XML 48 R37.htm IDEA: XBRL DOCUMENT v3.5.0.2
Rate Matters Rate Matters (Details)
1 Months Ended 3 Months Ended 9 Months Ended 12 Months Ended
Oct. 26, 2016
USD ($)
Sep. 28, 2016
Jun. 30, 2016
Oct. 31, 2016
USD ($)
Aug. 31, 2016
USD ($)
Jul. 31, 2016
USD ($)
Apr. 30, 2016
USD ($)
Mar. 31, 2015
USD ($)
Feb. 28, 2015
Nov. 30, 2013
Sep. 30, 2016
USD ($)
Sep. 30, 2015
USD ($)
Mar. 31, 2015
USD ($)
Sep. 30, 2016
USD ($)
Sep. 30, 2015
USD ($)
Dec. 31, 2015
MW
Dec. 31, 2013
USD ($)
Dec. 31, 2008
USD ($)
Public Utilities, General Disclosures [Line Items]                                    
Loss on Monticello life cycle management/extended power uprate project                     $ 0 $ 0   $ 0 $ 5,237,000      
NSP-Wisconsin | PSCW Proceeding - Wisconsin 2017 Electric and Gas Rate Case - Electric Rates 2017                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Requested Rate Increase (Decrease), Amount             $ 17,400,000                      
Public Utilities, Requested Rate Increase (Decrease), Percentage             2.40%                      
Public Utilities, Requested Rate Base, Amount             $ 1,188,000,000                      
Public Utilities, Requested Increase Related to Rate Base Investments             11,000,000                      
Public Utilities, Requested Increase Related to Generation and Transmission Expenses             6,800,000                      
Public Utilities, Requested Increase Related to Fuel and Purchased Power Expenses             11,000,000                      
Public Utilities, Total Requested Rate Increase Excluding Refunds             28,800,000                      
Public Utilities, Requested Decrease Related to Fuel Refunds             (9,500,000)                      
Public Utilities, Requested Decrease Related to Settlement Refund             (1,900,000)                      
NSP-Wisconsin | PSCW Proceeding - Wisconsin 2017 Electric and Gas Rate Case - Electric Rates 2017 | Public Service Commission of Wisconsin (PSCW) Staff [Member]                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Requested Rate Increase (Decrease), Amount         $ 19,500,000                          
Public Utilities, Requested Rate Increase (Decrease), Percentage         2.70%                          
Public Utilities, Difference Between Filed Request and PSCW Staff Recommendation         $ 7,400,000                          
Public Utilities, Requested Increase Related to Rate Base Investments         7,600,000                          
Public Utilities, Requested Increase Related to Generation and Transmission Expenses         6,100,000                          
Public Utilities, Requested Increase Related to Fuel and Purchased Power Expenses         7,700,000                          
Public Utilities, Total Requested Rate Increase Excluding Refunds         21,400,000                          
Public Utilities, Requested Decrease Related to Fuel Refunds         0                          
Public Utilities, Requested Decrease Related to Settlement Refund         (1,900,000)                          
NSP-Wisconsin | PSCW Proceeding - Wisconsin 2017 Electric and Gas Rate Case - Electric Rates 2017 | Public Service Commission of Wisconsin (PSCW)                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Adjustment to Rate Request Related to Fuel Refund           $ 9,500,000                        
Public Utilities, Revised Requested Rate Increase, Amount           $ 29,900,000                        
Public Utilities, Revised Requested Rate Increase, Percentage           4.20%                        
NSP-Wisconsin | PSCW Proceeding - Wisconsin 2017 Electric and Gas Rate Case - Gas Rates 2017                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Requested Rate Increase (Decrease), Amount             $ 4,800,000                      
Public Utilities, Requested Rate Increase (Decrease), Percentage             3.90%                      
NSP-Wisconsin | PSCW Proceeding - Wisconsin 2017 Electric and Gas Rate Case - Gas Rates 2017 | Public Service Commission of Wisconsin (PSCW) Staff [Member]                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Requested Rate Increase (Decrease), Amount         $ 4,800,000                          
Public Utilities, Requested Rate Increase (Decrease), Percentage         3.90%                          
NSP-Wisconsin | PSCW Proceeding - Wisconsin 2017 Electric and Gas Rate Case                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Requested Return on Equity, Percentage             10.00%                      
Public Utilities, Percentage of Excess Earnings to be Refunded due to Earnings Cap             100.00%                      
NSP-Wisconsin | MPUC Proceeding - Nuclear Project Prudency Investigation                                    
Public Utilities, General Disclosures [Line Items]                                    
Loss on Monticello life cycle management/extended power uprate project                         $ 5,000,000          
NSP-Minnesota | MPUC Proceeding - Nuclear Project Prudency Investigation                                    
Public Utilities, General Disclosures [Line Items]                                    
Nuclear Project Expenditures, Amount                                 $ 665,000,000  
Total Capitalized Nuclear Project Costs                                 $ 748,000,000  
Initial Estimated Nuclear Project Expenditures                                   $ 320,000,000
NSP-Minnesota | MPUC Proceeding - Nuclear Project Prudency Investigation | Minnesota Public Utilities Commission                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Amount Of Recoverable Investment, With Return               $ 415,000,000                    
