falsefalse--12-31--12-31Q2Q2202020202020-06-3010-Q00007646220000007286 AZAZ0.20000P5Y1.481.481.571.571500000001500000001125401261125911247000000000000513000080500029200013400013400024200024200087000870004810004810005060005440002180002970003340003610009000012400010354635983 0000764622 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember 2020-01-01 2020-06-30 0000764622 2020-07-30 0000764622 pnw:ArizonaPublicServiceCompanyMember 2020-07-30 0000764622 2020-04-01 2020-06-30 0000764622 2019-04-01 2019-06-30 0000764622 2019-01-01 2019-06-30 0000764622 2020-06-30 0000764622 2019-12-31 0000764622 us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2020-06-30 0000764622 us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2019-12-31 0000764622 2018-12-31 0000764622 2019-06-30 0000764622 us-gaap:CommonStockMember 2019-12-31 0000764622 us-gaap:TreasuryStockMember 2020-01-01 2020-06-30 0000764622 us-gaap:TreasuryStockMember 2020-06-30 0000764622 us-gaap:AccumulatedOtherComprehensiveIncomeMember 2020-01-01 2020-06-30 0000764622 us-gaap:AccumulatedOtherComprehensiveIncomeMember 2019-12-31 0000764622 us-gaap:RetainedEarningsMember 2020-01-01 2020-06-30 0000764622 us-gaap:RetainedEarningsMember 2019-12-31 0000764622 us-gaap:NoncontrollingInterestMember 2020-06-30 0000764622 us-gaap:CommonStockMember 2020-06-30 0000764622 us-gaap:NoncontrollingInterestMember 2020-01-01 2020-06-30 0000764622 us-gaap:CommonStockMember 2020-01-01 2020-06-30 0000764622 us-gaap:TreasuryStockMember 2019-12-31 0000764622 us-gaap:AccumulatedOtherComprehensiveIncomeMember 2020-06-30 0000764622 us-gaap:NoncontrollingInterestMember 2019-12-31 0000764622 us-gaap:RetainedEarningsMember 2020-06-30 0000764622 us-gaap:AccumulatedOtherComprehensiveIncomeMember 2019-04-01 2019-06-30 0000764622 us-gaap:RetainedEarningsMember 2019-04-01 2019-06-30 0000764622 us-gaap:NoncontrollingInterestMember 2019-04-01 2019-06-30 0000764622 us-gaap:TreasuryStockMember 2019-06-30 0000764622 us-gaap:TreasuryStockMember 2019-04-01 2019-06-30 0000764622 us-gaap:AccumulatedOtherComprehensiveIncomeMember 2019-03-31 0000764622 us-gaap:CommonStockMember 2019-06-30 0000764622 us-gaap:NoncontrollingInterestMember 2019-06-30 0000764622 us-gaap:NoncontrollingInterestMember 2019-03-31 0000764622 us-gaap:CommonStockMember 2019-03-31 0000764622 us-gaap:RetainedEarningsMember 2019-06-30 0000764622 us-gaap:AccumulatedOtherComprehensiveIncomeMember 2019-06-30 0000764622 us-gaap:TreasuryStockMember 2019-03-31 0000764622 us-gaap:RetainedEarningsMember 2019-03-31 0000764622 us-gaap:CommonStockMember 2019-04-01 2019-06-30 0000764622 2019-03-31 0000764622 us-gaap:TreasuryStockMember 2020-04-01 2020-06-30 0000764622 us-gaap:AccumulatedOtherComprehensiveIncomeMember 2020-04-01 2020-06-30 0000764622 us-gaap:RetainedEarningsMember 2020-04-01 2020-06-30 0000764622 us-gaap:NoncontrollingInterestMember 2020-03-31 0000764622 us-gaap:TreasuryStockMember 2020-03-31 0000764622 us-gaap:RetainedEarningsMember 2020-03-31 0000764622 us-gaap:CommonStockMember 2020-03-31 0000764622 us-gaap:NoncontrollingInterestMember 2020-04-01 2020-06-30 0000764622 us-gaap:CommonStockMember 2020-04-01 2020-06-30 0000764622 2020-03-31 0000764622 us-gaap:AccumulatedOtherComprehensiveIncomeMember 2020-03-31 0000764622 us-gaap:AccumulatedOtherComprehensiveIncomeMember 2018-12-31 0000764622 us-gaap:RetainedEarningsMember 2019-01-01 2019-06-30 0000764622 us-gaap:AccumulatedOtherComprehensiveIncomeMember 2019-01-01 2019-06-30 0000764622 us-gaap:NoncontrollingInterestMember 2019-01-01 2019-06-30 0000764622 us-gaap:CommonStockMember 2018-12-31 0000764622 us-gaap:CommonStockMember 2019-01-01 2019-06-30 0000764622 us-gaap:RetainedEarningsMember 2018-12-31 0000764622 us-gaap:TreasuryStockMember 2018-12-31 0000764622 us-gaap:TreasuryStockMember 2019-01-01 2019-06-30 0000764622 us-gaap:NoncontrollingInterestMember 2018-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember 2018-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AdditionalPaidInCapitalMember 