XML 23 R73.htm IDEA: XBRL DOCUMENT v3.19.3
Environmental Matters - Environmental Sites (Details)
$ in Thousands
1 Months Ended 9 Months Ended
Jul. 31, 2017
USD ($)
Jan. 31, 2017
USD ($)
May 31, 2012
USD ($)
Sep. 30, 2019
USD ($)
party
property
Dec. 31, 2018
USD ($)
Sep. 30, 2018
USD ($)
Site Contingency [Line Items]            
Current Liabilities       $ 22,403 $ 33,112 $ 18,746
Non-Current Liabilities       96,662 95,636 97,781
Gasco/Siltronic Sediments            
Site Contingency [Line Items]            
Current Liabilities       5,976 5,117 2,471
Non-Current Liabilities       43,861 44,351 44,410
Site Contingency, Environmental Remediation Costs Recognized       49,800    
Gasco/Siltronic Sediments | Minimum [Member]            
Site Contingency [Line Items]            
Environmental Exit Costs, Anticipated Cost     $ 49,800      
Gasco/Siltronic Sediments | Maximum [Member]            
Site Contingency [Line Items]            
Environmental Exit Costs, Anticipated Cost     $ 350,000      
Portland Harbor Other [Member]            
Site Contingency [Line Items]            
Current Liabilities       2,211 2,600 1,392
Non-Current Liabilities       5,331 6,273 3,540
Gasco/Siltronic Upland [Member]            
Site Contingency [Line Items]            
Current Liabilities       8,202 13,983 8,847
Non-Current Liabilities       42,267 44,830 44,310
Central Service Center [Member]            
Site Contingency [Line Items]            
Current Liabilities       5 10 25
Non-Current Liabilities       0 0 0
Front Street [Member]            
Site Contingency [Line Items]            
Current Liabilities       6,009 11,402 6,011
Non-Current Liabilities       5,024 3 5,342
Undiscounted environmental remediation expense $ 10,500          
Additional studies and design costs       500    
Oregon Steel Mills [Member]            
Site Contingency [Line Items]            
Current Liabilities       0 0 0
Non-Current Liabilities       $ 179 $ 179 $ 179
Portland Harbor [Member]            
Site Contingency [Line Items]            
Number of potentially responsible parties (more than) | party       100    
EPA final feasibility study and proposed remediation plan, clean-up costs, portland harbor   $ 1,050,000        
Number of remediation projects | property       2    
Portland Harbor [Member] | Minimum [Member]            
Site Contingency [Line Items]            
Percentage of clean-up costs   (30.00%)        
Portland Harbor [Member] | Maximum [Member]            
Site Contingency [Line Items]            
Percentage of clean-up costs   50.00%        
Yakama Nation [Member] | Portland Harbor Other [Member]            
Site Contingency [Line Items]            
Trustee Council Members - Number of Claimants       1    
Site Contingency, Number of Other Third-Party Defendants         29  
NRD liability claim yakama nation         $ 300  
Number of Amended Complaints Filed       2