XML 66 R22.htm IDEA: XBRL DOCUMENT v2.4.0.8
Commitments and Contingencies
12 Months Ended
Dec. 31, 2013
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
Commitments and Contingencies

Commitments

Capital Commitments — NSP-Wisconsin has made commitments in connection with a portion of its projected capital expenditures. NSP-Wisconsin’s capital commitments primarily relate to one major project, CapX2020.

CapX2020 — CapX2020 is an alliance of electric cooperatives, municipals and investor-owned utilities in the upper Midwest, including the NSP System that has proposed several groups of transmission projects to be completed by 2020.  Group 1 project investments consist of four transmission lines.  Major construction began in 2010 on the Group 1 transmission lines with an expected completion date in 2015.  NSP System’s investment depends on the routes and configurations approved by affected state commissions and on the allocation of costs borne by other participating utilities in the upper Midwest.

Fuel Contracts — NSP-Wisconsin has entered into various long-term commitments providing for the purchase and delivery of a significant portion of its current coal and natural gas requirements.  These contracts expire in various years between 2014 and 2029. In addition, NSP-Wisconsin is required to pay additional amounts depending on actual quantities shipped under these agreements. As NSP-Wisconsin does not have an automatic electric fuel adjustment clause for Wisconsin retail customers, NSP-Wisconsin utilizes deferred accounting treatment for future rate recovery or refund when fuel costs differ from the amount included in rates by more than two percent on an annual basis, as determined by the PSCW after an opportunity for a hearing and an earnings test based on NSP-Wisconsin’s authorized ROE.

The estimated minimum purchases for NSP-Wisconsin under these contracts as of Dec. 31, 2013 are as follows:
(Millions of dollars)
 
Coal
 
Natural gas
supply
 
Natural gas
storage and
transportation
2014
 
$
6.2

 
$
13.4

 
$
11.9

2015
 
1.3

 
0.3

 
11.6

2016
 
0.7

 
0.3

 
11.7

2017
 
0.7

 
0.2

 
9.5

2018
 
0.7

 

 
4.4

Thereafter
 
4.1

 

 
18.9

Total (a)
 
$
13.7

 
$
14.2

 
$
68.0


(a) 
Excludes additional amounts allocated to NSP-Wisconsin through intercompany charges.

Additional expenditures for fuel and natural gas storage and transportation will be required to meet expected future electric generation and natural gas needs.

Leases — NSP-Wisconsin leases a variety of equipment and facilities used in the normal course of business.  These leases, primarily for office space, trucks, aircraft, cars and power-operated equipment, are accounted for as operating leases.  Total expenses under operating lease obligations were approximately $1.4 million, $1.1 million and $1.4 million for 2013, 2012 and 2011, respectively.

Future commitments under operating leases are:
(Millions of Dollars)
 
 
2014
 
$
0.8

2015
 
0.8

2016
 
0.8

2017
 
0.9

2018
 
0.9

Thereafter
 
8.8

Total
 
$
13.0



Variable Interest Entities — The accounting guidance for consolidation of variable interest entities requires enterprises to consider the activities that most significantly impact an entity’s financial performance, and power to direct those activities, when determining whether an enterprise is a variable interest entity’s primary beneficiary.

NSP-Wisconsin has entered into limited partnerships for the construction and operation of affordable rental housing developments which qualify for low-income housing tax credits.  NSP-Wisconsin has determined the low-income housing limited partnerships to be variable interest entities primarily due to contractual arrangements within each limited partnership that establish sharing of ongoing voting control and profits and losses that does not consistently align with the partners’ proportional equity ownership.  These limited partnerships are designed to qualify for low-income housing tax credits, and NSP-Wisconsin generally receives a larger allocation of the tax credits than the general partners at inception of the arrangements.  NSP-Wisconsin has determined that it has the power to direct the activities that most significantly impact these entities’ economic performance, and therefore NSP-Wisconsin consolidates these limited partnerships in its consolidated financial statements.

