Palo Verde Units 1 and 3
 
Interests in jointly-owned facilities  
Percent Owned 29.10%
Plant in Service $ 1,701,844
Accumulated Depreciation 1,027,523
Construction Work in Progress 22,400
Palo Verde Unit 2
 
Interests in jointly-owned facilities  
Percent Owned 16.80%
Plant in Service 543,972
Accumulated Depreciation 338,918
Construction Work in Progress 10,095
Palo Verde Common
 
Interests in jointly-owned facilities  
Percent Owned 28.00%
Plant in Service 538,818
Accumulated Depreciation 219,801
Construction Work in Progress 81,599
Palo Verde Sale Leaseback
 
Interests in jointly-owned facilities  
Plant in Service 351,050
Accumulated Depreciation 225,925
Four Corners Units 4, 5 and Common
 
Interests in jointly-owned facilities  
Percent Owned 63.00%
Plant in Service 809,946
Accumulated Depreciation 608,194
Construction Work in Progress 14,434
Navajo Generating Station Units 1, 2 and 3
 
Interests in jointly-owned facilities  
Percent Owned 14.00%
Plant in Service 270,448
Accumulated Depreciation 150,501
Construction Work in Progress 2,864
Cholla common facilities
 
Interests in jointly-owned facilities  
Percent Owned 63.30%
Plant in Service 148,299
Accumulated Depreciation 47,851
Construction Work in Progress 7,159
ANPP 500kV System
 
Interests in jointly-owned facilities  
Percent Owned 34.20%
Plant in Service 98,145
Accumulated Depreciation 32,350
Construction Work in Progress 1,095
Navajo Southern System
 
Interests in jointly-owned facilities  
Percent Owned 22.20%
Plant in Service 58,702
Accumulated Depreciation 16,937
Construction Work in Progress 518
Palo Verde - Yuma 500kV System
 
Interests in jointly-owned facilities  
Percent Owned 18.00%
Plant in Service 12,115
Accumulated Depreciation 4,656
Construction Work in Progress 11,786
Four Corners Switchyards
 
Interests in jointly-owned facilities  
Percent Owned 48.10%
Plant in Service 33,460
Accumulated Depreciation 9,052
Construction Work in Progress 185
Phoenix - Mead System
 
Interests in jointly-owned facilities  
Percent Owned 17.10%
Plant in Service 39,758
Accumulated Depreciation 12,140
Palo Verde - Estrella 500kV System
 
Interests in jointly-owned facilities  
Percent Owned 50.00%
Plant in Service 89,571
Accumulated Depreciation 14,883
Construction Work in Progress 21
Morgan-Pinnacle Peak System
 
Interests in jointly-owned facilities  
Percent Owned 64.50%
Plant in Service 130,132
Accumulated Depreciation 6,651
Construction Work in Progress 1,042
Round Valley System
 
Interests in jointly-owned facilities  
Percent Owned 50.00%
Plant in Service 488
Accumulated Depreciation 268
Palo Verde - Morgan System
 
Interests in jointly-owned facilities  
Percent Owned 90.00%
Construction Work in Progress $ 36,601