XML 42 R22.htm IDEA: XBRL DOCUMENT v3.6.0.2
Environmental Matters
12 Months Ended
Dec. 31, 2016
Environmental Remediation Obligations [Abstract]  
Environmental Matters [Text Block]
15. ENVIRONMENTAL MATTERS

We own, or previously owned, properties that may require environmental remediation or action. We estimate the range of loss for environmental liabilities based on current remediation technology, enacted laws and regulations, industry experience gained at similar sites and an assessment of the probable level of involvement and financial condition of other potentially responsible parties (PRPs). When amounts are prudently expended related to site remediation, we have a recovery mechanism in place to collect 96.68% of remediation costs from Oregon customers, and we are allowed to defer environmental remediation costs allocated to customers in Washington annually until they are reviewed for prudence at a subsequent proceeding.

Our sites are subject to the remediation process prescribed by the Environmental Protection Agency (EPA) and the Oregon Department of Environmental Quality (ODEQ). The process begins with a remedial investigation (RI) to determine the nature and extent of contamination and then a risk assessment (RA) to establish whether the contamination at the site poses unacceptable risks to humans and the environment. Next, a feasibility study (FS) or an engineering evaluation/cost analysis (EE/CA) evaluates various remedial alternatives. It is at this point in the process when we are able to estimate a range of remediation costs and record a reasonable potential remediation liability, or make an adjustment to our existing liability. From this study, the regulatory agency selects a remedy and issues a Record of Decision (ROD).
After a ROD is issued, we would seek to negotiate a consent decree or consent judgment for designing and implementing the remedy. We would have the ability to further refine estimates of remediation liabilities at that time.
Remediation may include treatment of contaminated media such as sediment, soil and groundwater, removal and disposal of media, institutional controls such as legal restrictions on future property use, or natural recovery. Following construction of the remedy, the EPA and ODEQ also have requirements for ongoing maintenance, monitoring and other post-remediation care that may continue for many years. Where appropriate and reasonably known, we will provide for these costs in our remediation liabilities described above.
Due to the numerous uncertainties surrounding the course of environmental remediation and the preliminary nature of several site investigations, in some cases, we may not be able to reasonably estimate the high end of the range of possible loss. In those cases, we have disclosed the nature of the possible loss and the fact that the high end of the range cannot be reasonably estimated where a range of potential loss is available. Unless there is an estimate within the range of possible losses that is more likely than other cost estimates within that range, we record the liability at the low end of this range. It is likely changes in these estimates and ranges will occur throughout the remediation process for each of these sites due to our continued evaluation and clarification concerning our responsibility, the complexity of environmental laws and regulations and the determination by regulators of remediation alternatives. In addition to remediation costs, we could also be subject to Natural Resource Damages (NRD) claims. We will assess the likelihood and probability of each claim and recognize a liability if deemed appropriate. We received a claim made by the Yakama Nation on January 31, 2017 for costs related to the selection of remedial action and certain declaratory relief regarding NRD. We are currently in the process of assessing the nature of the claim as well as the potential liability.     

Environmental Sites
The following table summarizes information regarding liabilities related to environmental sites, which are recorded in other current liabilities and other noncurrent liabilities on the balance sheet at December 31:
 
 
Current Liabilities
 
Non-Current Liabilities
In thousands
 
2016
 
2015
 
2016
 
2015
Portland Harbor site:
 
 
 
 
 
 
 
 
Gasco/Siltronic Sediments
 
$
869

 
$
2,229

 
$
43,972

 
$
42,641

Other Portland Harbor
 
1,970

 
1,972

 
4,148

 
5,073

Gasco/Siltronic Upland site
 
10,657

 
11,550

 
49,183

 
52,454

Central Service Center site
 
73

 
25

 

 

Front Street site
 
906

 
1,155

 
7,786

 
7,748

Oregon Steel Mills
 

 