Equity financing for these entities has been provided by NSP-Wisconsin and the general partner of each limited partnership, and NSP-Wisconsin’s risk of loss is limited to its capital contributions, adjusted for any distributions and its share of undistributed profits and losses; no significant additional financial support has been, or is in the future, required to be provided to the limited partnerships by NSP-Wisconsin. Mortgage-backed debt typically comprises the majority of the financing at inception of each limited partnership and is paid over the life of the limited partnership arrangement.  Obligations of the limited partnerships are generally secured by the housing properties of each limited partnership, and the creditors of each limited partnership have no significant recourse to NSP-Wisconsin or its subsidiaries. Likewise, the assets of the limited partnerships may only be used to settle obligations of the limited partnerships, and not those of NSP-Wisconsin or its subsidiaries.

Amounts reflected in NSP-Wisconsin’s consolidated balance sheets for low-income housing limited partnerships include the following:
(Thousands of Dollars)
 
Dec. 31, 2013
 
Dec. 31, 2012
Current assets
 
$
223

 
$
357

Property, plant and equipment, net
 
2,427

 
2,599

Other noncurrent assets
 
112

 
105

Total assets
 
$
2,762

 
$
3,061

 
 
 
 
 
Current liabilities
 
$
233

 
$
1,388

Mortgages and other long-term debt payable
 
1,687

 
617

Other noncurrent liabilities
 
42

 
39

Total liabilities
 
$
1,962

 
$
2,044



Joint Operating System The electric production and transmission system of NSP-Wisconsin is managed as an integrated system with that of NSP-Minnesota, jointly referred to as the NSP System.  The electric production and transmission costs of the entire NSP System are shared by NSP-Minnesota and NSP-Wisconsin.  A FERC approved agreement between the two companies, called the Interchange Agreement, provides for the sharing of all costs of generation and transmission facilities of the system, including capital costs. Such costs include current and potential obligations of NSP-Minnesota related to its nuclear generating facilities.

NSP-Minnesota’s public liability for claims resulting from any nuclear incident is limited to $13.6 billion under the Price-Anderson amendment to the Atomic Energy Act.  NSP-Minnesota has secured $375 million of coverage for its public liability exposure with a pool of insurance companies.  The remaining $13.2 billion of exposure is funded by the Secondary Financial Protection Program, available from assessments by the federal government in case of a nuclear accident.  NSP-Minnesota is subject to assessments of up to $127.3 million per reactor per accident for each of its three licensed reactors, to be applied for public liability arising from a nuclear incident at any licensed nuclear facility in the United States.  The maximum funding requirement is $19 million per reactor during any one year. These maximum assessment amounts are both subject to inflation adjustment by the NRC and state premium taxes.  The NRC’s last adjustment was effective September 2013.

NSP-Minnesota purchases insurance for property damage and site decontamination cleanup costs from Nuclear Electric Insurance Ltd. (NEIL). The coverage limits are $2.3 billion for each of NSP-Minnesota’s two nuclear plant sites.  NEIL also provides business interruption insurance coverage, including the cost of replacement power obtained during certain prolonged accidental outages of nuclear generating units.  Premiums are expensed over the policy term.  All companies insured with NEIL are subject to retroactive premium adjustments if losses exceed accumulated reserve funds.  Capital has been accumulated in the reserve funds of NEIL to the extent that NSP-Minnesota would have no exposure for retroactive premium assessments in case of a single incident under the business interruption and the property damage insurance coverage.  However, in each calendar year, NSP-Minnesota could be subject to maximum assessments of approximately $16.1 million for business interruption insurance and $40.2 million for property damage insurance if losses exceed accumulated reserve funds.

Guarantees — NSP-Wisconsin provides a guarantee for payment of customer loans related to NSP-Wisconsin’s farm rewiring program. NSP-Wisconsin’s exposure under the guarantee is based upon the net liability under the agreement.  The guarantee issued by NSP-Wisconsin limits the exposure of NSP-Wisconsin to a maximum amount stated in the guarantee.  The guarantee contains no recourse provisions and requires no collateral.

The following table presents the guarantee issued and outstanding for NSP-Wisconsin:
(Millions of Dollars)
 
Guarantee
Amount
 
Current
Exposure
 
Term or
Expiration Date
 
Triggering
Event
Requiring
Performance
Guarantee of customer loans for the Farm Rewiring Program
 
$
1.0

 
$
0.3

 
2017
 
(a) 

(a) 
The debtor becomes the subject of bankruptcy or other insolvency proceedings.

