XML 48 R24.htm IDEA: XBRL DOCUMENT v3.8.0.1
Commitments and Contingencies
12 Months Ended
Dec. 31, 2017
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
Commitments and Contingencies

Commitments

Capital Commitments — Xcel Energy has made commitments in connection with a portion of its projected capital expenditures. Xcel Energy’s capital commitments primarily relate to the following major projects:

NSP-Minnesota Upper Midwest Wind Projects NSP-Minnesota has gained approval to build and own 1,150 MW of new wind generation in the Upper Midwest. NSP-Minnesota is also seeking approval from the MPUC to build and own the Dakota Range project, a 300 MW wind project in South Dakota.

PSCo Advanced Grid Intelligence and Security Initiative PSCo is pursuing projects to update and advance its electric distribution grid to increase reliability and security standards, meet customer expectations, offer additional customer choice and control over energy usage and implement new rate structures.

PSCo Rush Creek Wind Farm PSCo has gained approval to build, own and operate a 600 MW wind generation facility and proposed transmission line in Colorado.
PSCo Gas Transmission Integrity Management Programs PSCo is proactively identifying and addressing the safety and reliability of natural gas transmission pipelines. The pipeline integrity efforts include primarily pipeline assessment and maintenance projects.

PSCo Electric Distribution Integrity Management Programs PSCo is assessing aging infrastructure for distribution assets and replacing worn components to increase system performance.

SPS Transmission NTC SPS has accepted NTCs for several hundred miles of transmission line and related substation projects based on needs identified through SPP’s various planning processes, including those associated with economics, reliability, generator interconnection and the load addition processes. Most significant are the 345 KV transmission line from TUCO to Yoakum County to Hobbs Plant and the Hobbs Plant to China Draw 345 KV transmission lines.

SPS New Mexico and Texas Wind Projects SPS is seeking approval from the NMPRC and the PUCT to build, own and operate 1,000 MW of new wind generation through the addition of two wind generation facilities in New Mexico and Texas.

Fuel Contracts — Xcel Energy has entered into various long-term commitments for the purchase and delivery of a significant portion of its current coal, nuclear fuel and natural gas requirements. These contracts expire in various years between 2018 and 2060. Xcel Energy is required to pay additional amounts depending on actual quantities shipped under these agreements.

The estimated minimum purchases for Xcel Energy under these contracts as of Dec. 31, 2017 are as follows:
(Millions of Dollars)
 
Coal
 
Nuclear fuel
 
Natural gas supply
 
Natural gas
storage and
transportation
2018
 
$
655

 
$
61

 
$
391

 
$
263

2019
 
255

 
118

 
288

 
251

2020
 
146

 
34

 
277

 
237

2021
 
59

 
85

 
280

 
227

2022
 
59

 
66

 
127

 
217

Thereafter
 
186

 
379

 
57

 
1,046

Total
 
$
1,360

 
$
743

 
$
1,420

 
$
2,241



Additional expenditures for fuel and natural gas storage and transportation will be required to meet expected future electric generation and natural gas needs. Xcel Energy’s risk of loss, in the form of increased costs from market price changes in fuel, is mitigated through the use of natural gas and energy cost-rate adjustment mechanisms, which provide for pass-through of most fuel, storage and transportation costs to customers.

PPAs NSP Minnesota, PSCo and SPS have entered into PPAs with other utilities and energy suppliers with expiration dates through 2039 for purchased power to meet system load and energy requirements and meet operating reserve obligations. In general, these agreements provide for energy payments, based on actual energy delivered and capacity payments. Certain PPAs accounted for as executory contracts also contain minimum energy purchase commitments. Capacity and energy payments are typically contingent on the IPPs meeting contract obligations, including plant availability requirements. Contractual payments are adjusted based on market indices. The effects of price adjustments on our financial results are mitigated through purchased energy cost recovery mechanisms.

Included in electric fuel and purchased power expenses for PPAs accounted for as executory contracts were payments for capacity of $168 million, $191 million and $231 million in 2017, 2016 and 2015, respectively. At Dec. 31, 2017, the estimated future payments for capacity and energy that the utility subsidiaries of Xcel Energy are obligated to purchase pursuant to these executory contracts, subject to availability, are as follows:
(Millions of Dollars)
 
Capacity
 
Energy (a)
2018
 
$
133

 
$
93

2019
 
87

 
99

2020
 
68

 
105

2021
 
73

 
140

2022
 
77

 
155

Thereafter
 
205

 
368

Total
 
$
643

 
$
960

(a) 
Excludes contingent energy payments for renewable energy PPAs.

Additional energy payments under these PPAs and PPAs accounted for as operating leases will be required to meet expected future electric demand.

Leases — Xcel Energy leases a variety of equipment and facilities. Three of these leases are accounted for as capital leases. The assets and liabilities at the inception of a capital lease are recorded at the lower of fair market value or the present value of future lease payments and are amortized over the term of the contract.

WYCO is a joint venture with CIG to develop and lease natural gas pipeline, storage, and compression facilities. Xcel Energy Inc. has a 50 percent ownership interest in WYCO. WYCO generally leases its facilities to CIG, and CIG operates the facilities, providing natural gas storage services to PSCo under separate service agreements.

PSCo accounts for its Totem natural gas storage service arrangement with CIG as a capital lease. As a result, PSCo had $124 million and $127 million of capital lease obligations as of Dec. 31, 2017 and 2016, respectively. Xcel Energy Inc. eliminates 50 percent of the capital lease obligation related to WYCO in the consolidated balance sheet along with an equal amount of Xcel Energy Inc.’s equity investment in WYCO.

