Rate Matters (Notes)
12 Months Ended
Dec. 31, 2017
Public Utilities, General Disclosures [Abstract]  
Rate Matters
Rate Matters

Tax Reform - Regulatory Proceedings

The specific impacts of the TCJA on retail customer rates are subject to regulatory approval. NSP-Wisconsin is in the process of quantifying the rate impacts of the TCJA and addressing these impacts in its open and recently concluded proceedings focused on retail base rate impacts for its utility subsidiaries.

In January 2018, the PSCW issued an order requiring public utilities to apply deferred accounting for the impacts of the TCJA. The PSCW has also requested that utilities provide responses to questions on tax reform and its impact on electric and natural gas revenue requirements. In February 2018, NSP-Wisconsin proposed levelizing upcoming rate cases, advancing infrastructure investments and buying down assets such as the regulatory asset for Ashland clean-up.

The MPSC has issued an order for utilities to use deferred accounting for the impacts of the TCJA. In February 2018, the MPSC issued an order directing each utility in Michigan to file an application for determination of the benefits related to the reduction in the corporate federal tax rate by March 30, 2018. The MPSC will address the remaining benefits related to the TCJA in the second quarter of 2018. NSP-Wisconsin plans to include the TCJA tax benefits as part of the electric rate case pending before the MPSC.

Recently Concluded Regulatory Proceedings — PSCW

Wisconsin 2018 Electric and Gas Rate Case In May 2017, NSP-Wisconsin filed a request with the PSCW to increase electric rates by $25 million, or 3.6 percent, and natural gas rates by $12 million, or 10.1 percent, effective Jan. 1, 2018. The rate filing was based on a 2018 forecast test year, a ROE of 10 percent, an equity ratio of 52.53 percent and a forecasted rate base of approximately $1.2 billion for the electric utility and $138 million for the natural gas utility.

In December 2017, the PSCW approved electric and natural gas rate increases of approximately $9 million, or 1.4 percent, and $10 million, or 8.3 percent, respectively, based on a 9.8 percent ROE and an equity ratio of 51.45 percent. New rates went into effect on Jan. 1, 2018.

Pending Regulatory Proceedings - MPSC

Michigan 2018 Electric Rate Case — In November 2017, NSP-Wisconsin filed a request with the MPSC to increase rates for electric service by $1 million, or 7.1 percent. The filing was based on a 2018 forecast test year, a 10.1 percent ROE, an equity ratio of 52.5 percent and a forecasted average rate base of approximately $43 million. The primary driver of the requested increase is continuing investment in transmission and distribution infrastructure. The filing also included a request for step increases in 2019 and 2020 related to electric distribution system investments in those years. In addition to the MPSC staff, intervenors in the case include the Michigan Attorney General and the Association of Businesses Advocating Tariff Equity, a voluntary association of large industrial businesses. Hearings are scheduled for April 2018. The parties have agreed to meet in March 2018 to discuss potential settlement of the case.

Recently Concluded Regulatory Proceedings — MPUC

Monticello Prudence Investigation — In 2013, NSP-Minnesota completed the Monticello LCM/EPU project. The multi-year project extended the life of the facility and increased the capacity from 600 to 671 MW in 2015. The Monticello LCM/EPU project expenditures were approximately $665 million. Total capitalized costs were approximately $748 million, which includes AFUDC. In 2008, project expenditures were initially estimated at approximately $320 million, excluding AFUDC.

In 2015, the MPUC voted to allow for full recovery, including a return, on $415 million of the total plant costs (inclusive of AFUDC), but only allow recovery of the remaining $333 million of costs with no return on this portion of the investment. As a result, Xcel Energy recorded a pre-tax loss of $129 million in the first quarter of 2015, after which the remaining book value of the Monticello project represented the present value of the estimated future cash flows. As NSP-Wisconsin shares in the costs of the Monticello plant through the Interchange Agreement with NSP-Minnesota, the MPUC decision also affects NSP-Wisconsin. NSP-Wisconsin’s portion of the $129 million pre-tax loss, recorded in the first quarter of 2015, was approximately $5 million.

Pending Regulatory Proceedings — FERC

MISO ROE Complaints/ROE Adder — In November 2013, a group of customers filed a complaint at the FERC against MISO TOs, including NSP-Minnesota and NSP-Wisconsin. The complaint argued for a reduction in the ROE in transmission formula rates in the MISO region from 12.38 percent to 9.15 percent, and the removal of ROE adders (including those for RTO membership), effective Nov. 12, 2013.

In December 2015, an ALJ recommended the FERC approve a base ROE of 10.32 percent for the MISO TOs. The ALJ found the existing 12.38 percent ROE to be unjust and unreasonable. The recommended 10.32 percent ROE applied a FERC ROE policy adopted in a June 2014 order (Opinion 531). The FERC approved the ALJ recommended 10.32 percent base ROE in an order issued in September 2016. This ROE would be applicable for Nov. 12, 2013 to Feb. 11, 2015, and prospectively from the date of the FERC order. The total prospective ROE would be 10.82 percent, including a 50 basis point adder for RTO membership. Various parties requested rehearing of the September 2016 order. The requests are pending FERC action.

In February 2015, a second complaint seeking to reduce the MISO ROE from 12.38 percent to 8.67 percent prior to any adder was filed with the FERC, resulting in a second period of potential refund from Feb. 12, 2015 to May 11, 2016. In June 2016, the ALJ recommended a ROE of 9.7 percent, applying the methodology adopted by the FERC in Opinion 531. In April 2017, the D.C. Circuit vacated and remanded Opinion 531. It is unclear how the D.C. Circuit’s opinion to vacate and remand Opinion 531 will affect the September 2016 FERC order or the timing and outcome of the second ROE complaint. In September 2017, certain MISO TOs (not including NSP-Minnesota and NSP-Wisconsin) filed a motion to dismiss the second ROE complaint. The motion to dismiss is pending FERC action.

As of Dec. 31, 2017, NSP-Minnesota has processed the refunds for the Nov. 12, 2013 to Feb. 11, 2015 complaint period based on the 10.32 percent ROE. NSP-Minnesota has also recognized a current refund liability consistent with the best estimate of the final ROE for the Feb. 12, 2015 to May 11, 2016 complaint period.