Environmental Contingencies

NSP-Wisconsin has been or is currently involved with the cleanup of contamination from certain hazardous substances at several sites. In many situations, NSP-Wisconsin believes it will recover some portion of these costs through insurance claims. Additionally, where applicable, NSP-Wisconsin is pursuing, or intends to pursue, recovery from other PRPs and through the regulated rate process. New and changing federal and state environmental mandates can also create added financial liabilities for NSP-Wisconsin, which are normally recovered through the regulated rate process. To the extent any costs are not recovered through the options listed above, NSP-Wisconsin would be required to recognize an expense.

Site Remediation Various federal and state environmental laws impose liability, without regard to the legality of the original conduct, where hazardous substances or other regulated materials have been released to the environment. NSP-Wisconsin may sometimes pay all or a portion of the cost to remediate sites where past activities of NSP-Wisconsin or other parties have caused environmental contamination. Environmental contingencies could arise from various situations, including sites of former MGPs operated by NSP-Wisconsin, its predecessors, or other entities; and third-party sites, such as landfills, for which NSP-Wisconsin is alleged to be a PRP that sent hazardous materials and wastes to that site.

MGP Sites

Ashland MGP Site — NSP-Wisconsin has been named a PRP for contamination at a site in Ashland, Wis. The Ashland/Northern States Power Lakefront Superfund Site (the Ashland site) includes property owned by NSP-Wisconsin, which was a site previously operated by a predecessor company as a MGP facility (the Upper Bluff), and two other properties: an adjacent city lakeshore park area (Kreher Park), on which an unaffiliated third party previously operated a sawmill and conducted creosote treating operations; and an area of Lake Superior’s Chequamegon Bay adjoining the park (the Sediments).

The EPA issued its Record of Decision (ROD) in 2010, which describes the preferred remedy the EPA has selected for the cleanup of the Ashland site. For the Sediments at the Ashland Site, the ROD preferred remedy is a hybrid remedy involving both dry excavation and wet conventional dredging methodologies (the Hybrid Remedy). The ROD also identifies the possibility of a wet conventional dredging only remedy for the Sediments (the Wet Dredge), contingent upon the completion of a successful Wet Dredge pilot study.

In 2011, the EPA issued special notice letters identifying several entities, including NSP-Wisconsin, as PRPs, for future remediation at the site. The special notice letters requested that those PRPs participate in negotiations with the EPA regarding how the PRPs intended to conduct or pay for the remediation at the Ashland site. As a result of settlement negotiations with NSP-Wisconsin, the EPA agreed to segment the Ashland site into separate areas. The first area (Phase I Project Area) includes soil and groundwater in Kreher Park and the Upper Bluff. The second area includes the Sediments.

In October 2012, a settlement among the EPA, the WDNR, the Bad River and Red Cliff Bands of the Lake Superior Tribe of Chippewa Indians and NSP-Wisconsin was approved by the U.S. District Court for the Western District of Wisconsin. This settlement resolves claims against NSP-Wisconsin for its alleged responsibility for the remediation of the Phase I Project Area. Under the terms of the settlement, NSP-Wisconsin agreed to perform the remediation of the Phase I Project Area, but does not admit any liability with respect to the Ashland site. The settlement reflects a cost estimate for the clean up of the Phase I Project Area of $40 million. The settlement also resolves claims by the federal, state and tribal trustees against NSP-Wisconsin for alleged natural resource damages at the Ashland site, including both the Phase I Project Area and the Sediments. As part of the settlement, NSP-Wisconsin has conveyed approximately 1,390 acres of land to the State of Wisconsin and tribal trustees. Fieldwork to address the Phase I Project Area at the Ashland site began at the end of 2012 and continues.

Negotiations are ongoing between the EPA and NSP-Wisconsin regarding who will pay or perform the cleanup of the Sediments and what remedy will be implemented at the site to address the Sediments. In August and September 2013, NSP-Wisconsin performed field studies in the Sediments to gather more data about site conditions. The data from that investigation was received and reported to the EPA at the end of 2013. It is NSP-Wisconsin’s view that this data demonstrates the Hybrid Remedy is not safe or feasible to implement. The EPA’s ROD for the Ashland site includes estimates that the cost of the Hybrid Remedy is between $63 million and $77 million, with a potential deviation in such estimated costs of up to 50 percent higher to 30 percent lower. Also, in September 2013, the EPA requested NSP-Wisconsin consider re-submitting another proposal to perform a Wet Dredge pilot study for a portion of the Sediments. NSP-Wisconsin previously submitted a proposal for a Wet Dredge pilot study in 2011. In November 2013, NSP-Wisconsin submitted a revised Wet Dredge pilot study work plan proposal to the EPA. NSP-Wisconsin is in the process of negotiating a final pilot study work plan for possible implementation in late summer or early fall of 2014.