2019-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RetainedEarningsMember 2019-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:CommonStockMember 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember 2019-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:NoncontrollingInterestMember 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RetainedEarningsMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AdditionalPaidInCapitalMember 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedOtherComprehensiveIncomeMember 2019-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:NoncontrollingInterestMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:CommonStockMember 2019-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:NoncontrollingInterestMember 2019-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RetainedEarningsMember 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedOtherComprehensiveIncomeMember 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedOtherComprehensiveIncomeMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:NoncontrollingInterestMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:CommonStockMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RetainedEarningsMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:CommonStockMember 2020-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:NoncontrollingInterestMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RetainedEarningsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember 2020-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AdditionalPaidInCapitalMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RetainedEarningsMember 2020-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:NoncontrollingInterestMember 2020-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AdditionalPaidInCapitalMember 2020-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedOtherComprehensiveIncomeMember 2020-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedOtherComprehensiveIncomeMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedOtherComprehensiveIncomeMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:NoncontrollingInterestMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AdditionalPaidInCapitalMember 2018-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:CommonStockMember 2018-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedOtherComprehensiveIncomeMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:NoncontrollingInterestMember 2018-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RetainedEarningsMember 2018-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedOtherComprehensiveIncomeMember 2018-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RetainedEarningsMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RetainedEarningsMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:NoncontrollingInterestMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:NoncontrollingInterestMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedOtherComprehensiveIncomeMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RetainedEarningsMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:CommonStockMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedOtherComprehensiveIncomeMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AdditionalPaidInCapitalMember 2019-12-31 0000764622 pnw:ElectricandTransmissionServiceMember 2019-01-01 2019-06-30 0000764622 pnw:ElectricandTransmissionServiceMember 2020-01-01 2020-06-30 0000764622 pnw:ElectricandTransmissionServiceMember 2020-04-01 2020-06-30 0000764622 pnw:ElectricandTransmissionServiceMember 2019-04-01 2019-06-30 0000764622 2019-01-01 2019-12-31 0000764622 pnw:WholesaleMember pnw:ElectricServiceMember 2020-01-01 2020-06-30 0000764622 pnw:OtherServicesMember 2020-01-01 2020-06-30 0000764622 pnw:TransmissionServicesMember 2019-01-01 2019-06-30 0000764622 pnw:RetailNonResidentialMember pnw:ElectricServiceMember 2020-01-01 2020-06-30 0000764622 pnw:TransmissionServicesMember 2020-01-01 2020-06-30 0000764622 