XML 38 R23.htm IDEA: XBRL DOCUMENT v3.19.1
Environmental Matters
3 Months Ended
Mar. 31, 2019
Environmental Remediation Obligations [Abstract]  
Environmental Matters
ENVIRONMENTAL MATTERS

NW Natural owns, or previously owned, properties that may require environmental remediation or action. The range of loss for environmental liabilities is estimated based on current remediation technology, enacted laws and regulations, industry experience gained at similar sites, and an assessment of the probable level of involvement and financial condition of other potentially responsible parties (PRPs). When amounts are prudently expended related to site remediation of those sites described herein, NW Natural has a recovery mechanism in place to collect 96.68% of remediation costs allocable to Oregon customers, and NW Natural is allowed to defer environmental remediation costs allocated to customers in Washington annually until they are reviewed for prudence at a subsequent proceeding.

These sites are subject to the remediation process prescribed by the Environmental Protection Agency (EPA) and the Oregon Department of Environmental Quality (ODEQ). The process begins with a remedial investigation (RI) to determine the nature and extent of contamination and then a risk assessment (RA) to establish whether the contamination at the site poses unacceptable risks to humans and the environment. Next, a feasibility study (FS) or an engineering evaluation/cost analysis (EE/CA) evaluates various remedial alternatives. It is at this point in the process when NW Natural is able to estimate a range of remediation costs and record a reasonable potential remediation liability, or make an adjustment to the existing liability. From this study, the regulatory agency selects a remedy and issues a Record of Decision (ROD). After a ROD is issued, NW Natural would seek to negotiate a consent decree or consent judgment for designing and implementing the remedy. NW Natural would have the ability to further refine estimates of remediation liabilities at that time.

Remediation may include treatment of contaminated media such as sediment, soil and groundwater, removal and disposal of media, institutional controls such as legal restrictions on future property use, or natural recovery. Following construction of the remedy, the EPA and ODEQ also have requirements for ongoing maintenance, monitoring and other post-remediation care that may continue for many years. Where appropriate and reasonably known, NW Natural will provide for these costs in the remediation liabilities described below.

Due to the numerous uncertainties surrounding the course of environmental remediation and the preliminary nature of several site investigations, in some cases, NW Natural may not be able to reasonably estimate the high end of the range of possible loss. In those cases, the nature of the possible loss has been disclosed, as has the fact that the high end of the range cannot be reasonably estimated where a range of potential loss is available. Unless there is an estimate within the range of possible losses that is more likely than other cost estimates within that range, NW Natural records the liability at the low end of this range. It is likely changes in these estimates and ranges will occur throughout the remediation process for each of these sites due to the continued evaluation and clarification concerning responsibility, the complexity of environmental laws and regulations and the determination by regulators of remediation alternatives. In addition to remediation costs, NW Natural could also be subject to Natural Resource Damages (NRD) claims. NW Natural will assess the likelihood and probability of each claim and recognize a liability if deemed appropriate. Refer to "Other Portland Harbor" below.    

Environmental Sites
The following table summarizes information regarding liabilities related to environmental sites, which are recorded in other current liabilities and other noncurrent liabilities in NW Natural's balance sheet:
 
 
Current Liabilities
 
Non-Current Liabilities
 
 
March 31,
 
December 31,
 
March 31,
 
December 31,
In thousands
 
2019
 
2018
 
2018
 
2019
 
2018
 
2018
Portland Harbor site:
 
 
 
 
 
 
 
 
 
 
 
 
Gasco/Siltronic Sediments
 
$
4,595

 
$
2,797

 
$
5,117

 
$
44,427

 
$
45,015

 
$
44,351

Other Portland Harbor
 
2,299

 
1,769

 
2,600

 
5,958

 
3,928

 
6,273

Gasco/Siltronic Upland site
 
11,951

 
11,408

 
13,983

 
43,800

 
46,769

 
44,830

Central Service Center site
 
10

 
25

 
10

 

 

 

Front Street site
 
11,288

 
764

 
11,402

 

 
10,720

 
3

Oregon Steel Mills
 

 

 

 
179

 
179

 
179

Total
 
$
30,143


$
16,763

 
$
33,112

 
$
94,364

 
$
106,611

 
$
95,636



PORTLAND HARBOR SITE. The Portland Harbor is an EPA listed Superfund site that is approximately 10 miles long on the Willamette River and is adjacent to NW Natural's Gasco uplands site. NW Natural is one of over one hundred PRPs to the Superfund site. In January 2017, the EPA issued its Record of Decision, which selects the remedy for the clean-up of the Portland Harbor site (Portland Harbor ROD). The Portland Harbor ROD estimates the present value total cost at approximately $1.05 billion with an accuracy between -30% and +50% of actual costs.