In August 2012, NSP-Wisconsin also filed litigation against other PRPs for their share of the cleanup costs for the Ashland site. Trial for this matter is scheduled for April 2015. Negotiations between the EPA, NSP-Wisconsin and several of the other PRPs regarding the PRPs’ fair share of the cleanup costs for the Ashland site are also ongoing.

At Dec. 31, 2013 and 2012, NSP-Wisconsin had recorded a liability of $104.6 million and $103.7 million, respectively, for the Ashland site based upon potential remediation and design costs together with estimated outside legal and consultant costs; of which $25.2 million and $20.1 million, respectively, was considered a current liability. NSP-Wisconsin’s potential liability, the actual cost of remediation and the time frame over which the amounts may be paid are subject to change. NSP-Wisconsin also continues to work to identify and access state and federal funds to apply to the ultimate remediation cost of the entire site. Unresolved issues or factors that could result in higher or lower NSP-Wisconsin remediation costs for the Ashland site include the cleanup approach implemented for the Sediments, which party implements the cleanup, the timing of when the cleanup is implemented, potential contributions by other PRPs and whether federal or state funding may be directed to help offset remediation costs at the Ashland site.

NSP-Wisconsin has deferred the estimated site remediation costs, as a regulatory asset, based on an expectation that the PSCW will continue to allow NSP-Wisconsin to recover payments for environmental remediation from its customers. The PSCW has consistently authorized in NSP-Wisconsin rates recovery of all remediation costs incurred at the Ashland site, and has authorized recovery of MGP remediation costs by other Wisconsin utilities. External MGP remediation costs are subject to deferral in the Wisconsin retail jurisdiction and are reviewed for prudence as part of the Wisconsin retail rate case process. Under an existing PSCW policy, utilities have recovered remediation costs for MGPs in natural gas rates, amortized over a four- to six-year period. The PSCW historically has not allowed utilities to recover their carrying costs on unamortized regulatory assets for MGP remediation.

In the 2013 rate case decision, the PSCW recognized the potential magnitude of the future liability for the cleanup at the Ashland site and granted an exception to its existing policy at the request of NSP-Wisconsin. The elements of this exception include: 1) approval to begin recovery of estimated Phase 1 Project costs beginning on Jan. 1, 2013; 2) approval to amortize these estimated costs over a ten-year period; and 3) approval to apply a three percent carrying cost to the unamortized regulatory asset. In the 2014 rate case decision, the PSCW continued the cost recovery treatment established in the 2013 rate case, with respect to the 2013 and 2014 clean-up costs for the Phase I Project Area. The PSCW determined the timing of the clean-up of the Sediments was uncertain and declined NSP-Wisconsin’s request to begin cost recovery for this portion of the clean-up in 2014 rates. However, the PSCW allowed NSP-Wisconsin to increase its 2014 amortization expense related to the clean-up by an additional $1.1 million to offset the need for a rate decrease for the natural gas utility. The cost recovery treatment granted by the PSCW in the 2013 and 2014 rate cases will help mitigate the rate impact to natural gas customers and the risk to NSP-Wisconsin from a longer amortization period.

Other MGP Sites NSP-Wisconsin is currently involved in investigating and/or remediating several other MGP sites where hazardous or other regulated materials may have been deposited. NSP-Wisconsin has identified two sites, where former MGP activities have or may have resulted in site contamination and are under current investigation and/or remediation. At some or all of these MGP sites, there are other parties that may have responsibility for some portion of any remediation. NSP-Wisconsin anticipates that the majority of the remediation at these sites will continue through at least 2014. NSP-Wisconsin had accrued $3.9 million and $2.5 million for both of these sites at Dec. 31, 2013 and 2012, respectively. There may be insurance recovery and/or recovery from other PRPs that will offset any costs incurred. NSP-Wisconsin anticipates that any amounts spent will be fully recovered from customers.