 
179

 
179

Total
 
$
14,475

 
$
16,931

 
$
105,268

 
$
108,095



PORTLAND HARBOR SITE. The Portland Harbor is an EPA listed Superfund site that is approximately 10 miles long on the Willamette River and is adjacent to NW Natural's Gasco uplands sites. We are a PRP to the Superfund site and had previously joined with some of the other PRPs (the Lower Willamette Group or LWG) to develop a Portland Harbor Remedial Investigation/Feasibility Study (RI/FS), which we submitted to the EPA in 2012. In August 2015, the EPA issued its own Draft Feasibility Study (Draft FS) for comment. The EPA Draft FS provided a new range of remedial costs for the entire Portland Harbor Superfund Site, which includes the Gasco/Siltronic Sediment site, discussed below. The range of present value costs estimated by the EPA for various remedial alternatives for the entire Portland Harbor, as provided by the EPA's Draft FS, was $791 million to $2.45 billion. The range provided in the EPA's Draft FS was based on cost alternatives the EPA estimates to have an accuracy between -30% and +50% of actual costs, depending on the scope of work.

In June 2016, the EPA issued their Final Feasibility Study (Final FS) and proposed remediation plan (Proposed Plan) for the Portland Harbor Superfund site. The Proposed Plan presented the EPA's preferred clean-up alternative, which estimated the present value cost at approximately $746 million with an accuracy between -30% and +50% of actual costs. Along with several members of the LWG, we filed a dispute with the EPA over concerns that the EPA's Final FS contained factual and technical errors and was insufficient to support remedy selection. We also submitted comments to the Proposed Plan identifying technical errors and suggesting corrections to the Plan.

After reviewing all public comments, the EPA released its Record of Decision in January 2017, which outlines its determination of a cleanup approach for the Portland Harbor site (Portland Harbor ROD). The Portland Harbor ROD presents the EPA's decision on remedial alternatives and outlines the clean-up plan for the entire Portland Harbor. The Portland Harbor ROD estimates the present value cost at approximately $1.05 billion with an accuracy between -30% and +50% of actual costs.

While the Portland Harbor ROD provides a higher range of costs than the LWG's submission in 2012, our potential liability is still a portion of the costs of the remedy for the entire Portland Harbor Superfund site. The cost of that remedy is expected to be allocated among more than 100 PRPs. In addition, we are actively pursuing clarification and flexibility under the ROD in order to better understand our obligation under the clean-up. We are also participating in a non-binding allocation process in an effort to resolve our potential liability. The Portland Harbor ROD does not provide any additional clarification around allocation of costs.

We manage our liability related to the Superfund site as two distinct remediation projects, the Gasco/Siltronic Sediments and Other Portland Harbor projects.

Gasco/Siltronic Sediments. In 2009, NW Natural and Siltronic Corporation entered into a separate Administrative Order on Consent with the EPA to evaluate and design specific remedies for sediments adjacent to the Gasco uplands and Siltronic uplands sites. We submitted a draft EE/CA to the EPA in May 2012 to provide the estimated cost of potential remedial alternatives for this site. At this time, the estimated costs for the various sediment remedy alternatives in the draft EE/CA as well as costs for the additional studies and design work needed before the cleanup can occur, and for regulatory oversight throughout the clean-up range from $44.8 million to $350 million. We have recorded a liability of $44.8 million for the sediment clean-up, which reflects the low end of the range. At this time, we believe sediments at this site represent the largest portion of our liability related to the Portland Harbor site, discussed above. 

