XML 35 R22.htm IDEA: XBRL DOCUMENT v3.6.0.2
Commitments and Contingencies
12 Months Ended
Dec. 31, 2016
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
Commitments and Contingencies

Commitments

Fuel Contracts — NSP-Wisconsin has entered into various long-term commitments for the purchase and delivery of a significant portion of its current coal and natural gas requirements. These contracts expire in various years between 2017 and 2029. In addition, NSP-Wisconsin is required to pay additional amounts depending on actual quantities shipped under these agreements. As NSP-Wisconsin does not have an automatic electric fuel adjustment clause for Wisconsin retail customers, NSP-Wisconsin utilizes deferred accounting treatment for future rate recovery or refund when fuel costs differ from the amount included in rates by more than two percent on an annual basis, as determined by the PSCW after an opportunity for a hearing and an earnings test based on NSP-Wisconsin’s authorized ROE.

The estimated minimum purchases for NSP-Wisconsin under these contracts as of Dec. 31, 2016 are as follows:
(Millions of Dollars)
 
Coal
 
Natural gas
supply
 
Natural gas
storage and
transportation
2017
 
$
6.9

 
$
10.9

 
$
13.2

2018
 
2.5

 
0.3

 
12.3

2019
 
0.8

 
0.3

 
11.4

2020
 
0.8

 
0.3

 
9.1

2021
 
0.8

 
0.3

 
8.4

Thereafter
 
1.7

 
0.4

 
36.1

Total (a)
 
$
13.5

 
$
12.5

 
$
90.5


(a) 
Excludes additional amounts allocated to NSP-Wisconsin through intercompany charges.

Additional expenditures for fuel and natural gas storage and transportation will be required to meet expected future electric generation and natural gas needs.

Leases — NSP-Wisconsin leases a variety of equipment and facilities used in the normal course of business. These leases, primarily for office space, vehicles, aircraft and power-operated equipment, are accounted for as operating leases. Total expenses under operating lease obligations were approximately $1.2 million, $1.1 million and $1.3 million for 2016, 2015 and 2014, respectively.

Future commitments under operating leases are:
(Millions of Dollars)
 
 
2017
 
$
1.0

2018
 
1.0

2019
 
1.0

2020
 
0.9

2021
 
0.8

Thereafter
 
5.3

Total
 
$
10.0



Variable Interest Entities — The accounting guidance for consolidation of variable interest entities requires enterprises to consider the activities that most significantly impact an entity’s financial performance, and power to direct those activities, when determining whether an enterprise is a variable interest entity’s primary beneficiary.

NSP-Wisconsin has entered into limited partnerships for the construction and operation of affordable rental housing developments which qualify for low-income housing tax credits. NSP-Wisconsin has determined the low-income housing limited partnerships to be variable interest entities primarily due to contractual arrangements within each limited partnership that establish sharing of ongoing voting control and profits and losses that does not consistently align with the partners’ proportional equity ownership. These limited partnerships are designed to qualify for low-income housing tax credits, and NSP-Wisconsin generally receives a larger allocation of the tax credits than the general partners at inception of the arrangements. NSP-Wisconsin has determined that it has the power to direct the activities that most significantly impact these entities’ economic performance, and therefore NSP-Wisconsin consolidates these limited partnerships in its consolidated financial statements.

Equity financing for these entities has been provided by NSP-Wisconsin and the general partner of each limited partnership, and NSP-Wisconsin’s risk of loss is limited to its capital contributions, adjusted for any distributions and its share of undistributed profits and losses; no significant additional financial support has been, or is required to be provided to the limited partnerships by NSP-Wisconsin. Mortgage-backed debt typically comprises the majority of the financing at inception of each limited partnership and is paid over the life of the limited partnership arrangement. Obligations of the limited partnerships are generally secured by the housing properties of each limited partnership, and the creditors of each limited partnership have no significant recourse to NSP-Wisconsin or its subsidiaries. Likewise, the assets of the limited partnerships may only be used to settle obligations of the limited partnerships, and not those of NSP-Wisconsin or its subsidiaries.

