XML 48 R37.htm IDEA: XBRL DOCUMENT v3.4.0.3
Rate Matters Rate Matters (Details)
$ in Thousands
1 Months Ended 3 Months Ended 12 Months Ended
Apr. 01, 2016
USD ($)
Jan. 06, 2015
Dec. 31, 2015
Mar. 31, 2015
USD ($)
Feb. 28, 2015
Jun. 30, 2014
Nov. 30, 2013
Mar. 31, 2016
USD ($)
Mar. 31, 2015
USD ($)
Dec. 31, 2015
MW
Dec. 31, 2013
USD ($)
Dec. 31, 2008
USD ($)
Public Utilities, General Disclosures [Line Items]                        
Loss on Monticello life cycle management/extended power uprate project               $ 0 $ 5,237      
NSP-Minnesota | MPUC Proceeding - Nuclear Project Prudency Investigation                        
Public Utilities, General Disclosures [Line Items]                        
Nuclear Project Expenditures, Amount                     $ 665,000  
Total Capitalized Nuclear Project Costs                     $ 748,000  
Initial Estimated Nuclear Project Expenditures                       $ 320,000
NSP-Minnesota | MPUC Proceeding - Nuclear Project Prudency Investigation | Minnesota Public Utilities Commission [Member]                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, Amount Of Recoverable Investment, With Return       $ 415,000                
Public Utilities, Amount Of Recoverable Investment, Without A Return       $ 333,000                
Public Utilities, Percentage Of Investment Considered Used And Useful       50.00%                
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint [Member]                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, Base Return On Equity Charged To Customers Through Transmission Formula Rates         12.38%   12.38%          
Public Utilities, ROE Applicable To Transmission Formula Rates In The Regional Transmission Operator's Region, Recommended By Third Parties         8.67%   9.15%          
Public Utilities, Maximum Equity Capital Structure Percentage Allowed Per The Complaint             50.00%          
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint [Member] | Federal Energy Regulatory Commission (FERC)                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, Number Of Steps Required For Newly Adopted ROE Discounted Cash Flow Methodology           2            
Public Utilities, ROE Basis Point Adder Requested By Third Parties   50                    
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint [Member] | Administrative Law Judge [Member]                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, ROE Applicable To Transmission Formula Rates In The Regional Transmission Operator's Region, Recommended By Third Parties     10.32%                  
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint [Member] | MPUC, NDPSC, SDPUC, and DOC [Member]                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, ROE Applicable To Transmission Formula Rates In The MISO Region, Upper Bound, Percentage               8.82%        
Public Utilities, ROE Applicable To Transmission Formula Rates In The MISO Region, Lower Bound, Percentage               8.81%        
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint [Member] | FERC Staff [Member]                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, ROE Applicable To Transmission Formula Rates In The Regional Transmission Operator's Region, Recommended By Third Parties               8.78%        
NSP-Minnesota | FERC Proceeding, MISO ROE Complaint [Member] | MISO TOs [Member]                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, ROE Applicable To Transmission Formula Rates In The Regional Transmission Operator's Region, Recommended By Third Parties               10.92%        
Xcel Energy Inc. | MPUC Proceeding - Nuclear Project Prudency Investigation                        
Public Utilities, General Disclosures [Line Items]                        
Loss on Monticello life cycle management/extended power uprate project                 129,000      
NSP-Wisconsin | MPUC Proceeding - Nuclear Project Prudency Investigation                        
Public Utilities, General Disclosures [Line Items]                        
Loss on Monticello life cycle management/extended power uprate project                 $ 5,000      
Minimum | NSP-Minnesota | MPUC Proceeding - Nuclear Project Prudency Investigation                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, Facility Generating Capacity, In MW | MW                   600    
Minimum | NSP-Minnesota | FERC Proceeding, MISO ROE Complaint [Member]                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, Decrease In Transmission Revenue, Net Of Expense, Due To New ROE Methodology               $ 8,000        
Maximum | NSP-Minnesota | MPUC Proceeding - Nuclear Project Prudency Investigation                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, Facility Generating Capacity, In MW | MW                   671    
Maximum | NSP-Minnesota | FERC Proceeding, MISO ROE Complaint [Member]                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, Decrease In Transmission Revenue, Net Of Expense, Due To New ROE Methodology               $ 10,000        
Subsequent Event [Member] | NSP-Wisconsin | PSCW Proceeding - Wisconsin 2017 Electric and Gas Rate Case - Electric Rates 2017 [Member]                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, Requested Rate Increase (Decrease), Amount $ 17,400                      
Public Utilities, Requested Rate Increase (Decrease), Percentage 2.40%                      
Public Utilities, Requested Rate Base, Amount $ 1,188,000                      
Public Utilities, Requested Increase Related to Rate Base Investments 11,000                      
Public Utilities, Requested Increase Related to Generation and Transmission Expenses [1] 6,800                      
Public Utilities, Requested Increase Related to Fuel and Purchased Power Expenses 11,000                      
Public Utilities, Total Requested Rate Increase Excluding Refunds 28,800                      
Public Utilities, Requested Decrease Related to Fuel Refunds (9,500)                      
Public Utilities, Requested Decrease Related to Settlement Refund $ (1,900)                      
Subsequent Event [Member] | NSP-Wisconsin | PSCW Proceeding - Wisconsin 2017 Electric and Gas Rate Case [Member]                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, Requested Return on Equity, Percentage 10.00%                      
Public Utilities, Percentage of Excess Earnings to be Refunded due to Earnings Cap 100.00%                      
Subsequent Event [Member] | NSP-Wisconsin | PSCW Proceeding - Wisconsin 2017 Electric and Gas Rate Case - Gas Rates 2017 [Member]                        
Public Utilities, General Disclosures [Line Items]                        
Public Utilities, Requested Rate Increase (Decrease), Amount $ 4,800                      
Public Utilities, Requested Rate Increase (Decrease), Percentage 3.90%                      
Public Utilities, Increase Related Environmental Remediation Expenses $ 4,800                      
[1] Includes Interchange Agreement billings. The Interchange Agreement is a Federal Energy Regulatory Commission (FERC) tariff under which NSP-Wisconsin and its affiliate, NSP-Minnesota, own and operate a single integrated electric generation and transmission system and both companies pay a pro-rata share of system capital and operating costs. For financial reporting purposes, these expenses are included in operating and maintenance (O&M) expenses.