Environmental Requirements

Water and waste
Asbestos Removal — Some of NSP-Wisconsin’s facilities contain asbestos. Most asbestos will remain undisturbed until the facilities that contain it are demolished or removed. NSP-Wisconsin has recorded an estimate for final removal of the asbestos as an ARO. It may be necessary to remove some asbestos to perform maintenance or make improvements to other equipment. The cost of removing asbestos as part of other work is not expected to be material and is recorded as incurred as operating expenses for maintenance projects, capital expenditures for construction projects or removal costs for demolition projects.

Federal Clean Water Act (CWA) Effluent Limitations Guidelines (ELG) — In June 2013, the EPA published a proposed ELG rule for power plants that use coal, natural gas, oil or nuclear materials as fuel and discharge treated effluent to surface waters as well as utility-owned landfills that receive coal combustion residuals. Refuse derived fuel, biomass and other alternatively fueled power plants are not addressed by the proposed revisions. The proposed rule identifies four potential regulatory options and invites comments on those regulatory approaches. The options differ in the number of waste streams covered, size of the units controlled and stringency of controls. It is not yet known when the EPA will issue a finalized rule. Under the current proposed rule, facilities would need to comply as soon as possible after July 2017 but no later than July 2022. The impact of this rule on NSP-Wisconsin is uncertain at this time.

Federal CWA Section 316 (b) — The federal CWA requires the EPA to regulate cooling water intake structures to assure that these structures reflect the best technology available for minimizing adverse environmental impacts to aquatic species. In 2011, the EPA published the proposed rule that sets standards for minimization of aquatic species impingement, but leaves entrainment reduction requirements at the discretion of the permit writer and the regional EPA office. A final rule is anticipated in April 2014. It is not possible to provide an accurate estimate of the overall cost of this rulemaking at this time due to the uncertainty of the final regulatory requirements.

Proposed Coal Ash Regulation — NSP-Wisconsin’s operations are subject to federal and state laws that impose requirements for handling, storage, treatment and disposal of hazardous waste. In 2010, the EPA published a proposed rule on whether to regulate coal combustion byproducts (coal ash) as hazardous or nonhazardous waste. Coal ash is currently exempt from hazardous waste regulation. NSP-Wisconsin’s costs for the management and disposal of coal ash would significantly increase and the beneficial reuse of coal ash would be negatively impacted if the EPA ultimately issues a rule under which coal ash is regulated as hazardous waste. The EPA has entered into a consent decree to act on final regulations by December 2014. The timing, scope and potential cost of any final rule that might be implemented are not determinable at this time.

Air
EPA GHG Regulation — In 2009, the EPA issued its “endangerment” finding that GHG emissions pose a threat to public health and welfare. This finding required the EPA to adopt GHG emission standards for mobile sources. In 2011, new EPA permitting requirements became effective for GHG emissions of new and modified large stationary sources, which are applicable to the construction of new power plants or power plant modifications that increase emissions above a certain threshold. These rules were upheld on appeal to the D.C. Circuit. The U.S. Supreme Court has granted review on one issue related to these rules, specifically whether the EPA’s regulation of GHG emissions from mobile sources triggered, by operation of law, new source review permitting requirements for stationary sources, which was the EPA’s basis for adopting the 2011 permitting rules. The Court is scheduled to hear arguments in February 2014. A ruling is anticipated by June 2014. NSP-Wisconsin is unable to determine the cost of compliance with these new EPA requirements as it is not clear whether these requirements will apply to future changes at NSP-Wisconsin’s power plants.

GHG Emission Standard for Existing Sources and NSPS Proposal — In June 2013, President Obama issued a memorandum directing the EPA to develop GHG emission standards for existing power plants. The memorandum anticipates the EPA will issue a proposed GHG emission standard for existing power plants in June 2014. It is not possible to evaluate the impact of existing source standards until the upcoming proposal and final requirements are known.