Amounts reflected in NSP-Wisconsin’s consolidated balance sheets for low-income housing limited partnerships include the following:
(Thousands of Dollars)
 
Dec. 31, 2016
 
Dec. 31, 2015
Current assets
 
$
375

 
$
377

Property, plant and equipment, net
 
2,025

 
2,199

Other noncurrent assets
 
125

 
127

Total assets
 
$
2,525

 
$
2,703

 
 
 
 
 
Current liabilities
 
$
1,269

 
$
1,246

Mortgages and other long-term debt payable
 
486

 
537

Other noncurrent liabilities
 
54

 
51

Total liabilities
 
$
1,809

 
$
1,834



Joint Operating System The electric production and transmission system of NSP-Wisconsin is managed as an integrated system with that of NSP-Minnesota, jointly referred to as the NSP System. The electric production and transmission costs of the entire NSP System are shared by NSP-Minnesota and NSP-Wisconsin. A FERC approved agreement between the two companies, called the Interchange Agreement, provides for the sharing of all costs of generation and transmission facilities of the system, including capital costs. Such costs include current and potential obligations of NSP-Minnesota related to its nuclear generating facilities.

On Dec. 31, 2016, NSP-Minnesota’s public liability for claims resulting from any nuclear incident was limited to $13.4 billion under the Price-Anderson amendment to the Atomic Energy Act. NSP-Minnesota had secured $375 million of coverage for its public liability exposure with a pool of insurance companies. The remaining $13.0 billion of exposure was funded by the Secondary Financial Protection Program, available from assessments by the federal government in case of a nuclear accident. On Jan. 1, 2017, the available insurance limit was increased from $375 million to $450 million. This increase in limit occurs periodically and the Price-Anderson amendment to the Atomic Energy Act requires purchasing the full available limit. On Jan. 1, 2017 this $450 million limit was secured from the insurance pool. NSP-Minnesota is subject to assessments of up to $127.3 million per reactor per accident for each of its three licensed reactors, to be applied for public liability arising from a nuclear incident at any licensed nuclear facility in the United States. The maximum funding requirement is $19.0 million per reactor per incident during any one year. These maximum assessment amounts are both subject to inflation adjustment by the NRC and state premium taxes. The NRC’s last adjustment was effective September 2013.

NSP-Minnesota purchases insurance for property damage and site decontamination cleanup costs from Nuclear Electric Insurance Ltd. (NEIL). The coverage limits are $2.3 billion for each of NSP-Minnesota’s two nuclear plant sites. NEIL also provides business interruption insurance coverage, including the cost of replacement power obtained during certain prolonged accidental outages of nuclear generating units. Premiums are expensed over the policy term. All companies insured with NEIL are subject to retroactive premium adjustments if losses exceed accumulated reserve funds. Capital has been accumulated in the reserve funds of NEIL to the extent that NSP-Minnesota would have no exposure for retroactive premium assessments in case of a single incident under the business interruption and the property damage insurance coverage. However, in each calendar year, NSP-Minnesota could be subject to maximum assessments of approximately $19.8 million for business interruption insurance and $43.0 million for property damage insurance if losses exceed accumulated reserve funds.

Guarantees — NSP-Wisconsin provides a guarantee for payment of customer loans related to NSP-Wisconsin’s farm rewiring program. NSP-Wisconsin’s exposure under the guarantee is based upon the net liability under the agreement. The guarantee issued by NSP-Wisconsin limits the exposure of NSP-Wisconsin to a maximum amount stated in the guarantee. The guarantee contains no recourse provisions and requires no collateral.

The following table presents the guarantee issued and outstanding for NSP-Wisconsin:
(Millions of Dollars)
 
Guarantee
Amount
 
Current
Exposure
 
Term or
Expiration Date
 
Triggering
Event
Guarantee of customer loans for the Farm Rewiring Program(a)
 
$
1.0

 
$
0.1

 
2020
 
(b) 
(a) 
The term of this guarantee expires in 2020, which is the final scheduled repayment date for the loans. As of Dec. 31, 2016, no claims had been made by the lender.
(b) 
The debtor becomes the subject of bankruptcy or other insolvency proceedings.

