost of approximately $600 million to $800 million.
[7] Consists of capital expenditures that have received applicable internal approvals.
[8] Consists of capital expenditures that have received applicable internal approvals and includes AFUDC of approximately $9 million and $14 million in 2012 and 2013, respectively.