XML 58 R47.htm IDEA: XBRL DOCUMENT v3.10.0.1
Commitments and Contingencies, Environmental Contingencies - Site Contingencies (Details)
$ in Millions
9 Months Ended 12 Months Ended
Sep. 30, 2018
USD ($)
Dec. 31, 2017
USD ($)
Other MGP Sites [Member]    
Manufactured Gas Plant (MGP) Site [Abstract]    
Accrual for Environmental Loss Contingencies, Gross $ 4 $ 4
Number of identified MGP sites under current investigation and/or remediation in addition to those separately disclosed 11  
NSP-Wisconsin | Ashland MGP Site    
Manufactured Gas Plant (MGP) Site [Abstract]    
Accrual for Environmental Loss Contingencies, Gross $ 28 30
Current Cost Estimate for Site Remediation 184  
Estimated amount spent on cleanup $ 156  
Approved amortization period for recovery of remediation costs in natural gas rates (in years) 10  
Carrying cost percentage to be applied to unamortized regulatory asset 3.00%  
NSP-Minnesota | Fargo MGP Site    
Manufactured Gas Plant (MGP) Site [Abstract]    
Accrual for Environmental Loss Contingencies, Gross $ 6 16
Current Cost Estimate for Site Remediation 25  
Estimated amount spent on cleanup $ 19  
Percentage of Response Costs Allocable to the Minnesota Jurisdiction 88.00%  
PSCW Proceeding - Gas Rate Case 2017 - Gas Rates 2017 | NSP-Wisconsin | Ashland MGP Site    
Manufactured Gas Plant (MGP) Site [Abstract]    
Public Utilities, Requested annual recovery collected through base rates   $ 12
PSCW Proceeding - Gas Rate Case 2017 - Gas Rates 2018 [Member] | NSP-Wisconsin | Ashland MGP Site    
Manufactured Gas Plant (MGP) Site [Abstract]    
Public Utilities, Requested annual recovery collected through base rates $ 18