Other Portland Harbor. NW Natural incurs costs related to its membership in the LWG. NW Natural also incurs costs related to NRD from these sites. The Company and other parties have signed a cooperative agreement with the Portland Harbor Natural Resource Trustee council to participate in a phased NRD assessment to estimate liabilities to support an early restoration-based settlement of NRD claims. One member of this Trustee council, the Yakama Nation, withdrew from the council in June 2009, and in January 2017, filed suit against the Company and 31 other parties seeking remedial costs and NRD assessment costs associated with the Portland Harbor, as defined in the complaint by the Yakama Nation. The complaint seeks recovery of alleged costs totaling $0.3 million in connection with the selection of a remedial action for the Portland Harbor as well as declaratory judgment for unspecified future remedial action costs and for costs to assess the injury, loss or destruction of natural resources resulting from the release of hazardous substances at and from the Portland Harbor site. Generally, NRD claims may arise only after a remedy for clean-up has been settled. We have recorded a liability for these claims which is at the low end of the range of the potential liability; the high end of the range cannot be reasonably estimated at this time. This liability is not included in the range of costs provided in the Final FS or the Portland Harbor ROD.

GASCO UPLANDS SITE. A predecessor of NW Natural, Portland Gas and Coke Company, owned a former gas manufacturing plant that was closed in 1958 (Gasco site) and is adjacent to the Portland Harbor site described above. The Gasco site has been under investigation by us for environmental contamination under the ODEQ Voluntary Clean-Up Program (VCP). It is not included in the range of remedial costs for the Portland Harbor site noted above. We manage the Gasco site in two parts, the uplands portion and the groundwater source control action.

We submitted a revised Remedial Investigation Report for the uplands to ODEQ in May 2007. In March 2015, ODEQ approved the RA NW Natural submitted in 2010, enabling us to begin work on the FS in 2016. We have recognized a liability for the remediation of the uplands portion of the site which is at the low end of the range of potential liability; the high end of the range cannot be reasonably estimated at this time.

In October 2016, ODEQ and NW Natural agreed to amend their VCP agreement to incorporate a portion of the Siltronic property adjacent to the Gasco site formerly owned by Portland Gas & Coke between 1939 and 1960 into the Gasco RA and FS. Previously we were conducting an investigation of manufactured gas plant constituents on the entire Siltronic uplands for ODEQ. Siltronic will be working with ODEQ directly on environmental impacts to the remainder of its property.

In September 2013, we completed construction of a groundwater source control system, including a water treatment station, at the Gasco site. We are working with ODEQ on monitoring the effectiveness of the system and at this time it is unclear what, if any, additional actions ODEQ may require subsequent to the initial testing of the system or as part of the final remedy for the uplands portion of the Gasco site. We have estimated the cost associated with the ongoing operation of the system and have recognized a liability which is at the low end of the range of potential cost. We cannot estimate the high end of the range at this time due to the uncertainty associated with the duration of running the water treatment station, which is highly dependent on the remedy determined for both the upland portion as well as the final remedy for our Gasco sediment exposure.

Beginning November 1, 2013, capital asset costs of $19.0 million for the Gasco water treatment station were placed into rates with OPUC approval. The OPUC deemed these costs prudent. Beginning November 1, 2014, the OPUC approved the application of $2.5 million from insurance proceeds plus interest to reduce the total amount of Gasco capital costs to be recovered through rate base. A portion of these proceeds was noncash in 2014.

OTHER SITES. In addition to those sites above, we have environmental exposures at three other sites: Central Service Center, Front Street and Oregon Steel Mills. Due to the uncertainty of the design of remediation, regulation, timing of the remediation and in the case of the Oregon Steel Mills site, pending litigation, liabilities for each of these sites have been recognized at their respective low end of the range of potential liability; the high end of the range could not be reasonably estimated at this time.
 
Central Service Center site. We are currently performing an environmental investigation of the property under ODEQ's Independent Cleanup Pathway. This site is on ODEQ's list of sites with confirmed releases of hazardous substances, and cleanup is necessary. 
 
Front Street site. The Front Street site was the former location of a gas manufacturing plant we operated (the former Portland Gas Manufacturing site, or PGM).  At ODEQ’s request, we conducted a sediment and source control investigation and provided findings to ODEQ.  In December 2015, we completed a FS on the former Portland Gas Manufacturing site. The FS provided a range of $7.6 million to $12.9 million for remedial costs. We have recorded a liability at the low end of the range of possible loss as no alternative in the range is considered more likely than another. Further, we have recognized an additional liability of $1.1 million for additional studies and design costs as well as regulatory oversight throughout the clean-up that will be required to assist in ODEQ making a remedy selection and completing a design.