NW Natural's potential liability is a portion of the costs of the remedy for the entire Portland Harbor Superfund site. The cost of that remedy is expected to be allocated among more than 100 PRPs. In addition, NW Natural is actively pursuing clarification and flexibility under the ROD in order to better understand its obligation under the clean-up. NW Natural is also participating in a non-binding allocation process with the other PRPs in an effort to resolve its potential liability. The Portland Harbor ROD does not provide any additional clarification around allocation of costs among PRPs and, as a result of issuance of the Portland Harbor ROD, NW Natural has not modified any of the recorded liabilities at this time.

NW Natural manages the liability related to the Superfund site as two distinct remediation projects: the Gasco/Siltronic Sediments and Other Portland Harbor projects.

Gasco/Siltronic Sediments. In 2009, NW Natural and Siltronic Corporation entered into a separate Administrative Order on Consent with the EPA to evaluate and design specific remedies for sediments adjacent to the Gasco uplands and Siltronic uplands sites. NW Natural submitted a draft EE/CA to the EPA in May 2012 to provide the estimated cost of potential remedial alternatives for this site. At this time, the estimated costs for the various sediment remedy alternatives in the draft EE/CA for the additional studies and design work needed before the cleanup can occur, and for regulatory oversight throughout the clean-up range from $49.0 million to $350 million. NW Natural has recorded a liability of $49.0 million for the sediment clean-up, which reflects the low end of the range. At this time, NW Natural believes sediments at this site represent the largest portion of its liability related to the Portland Harbor site discussed above. 

Other Portland Harbor. While we believe liabilities associated with the Gasco/Siltronic sediments site represent NW Natural's largest exposure, there are other potential exposures associated with the Portland Harbor ROD, including NRD costs and harborwide clean-up costs (including downstream petroleum contamination), for which allocations among the PRPs have not yet been determined. 

NW Natural and other parties have signed a cooperative agreement with the Portland Harbor Natural Resource Trustee council to participate in a phased NRD assessment to estimate liabilities to support an early restoration-based settlement of NRD claims. One member of this Trustee council, the Yakama Nation, withdrew from the council in 2009, and in 2017, filed suit against NW Natural and 29 other parties seeking remedial costs and NRD assessment costs associated with the Portland Harbor site, set forth in the complaint. The complaint seeks recovery of alleged costs totaling $0.3 million in connection with the selection of a remedial action for the Portland Harbor site as well as declaratory judgment for unspecified future remedial action costs and for costs to assess the injury, loss or destruction of natural resources resulting from the release of hazardous substances at and from the Portland Harbor site. The Yakama Nation has filed two amended complaints addressing certain pleading defects and dismissing the State of Oregon. The Magistrate Judge has recommended granting NW Natural and certain other defendants' motion to stay the case. NW Natural has recorded a liability for NRD claims which is at the low end of the range of the potential liability; the high end of the range cannot be reasonably estimated at this time. The NRD liability is not included in the aforementioned range of costs provided in the Portland Harbor ROD.

GASCO UPLANDS SITE. A predecessor of NW Natural, Portland Gas and Coke Company, owned a former gas manufacturing plant that was closed in 1958 (Gasco site) and is adjacent to the Portland Harbor site described above. The Gasco site has been under investigation by NW Natural for environmental contamination under the ODEQ Voluntary Clean-Up Program (VCP). It is not included in the range of remedial costs for the Portland Harbor site noted above. The Gasco site is managed in two parts, the uplands portion and the groundwater source control action.

NW Natural submitted a revised Remedial Investigation Report for the uplands to ODEQ in May 2007. In March 2015, ODEQ approved the RA, enabling commencement of work on the FS in 2016. NW Natural has recognized a liability for the remediation of the uplands portion of the site which is at the low end of the range of potential liability; the high end of the range cannot be reasonably estimated at this time.

In October 2016, ODEQ and NW Natural agreed to amend their VCP agreement to incorporate a portion of the Siltronic property adjacent to the Gasco site formerly owned by Portland Gas & Coke between 1939 and 1960 into the Gasco RA and FS, excluding the uplands for Siltronic. Previously, NW Natural was conducting an investigation of manufactured gas plant constituents on the entire Siltronic uplands for ODEQ. Siltronic will be working with ODEQ directly on environmental impacts to the remainder of its property.

In September 2013, NW Natural completed construction of a groundwater source control system, including a water treatment station, at the Gasco site. NW Natural has estimated the cost associated with the ongoing operation of the system and has recognized a liability which is at the low end of the range of potential cost. NW Natural cannot estimate the high end of the range at this time due to the uncertainty associated with the duration of running the water treatment station, which is highly dependent on the remedy determined for both the upland portion as well as the final remedy for Gasco sediment exposure.

OTHER SITES. In addition to those sites above, NW Natural has environmental exposures at three other sites: Central Service Center, Front Street and Oregon Steel Mills. NW Natural may have exposure at other sites that have not been identified at this time. Due to the uncertainty of the design of remediation, regulation, timing of the remediation and in the case of the Oregon Steel Mills site, pending litigation, liabilities for each of these sites have been recognized at their respective low end of the range of potential liability; the high end of the range could not be reasonably estimated at this time.
 