Environmental Contingencies

NSP-Wisconsin has been or is currently involved with the cleanup of contamination from certain hazardous substances at several sites. In many situations, NSP-Wisconsin believes it will recover some portion of these costs through insurance claims. Additionally, where applicable, NSP-Wisconsin is pursuing, or intends to pursue, recovery from other PRPs and through the regulated rate process. New and changing federal and state environmental mandates can also create added financial liabilities for NSP-Wisconsin, which are normally recovered through the regulated rate process. To the extent any costs are not recovered through the options listed above, NSP-Wisconsin would be required to recognize an expense.

Site Remediation Various federal and state environmental laws impose liability, without regard to the legality of the original conduct, where hazardous substances or other regulated materials have been released to the environment. NSP-Wisconsin may sometimes pay all or a portion of the cost to remediate sites where past activities of NSP-Wisconsin or other parties have caused environmental contamination. Environmental contingencies could arise from various situations, including sites of former MGPs operated by NSP-Wisconsin, its predecessors, or other entities; and third-party sites, such as landfills, for which NSP-Wisconsin is alleged to be a PRP that sent wastes to that site.

MGP Sites

Ashland MGP Site — NSP-Wisconsin has been named a PRP for contamination at a site in Ashland, Wis. The Ashland/Northern States Power Lakefront Superfund Site (the Site) includes NSP-Wisconsin property, previously operated as a MGP facility (the Upper Bluff), and two other properties: an adjacent city lakeshore park area (Kreher Park); and an area of Lake Superior’s Chequamegon Bay adjoining the park.

In 2012, under a settlement agreement with the EPA, NSP-Wisconsin agreed to remediate the Phase I Project Area (which includes the Upper Bluff and Kreher Park areas of the Site). The current cost estimate for the cleanup of the Phase I Project Area is approximately $72.4 million, of which approximately $56.7 million has been spent.

NSP-Wisconsin performed a wet dredge pilot study in the summer of 2016 and demonstrated that a wet dredge remedy can meet the performance standards for remediation of the Sediments. As a result, the EPA authorized NSP-Wisconsin to extend the wet dredge pilot to additional areas of the Site. In January 2017, under a settlement agreement with the EPA, NSP-Wisconsin agreed to remediate the Phase II Project Area (the Sediments). The settlement agreement was lodged with the U.S. District Court for the Western District of Wisconsin (District Court) in January 2017, and a 30-day public comment period lapsed in February 2017. If the settlement is timely approved by the District Court, NSP-Wisconsin anticipates a full scale wet dredge remedy of the Sediments will be performed in 2017, with restoration activities concluding in 2018.

At Dec. 31, 2016 and 2015, NSP-Wisconsin had recorded a total liability of $64.3 million and $94.4 million, respectively, for the entire site.

NSP-Wisconsin has deferred the unrecovered portion of the estimated Site remediation costs as a regulatory asset. The PSCW has consistently authorized NSP-Wisconsin rate recovery for all remediation costs incurred at the Site. In 2012, the PSCW agreed to allow NSP-Wisconsin to pre-collect certain costs, to amortize costs over a ten-year period and to apply a three percent carrying cost to the unamortized regulatory asset. In April 2016, NSP-Wisconsin filed a limited natural gas rate case for recovery of additional expenses associated with remediating the Site. In December 2016, the PSCW issued a written order approving the requested increase in annual recovery of MGP clean-up costs from $7.6 million in 2016 to $12.4 million in 2017.

Other MGP Sites NSP-Wisconsin is currently involved in investigating and/or remediating several other MGP sites where regulated materials may have been deposited. NSP-Wisconsin has identified one site where former MGP activities may have resulted in site contamination and is under current investigation. At this MGP site, there are other parties that may have responsibility for some portion of any remediation. NSP-Wisconsin anticipates that the majority of the remediation at this site will continue through at least 2017. NSP-Wisconsin had accrued $0.1 million and $0.2 million for this site at Dec. 31, 2016 and 2015, respectively. There may be insurance recovery and/or recovery from other PRPs that will offset any costs incurred. NSP-Wisconsin anticipates that any amounts spent will be fully recovered from customers.

Environmental Requirements

Water and Waste
Asbestos Removal — Some of NSP-Wisconsin’s facilities contain asbestos. Most asbestos will remain undisturbed until the facilities that contain it are demolished or removed. NSP-Wisconsin has recorded an estimate for final removal of the asbestos as an ARO. It may be necessary to remove some asbestos to perform maintenance or make improvements to other equipment. The cost of removing asbestos as part of other work is not expected to be material and is recorded as incurred as operating expenses for maintenance projects, capital expenditures for construction projects or removal costs for demolition projects.