PSCo records amortization for its capital leases as cost of natural gas sold and transported on the consolidated statements of income. Total amortization expenses under capital lease assets were approximately $5 million, $8 million and $8 million for 2017, 2016 and 2015, respectively. Following is a summary of property held under capital leases:
(Millions of Dollars)
 
Dec. 31, 2017
 
Dec. 31, 2016
Gas storage facilities
 
$
201

 
$
201

Gas pipeline
 
21

 
21

Property held under capital leases
 
222

 
222

Accumulated depreciation
 
(71
)
 
(66
)
Total property held under capital leases, net
 
$
151

 
$
156



The remainder of the leases, primarily for office space, railcars, generating facilities, natural gas pipeline transportation, vehicles, aircraft and power-operated equipment, are accounted for as operating leases. Total expenses under operating lease obligations for Xcel Energy were approximately $246 million, $255 million and $265 million for 2017, 2016 and 2015, respectively. These expenses include capacity payments for PPAs accounted for as operating leases of $210 million, $216 million and $224 million in 2017, 2016 and 2015, respectively, recorded to electric fuel and purchased power expenses.

Included in the future commitments under operating leases are estimated future capacity payments under PPAs that have been accounted for as operating leases in accordance with the applicable accounting guidance. Future commitments under operating and capital leases are:
(Millions of Dollars)
 
Operating
Leases
 
        PPA (a) (b)
Operating
Leases
 
Total
Operating
Leases
 
Capital Leases
 
2018
 
$
25

 
$
213

 
$
238

 
$
15

 
2019
 
30

 
230

 
260

 
14

 
2020
 
24

 
244

 
268

 
14

 
2021
 
24

 
246

 
270

 
14

 
2022
 
22

 
235

 
257

 
12

 
Thereafter
 
148

 
1,682

 
1,830

 
233

 
Total minimum obligation
 
 
 
 
 
 
 
302

 
Interest component of obligation
 
 
 
 
 
 
 
(213
)
 
Present value of minimum obligation
 
 
 
 
 
 
 
$
89

(c) 
(a) 
Amounts do not include PPAs accounted for as executory contracts.
(b) 
PPA operating leases contractually expire through 2039.
(c) 
Future commitments exclude certain amounts related to Xcel Energy’s 50 percent ownership interest in WYCO.

Variable Interest Entities — The accounting guidance for consolidation of VIEs requires enterprises to consider the activities that most significantly impact an entity’s financial performance, and power to direct those activities, when determining whether an enterprise is a VIE’s primary beneficiary.

PPAs Under certain PPAs, NSP-Minnesota, PSCo and SPS purchase power from IPPs for which the utility subsidiaries are required to reimburse natural gas or biomass fuel costs, or to participate in tolling arrangements under which the utility subsidiaries procure the natural gas required to produce the energy that they purchase. In addition, certain solar PPAs provide the utility subsidiaries with an option to purchase emission allowances or sharing provisions related to production credits generated by the solar facility under contract. These specific PPAs create a variable interest in the IPP.

Xcel Energy has determined that certain IPPs are VIEs. Xcel Energy is not subject to risk of loss from the operations of these entities, and no significant financial support has been, or is required to be provided other than contractual payments for energy and capacity set forth in the PPAs.

Xcel Energy has evaluated each of these VIEs for possible consolidation, including review of qualitative factors such as the length and terms of the contract, control over O&M, control over dispatch of electricity, historical and estimated future fuel and electricity prices, and financing activities. Xcel Energy has concluded that these entities are not required to be consolidated in its consolidated financial statements because it does not have the power to direct the activities that most significantly impact the entities’ economic performance. Xcel Energy’s utility subsidiaries had approximately 3,537 MW of capacity under long-term PPAs at both Dec. 31, 2017 and 2016 with entities that have been determined to be VIEs. These agreements have expiration dates through the year 2041.

Fuel Contracts — SPS purchases all of its coal requirements for its Harrington and Tolk electric generating stations from TUCO under contracts for those facilities that will expire in December 2022. TUCO arranges for the purchase, receiving, transporting, unloading, handling, crushing, weighing, and delivery of coal to meet SPS’ requirements. TUCO is responsible for negotiating and administering contracts with coal suppliers, transporters and handlers.

No significant financial support has been, or is required to be provided to TUCO by SPS, other than contractual payments for delivered coal. However, the fuel contracts create a variable interest in TUCO due to SPS’ reimbursement of certain fuel procurement costs. SPS has determined that TUCO is a VIE. SPS has concluded that it is not the primary beneficiary of TUCO because SPS does not have the power to direct the activities that most significantly impact TUCO’s economic performance.

Low-Income Housing Limited Partnerships — Eloigne and NSP-Wisconsin have entered into limited partnerships for the construction and operation of affordable rental housing developments which qualify for low-income housing tax credits. Xcel Energy Inc. has determined Eloigne and NSP-Wisconsin’s low-income housing limited partnerships to be VIEs primarily due to contractual arrangements within each limited partnership that establish sharing of ongoing voting control and profits and losses that does not consistently align with the partners’ proportional equity ownership. Xcel Energy Inc. has determined that Eloigne and NSP-Wisconsin have the power to direct the activities that most significantly impact these entities’ economic performance, and therefore Xcel Energy Inc. consolidates these limited partnerships in its consolidated financial statements.

Equity financing for these entities has been provided by Eloigne, NSP-Wisconsin and the general partner of each limited partnership. Xcel Energy’s risk of loss is limited to its capital contributions, adjusted for any distributions and its share of undistributed profits and losses; no significant additional financial support has been, or is required to be provided to the limited partnerships by Eloigne or NSP-Wisconsin. Obligations of the limited partnerships are generally secured by the housing properties of each limited partnership, and the creditors of each limited partnership have no significant recourse to Xcel Energy Inc. or its subsidiaries. Likewise, the assets of the limited partnerships may only be used to settle obligations of the limited partnerships, and not those of Xcel Energy Inc. or its subsidiaries.