Central Service Center site. NW Natural is currently performing an environmental investigation of the property under ODEQ's Independent Cleanup Pathway. This site is on ODEQ's list of sites with confirmed releases of hazardous substances, and cleanup is necessary. 
 
Front Street site. The Front Street site was the former location of a gas manufacturing plant NW Natural operated (the former Portland Gas Manufacturing site, or PGM). At ODEQ’s request, NW Natural conducted a sediment and source control investigation and provided findings to ODEQ. In December 2015, an FS on the former Portland Gas Manufacturing site was completed. 

In July 2017, ODEQ issued the PGM ROD. The ROD specifies the selected remedy, which requires a combination of dredging, capping, treatment, and natural recovery. In addition, the selected remedy also requires institutional controls and long-term inspection and maintenance. NW Natural revised the liability in the second quarter of 2017 to incorporate the estimated undiscounted cost of approximately $10.5 million for the selected remedy. Further, NW Natural has recognized an additional liability of $0.8 million for additional studies and design costs as well as regulatory oversight throughout the clean-up. NW Natural plans to complete the remedial design in early 2019 and currently expects to construct the remedy during 2019.

Oregon Steel Mills site. Refer to the “Legal Proceedings,” below.
 
Site Remediation and Recovery Mechanism (SRRM)
NW Natural has an SRRM through which it tracks and has the ability to recover past deferred and future prudently incurred environmental remediation costs allocable to Oregon, subject to an earnings test, for those sites identified therein. See Note 17 in the 2018 Form 10-K for a description of the SRRM collection process.

The following table presents information regarding the total regulatory asset deferred:
 
 
March 31,
 
December 31,
In thousands
 
2019
 
2018
 
2018
Deferred costs and interest (1)
 
$
36,874

 
$
44,686

 
$
41,883

Accrued site liabilities (2)
 
124,133

 
122,962

 
128,369

Insurance proceeds and interest
 
(89,305
)
 
(95,100
)
 
(88,502
)
Total regulatory asset deferral(1)
 
$
71,702

 
$
72,548

 
$
81,750

Current regulatory assets(3)
 
5,090

 
5,818

 
5,601

Long-term regulatory assets(3)
 
66,612

 
66,730

 
76,149


(1)
Includes pre-review and post-review deferred costs, amounts currently in amortization, and interest, net of amounts collected from customers.
(2) 
Excludes 3.32% of the Front Street site liability, or $0.4 million in 2019 and $0.4 million in 2018, as the OPUC only allows recovery of 96.68% of costs for those sites allocable to Oregon, including those that historically served only Oregon customers.
(3) 
Environmental costs relate to specific sites approved for regulatory deferral by the OPUC and WUTC. In Oregon, NW Natural earns a carrying charge on cash amounts paid, whereas amounts accrued but not yet paid do not earn a carrying charge until expended. It also accrues a carrying charge on insurance proceeds for amounts owed to customers. In Washington, a carrying charge related to deferred amounts will be determined in a future proceeding. Current environmental costs represent remediation costs management expects to collect from customers in the next 12 months. Amounts included in this estimate are still subject to a prudence and earnings test review by the OPUC and do not include the $5.0 million tariff rider. The amounts allocable to Oregon are recoverable through NGD rates, subject to an earnings test.

ENVIRONMENTAL EARNINGS TEST. To the extent NW Natural earns at or below its authorized Return on Equity (ROE) as defined by the SRRM, remediation expenses and interest in excess of the $5.0 million tariff rider and $5.0 million insurance proceeds are recoverable through the SRRM. To the extent that NW Natural earns more than its authorized ROE in a year, it is required to cover environmental expenses and interest on expenses greater than the $10.0 million with those earnings that exceed its authorized ROE. At March 31, 2019 NW Natural reserved approximately $4.4 million related to this mechanism.

Under the 2015 Order, the OPUC stated they would revisit the deferral and amortization of future remediation expenses, as well as the treatment of remaining insurance proceeds three years from the original Order, or earlier if NW Natural gains greater certainty about future remediation costs, to consider whether adjustments to the mechanism may be appropriate. NW Natural filed an update with the OPUC in March 2018 and recommended no changes.

WASHINGTON DEFERRAL. Cost recovery and carrying charges on amounts deferred for costs associated with services provided to Washington customers will be determined in a future proceeding.

Legal Proceedings
Other than the matters discussed above, NW Holdings is not currently party to any direct claims or litigation, though in the future it may be subject to claims and litigation arising in the ordinary course of business.

NW Natural is subject to claims and litigation arising in the ordinary course of business. Although the final outcome of any of these legal proceedings cannot be predicted with certainty, including the matter described below, NW Natural and NW Holdings do not expect that the ultimate disposition of any of these matters will have a material effect on financial condition, results of operations or cash flows. See also Part II, Item 1, “Legal Proceedings".

OREGON STEEL MILLS SITE. See Note 17 in the 2018 Form 10-K.

For additional information regarding other commitments and contingencies, see Note 16 in the 2018 Form 10-K.