Federal Clean Water Act (CWA) Effluent Limitations Guidelines (ELG) — In 2015, the EPA issued a final ELG rule for power plants that use coal, natural gas, oil or nuclear materials as fuel and discharge treated effluent to surface waters as well as utility-owned landfills that receive coal combustion residuals. NSP-Wisconsin has reviewed the final rule and is in the process of evaluating whether the costs of compliance could have a material impact on the results of operations, financial position or cash flows. NSP-Wisconsin believes that compliance costs would be recoverable through regulatory mechanisms.

Federal CWA Section 316(b) Section 316(b) of the federal CWA requires the EPA to regulate cooling water intake structures to assure that these structures reflect the best technology available for minimizing adverse environmental impacts to aquatic species. The EPA published the final 316(b) rule in 2014. The rule prescribes technology for protecting fish that get stuck on plant intake screens (known as impingement) and describes a process for site-specific determinations by each state for sites that must protect the small aquatic organisms that pass through the intake screens into the plant cooling systems (known as entrainment). The timing of compliance with the requirements will vary from plant-to-plant since the new rule does not have a final compliance deadline. Many of the compliance requirements depend on site-specific determinations by state regulators; therefore, the exact cost is somewhat uncertain. NSP-Wisconsin believes at least two plants could be required by state regulators to make improvements to reduce entrainment. NSP-Wisconsin estimates the likely cost for complying with impingement requirements may be incurred between 2017 and 2027 and is approximately $4 million and anticipates these costs will be fully recoverable in rates.

Federal CWA Waters of the United States Rule — In June 2015, the EPA and the U.S. Army Corps of Engineers published a final rule that significantly expands the types of water bodies regulated under the CWA and broadens the scope of waters subject to federal jurisdiction. The expansion of the term “Waters of the U.S.” will subject more utility projects to federal CWA jurisdiction, thereby potentially delaying the siting of new generation projects, pipelines, transmission lines and distribution lines, as well as increasing project costs and expanding permitting and reporting requirements. In October 2015, the U.S. Court of Appeals for the Sixth Circuit issued a nationwide stay of the final rule and subsequently ruled that it, rather than the federal district courts, had jurisdiction over challenges to the rule.  In January 2017, the U.S. Supreme Court agreed to resolve the dispute as to which court should hear challenges to the rule. A ruling is expected by June 2017.

Air
GHG Emission Standard for Existing Sources (Clean Power Plan or CPP) — In 2015, a final rule was published by the EPA for GHG emission standards for existing power plants.  Under the rule, states were required to develop implementation plans by September 2016, with the possibility of an extension to September 2018, or submit to a federal plan for the state prepared by the EPA.  Among other things, the rule requires that state plans include enforceable measures to ensure emissions from existing power plants achieve the EPA’s state-specific interim (2022-2029) and final (2030 and thereafter) emission performance targets.  The CPP was challenged by multiple parties in the D.C. Circuit Court.  In January 2016, the D.C. Circuit Court denied requests to stay the effectiveness of the rule. In February 2016, the U.S. Supreme Court issued an order staying the final CPP rule. In September 2016, the D.C. Circuit Court heard oral arguments in the consolidated challenges to the CPP. The stay will remain in effect until the D.C. Circuit Court reaches its decision and the U.S. Supreme Court either declines to review the lower court’s decision or reaches a decision of its own. During the pendency of the stay, states are not required to submit implementation plans and the EPA will not enforce deadlines or issue a federal plan for any state. All states served by NSP-Wisconsin have suspended formal planning efforts.