Amounts reflected in Xcel Energy’s consolidated balance sheets for the Eloigne and NSP-Wisconsin low-income housing limited partnerships include the following:
(Millions of Dollars)
 
Dec. 31, 2017
 
Dec. 31, 2016
Current assets
 
$
6

 
$
7

Property, plant and equipment, net
 
46

 
50

Other noncurrent assets
 
1

 
1

Total assets
 
$
53

 
$
58

 
 
 
 
 
Current liabilities
 
$
9

 
$
8

Mortgages and other long-term debt payable
 
26

 
30

Other noncurrent liabilities
 
1

 
1

Total liabilities
 
$
36

 
$
39



Technology Agreements — Xcel Energy has a contract that extends through December 2022 with International Business Machines Corp. (IBM) for information technology services. The contract is cancelable at Xcel Energy’s option, although Xcel Energy would be obligated to pay 50 percent of the contract value for early termination. Xcel Energy capitalized or expensed $98 million, $119 million and $109 million associated with the IBM contract in 2017, 2016 and 2015, respectively.

Xcel Energy’s contract with Accenture for information technology services extends through December 2020. The contract is cancelable at Xcel Energy’s option, although there are financial penalties for early termination. Xcel Energy capitalized or expensed $16 million, $35 million and $17 million associated with the Accenture contract in 2017, 2016 and 2015, respectively.

Committed minimum payments under these obligations are as follows:
(Millions of Dollars)
 
IBM
Agreement
 
Accenture
Agreement
2018
 
$
26

 
$
11

2019
 
26

 
11

2020
 
8

 
11

2021
 
8

 

2022
 
3

 

Thereafter
 

 



Guarantees and Indemnifications

Xcel Energy Inc. and its subsidiaries provide guarantees and bond indemnities under specified agreements or transactions, which guarantee payment or performance. Xcel Energy Inc.’s exposure is based upon the net liability of the relevant subsidiary under the specified agreements or transactions. Most of the guarantees and bond indemnities issued by Xcel Energy Inc. and its subsidiaries limit the exposure to a maximum stated amount. As of Dec. 31, 2017 and 2016, Xcel Energy Inc. and its subsidiaries had no assets held as collateral related to their guarantees, bond indemnities and indemnification agreements.

Guarantees and Surety Bonds

The following table presents guarantees and bond indemnities issued and outstanding as of Dec. 31, 2017:
(Millions of Dollars)
 
Guarantor
 
Guarantee
Amount
 
Current
Exposure
 
Triggering
Event
Guarantee of customer loans for the Farm Rewiring Program (a)
 
NSP-Wisconsin
 
$
1.0

 
$

 
(f) 
Guarantee of the indemnification obligations of Xcel Energy Services Inc. under the aircraft leases (b)
 
Xcel Energy Inc.
 
12.0

 

 
(g) 
Guarantee of residual value of assets under the Bank of Tokyo-Mitsubishi Capital Corporation Equipment Leasing Agreement (c)
 
NSP-Minnesota
 
4.8

 

 
(h) 
Guarantee of loan for Hiawatha Collegiate High School (d)
 
Xcel Energy Inc.
 
1.0

 

 
(g) 
Total guarantees issued
 
 
 
$
18.8

 
$

 
 
Guarantee performance and payment of surety bonds for Xcel Energy Inc.’s utility subsidiaries (e)
 
Xcel Energy Inc.
 
$
53.1

 
(j) 
 
(i) 
(a) 
The term of this guarantee expires in 2020, which is the final scheduled repayment date for the loans. As of Dec. 31, 2017, no claims had been made by the lender.
(b) 
The terms of this guarantee expires in 2021 and 2023 when the associated leases expire.
(c) 
The term of this guarantee expires in 2019 when the associated lease expires.
(d) 
The term of this guarantee expires the earlier of 2024 or full repayment of the loan.
(e) 
The surety bonds primarily relate to workers compensation benefits and utility projects. The workers compensation bonds are renewed annually and the project based bonds expire in conjunction with the completion of the related projects.
(f) 
The debtor becomes the subject of bankruptcy or other insolvency proceedings.
(g) 
Nonperformance and/or nonpayment.
(h) 
Actual fair value of leased assets is less than the guaranteed residual value amount at the end of the lease term.
(i) 
Failure of any one of Xcel Energy Inc.’s utility subsidiaries to perform under the agreement that is the subject of the relevant bond. In addition, per the indemnity agreement between Xcel Energy Inc. and the various surety companies, the surety companies have the discretion to demand that collateral be posted.
(j) 
Due to the magnitude of projects associated with the surety bonds, the total current exposure of this indemnification cannot be determined. Xcel Energy Inc. believes the exposure to be significantly less than the total amount of the outstanding bonds.

Indemnification Agreements

Xcel Energy Inc. and its subsidiaries provide indemnifications through contracts entered into in the normal course of business. These are primarily indemnifications against adverse litigation outcomes in connection with underwriting agreements, as well as breaches of representations and warranties, including corporate existence, transaction authorization and income tax matters with respect to assets sold. Xcel Energy Inc.’s and its subsidiaries’ obligations under these agreements may be limited in terms of duration and amount. The maximum future payments under these indemnifications cannot be reasonably estimated as the dollar amounts are often not explicitly stated.

Environmental Contingencies

Xcel Energy has been or is currently involved with the cleanup of contamination from certain hazardous substances at several sites. In many situations, the subsidiary involved believes it will recover some portion of these costs through insurance claims. Additionally, where applicable, the subsidiary involved is pursuing, or intends to pursue, recovery from other PRPs and through the regulated rate process. New and changing federal and state environmental mandates can also create added financial liabilities for Xcel Energy, which are normally recovered through the regulated rate process. To the extent any costs are not recovered through the options listed above, Xcel Energy would be required to recognize an expense.

