Commitments and Contingencies, Environmental Contingencies - Site Contingencies (Details) (USD $)
9 Months Ended
Sep. 30, 2014
Site
Dec. 31, 2013
Ashland Manufactured Gas Plant (MGP) Site [Abstract]    
Liability for estimated cost of remediating sites, current $ 25,893,000 $ 28,785,000
Ashland MGP Site
   
Ashland Manufactured Gas Plant (MGP) Site [Abstract]    
Number of properties included in superfund site which NSP-Wisconsin does not own 2  
Liability for estimated cost of remediating sites 106,900,000 104,600,000
Liability for estimated cost of remediating sites, current 25,400,000 25,200,000
Amortization period for recovery of remediation costs in natural gas rates, low end of range (in years) 4 years  
Amortization period for recovery of remediation costs in natural gas rates, high end of range (in years) 6 years  
Ashland MGP Site - Phase I Project Area
   
Ashland Manufactured Gas Plant (MGP) Site [Abstract]    
Liability for estimated cost of remediating sites 52,000,000  
Estimated amount spent on Phase I Project Area cleanup 21,000,000  
Approved amortization period for recovery of remediation costs in natural gas rates (in years) 10 years  
Carrying cost percentage to be applied to the unamortized regulatory asset for MGP remediation (in hundredths) 3.00%  
Approved increase (decrease) in amortization expense granted by a regulatory body 1,100,000  
Ashland MGP Site - Sediments
   
Ashland Manufactured Gas Plant (MGP) Site [Abstract]    
Estimated cost of remediating site, low end of range 63,000,000  
Estimated cost of remediating site, high end of range $ 77,000,000  
Potential percent of increase to the high end of the range of estimated site remediation costs (in hundredths) 50.00%  
Potential percent of decrease to the low end of the range of estimated site remediation costs (in hundredths) 30.00%