pnw:OtherServicesMember 2019-01-01 2019-06-30 0000764622 pnw:RetailResidentialMember pnw:ElectricServiceMember 2019-04-01 2019-06-30 0000764622 pnw:RetailResidentialMember pnw:ElectricServiceMember 2019-01-01 2019-06-30 0000764622 pnw:RetailNonResidentialMember pnw:ElectricServiceMember 2020-04-01 2020-06-30 0000764622 pnw:RetailResidentialMember pnw:ElectricServiceMember 2020-04-01 2020-06-30 0000764622 pnw:OtherServicesMember 2019-04-01 2019-06-30 0000764622 pnw:RetailResidentialMember pnw:ElectricServiceMember 2020-01-01 2020-06-30 0000764622 pnw:RetailNonResidentialMember pnw:ElectricServiceMember 2019-01-01 2019-06-30 0000764622 pnw:TransmissionServicesMember 2020-04-01 2020-06-30 0000764622 pnw:WholesaleMember pnw:ElectricServiceMember 2020-04-01 2020-06-30 0000764622 pnw:WholesaleMember pnw:ElectricServiceMember 2019-04-01 2019-06-30 0000764622 pnw:RetailNonResidentialMember pnw:ElectricServiceMember 2019-04-01 2019-06-30 0000764622 pnw:OtherServicesMember 2020-04-01 2020-06-30 0000764622 pnw:WholesaleMember pnw:ElectricServiceMember 2019-01-01 2019-06-30 0000764622 pnw:TransmissionServicesMember 2019-04-01 2019-06-30 0000764622 srt:ParentCompanyMember us-gaap:CommercialPaperMember pnw:RevolvingCreditFacilityMaturingJuly2023Member 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SeniorUnsecuredNotesMember 2020-05-22 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:TermLoanMember 2020-05-22 2020-05-22 0000764622 pnw:SeniorUnsecuredNotesMember us-gaap:SeniorNotesMember 2020-06-16 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RevolvingCreditFacilityMember pnw:RevolvingCreditFacilityMaturingJune2022Member 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SeniorUnsecuredNotesMember us-gaap:SeniorNotesMember 2020-01-15 2020-01-15 0000764622 2018-11-27 0000764622 pnw:ArizonaPublicServiceCompanyMember 2020-03-26 0000764622 pnw:TermLoanMember 2020-06-17 2020-06-17 0000764622 srt:ParentCompanyMember us-gaap:RevolvingCreditFacilityMember pnw:RevolvingCreditFacilityMaturingJuly2023Member 2020-06-30 0000764622 srt:ParentCompanyMember pnw:TermLoanMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RevolvingCreditFacilityMember pnw:RevolvingCreditFacilityMaturingin2022and2023Member 2020-06-30 0000764622 srt:ParentCompanyMember us-gaap:LetterOfCreditMember pnw:RevolvingCreditFacilityMaturingJuly2023Member 2020-06-30 0000764622 srt:ParentCompanyMember pnw:TermLoanMember 2020-06-30 0000764622 pnw:SeniorUnsecuredNotesMember 2020-06-16 0000764622 srt:ParentCompanyMember pnw:TermLoanMember 2020-05-05 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SeniorUnsecuredNotesMember us-gaap:SeniorNotesMember 2020-01-15 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:CommercialPaperMember pnw:RevolvingCreditFacilityMaturingin2022and2023Member 2020-06-30 0000764622 pnw:SeniorUnsecuredNotesMember us-gaap:SeniorNotesMember 2020-06-17 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:RevolvingCreditFacilityMember pnw:RevolvingCreditFacilityMaturingJuly2023Member 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember srt:MinimumMember pnw:SeniorUnsecuredNotesMember 2020-01-15 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SeniorUnsecuredNotesMember us-gaap:SeniorNotesMember 2020-05-22 0000764622 pnw:SeniorUnsecuredNotesMember 2020-06-17 0000764622 srt:ParentCompanyMember pnw:TermLoanMember 2020-05-04 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:CommercialPaperMember 2020-06-30 0000764622 srt:ParentCompanyMember 2019-12-31 0000764622 srt:ParentCompanyMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:RetailRateCaseFilingwithArizonaCorporationCommissionMember pnw:ArizonaCorporationCommissionMember 2019-10-31 2019-10-31 0000764622 2019-10-31 2019-10-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:RetailRateCaseFilingwithArizonaCorporationCommissionMember 2019-10-31 2019-10-31 0000764622 pnw:TaxExpenseAdjustorMechanismMember 2019-12-31 0000764622 pnw:LostFixedCostRecoveryMember 2019-12-31 0000764622 pnw:LostFixedCostRecoveryMember 2020-06-30 0000764622 