Site Remediation Various federal and state environmental laws impose liability, without regard to the legality of the original conduct, where hazardous substances or other regulated materials have been released to the environment. Xcel Energy Inc.’s subsidiaries may sometimes pay all or a portion of the cost to remediate sites where past activities of their predecessors or other parties have caused environmental contamination. Environmental contingencies could arise from various situations, including sites of former MGPs operated by Xcel Energy Inc.’s subsidiaries or their predecessors, or other entities; and third-party sites, such as landfills, for which one or more of Xcel Energy Inc.’s subsidiaries are alleged to be a PRP that sent wastes to that site.

MGP Sites

Ashland MGP Site — NSP-Wisconsin was named a PRP for contamination at a site in Ashland, Wis. The Ashland/Northern States Power Lakefront Superfund Site (the Site) includes NSP-Wisconsin property, previously operated as a MGP facility (the Upper Bluff), and two other properties: an adjacent city lakeshore park area (Kreher Park); and an area of Lake Superior’s Chequamegon Bay adjoining the park.

In 2012, NSP-Wisconsin agreed to remediate the Phase I Project Area (which includes the Upper Bluff and Kreher Park areas of the Site), under a settlement agreement with the EPA. In January 2017, NSP-Wisconsin agreed to remediate the Phase II Project Area (the Sediments), under a settlement agreement with the EPA. The settlement agreements were approved by the U.S. District Court for the Western District of Wisconsin. NSP-Wisconsin initiated a full scale wet dredge remedy of the Sediments in 2017. Going forward, NSP-Wisconsin anticipates completion of restoration activities of the Sediments in 2018 with finalization of Phase I Project Area construction and restoration activities in 2019. Groundwater treatment activities at the Site will continue.

The current cost estimate for the entire site (both Phase I Project Area and the Sediments) is approximately $168 million, of which approximately $138 million has been spent. As of Dec. 31, 2017 and 2016, NSP-Wisconsin had recorded a total liability of $30 million and $64 million, respectively, for the entire site.

NSP-Wisconsin has deferred the unrecovered portion of the estimated Site remediation costs as a regulatory asset. The PSCW has authorized NSP-Wisconsin rate recovery for all remediation costs incurred at the Site. In 2012, the PSCW agreed to allow NSP-Wisconsin to pre-collect certain costs, to amortize costs over a ten-year period and to apply a three percent carrying cost to the unamortized regulatory asset. In December 2017, the PSCW approved an NSP-Wisconsin natural gas rate case, which included recovery of additional expenses associated with remediating the Site. The annual recovery of MGP clean-up costs will increase from $12 million in 2017 to $18 million in 2018.

Fargo, N.D. MGP Site — In May 2015, underground pipes, tars and impacted soils were discovered in a right-of-way in Fargo, N.D. that appeared to be associated with a former MGP operated by NSP-Minnesota or prior companies. NSP-Minnesota removed impacted soils and other materials and commenced an investigation of the historic MGP and adjacent properties (the Fargo MGP Site). The North Dakota Department of Health approved NSP-Minnesota’s proposed cleanup plan in January 2017, which involves targeted source removal of impacted soils and historic MGP infrastructure. It is anticipated that remediation activities will be performed in 2018. NSP-Minnesota has also initiated insurance recovery litigation in North Dakota. The U.S. District Court for the District of North Dakota agreed to the parties’ request for a stay of the litigation until May 31, 2018.

NSP-Minnesota had recorded an estimated liability of $16 million as of Dec. 31, 2017, and $11 million as of Dec. 31, 2016, for the Fargo MGP Site. The current cost estimate for the remediation of the site is approximately $23 million, of which approximately $7 million has been spent. NSP-Minnesota has deferred Fargo MGP Site costs allocable to the North Dakota jurisdiction, or approximately 88 percent of all remediation costs, as approved by the NDPSC. In December 2017, NSP-Minnesota filed a request with the MPUC to defer post-2017 expenditures allocable to the Minnesota jurisdiction.

Other MGP, Landfill or Disposal Sites Xcel Energy is currently involved in investigating and/or remediating several MGP, landfill or other disposal sites. Xcel Energy has identified twelve sites across its service territories in addition to the sites in Ashland and Fargo, where contamination is present and where investigation and/or remediation activities are currently underway. Other parties may have responsibility for some portion of the investigation and/or remediation activities that are underway. Xcel Energy anticipates that these investigation or remediation activities will continue through at least 2018. Xcel Energy had accrued $4 million as of Dec. 31, 2017 and $2 million as of Dec. 31, 2016 for all of these sites. There may be insurance recovery and/or recovery from other PRPs that will offset any costs incurred. Xcel Energy anticipates that any amounts spent will be fully recovered from customers.

Environmental Requirements

Water and Waste
Asbestos Removal — Some of Xcel Energy’s facilities contain asbestos. Most asbestos will remain undisturbed until the facilities that contain it are demolished or removed. Xcel Energy has recorded an estimate for final removal of the asbestos as an ARO. It may be necessary to remove some asbestos to perform maintenance or make improvements to other equipment. The cost of removing asbestos as part of other work is not expected to be material and is recorded as incurred as operating expenses for maintenance projects, capital expenditures for construction projects or removal costs for demolition projects.

Coal Ash Regulation Xcel Energy’s operations are subject to federal and state laws that impose requirements for handling, storage, treatment and disposal of solid waste. In 2015, the EPA published a final rule regulating the management, storage, and disposal of coal combustion residuals (CCRs) as a nonhazardous waste (CCR Rule). Industry and environmental non-governmental organizations sought judicial review of the final CCR Rule, but a final decision has not been issued in that litigation. The EPA announced in late 2017 its intent to revise the CCR Rule. It is anticipated that the EPA will publish the revised rule in the first quarter of 2018.