In January 2014, the EPA re-proposed a GHG NSPS for newly constructed power plants which seeks to establish CO2 emission rates for coal-fired power plants that reflect emission reductions using partial carbon capture and storage technology (CCS). The EPA’s proposed CO2 emission limits for gas-fired power plants reflect emissions levels from combined cycle technology with no CCS. The EPA continues to propose that the NSPS not apply to modified or reconstructed existing power plants. In addition, installation of control equipment on existing plants would not constitute a “modification” to those plants under the NSPS program. It is not possible to evaluate the impact of the re-proposed NSPS until its final requirements are known.

CSAPR In 2011, the EPA issued the CSAPR to address long range transport of PM and ozone by requiring reductions in SO2 and NOx from utilities in the eastern half of the United States, including Wisconsin. The CSAPR would have set more stringent requirements than the proposed Clean Air Transport Rule. The rule also would have created an emissions trading program.

In August 2012, the D.C. Circuit vacated the CSAPR and remanded it back to the EPA. The D.C. Circuit stated that the EPA must continue administering the CAIR pending adoption of a valid replacement. In December 2013, the U.S. Supreme Court heard oral arguments on the D.C. Circuit’s 2012 decision to vacate the CSAPR. A decision is anticipated by June 2014. It is not yet known whether the D.C. Circuit’s decision will be upheld, or how the EPA might approach a replacement rule. Therefore, it is not known what requirements may be imposed in the future.

As the EPA continues administering the CAIR while the CSAPR or a replacement rule is pending, NSP-Wisconsin expects to comply with the CAIR as described below.

CAIR — In 2005, the EPA issued the CAIR to further regulate SO2 and NOx emissions. Under the CAIR’s cap and trade structure, companies can comply through capital investments in emission controls or purchase of emission allowances from other utilities making reductions on their systems. NSP-Wisconsin purchased allowances in 2012 and 2013 and plans to continue to purchase allowances in 2014 to comply with the CAIR. At Dec. 31, 2013, the estimated annual CAIR NOx allowance cost for NSP-Wisconsin did not have a material impact on the results of operations, financial position or cash flows.

Electric Generating Unit (EGU) Mercury and Air Toxics Standards (MATS) Rule — The final EGU MATS rule became effective in April 2012. The EGU MATS rule sets emission limits for acid gases, mercury and other hazardous air pollutants and requires coal-fired utility facilities greater than 25 MW to demonstrate compliance within three to four years of the effective date. NSP-Wisconsin will not have any units subject to EGU MATS because it will cease coal combustion in Bay Front Unit 5.

Industrial Boiler (IB) MACT Rules — In 2011, the EPA finalized IB MACT rules to regulate boilers and process heaters fueled with coal, biomass and liquid fuels, which would apply to NSP-Wisconsin’s Bay Front Units 1 and 2. The capital cost to install controls to meet the requirements in the final reconsidered rule is anticipated to be $17.2 million in total and is targeted for completion in 2014.

Revisions to National Ambient Air Quality Standards (NAAQS) for PM — In December 2012, the EPA lowered the primary health-based NAAQS for annual average fine PM and retained the current daily standard for fine PM. In areas where NSP-Wisconsin operates power plants, current monitored air concentrations are below the level of the final annual primary standard. The EPA is expected to designate non-compliant locations by December 2014. States would then study the sources of the nonattainment and make emission reduction plans to attain the standards. It is not possible to evaluate the impact of this regulation further until the final designations have been made.

Asset Retirement Obligations

Recorded AROs — AROs have been recorded for property related to the following: electric production (steam, other and hydro), electric distribution and transmission, natural gas transmission and distribution, and general property.  The electric production obligations include ash-containment facilities, storage tanks, control panels and asbestos.  The asbestos recognition associated with the steam production includes certain plants.  This asbestos abatement removal obligation originated in 1973 with the CAA, which applied to the demolition of buildings or removal of equipment containing asbestos that can become airborne on removal.  The electric transmission and distribution ARO consists of many small potential obligations associated with PCBs, mineral oil, storage tanks, treated poles, lithium batteries, mercury and street lighting lamps.  The common general AROs include small obligations related to storage tanks and office buildings. These assets have numerous in-service dates for which it is difficult to assign the obligation to a particular year. Therefore, the obligation was measured using an average service life.

