XML 105 R16.htm IDEA: XBRL DOCUMENT v3.19.3.a.u2
COMMITMENTS AND CONTINGENCIES
6 Months Ended
Sep. 30, 2019
Commitments and Contingencies Disclosure [Abstract]  
COMMITMENTS AND CONTINGENCIES
COMMITMENTS AND CONTINGENCIES
Aircraft Purchase Contracts — As shown in the table below, we have obligations to make additional capital expenditures over the next two fiscal years to purchase additional aircraft. As of September 30, 2019, we had three aircraft on order and no options to acquire additional aircraft.
 
 
Six Months Ending March 31, 2020
 
Fiscal Year Ending March 31,
 
 
 
 
2021
 
2022
 
2023
 
2024 and thereafter
 
Total
Commitments as of September 30, 2019:(1)(2)
 
 
 
 
 
 
 
 
 
 
 
 
Number of aircraft:
 
 
 
 
 
 
 
 
 
 
 
 
U.K. SAR (3)
 
2

 
1

 

 

 

 
3

 
 
 
 
 
 
 
 
 
 
 
 
 
Related commitment expenditures (in thousands)
 
 
 
 
 
 
 
 
 
 
 
 
U.K. SAR
 
$
28,747

 
$
14,374

 
$

 
$

 
$

 
$
43,121


_____________ 
(1) 
On July 25, 2019, we entered into an amendment to our agreement for the purchase of four AW189 U.K. SAR configuration helicopters. Pursuant to the amendment, the parties mutually agreed to postpone the delivery dates for three helicopters to the second half of fiscal year 2020 and the first quarter of fiscal year 2021. The postponement in deliveries resulted in deferral of approximately $14.4 million in capital expenditures scheduled for fiscal years 2020 into fiscal year 2021. The impact of this amendment is included in the table above. One of the four AW189s was purchased in August 2019.
(2) 
In October 2019, the Bankruptcy Court approved our agreement with Airbus Helicopters S.A.S. to reject our aircraft purchase contract for 22 large aircraft. This impact of this agreement is included in the table above.
(3) 
The three AW189 U.K. SAR configured aircraft on order were being leased as of March 31, 2019. One of the AW189s was purchased in October 2019.
We periodically purchase aircraft for which we have no orders.
Separation Programs — Beginning in March 2015, we initiated involuntary separation programs (“ISPs”) in certain regions. The expense related to the ISPs for the three and six months ended September 30, 2019 and 2018 is as follows (in thousands):
 