Under the CCR Rule, utilities were required to complete groundwater sampling around their CCR landfills and surface impoundments and to analyze the results by early 2018 to determine if there were any statistically significant increases (SSIs) above background levels of certain constituents in the groundwater. Xcel Energy has identified SSIs at several sites located in Colorado and one site in Minnesota. Going forward, Xcel Energy will either conduct additional groundwater sampling to determine whether another source besides plant operations is impacting groundwater and/or to determine if corrective action is needed. Several Xcel Energy sites where SSIs were identified were already undergoing cessation of coal operations and closure of the on-site coal units and therefore no further corrective action is expected at those sites.

Until a final decision is reached in the litigation, the EPA publishes its revised rule, and Xcel Energy completes additional groundwater sampling, it is uncertain what impact, if any, there will be on the operations, financial position or cash flows of Xcel Energy. Xcel Energy believes that any associated costs would be recoverable through regulatory mechanisms.

Federal CWA Waters of the United States Rule In 2015, the EPA and the U.S. Army Corps of Engineers (Corps) published a final rule that significantly expanded the types of water bodies regulated under the CWA and broadened the scope of waters subject to federal jurisdiction. In October 2015, the U.S. Court of Appeals for the Sixth Circuit issued a nationwide stay of the final rule and subsequently ruled that it, rather than the federal district courts, had jurisdiction over challenges to the rule.  In January 2017, the U.S. Supreme Court agreed to resolve the dispute as to which court should hear challenges to the rule. A ruling is expected in 2018.

In February 2017, President Trump issued an executive order requiring the EPA and the Corps to review and revise the final rule. In June 2017, the agencies issued a proposed rule that rescinds the final rule and reinstates the prior definition of “Water of the U.S.” The agencies are also undertaking a rulemaking to develop a new definition of “Waters of the U.S.”

Federal CWA Effluent Limitations Guidelines (ELG) — In 2015, the EPA issued a final ELG rule for power plants that use coal, natural gas, oil or nuclear materials as fuel and discharge treated effluent to surface waters as well as utility-owned landfills that receive coal combustion residuals.  In 2017, the EPA delayed the compliance date for flue gas desulfurization wastewater and bottom ash transport until November 2020 while the agency conducts a rulemaking process to potentially revise the effluent limitations and pretreatment standards for these waste streams.

Federal CWA Section 316(b) — The federal CWA requires the EPA to regulate cooling water intake structures to assure that these structures reflect the best technology available for minimizing adverse environmental impacts to aquatic species. The EPA published the final 316(b) rule in 2014. The rule prescribes technology for protecting fish that get stuck on plant intake screens (known as impingement) and describes a process for site-specific determinations by each state for sites that must protect the small aquatic organisms that pass through the intake screens into the plant cooling systems (known as entrainment). For Xcel Energy, these requirements will primarily impact plants at NSP-Minnesota. Xcel Energy estimates the likely cost for complying with impingement requirements may be incurred between 2018 and 2027 and is approximately $41 million with the majority needed for NSP-Minnesota. Xcel Energy believes at least six NSP-Minnesota plants and two NSP-Wisconsin plants could be required by state regulators to make improvements to reduce entrainment. The exact total cost of the entrainment improvements is uncertain, but could be up to $192 million. Xcel Energy anticipates these costs will be fully recoverable in rates.

Air
GHG Emission Standard for Existing Sources (CPP) — In 2015, the EPA issued its final CPP rule for existing power plants.  Among other things, the CPP requires that state plans include enforceable measures to ensure emissions from existing power plants achieve the EPA’s state-specific interim and final emission performance targets. 

The CPP was challenged by multiple parties in the D.C. Circuit Court.  In February 2016, the U.S. Supreme Court issued an order staying the final CPP rule. The stay will remain in effect until the D.C. Circuit Court reaches its decision and the U.S. Supreme Court either declines to review the lower court’s decision or reaches a decision of its own.

In March 2017, President Trump signed an executive order requiring the EPA Administrator to review the CPP rule and if appropriate publish proposed rules suspending, revising or rescinding it. Accordingly, the EPA requested that the D.C. Circuit Court hold the litigation in abeyance until the EPA completes its work under the executive order. The D.C. Circuit granted the EPA’s request and is holding the litigation in abeyance, while considering briefs by the parties on whether the court should remand the challenges to the EPA rather than holding them in abeyance, determining whether and how the court continues or ends the stay that currently applies to the CPP.

In October 2017, the EPA published a proposed rule to repeal the CPP, based on an analysis that the CPP exceeds the EPA’s statutory authority under the CAA. In the proposal, the EPA stated it has not yet determined whether it will promulgate a new rule to regulate GHG emissions from existing EGUs. In December 2017, the EPA issued an Advanced Notice of Proposed Rulemaking to take and consider comments on whether to issue a future rule and what such a rule should include.

CSAPR — CSAPR addresses long range transport of PM and ozone by requiring reductions in SO2 and NOx from utilities in the eastern half of the United States using an emissions trading program. For Xcel Energy, the rule applies in Minnesota, Wisconsin and Texas.

CSAPR was adopted to address interstate emissions impacting downwind states’ attainment of the ozone and particulate NAAQS. As the EPA revises NAAQS, it will consider whether to make any further reductions to CSAPR emission budgets and whether to change which states are included in the emissions trading program.

In September 2017, the EPA adopted a final rule that withdraws Texas from the CSAPR particle program and determines that further emission reductions in Texas are not needed to address interstate particle transport. Texas is no longer subject to the annual SO2 and NOX emission budgets under CSAPR. In November 2017, the National Parks Conservation Association and Sierra Club appealed this rule to the D.C. Circuit Court. In January 2018, the Court granted SPS’ motion to intervene in support of the EPA’s final rule.