NSP-Wisconsin has undertaken a number of initiatives that reduce GHG emissions and respond to state renewable and energy efficiency goals.  The CPP could require additional emission reductions in states in which NSP-Wisconsin operates.  If state plans do not provide credit for the investments NSP-Wisconsin has already made to reduce GHG emissions, or if they require additional initiatives or emission reductions, then their requirements would potentially impose additional substantial costs.  Until NSP-Wisconsin has more information about SIPs or the EPA finalizes its proposed federal plan for the states that do not develop related plans, NSP-Wisconsin cannot predict the costs of compliance with the final rule once it takes effect. NSP-Wisconsin believes compliance costs will be recoverable through regulatory mechanisms.  If NSP-Wisconsin’s regulators do not allow recovery of all or a part of the cost of capital investment or the O&M costs incurred to comply with the CPP or cost recovery is not provided in a timely manner, it could have a material impact on results of operations, financial position or cash flows.

CSAPR CSAPR addresses long range transport of PM and ozone by requiring reductions in SO2 and NOx from utilities in the eastern half of the United States, including Wisconsin, using an emissions trading program.

CSAPR was adopted to address interstate emissions impacting downwind states’ attainment of the 1997 ozone NAAQS and the 1997 and 2006 particulate NAAQS. As the EPA revises NAAQS, it will consider whether to make any further reductions to CSAPR emission budgets and whether to change which states are included in the emissions trading program. In December 2015, the EPA proposed adjustments to CSAPR emission budgets which address attainment of the more stringent 2008 ozone NAAQS. The EPA adopted a final rule in September 2016 for the ozone season emission budget for NOx which did not materially impact NSP-Wisconsin.

Revisions to the NAAQS for Ozone — In 2015, the EPA revised the NAAQS for ozone by lowering the eight-hour standard from 75 parts per billion (ppb) to 70 ppb. Current monitored air quality concentrations in areas of Wisconsin, where NSP-Wisconsin operates, are below the new standard. Therefore, NSP-Wisconsin does not expect a material impact on results of operations, financial position or cash flows.

Asset Retirement Obligations

Recorded AROs — AROs have been recorded for property related to the following: electric production (steam, other and hydro), electric distribution and transmission, natural gas distribution, and general property. The electric production obligations include asbestos, ash-containment facilities, storage tanks and control panels. The asbestos recognition associated with electric production includes certain specific plants. AROs also have been recorded for NSP-Wisconsin steam production related to ash-containment facilities such as bottom ash ponds, evaporation ponds and solid waste landfills.

NSP-Wisconsin has recognized an ARO for the retirement costs of natural gas mains and lines and for the removal of electric transmission and distribution equipment, which consists of many small potential obligations associated with PCBs, mineral oil, storage tanks, lithium batteries, mercury and street lighting lamps. The electric and common general AROs include small obligations primarily related to storage tanks.

In April 2015, the EPA published the final rule regulating the management and disposal of coal combustion byproducts (e.g., coal ash) as a nonhazardous waste to the Federal Register. The rule became effective in October 2015. No cash flow revisions were necessary, as a result of the final rule, as of Dec. 31, 2015.

A reconciliation of NSP-Wisconsin’s AROs for the years ended Dec. 31, 2016 and 2015 is as follows:
(Thousands of Dollars)
 
Beginning Balance
Jan. 1, 2016
 
Liabilities Settled
 
Accretion
 
Cash Flow Revisions
 
Ending Balance
   Dec. 31, 2016 (a)
Electric plant
 
 
 
 
 
 
 
 
 
 
Steam production asbestos
 
$
2,145

 
$

 
$
49

 
$

 
$
2,194

Steam production ash containment
 
617

 

 
18

 
(183
)
 
452

Electric distribution
 
72

 

 
3

 
(43
)
 
32

Other
 
391

 
(29
)
 
14

 

 
376

Natural gas plant
 
 
 
 
 
 
 
 
 
 
Gas distribution
 
6,367

 

 
256

 
1,670

 
8,293

Common and other property
 
 
 
 
 
 
 
 
 
 
Common miscellaneous
 
95

 

 
2

 
(52
)
 
45

Total liability (b)
 
$
9,687

 
$
(29
)
 
$
342

 
$
1,392

 
$
11,392


(a) 
There were no ARO liabilities recognized during the year ended Dec. 31, 2016.
(b) 
Included in other long-term liabilities balance in the consolidated balance sheet.