Three Months Ended
 September 30,
 
Six Months Ended
 September 30,
 
2019
 
2018
 
2019
 
2018
Direct cost
$
2,525

 
$
1,212

 
$
3,988

 
$
2,713

General and administrative
10

 
1,515

 
163

 
1,733

Total
$
2,535

 
$
2,727

 
$
4,151

 
$
4,446


Environmental Contingencies — The U.S. Environmental Protection Agency (the “EPA”), has in the past notified us that we are a potential responsible party (“PRP”) at three former waste disposal facilities that are on the National Priorities List of contaminated sites. Under the federal Comprehensive Environmental Response, Compensation and Liability Act, also known as the Superfund law, persons who are identified as PRPs may be subject to strict, joint and several liability for the costs of cleaning up environmental contamination resulting from releases of hazardous substances at National Priorities List sites. Although we have not yet obtained a formal release of liability from the EPA with respect to any of the sites, we believe that our potential liability in connection with the sites is not likely to have a material adverse effect on our business, financial condition or results of operations.
Other Purchase Obligations — As of September 30, 2019, we had $28.3 million of other purchase obligations representing unfilled purchase orders for aircraft parts and non-cancelable power-by-the-hour maintenance commitments.
Sikorsky Lawsuit — On January 8, 2019, we filed suit in the District Court of Harris County, Texas against Sikorsky Aircraft Corporation (“Sikorsky”) for breach of contract, unjust enrichment and conversion as a result of Sikorsky terminating a sales agreement after we sought to delay delivery of a helicopter and retaining our $11.7 million deposit as liquidated damages. We are seeking a ruling that Sikorsky be required to return the deposit and provide an accurate calculation of its damages under the sales agreement. Bristow recently removed the claim to the Southern District of Texas bankruptcy court based on Sikorsky’s decision to file a claim in bankruptcy related to this case. We expect a resolution in the next six to nine months.
Other Matters Although infrequent, aircraft accidents have occurred in the past, and the related losses and liability claims have been covered by insurance subject to deductible, self-insured retention and loss sensitive factors.
On November 6, 2017, the Huntington National Bank (“Huntington”) filed suit against the Company and Bristow U.S. LLC in the U.S. District Court for the Southern District of New York (the “Southern District of New York Court”). Huntington alleges violation of an addendum of a lease agreement for failure to arrange for the enrollment of the aircraft engines in a maintenance agreement and seeks approximately $2.5 million in damages. We submitted a counterclaim for approximately $100,000 of costs related to storage, maintenance and insurance of the aircraft following the expiration of the lease. On March 1, 2019, the Southern District of New York Court denied Huntington’s motion for summary judgment. We initiated discovery; however, on May 16, 2019, the proceedings were stayed as a result of the Chapter 11 Cases. Huntington filed a claim in the bankruptcy proceedings for the damages alleged in its initial lawsuit and for damages allegedly incurred as a result of Bristow returning a second leased aircraft. The Company, Bristow U.S. LLC, and Huntington entered into a Settlement Agreement on October 17, 2019 that provides a framework for resolution of Huntington’s claims with respect to both leased aircraft.  The Bankruptcy Court approved the settlement on October 23, 2019.
Two purported class action complaints, Kokareva v. Bristow Group Inc., Case No. 4:19-cv-0509 and Lilienfield v. Bristow Group Inc., Case No. 4:19-cv-1064, were filed in the U.S. District Court for the Southern District of Texas (the “Southern District of Texas Court”) on February 14, 2019 and March 21, 2019, respectively. The complaints, which also name Jonathan E. Baliff and L. Don Miller as defendants, allege violations of Sections 10(b) and 20(a) of the Securities Exchange Act of 1934, as amended (the “Exchange Act”), arising out of the Company’s disclosures and alleged failure to make timely disclosure of inadequate monitoring control processes related to non-financial covenants within certain of its secured financing and lease agreements. On May 17, 2019, the Southern District of Texas Court appointed BRS Investor Group as Lead Plaintiff and consolidated both actions under Kokareva v. Bristow Group Inc., Case No. 4:19-cv-0509. When the Company filed the Chapter 11 Cases on May 11, 2019, the litigation against the Company was automatically stayed. When the Company emerged from bankruptcy, all the claims against the Company were released, but the case is still proceeding against the individual defendants. Plaintiffs filed a Consolidated Amended Complaint on November 4, 2019, and defendants have until January 3, 2020 to file a response. The defendants believe that the claims are without merit and intend to vigorously defend against them.
On June 7, 2019, Marilyn DeVault filed a Stockholder Derivative Complaint against Thomas N. Amonett, Gaurdie Banister Jr., Ian A. Godden, Lori A. Gobillot, A. William Higgins, Thomas C. Knudson, Biggs C. Porter, Jonathan E. Baliff, Stephen A. King, Matthew Masters, David C. Gompert, Bruce H. Stover, L. Don Miller, and Brian J. Allman (the “Derivative Defendants”) in the United States District Court for the District of Delaware. The complaint alleges breaches of fiduciary duties and violations of Section 10(b) of the Exchange Act arising out of Company disclosures and failing to have adequate monitoring control processes related to non-financial covenants within certain of our secured financing and lease agreements. The complaint also alleges waste of corporate assets, gross mismanagement, and unjust enrichment. On July 19, 2019, the parties submitted a Joint Stipulation to stay the case pending the resolution of any motion to dismiss filed in the actions in the Southern District of Texas Court. The Derivative Defendants believe that the claims are without merit and intend to vigorously defend against them.
We operate in jurisdictions internationally where we are subject to risks that include government action to obtain additional tax revenue. In a number of these jurisdictions, political unrest, the lack of well-developed legal systems and legislation that is not clear enough in its wording to determine the ultimate application, can make it difficult to determine whether legislation may impact our earnings until such time as a clear court or other ruling exists. We operate in jurisdictions currently where amounts may be due to governmental bodies that we are not currently recording liabilities for as it is unclear how broad or narrow legislation may ultimately be interpreted. We believe that payment of amounts in these instances is not probable at this time, but is reasonably possible.
We are a defendant in certain claims and litigation arising out of operations in the normal course of business. In the opinion of management, uninsured losses, if any, will not be material to our financial position, results of operations or cash flows.