Regional Haze Rules — The regional haze program requires SO2, NOX and PM emission controls at power plants and other industrial facilities to reduce visibility impairment in national parks and wilderness areas. The program is divided into two parts: BART and reasonable further progress. The requirements of the first regional haze plans developed by Minnesota and Colorado that apply to NSP-Minnesota and PSCo have been fully approved and implemented. Texas’ first regional haze plan has undergone federal review as described below.

BART Determination for Texas: The EPA published a proposed BART rule for Texas in January 2017 that could have required installation of dry scrubbers to reduce SO2 emissions from Harrington Units 1 and 2. Investment costs associated with dry scrubbers for Harrington Units 1 and 2 could have been approximately $400 million. In October 2017, the EPA issued a revised final rule adopting a BART alternative Texas only SO2 trading program that applies to all Harrington and Tolk units. Under the trading program, SPS expects the allowance allocations to be sufficient for SO2 emissions from units in 2019 and future years. The anticipated costs of compliance are not expected to have a material impact on the results of operations, financial position or cash flows; and SPS believes that compliance costs would be recoverable through regulatory mechanisms.

Several parties have challenged whether the final rule issued by the EPA should be considered to have met the requirements imposed in a Consent Decree entered the United States District Court for the District of Columbia that established deadlines for the EPA to take final action on state regional haze plan submissions. The matter is now submitted to the court.

In December 2017, the National Parks Conservation Association, Sierra Club, and Environmental Defense Fund appealed the EPA’s October 2017 final BART rule to the Fifth Circuit, and filed a petition for administrative reconsideration of the final rule with the EPA. In January 2018, the court granted SPS’ motion to intervene in the Fifth Circuit litigation in support of the EPA’s final rule.

Reasonable Progress Rule: In January 2016, the EPA adopted a final rule establishing a federal implementation plan for reasonable further progress under the regional haze program for the state of Texas. The rule imposes SO2 emission limitations that would require the installation of dry scrubbers on Tolk Units 1 and 2, with compliance required by February 2021. Investment costs associated with dry scrubbers could be approximately $600 million. SPS appealed the EPA’s decision and obtained a stay of the final rule. In March 2017, the Fifth Circuit remanded the rule to the EPA for reconsideration, leaving the stay in effect. In a future rulemaking, the EPA will address whether SO2 emission reductions beyond those required in the BART alternative rule are needed at Tolk under the “reasonable progress” requirements of the regional haze program. The risk of these controls being imposed along with the risk of investments to provide additional cooling water to Tolk have caused SPS to seek to decrease the remaining depreciable life of the Tolk units. The EPA has not announced a schedule for acting on the remanded rule.

Implementation of the NAAQS for SO2 — The EPA adopted a more stringent NAAQS for SO2 in 2010, and evaluated areas in three phases. In December 2017, the EPA adopted a final rule that completed its initial designations of areas attaining or not attaining the standard. The EPA’s final actions designate all areas near Xcel Energy’s generating plants as meeting the SO2 NAAQS with two exceptions. In June 2016, the EPA issued final designations which found the areas near the SPS Harrington and PSCo Pawnee plants as “unclassifiable.” The area near the Harrington plant is to be monitored for three years and a final designation is expected to be made by December 2020. Since the 2016 “unclassifiable” designation, the Colorado Department of Public Health and Environment has prepared and submitted air dispersion modeling to the EPA demonstrating that the area near the Pawnee plant meets the SO2 NAAQS. The EPA has not yet completed its evaluation of the Pawnee plant.

If the area near the Harrington plant is designated nonattainment in 2020, the Texas Commission on Environmental Quality (TCEQ) will need to develop an implementation plan, which would be due by 2022, designed to achieve the NAAQS by 2025. The TCEQ could require additional SO2 controls at Harrington as part of such a plan. Xcel Energy cannot evaluate the impacts until the final designation is made and any required state plans are developed. Xcel Energy believes that should SO2 control systems be required or require upgrades for a plant, compliance costs or the costs of alternative cost-effective generation will be recoverable through regulatory mechanisms and therefore does not expect a material impact on results of operations, financial position or cash flows.

Revisions to the NAAQS for Ozone — In 2015, the EPA revised the NAAQS for ozone by lowering the eight-hour standard from 75 parts per billion (ppb) to 70 ppb. In November 2017, the EPA published final designations of areas that meet the 2015 ozone standard. Xcel Energy meets the 2015 ozone standard in all areas where its generating units operate, except for the Denver Metropolitan Area. PSCo’s scheduled retirement of coal fired plants in Denver that began in 2011 and was completed in August 2017, should help in any plan to mitigate non-attainment. The EPA has not yet taken final action on the designation, but notified the State of Colorado in December 2017 that it intends to designate the parts of the Denver Metropolitan Area that currently do not attain the 2008 ozone standards as also not attaining the more stringent 2015 ozone standard.

Asset Retirement Obligations

Recorded AROs — AROs have been recorded for property related to the following: electric production (nuclear, steam, wind, other and hydro), electric distribution and transmission, natural gas production, natural gas transmission and distribution, natural gas storage, thermal and general property. The electric production obligations include asbestos, processed water and ash-containment facilities, radiation sources, storage tanks, control panels and decommissioning. The asbestos recognition associated with electric production includes certain plants at NSP-Minnesota, NSP-Wisconsin, PSCo and SPS. AROs also have been recorded for NSP-Minnesota, NSP-Wisconsin, PSCo and SPS steam production related to processed water and ash-containment facilities such as ash ponds, evaporation ponds and solid waste landfills. NSP-Minnesota and PSCo have also recorded AROs for the retirement and removal of assets at certain wind production facilities for which the land is leased and removal is required by contract.

Xcel Energy has recognized AROs for the retirement costs of natural gas mains and lines at NSP-Minnesota, NSP-Wisconsin and PSCo and AROs for the retirement of above ground gas gathering equipment, impoundments at gas extraction sites and wells related to gas storage facilities at PSCo. In addition, an ARO was recognized for the removal of electric transmission and distribution equipment at NSP-Minnesota, NSP-Wisconsin, PSCo and SPS, which consists of obligations associated with polychlorinated biphenyl, mineral oil, lithium batteries, mercury and street lighting lamps. The common general AROs include obligations related to storage tanks, radiation sources and office buildings.