Oregon Steel Mills site. Refer to the “Legal Proceedings,” below.
 
Site Remediation and Recovery Mechanism (SRRM)
We have a SRRM through which we track and have the ability to recover past deferred and future prudently incurred environmental remediation costs allocable to Oregon, subject to an earnings test.

REGULATORY ACTIVITIES. In February 2015, the OPUC issued an Order addressing outstanding issues related to the SRRM (2015 Order), which required us to forego the collection of $15 million out of approximately $95 million in total environmental remediation expenses and associated carrying costs we had deferred through 2012 based on the OPUC's determination of how an earnings test should apply to amounts deferred from 2003 to 2012, with adjustments for other factors the OPUC deemed relevant. As a result, we recognized a $15 million non-cash charge in operations and maintenance expense in the first quarter of 2015. Also, as a result of the 2015 Order, we recognized $5.3 million pre-tax of interest income related to the equity earnings on our deferred environmental expenses.

In addition, the OPUC issued a subsequent Order regarding the SRRM implementation in January 2016 (2016 Order) in which the OPUC: (1) disallowed the recovery of $2.8 million of interest earned on the previously disallowed environmental expenditure amounts; (2) clarified the state allocation of 96.68% of environmental remediation costs for all environmental sites to Oregon; and (3) confirmed our treatment of $13.8 million of expenses put into the SRRM amortization account was correct and in compliance with prior OPUC orders. As a result of the 2016 Order, we recognized a $3.3 million non-cash charge in the first quarter of 2016, of which $2.8 million is reflected in other income and expense, net and $0.5 million is included in operations and maintenance expense.

COLLECTIONS FROM OREGON CUSTOMERS. The SRRM provides us with the ability to recover past deferred and future prudently incurred environmental remediation costs allocable to Oregon, subject to an earnings test. The SRRM created three classes of deferred environmental remediation expense:
Pre-review - This class of costs represents remediation spend that has not yet been deemed prudent by the OPUC. Carrying costs on these remediation expenses are recorded at our authorized cost of capital. The Company anticipates the prudence review for annual costs and approval of the earnings test prescribed by the OPUC to occur by the third quarter of the following year.
Post-review - This class of costs represents remediation spend that has been deemed prudent and allowed after applying the earnings test, but is not yet included in amortization. We earn a carrying cost on these amounts at a rate equal to the five-year treasury rate plus 100 basis points.
Amortization - This class of costs represents amounts included in current customer rates for collection and is generally calculated as one-fifth of the post-review deferred balance. We earn a carrying cost equal to the amortization rate determined annually by the OPUC, which approximates a short-term borrowing rate. We included $9.0 million of deferred remediation expense approved by the OPUC for collection during the 2016-2017 PGA year.

In addition to the collection amount noted above, the Order also provides for the annual collection of $5 million from Oregon customers through a tariff rider. As we collect amounts from customers, we recognize these collections as revenue and separately amortize our deferred regulatory asset balance through operating expense.

We received total environmental insurance proceeds of approximately $150 million as a result of settlements from our litigation that was dismissed in July 2014. Under the OPUC Order, one-third of the Oregon allocated proceeds were applied to costs deferred through 2012, and the remaining two-thirds will be applied to costs over the next 20 years. Annually, the Order provided for the application of $5 million of insurance proceeds plus interest against deferred remediation expense deemed prudent in the same annual period; annual amounts not utilized are carried forward to apply against future prudently incurred costs. We accrue interest on the insurance proceeds in the customer’s favor at a rate equal to the five-year treasury rate plus 100 basis points. As of December 31, 2016, we have applied $63.2 million of insurance proceeds to prudently incurred remediation costs.