(Thousands of Dollars)
 
Beginning Balance
Jan. 1, 2015
 
Accretion
 
Cash Flow
   Revisions
 
Ending Balance
    Dec. 31, 2015 (a)
Electric plant
 
 
 
 
 
 
 
 
Steam production asbestos
 
$
2,049

 
$
45

 
$
51

 
$
2,145

Steam production ash containment
 
374

 
14

 
229

 
617

Electric distribution
 
37

 
1

 
34

 
72

Other
 
412

 
15

 
(36
)
 
391

Natural gas plant
 
 
 
 
 
 
 
 
Gas distribution
 
6,127

 
240

 

 
6,367

Common and other property
 
 
 
 
 
 
 
 
Common miscellaneous
 
91

 
4

 

 
95

Total liability (b)
 
$
9,090

 
$
319

 
$
278

 
$
9,687

 
(a) 
There were no ARO liabilities recognized or settled during the year ended Dec. 31, 2015.
(b) 
Included in other long-term liabilities balance in the consolidated balance sheet.


Indeterminate AROs Outside of the known and recorded asbestos AROs, other plants or buildings may contain asbestos due to the age of many of NSP-Wisconsin’s facilities, but no confirmation or measurement of the amount of asbestos or cost of removal could be determined as of Dec. 31, 2016. Therefore, an ARO has not been recorded for these facilities.

Removal Costs NSP-Wisconsin records a regulatory liability for the plant removal costs of generation, transmission and distribution facilities that are recovered currently in rates. Generally, the accrual of future non-ARO removal obligations is not required. However, long-standing ratemaking practices approved by applicable state and federal regulatory commissions have allowed provisions for such costs in historical depreciation rates. These removal costs have accumulated over a number of years based on varying rates as authorized by the appropriate regulatory entities. Given the long time periods over which the amounts were accrued and the changing of rates over time, NSP-Wisconsin has estimated the amount of removal costs accumulated through historic depreciation expense based on current factors used in the existing depreciation rates. Accordingly, the recorded amounts of estimated future removal costs are considered regulatory liabilities. Removal costs as of Dec. 31, 2016 and 2015 were $140 million and $132 million, respectively.

Legal Contingencies

NSP-Wisconsin is involved in various litigation matters that are being defended and handled in the ordinary course of business. The assessment of whether a loss is probable or is a reasonable possibility, and whether the loss or a range of loss is estimable, often involves a series of complex judgments about future events. Management maintains accruals for such losses that are probable of being incurred and subject to reasonable estimation. Management is sometimes unable to estimate an amount or range of a reasonably possible loss in certain situations, including but not limited to when (1) the damages sought are indeterminate, (2) the proceedings are in the early stages, or (3) the matters involve novel or unsettled legal theories. In such cases, there is considerable uncertainty regarding the timing or ultimate resolution of such matters, including a possible eventual loss. For current proceedings not specifically reported herein, management does not anticipate that the ultimate liabilities, if any, arising from such current proceedings would have a material effect on NSP-Wisconsin’s financial statements. Unless otherwise required by GAAP, legal fees are expensed as incurred.

Gas Trading Litigation — e prime, inc. (e prime) is a wholly owned subsidiary of Xcel Energy.  e prime was in the business of natural gas trading and marketing, but has not engaged in natural gas trading or marketing activities since 2003.  Thirteen lawsuits were commenced against e prime and Xcel Energy (and NSP-Wisconsin, in two instances) between 2003 and 2009 alleging fraud and anticompetitive activities in conspiring to restrain the trade of natural gas and manipulate natural gas prices.

The cases were consolidated in U.S. District Court in Nevada. Five of the cases have since been settled and seven have been dismissed. One multi-district litigation (MDL) matter remains and it consists of a Colorado class (Breckenridge), a Wisconsin class (NSP-Wisconsin), a Kansas class, and two other cases identified as “Sinclair Oil” and “Farmland.” In November 2016, the MDL judge dismissed e prime and Xcel Energy from the Farmland lawsuit. Motions for summary judgment have been filed by defendants, including e prime, in all of the remaining lawsuits. Defendants have also filed briefs opposing plaintiffs’ motion for class certification.

The majority of the motions filed were argued to the court in January 2017. It is uncertain when the court will render a decision concerning these motions. Xcel Energy, NSP-Wisconsin and e prime have concluded that a loss is remote.

Other Contingencies

See Note 10 for further discussion.