pnw:SCRDeferralMember 2019-12-31 0000764622 pnw:DeferredCompensationMember 2020-06-30 0000764622 pnw:TransmissionCostAdjustorMember 2020-06-30 0000764622 pnw:DeferredFuelAndPurchasedPowerMTMCostsMember 2020-06-30 0000764622 us-gaap:OtherRegulatoryAssetsLiabilitiesMember 2019-12-31 0000764622 us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2020-06-30 0000764622 pnw:PensionMember 2020-06-30 0000764622 pnw:PensionMember 2019-12-31 0000764622 us-gaap:LossOnReacquiredDebtMember 2020-06-30 0000764622 pnw:FourCornersCostDeferralMember 2019-12-31 0000764622 pnw:DeferredPropertyTaxesMember 2020-06-30 0000764622 pnw:FourCornersCostDeferralMember 2020-06-30 0000764622 pnw:TransmissionCostAdjustorMember 2019-12-31 0000764622 pnw:DeferredCompensationMember 2019-12-31 0000764622 pnw:AG1DeferralMember 2019-12-31 0000764622 us-gaap:LossOnReacquiredDebtMember 2019-12-31 0000764622 pnw:RetiredPowerPlantCostsMember 2019-12-31 0000764622 pnw:MeadPhoenixtransmissionlineCIACMember 2019-12-31 0000764622 us-gaap:DeferredIncomeTaxChargesMember 2019-12-31 0000764622 pnw:RetiredPowerPlantCostsMember 2020-06-30 0000764622 pnw:CoalReclamationMember 2020-06-30 0000764622 pnw:MeadPhoenixtransmissionlineCIACMember 2020-06-30 0000764622 pnw:CoalReclamationMember 2019-12-31 0000764622 pnw:SCRDeferralMember 2020-06-30 0000764622 pnw:DeferredFuelAndPurchasedPowerMTMCostsMember 2019-12-31 0000764622 pnw:DeferredFuelandPurchasedPowerMember 2020-06-30 0000764622 us-gaap:DeferredIncomeTaxChargesMember 2020-06-30 0000764622 pnw:AG1DeferralMember 2020-06-30 0000764622 pnw:TaxExpenseOfMedicareSubsidyMember 2020-06-30 0000764622 pnw:OctotilloDeferralMember 2020-06-30 0000764622 pnw:DeferredPropertyTaxesMember 2019-12-31 0000764622 pnw:OctotilloDeferralMember 2019-12-31 0000764622 us-gaap:InvestmentCreditMember 2019-12-31 0000764622 pnw:DeferredFuelandPurchasedPowerMember 2019-12-31 0000764622 pnw:TaxExpenseAdjustorMechanismMember 2020-06-30 0000764622 pnw:TaxExpenseOfMedicareSubsidyMember 2019-12-31 0000764622 us-gaap:InvestmentCreditMember 2020-06-30 0000764622 us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2019-12-31 0000764622 us-gaap:OtherRegulatoryAssetsLiabilitiesMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2018-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember 2020-05-05 0000764622 pnw:ArizonaPublicServiceCompanyMember srt:MinimumMember pnw:RetailRateCaseFilingwithArizonaCorporationCommissionMember pnw:ArizonaCorporationCommissionMember 2017-03-27 2017-03-27 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2019-02-01 2019-02-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaCorporationCommissionMember 2019-10-29 2019-10-29 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OpenAccessTransmissionTariffMember pnw:UnitedStatesFederalEnergyRegulatoryCommissionMember 2018-06-01 2018-06-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:RetiredPowerPlantCostsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SolarCommunitiesMember srt:MinimumMember pnw:ArizonaRenewableEnergyStandardandTariff2018Member pnw:ArizonaCorporationCommissionMember 2017-11-20 2017-11-20 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:LostFixedCostRecoveryMechanismsMember 2019-02-15 2019-02-15 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OpenAccessTransmissionTariffMember pnw:UnitedStatesFederalEnergyRegulatoryCommissionMember 2020-06-01 2020-06-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:RetailRateCaseFilingwithArizonaCorporationCommissionMember pnw:ArizonaCorporationCommissionMember 2017-03-27 2017-03-27 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NetMeteringMember pnw:ArizonaCorporationCommissionMember 2016-12-20 2016-12-20 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NetMeteringMember pnw:ArizonaCorporationCommissionMember 2020-05-01 2020-05-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OpenAccessTransmissionTariffMember pnw:UnitedStatesFederalEnergyRegulatoryCommissionMember 2019-06-01 