For the nuclear assets, the ARO is associated with the decommissioning of the NSP-Minnesota nuclear generating plants, Monticello and PI. See Note 14 for further discussion of nuclear obligations.

A reconciliation of Xcel Energy’s AROs for the years ended Dec. 31, 2017 and 2016 is as follows:
(Millions of Dollars)
 
Beginning
Balance
Jan. 1, 2017
 
Liabilities
Recognized
 
Liabilities
Settled (a)
 
Accretion
 
Cash Flow Revisions (b)
 
Ending
Balance
Dec. 31, 2017
Electric plant
 
 
 
 
 
 
 
 
 
 
 
 
Nuclear production decommissioning
 
$
2,249

 
$

 
$

 
$
114

 
$
(489
)
 
$
1,874

Steam and other production ash containment
 
117

 

 
(16
)
 
5

 
9

 
115

Wind production
 
92

 

 

 
4

 

 
96

Steam, hydro and other production asbestos
 
88

 
1

 
(13
)
 
4

 
(3
)
 
77

Electric distribution
 
20

 

 

 
1

 

 
21

Other
 
5

 

 

 

 

 
5

Natural gas plant
 
 
 
 
 
 
 
 
 
 
 
 
Gas transmission and distribution
 
205

 

 

 
8

 
69

 
282

Other
 
4

 

 

 

 

 
4

Common and other property
 
 
 
 
 
 
 
 
 
 
 
 
Common general plant asbestos
 
1

 

 
(1
)
 

 

 

Common miscellaneous
 
1

 

 

 

 

 
1

Total liability
 
$
2,782

 
$
1

 
$
(30
)
 
$
136

 
$
(414
)
 
$
2,475


(a) 
The liabilities settled relate to asbestos abatement projects, the closure of certain ash containment facilities, and removal and proper disposal of storage tanks and other above ground equipment.
(b) 
In 2017, AROs were revised for changes in estimated cash flows and the timing of those cash flows. The nuclear decommissioning ARO decreased due to updated assumptions in the nuclear triennial filing. Changes in the gas transmission and distribution AROs were mainly related to increased labor costs.
The aggregate fair value of NSP-Minnesota’s legally restricted assets, for purposes of funding future nuclear decommissioning, was $2.1 billion as of Dec. 31, 2017, consisting of external investment funds.

(Millions of Dollars)
 
Beginning
Balance
Jan. 1, 2016
 
Liabilities
Recognized
 
Liabilities
Settled
 
Accretion
 
Cash Flow Revisions (b)
 
Ending
Balance
Dec. 31, 2016
Electric plant
 
 
 
 
 
 
 
 
 
 
 
 
Nuclear production decommissioning
 
$
2,141

 
$

 
$

 
$
108

 
$

 
$
2,249

Steam and other production ash containment
 
132

 

 
(6
)
 
5

 
(14
)
 
117

Steam, hydro and other production asbestos
 
84

 

 

 
4

 

 
88

Wind production
 
72

 
17

(a) 

 
3

 

 
92

Electric distribution
 
13

 

 

 
1

 
6

 
20

Other
 
4

 
1

 

 

 

 
5

Natural gas plant
 
 
 
 
 
 
 
 
 
 
 
 
Gas transmission and distribution
 
156

 

 

 
7

 
42

 
205

Other
 
4

 

 

 

 

 
4

Common and other property
 
 
 
 
 
 
 
 
 
 
 
 
Common general plant asbestos
 
1

 

 

 

 

 
1

Common miscellaneous
 
2

 

 

 

 
(1
)
 
1

Total liability
 
$
2,609

 
$
18

 
$
(6
)
 
$
128

 
$
33

 
$
2,782


(a) 
The liability recognized relates to the NSP-Minnesota Courtenay Wind Farm which was placed in service during 2016.
(b) 
In 2016, AROs were revised for changes in estimated cash flows and the timing of those cash flows. Changes in the gas transmission and distribution AROs were mainly related to increased miles of gas mains.

The aggregate fair value of NSP-Minnesota’s legally restricted assets, for purposes of funding future nuclear decommissioning, was $1.9 billion as of Dec. 31, 2016, consisting of external investment funds.

Indeterminate AROs — Outside of the known and recorded asbestos AROs, other plants or buildings may contain asbestos due to the age of many of Xcel Energy’s facilities, but no confirmation or measurement of the amount of asbestos or cost of removal could be determined as of Dec. 31, 2017. Therefore, an ARO has not been recorded for these facilities.

Removal Costs — Xcel Energy records a regulatory liability for the plant removal costs of generation, transmission and distribution facilities of its utility subsidiaries that are recovered currently in rates. Generally, the accrual of future non-ARO removal obligations is not required. However, long-standing ratemaking practices approved by applicable state and federal regulatory commissions have allowed provisions for such costs in historical depreciation rates. These removal costs have accumulated over a number of years based on varying rates as authorized by the appropriate regulatory entities. Given the long time periods over which the amounts were accrued and the changing of rates over time, the utility subsidiaries have estimated the amount of removal costs accumulated through historic depreciation expense based on current factors used in the existing depreciation rates.