Public Utilities, Amount Of Recoverable Investment, Without A Return               $ 333,000,000                    
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Base Return On Equity Charged To Customers Through Transmission Formula Rates                 12.38% 12.38%                
Public Utilities, ROE Applicable To Transmission Formula Rates In The Regional Transmission Operator's Region, Recommended By Third Parties                 8.67% 9.15%                
Public Utilities, Maximum Equity Capital Structure Percentage Allowed Per The Complaint                   50.00%                
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint | Administrative Law Judge                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, ROE Applicable To Transmission Formula Rates In The Regional Transmission Operator's Region, Recommended By Third Parties     9.70%                              
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint | MPUC, NDPSC, SDPUC, and DOC                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, ROE Applicable To Transmission Formula Rates In The Regional Transmission Operator's Region, Recommended By Third Parties                           8.81%        
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint | FERC Staff                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, ROE Applicable To Transmission Formula Rates In The Regional Transmission Operator's Region, Recommended By Third Parties                           8.78%        
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint | MISO TOs                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, ROE Applicable To Transmission Formula Rates In The Regional Transmission Operator's Region, Recommended By Third Parties                           10.92%        
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint | Federal Energy Regulatory Commission (FERC)                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, ROE Applicable To Transmission Formula Rates In The MISO Region, Approved   10.32%                                
Public Utilities, Length of Refund Period, In Months   15 months                                
Public Utilities, ROE Applicable To Transmission Formula Rates In The MISO Region, with RTO Adder, Approved                           10.82%        
Public Utilities, ROE Basis Point Adder, Approved                           50        
Xcel Energy Inc. | MPUC Proceeding - Nuclear Project Prudency Investigation                                    
Public Utilities, General Disclosures [Line Items]                                    
Loss on Monticello life cycle management/extended power uprate project                         $ 129,000,000          
Minimum | NSP-Minnesota | MPUC Proceeding - Nuclear Project Prudency Investigation                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Facility Generating Capacity, In MW | MW                               600    
Maximum | NSP-Minnesota | MPUC Proceeding - Nuclear Project Prudency Investigation                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Facility Generating Capacity, In MW | MW                               671    
Subsequent Event [Member] | NSP-Wisconsin | PSCW Proceeding - Wisconsin 2017 Electric and Gas Rate Case - Electric Rates 2017 | Public Service Commission of Wisconsin (PSCW)                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Approved Rate Increase (Decrease), Amount $ 22,500,000                                  
Public Utilities, Approved Rate Increase (Decrease), Percentage 3.20%                                  
Public Utilities, Approved Increase Related to Rate Base Investments $ 7,600,000                                  
Public Utilities, Approved Increase Related to Generation and Transmission Expenses 6,100,000                                  
Public Utilities, Approved Increase Related to Fuel and Purchased Power Expenses 10,700,000                                  
Public Utilities, Total Approved Rate Increase, Excluding Refunds 24,400,000                                  
Public Utilities, Approved Decrease Related to Fuel Refunds 0                                  
Public Utilities, Approved Decrease Related to Settlement Refund (1,900,000)                                  
Subsequent Event [Member] | NSP-Wisconsin | PSCW Proceeding - Wisconsin 2017 Electric and Gas Rate Case - Gas Rates 2017 | Public Service Commission of Wisconsin (PSCW)                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Approved Rate Increase (Decrease), Amount $ 4,800,000                                  
Public Utilities, Approved Rate Increase (Decrease), Percentage 3.90%                                  
Subsequent Event [Member] | NSP-Wisconsin | MPSC Proceeding - Michigan 2017 Natural Gas Rate Case [Member]                                    
Public Utilities, General Disclosures [Line Items]                                    
Public Utilities, Requested Rate Increase (Decrease), Amount       $ 347,000                            
Public Utilities, Requested Rate Increase (Decrease), Percentage       6.50%                            
Public Utilities, Requested Rate Base, Amount       $ 6,400,000                            
Public Utilities, Requested Return on Equity, Percentage       10.20%                            
Public Utilities, Requested Equity Capital Structure, Percentage       52.56%                            
Public Utilities, Requested Rider Revenue, Amount       $ 129,000                            
Public Utilities, Requested Rider Revenue, Percentage       2.40%