A reconciliation of NSP-Wisconsin’s AROs is shown in the tables below for the years ended Dec. 31, 2013 and 2012, respectively:
(Thousands of Dollars)
 
Beginning Balance
Jan. 1, 2013
 
Liabilities Recognized
 
Accretion
 
Revisions to
Prior Estimates
 
Ending Balance
Dec. 31, 2013 (a)
Electric plant
 
 
 
 
 
 
 
 
 
 
Steam production asbestos
 
$
1,962

 
$

 
$
43

 
$

 
$
2,005

Steam and other production ash containment
 
125

 

 
12

 
224

 
361

Electric distribution
 
13

 

 
1

 
22

 
36

Other
 
826

 

 
20

 
(557
)
 
289

Natural gas plant
 
 

 
 
 
 
 
 
 
 
Gas transmission and distribution
 
75

 

 
5

 
(5
)
 
75

Common and other property
 
 
 
 
 
 
 
 
 
 
Common miscellaneous
 
35

 

 
3

 
49

 
87

Total liability (b)
 
$
3,036

 
$

 
$
84

 
$
(267
)
 
$
2,853

(Thousands of Dollars)
 
Beginning Balance
Jan. 1, 2012
 
Liabilities Recognized
 
Accretion
 
Revisions to
Prior Estimates
 
Ending Balance
Dec. 31, 2012 (a)
Electric plant
 
 
 
 
 
 
 
 
 
 
Steam production asbestos
 
$

 
$
1,962

 
$

 
$

 
$
1,962

Steam and other production ash containment
 
120

 

 
5

 

 
125

Electric distribution
 
13

 

 

 

 
13

Other
 
186

 

 
7

 
633

 
826

Natural gas plant
 
 
 
 
 
 
 
 
 
 
Gas transmission and distribution
 
71

 

 
4

 

 
75

Common and other property
 
 
 
 
 
 
 
 
 
 
Common miscellaneous
 
34

 

 
1

 

 
35

Total liability (b)
 
$
424

 
$
1,962

 
$
17

 
$
633

 
$
3,036


(a) 
There were no ARO liabilities settled during the 12 months ended Dec. 31, 2013 or 2012.
(b) 
Included in the other long-term liabilities balance in the consolidated balance sheets.

In 2013, NSP-Wisconsin revised ash containment facilities, miscellaneous electric production, electric transmission and distribution, natural gas transmission and distribution and common general AROs due to revised estimated cash flows. In 2012, NSP-Wisconsin revised electric transmission and distribution AROs due to revised estimated cash flows.  Additionally, in 2012, an ARO was recorded to reflect the expected costs with asbestos abatement at certain steam production facilities.

Removal Costs NSP-Wisconsin records a regulatory liability for plant removal costs of steam and other generation, transmission and distribution facilities. Generally, the accrual of future non-ARO removal obligations is not required.  However, long-standing ratemaking practices approved by applicable state and federal regulatory commissions have allowed provisions for such costs in historical depreciation rates. These removal costs have accumulated over a number of years based on varying rates as authorized by the appropriate regulatory entities. Given the long periods over which the amounts were accrued and the changing of rates through time, NSP-Wisconsin has estimated the amount of removal costs accumulated through historic depreciation expense based on current factors used in the existing depreciation rates.  Accordingly, the recorded amounts of estimated future removal costs are considered regulatory liabilities. Removal costs as of Dec. 31, 2013 and 2012 were $116 million and $114 million, respectively.

Legal Contingencies

NSP-Wisconsin is involved in various litigation matters that are being defended and handled in the ordinary course of business. The assessment of whether a loss is probable or is a reasonable possibility, and whether the loss or a range of loss is estimable, often involves a series of complex judgments about future events.  Management maintains accruals for such losses that are probable of being incurred and subject to reasonable estimation.  Management is sometimes unable to estimate an amount or range of a reasonably possible loss in certain situations, including but not limited to when (1) the damages sought are indeterminate, (2) the proceedings are in the early stages, or (3) the matters involve novel or unsettled legal theories.  In such cases, there is considerable uncertainty regarding the timing or ultimate resolution of such matters, including a possible eventual loss.  For current proceedings not specifically reported herein, management does not anticipate that the ultimate liabilities, if any, arising from such current proceedings would have a material effect on NSP-Wisconsin’s financial statements. Unless otherwise required by GAAP, legal fees are expensed as incurred.