The accumulated balances by entity were as follows at Dec. 31:
(Millions of Dollars)
 
2017
 
2016
NSP-Minnesota
 
$
442

 
$
419

PSCo
 
346

 
367

SPS
 
197

 
209

NSP-Wisconsin
 
146

 
140

Total Xcel Energy
 
$
1,131

 
$
1,135


Nuclear Insurance

NSP-Minnesota’s public liability for claims resulting from any nuclear incident is limited to $13.4 billion under the Price-Anderson amendment to the Atomic Energy Act. NSP-Minnesota has secured $450 million of coverage for its public liability exposure with a pool of insurance companies. The remaining $13.0 billion of exposure is funded by the Secondary Financial Protection Program, available from assessments by the federal government in case of a nuclear incident. NSP-Minnesota is subject to assessments of up to $127 million per reactor-incident for each of its three licensed reactors, to be applied for public liability arising from a nuclear incident at any licensed nuclear facility in the United States. The maximum funding requirement is $19 million per reactor per incident during any one year. These maximum assessment amounts are both subject to inflation adjustment by the NRC and state premium taxes. The NRC’s last adjustment was effective September 2013.

NSP-Minnesota purchases insurance for property damage and site decontamination cleanup costs from Nuclear Electric Insurance Ltd. (NEIL) and European Mutual Association for Nuclear Insurance (EMANI). The coverage limits are $2.3 billion for each of NSP-Minnesota’s two nuclear plant sites. NEIL also provides business interruption insurance coverage, including the cost of replacement power obtained during certain prolonged accidental outages of nuclear generating units. Premiums are expensed over the policy term. All companies insured with NEIL are subject to retroactive premium adjustments if losses exceed accumulated reserve funds. Capital has been accumulated in the reserve funds of NEIL and EMANI to the extent that NSP-Minnesota would have no exposure for retroactive premium assessments in case of a single incident under the business interruption and the property damage insurance coverage. However, in each calendar year, NSP-Minnesota could be subject to maximum assessments of approximately $19 million for business interruption insurance and $41 million for property damage insurance if losses exceed accumulated reserve funds.

Legal Contingencies

Xcel Energy is involved in various litigation matters that are being defended and handled in the ordinary course of business. The assessment of whether a loss is probable or is a reasonable possibility, and whether the loss or a range of loss is estimable, often involves a series of complex judgments about future events. Management maintains accruals for such losses that are probable of being incurred and subject to reasonable estimation. Management is sometimes unable to estimate an amount or range of a reasonably possible loss in certain situations, including but not limited to when (1) the damages sought are indeterminate, (2) the proceedings are in the early stages, or (3) the matters involve novel or unsettled legal theories. In such cases, there is considerable uncertainty regarding the timing or ultimate resolution of such matters, including a possible eventual loss. For current proceedings not specifically reported herein, management does not anticipate that the ultimate liabilities, if any, arising from such current proceedings would have a material effect on Xcel Energy’s financial statements. Unless otherwise required by GAAP, legal fees are expensed as incurred.

Employment, Tort and Commercial Litigation

Gas Trading Litigation — e prime inc. (e prime) is a wholly owned subsidiary of Xcel Energy Inc. e prime was in the business of natural gas trading and marketing but has not engaged in natural gas trading or marketing activities since 2003.  Thirteen lawsuits were commenced against e prime and Xcel Energy (and NSP-Wisconsin, in two instances) between 2003 and 2009 alleging fraud and anticompetitive activities in conspiring to restrain the trade of natural gas and manipulate natural gas prices.

e prime, Xcel Energy Inc. and its other affiliates were sued along with several other gas marketing companies. These cases were all consolidated in the U.S. District Court in Nevada. Six of the cases remain active, which includes a multi-district litigation (MDL) matter consisting of a Colorado class (Breckenridge), a Wisconsin class (Arandell Corp.), a Missouri class, a Kansas class, and two other cases identified as “Sinclair Oil” and “Farmland.” In March 2017, summary judgment was granted by the MDL judge in favor of Xcel Energy and e prime in the Sinclair Oil and Farmland cases. In November 2017, the U.S District Court in Nevada granted summary judgment against two plaintiffs in the Arandell Corp. case in favor of Xcel Energy and NSP-Wisconsin, leaving only three individual plaintiffs remaining in the litigation. In addition, the plaintiffs’ motions for class certification and remand back to originating courts in these cases were denied in March 2017. Plaintiffs have appealed the summary judgment motions granted in the Farmland and Sinclair Oil cases and the denial of class certification and remand to the U.S. Court of Appeals for the Ninth Circuit (Ninth Circuit). Oral arguments were heard before the Ninth Circuit in February 2018. A final decision is expected by the end of the first quarter of 2019. Xcel Energy, NSP-Wisconsin and e prime have concluded that a loss is remote.

Line Extension Disputes — In December 2015, Development Recovery Company (DRC) filed a lawsuit in the Denver District Court, stating PSCo failed to award proper allowances and refunds for line extensions to new developments pursuant to the terms of electric and gas service agreements entered into by PSCo and various developers. The dispute involves claims by over fifty developers. In May 2016, the Denver District Court granted PSCo’s motion to dismiss the lawsuit, concluding that jurisdiction over this dispute resides with the CPUC. In June 2016, DRC appealed the Denver District Court’s dismissal of the lawsuit, and the Colorado Court of Appeals affirmed the lower court decision in favor of PSCo. In July 2017, DRC filed a petition to appeal the decision with the Colorado Supreme Court. In February 2018, the Colorado Supreme Court denied DRC’s petition effectively terminating this litigation.

In January 2018, DRC filed a new lawsuit in Boulder County District Court, asserting a single claim that PSCo was required to file its line extension agreements with the CPUC but failed to do so. This claim is substantially similar to the arguments previously raised by DRC. Dates for this proceeding have not been scheduled.

PSCo has concluded that a loss is remote with respect to both of these matters as the service agreements were developed to implement CPUC approved tariffs and PSCo has complied with the tariff provisions. Also, if a loss were sustained, PSCo believes it would be allowed to recover these costs through traditional regulatory mechanisms. The amount or range in dispute is presently unknown and no accrual has been recorded for this matter.

Other Contingencies

See Note 12 for further discussion.