Recently Concluded Regulatory Proceedings — PSCW

Wisconsin 2015 Electric Rate Case  In May 2014, NSP-Wisconsin filed a request with the PSCW to increase electric rates by $20.6 million, or 3.2 percent, effective Jan. 1, 2015. The request was for the limited purpose of updating 2015 electric rates to reflect anticipated increases in the production and transmission fixed charges and the fuel and purchased power components of the interchange agreement with NSP-Minnesota. No changes were requested to the capital structure or the 10.2 percent ROE authorized by the PSCW in the 2014 rate case. As part of an agreement with stakeholders to limit the size and scope of the case, NSP-Wisconsin also agreed to an earnings cap for 2015 only, in which 100 percent of the earnings above the authorized ROE would be refunded to customers.

In December 2014, the PSCW issued its order approving an overall increase in NSP-Wisconsin’s electric rates of approximately $14.2 million, or 2.2 percent, reflecting the updated November forecast for fuel and purchased power costs. The PSCW order was consistent with the agreement reached by the parties, as described above. The new rates were effective Jan. 1, 2015.

Pending Regulatory Proceedings - Michigan Public Service Commission (MPSC)

Michigan 2015 Electric Rate Case — In October 2014, NSP-Wisconsin filed a request with the MPSC to increase rates for electric service by $900,000, or 6.1 percent. The filing was based on a 2015 forecast test year, a 10.3 percent ROE, an equity ratio of 52.59 percent and a forecasted average rate base of approximately $35.2 million. The primary drivers of the requested increase are continuing investment in transmission and distribution infrastructure. The filing also included a request for a $289,000, or 1.9 percent, step increase in 2016, to reflect the expiration in 2016 of certain credits that were used to offset the 2015 rate request. In addition to the MPSC staff, intervenors in the case include the Michigan Attorney General and the Association of Businesses Advocating Tariff Equity, a voluntary association of large industrial businesses. Hearings are scheduled for April 2015. The parties have agreed to meet in February 2015 to discuss potential settlement of the case.

Pending Regulatory Proceedings — FERC

MISO ROE Complaint/ROE Adder — In November 2013, a group of customers filed a complaint at the FERC against MISO transmission owners, including NSP-Minnesota and NSP-Wisconsin. The complaint argued for a reduction in the ROE applicable to transmission formula rates in the MISO region from 12.38 percent to 9.15 percent, a prohibition on capital structures in excess of 50 percent equity, and the removal of ROE adders (including those for RTO membership and being an independent transmission company), effective Nov. 12, 2013.

In June 2014, the FERC issued an order in a different ROE proceeding adopting a new ROE methodology for electric utilities. The new ROE methodology requires electric utilities to use a two-step discounted cash flow analysis to estimate cost of equity that incorporates both short-term and long-term growth projections.

In October 2014, the FERC upheld the determination of the long-term growth rate to be used together with a short term growth rate in its new ROE methodology. The FERC separately set the ROE complaint against the MISO transmission owners for settlement judge and hearing procedures. The FERC directed parties to apply the new ROE methodology, but denied the complaints related to equity capital structures and ROE adders. The FERC established a Nov. 12, 2013 refund effective date. The settlement judge procedures were unsuccessful. FERC action is pending. In January 2015, the ROE complaint was set for full hearing procedures, with an ALJ initial decision to be issued by November 2015 and a FERC order issued no earlier than 2016.

In November 2014, the MISO transmission owners filed a request for FERC approval of a 50 basis point RTO membership ROE adder, with collection deferred until resolution of the ROE complaint. In January 2015, the FERC approved the ROE adder, subject to the outcome of the ROE complaint. The total ROE, including the RTO membership adder, may not exceed the top of the discounted cash flow range under the new ROE methodology. In 2015, several intervenors sought rehearing of the commission order.

In February 2015, a separate group of customers filed an additional complaint proposing to reduce the MISO region ROE to 8.67 percent, prior to any 50 basis point RTO adder, with a refund effective date of Feb. 12, 2015.  Answers to the complaint are to be filed by March 2015.

NSP-Minnesota recorded a current liability representing the current best estimate of a refund obligation associated with the new ROE as of Dec. 31, 2014. The new FERC ROE methodology is estimated to reduce transmission revenue, net of expense, between $5 million and $7 million annually for the NSP System.