XML 48 R37.htm IDEA: XBRL DOCUMENT v3.7.0.1
Commitments and Contingencies, Environmental Contingencies - Site Contingencies (Details)
$ in Millions
6 Months Ended 12 Months Ended
Jun. 30, 2017
USD ($)
Site
Dec. 31, 2016
USD ($)
Ashland MGP Site    
Ashland Manufactured Gas Plant (MGP) Site [Abstract]    
Number of properties not owned included in superfund site | Site 2  
Current Cost Estimate for Site Remediation $ 160.0  
Estimated amount spent on cleanup 113.2  
Accrual for Environmental Loss Contingencies, Gross $ 46.8 $ 64.3
Approved amortization period for recovery of remediation costs in natural gas rates (in years) 10 years  
Carrying cost percentage to be applied to unamortized regulatory asset 3.00%  
Other MGP Sites [Member]    
Ashland Manufactured Gas Plant (MGP) Site [Abstract]    
Accrual for Environmental Loss Contingencies, Gross $ 0.1  
Number of identified MGP sites under current investigation and/or remediation in addition to those separately disclosed 1  
PSCW Proceeding - Gas Rate Case 2017 - Gas Rates 2017 [Member] | Ashland MGP Site    
Ashland Manufactured Gas Plant (MGP) Site [Abstract]    
Public Utilities, Approved annual recovery collected through base rates   $ 12.4
PSCW Proceeding - Gas Rate Case 2017 - Gas Rates 2018 [Member] | Ashland MGP Site    
Ashland Manufactured Gas Plant (MGP) Site [Abstract]    
Public Utilities, Requested annual recovery collected through base rates $ 18.1