The following table presents information regarding the total regulatory asset deferred as of December 31:
In thousands
 
2016
 
2015
Deferred costs and interest (1)
 
$
53,039

 
$
79,505

Accrued site liabilities (2)
 
119,443

 
125,026

Insurance proceeds and interest
 
(98,523
)
 
(118,677
)
Total regulatory asset deferral(1)
 
$
73,959

 
$
85,854

Current regulatory assets(3)
 
9,989

 
9,270

Long-term regulatory assets(3)
 
63,970

 
76,584


(1)
Includes pre-review and post-review deferred costs, amounts currently in amortization, and interest, net of amounts collected from customers.
(2) 
Excludes $0.3 million, or 3.32% of the Front Street site liability as the OPUC allows recovery of 96.68% of costs for all sites, including those that historically served only Oregon customers.
(3) 
Environmental costs relate to specific sites approved for regulatory deferral by the OPUC and WUTC. In Oregon, we earn a carrying charge on cash amounts paid, whereas amounts accrued but not yet paid do not earn a carrying charge until expended. We also accrue a carrying charge on insurance proceeds for amounts owed to customers. In Washington, a carrying charge related to deferred amounts will be determined in a future proceeding. Current environmental costs represent remediation costs management expects to collect from customers in the next 12 months. Amounts included in this estimate are still subject to a prudence and earnings test review by the OPUC and do not include the $5 million tariff rider. The amounts allocable to Oregon are recoverable through utility rates, subject to an earnings test.

ENVIRONMENTAL EARNINGS TEST. The 2015 Order directed us to implement an annual environmental earnings test for our prudently incurred remediation expense. Prudently incurred Oregon allocated annual remediation expense and interest in excess of the $5 million tariff rider and $5 million insurance proceeds application plus interest on the insurance proceeds are recoverable through the SRRM, to the extent the utility earns at or below our authorized Return On Equity (ROE). To the extent the utility earns more than its authorized ROE in a year, the utility is required to cover environmental expenses and interest on expenses greater than the $10 million (plus interest from insurance proceeds) with those earnings that exceed its authorized ROE.

Under the 2015 Order, the OPUC will revisit the deferral and amortization of future remediation expenses, as well as the treatment of remaining insurance proceeds three years from the original Order, or earlier if the Company gains greater certainty about its future remediation costs, to consider whether adjustments to the mechanism may be appropriate.

WASHINGTON DEFERRAL. In Washington, cost recovery and carrying charges on amounts deferred for costs associated with services provided to Washington customers will be determined in a future proceeding. Annually, we review all regulatory assets for recoverability or more often if circumstances warrant. If we should determine all or a portion of these regulatory assets no longer meet the criteria for continued application of regulatory accounting, then we would be required to write off the net unrecoverable balances against earnings in the period such a determination is made.

Legal Proceedings
NW Natural is subject to claims and litigation arising in the ordinary course of business. Although the final outcome of any of these legal proceedings cannot be predicted with certainty, including the matter described below, we do not expect that the ultimate disposition of any of these matters will have a material effect on our financial condition, results of operations or cash flows. See also Part I, Item 3, “Legal Proceedings.”

OREGON STEEL MILLS SITE. In 2004, NW Natural was served with a third-party complaint by the Port of Portland (the Port) in a Multnomah County Circuit Court case, Oregon Steel Mills, Inc. v. The Port of Portland. The Port alleges that in the 1940s and 1950s petroleum wastes generated by our predecessor, Portland Gas & Coke Company, and 10 other third-party defendants, were disposed of in a waste oil disposal facility operated by the United States or Shaver Transportation Company on property then owned by the Port and now owned by Evraz Oregon Steel Mills. The complaint seeks contribution for unspecified past remedial action costs incurred by the Port regarding the former waste oil disposal facility as well as a declaratory judgment allocating liability for future remedial action costs. No date has been set for trial. Although the final outcome of this proceeding cannot be predicted with certainty, we do not expect the ultimate disposition of this matter will have a material effect on our financial condition, results of operations or cash flows.

For additional information regarding other commitments and contingencies, see Note 14.