2019-06-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:CostRecoveryMechanismsMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2019-03-15 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:DemandSideManagementAdjustorCharge2020Member pnw:ArizonaCorporationCommissionMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SouthernCaliforniaEdisonCompanyMember pnw:FourCornersUnits4And5Member 2018-09-01 2018-09-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2018-02-01 2018-02-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:LostFixedCostRecoveryMechanismsMember 2020-06-30 0000764622 2019-11-14 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:LostFixedCostRecoveryMechanismsMember 2018-02-15 2018-02-15 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:DemandSideManagementAdjustorCharge2018Member pnw:ArizonaCorporationCommissionMember 2017-09-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:DemandSideManagementAdjustorCharge2020Member pnw:ArizonaCorporationCommissionMember 2020-05-15 0000764622 pnw:ArizonaPublicServiceCompanyMember srt:MaximumMember srt:ScenarioForecastMember us-gaap:DamageFromFireExplosionOrOtherHazardMember 2020-01-01 2020-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:AZSunProgramPhase2Member pnw:RetailRateCaseFilingwithArizonaCorporationCommissionMember pnw:ArizonaCorporationCommissionMember 2017-03-27 2017-03-27 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:RetailRateCaseFilingwithArizonaCorporationCommissionMember pnw:ArizonaCorporationCommissionMember 2019-06-30 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember srt:MaximumMember pnw:RetailRateCaseFilingwithArizonaCorporationCommissionMember pnw:ArizonaCorporationCommissionMember 2017-03-27 2017-03-27 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NavajoPlantMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaRenewableEnergyStandardandTariff2018Member pnw:ArizonaCorporationCommissionMember us-gaap:SubsequentEventMember 2020-07-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaCorporationCommissionMember 2019-04-10 2019-04-10 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:LostFixedCostRecoveryMechanismsMember 2020-02-14 2020-02-14 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2020-02-01 2020-02-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaCorporationCommissionMember 2016-08-01 2016-08-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SolarCommunitiesMember pnw:ArizonaRenewableEnergyStandardandTariff2018Member pnw:ArizonaCorporationCommissionMember 2017-11-20 2017-11-20 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:CostRecoveryMechanismsMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2020-02-01 2020-02-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaCorporationCommissionMember 2018-08-13 2018-08-13 0000764622 2019-11-14 2019-11-14 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaCorporationCommissionMember 2018-01-08 2018-01-08 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NetMeteringMember pnw:ArizonaCorporationCommissionMember 2019-05-01 2019-05-01 0000764622 pnw:ArizonaPublicServiceCompanyMember srt:MinimumMember pnw:ArizonaCorporationCommissionMember 2019-10-31 2019-10-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NetMeteringMember pnw:ArizonaCorporationCommissionMember 2018-05-01 2018-05-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:EnvironmentalImprovementSurchargeMember pnw:UnitedStatesFederalEnergyRegulatoryCommissionMember 2020-02-01 2020-02-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SolarCommunitiesMember srt:MaximumMember pnw:ArizonaRenewableEnergyStandardandTariff2018Member pnw:ArizonaCorporationCommissionMember 2017-11-20 2017-11-20 0000764622 pnw:ArizonaPublicServiceCompanyMember srt:MinimumMember srt:ScenarioForecastMember us-gaap:DamageFromFireExplosionOrOtherHazardMember 2020-01-01 2020-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SouthernCaliforniaEdisonCompanyMember pnw:FourCornersUnits4And5Member 2018-04-01 2018-04-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaRenewableEnergyStandardandTariff2018Member pnw:ArizonaCorporationCommissionMember 2018-06-29 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:DemandSideManagementAdjustorCharge2018Member pnw:ArizonaCorporationCommissionMember 2017-11-14 0000764622 pnw:ArizonaPublicServiceCompanyMember srt:ScenarioForecastMember pnw:EnvironmentalImprovementSurchargeMember pnw:UnitedStatesFederalEnergyRegulatoryCommissionMember 2020-01-01 2020-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaRenewableEnergyStandardandTariff2018Member pnw:ArizonaCorporationCommissionMember 2019-07-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:DemandSideManagementAdjustorCharge2019Member pnw:ArizonaCorporationCommissionMember 2018-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaCorporationCommissionMember 2019-10-31 2019-10-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:CostRecoveryMechanismsMember pnw:PowerSupplyAdjustorMember pnw:ArizonaCorporationCommissionMember 2019-02-01 2019-02-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:LostFixedCostRecoveryMechanismsMember 2017-01-01 2017-12-31 0000764622 pnw:ActiveUnionMedicalTrustMember 2019-12-31 0000764622 pnw:SundanceMaintenanceMember 2019-12-31 0000764622 pnw:SpentNuclearFuelMember 2020-06-30 0000764622 pnw:TaxExpenseAdjustorMechanismMember 2019-12-31 0000764622 us-gaap:InvestmentCreditMember 2020-06-30 0000764622 pnw:FERCTransmissionTrueUpMember 2020-06-30 0000764622 pnw:ArizonaCorporationCommissionMember pnw:TaxCutsandJobsActof2017ExcessDeferredIncomeTaxesMember 2020-06-30 0000764622 pnw:DeferredGainsonUtilityPropertyMember 2020-06-30 0000764622 pnw:UnitedStatesFederalEnergyRegulatoryCommissionMember pnw:TaxCutsandJobsActof2017ExcessDeferredIncomeTaxesMember 2020-06-30 0000764622 pnw:OtherRegulatoryLiabilitiesMember 2019-12-31 0000764622 pnw:OtherRegulatoryLiabilitiesMember 2020-06-30 0000764622 pnw:FourCornersCoalReclamationMember 2020-06-30 0000764622 pnw:ActiveUnionMedicalTrustMember 2020-06-30 0000764622 pnw:SpentNuclearFuelMember 2019-12-31 0000764622 pnw:DemandSideManagementMember 2020-06-30 0000764622 pnw:ArizonaCorporationCommissionMember pnw:TaxCutsandJobsActof2017ExcessDeferredIncomeTaxesMember 2019-12-31 0000764622 pnw:FERCTransmissionTrueUpMember 2019-12-31 0000764622 us-gaap:InvestmentCreditMember 2019-12-31 0000764622 pnw:SundanceMaintenanceMember 2020-06-30 0000764622 pnw:TaxExpenseAdjustorMechanismMember 2020-06-30 0000764622 us-gaap:PostretirementBenefitCostsMember 2019-12-31 0000764622 pnw:UnitedStatesFederalEnergyRegulatoryCommissionMember pnw:TaxCutsandJobsActof2017ExcessDeferredIncomeTaxesMember 2019-12-31 0000764622 us-gaap:RenewableEnergyProgramMember 2020-06-30 0000764622 us-gaap:AssetRetirementObligationCostsMember 2019-12-31 0000764622 pnw:DeferredPropertyTaxesMember 2019-12-31 0000764622 us-gaap:DeferredIncomeTaxChargesMember 2019-12-31 0000764622 us-gaap:RemovalCostsMember 2020-06-30 0000764622 pnw:DeferredPropertyTaxesMember 2020-06-30 0000764622 pnw:FourCornersCoalReclamationMember 2019-12-31 0000764622 us-gaap:PostretirementBenefitCostsMember 2020-06-30 0000764622 pnw:DeferredGainsonUtilityPropertyMember 2019-12-31 0000764622 us-gaap:AssetRetirementObligationCostsMember 2020-06-30 0000764622 pnw:DemandSideManagementMember 2019-12-31 0000764622 us-gaap:DeferredIncomeTaxChargesMember 2020-06-30 0000764622 us-gaap:RemovalCostsMember 2019-12-31 0000764622 us-gaap:RenewableEnergyProgramMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaRenewableEnergyStandardAndTariffMember pnw:ArizonaCorporationCommissionMember 2020-01-01 2020-06-30 0000764622 us-gaap:PensionPlansDefinedBenefitMember 2019-01-01 2019-06-30 0000764622 us-gaap:PensionPlansDefinedBenefitMember 2020-04-01 2020-06-30 0000764622 us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember 2020-01-01 2020-06-30 0000764622 us-gaap:PensionPlansDefinedBenefitMember 2019-04-01 2019-06-30 0000764622 us-gaap:PensionPlansDefinedBenefitMember 2020-01-01 2020-06-30 0000764622 us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember 2019-01-01 2019-06-30 0000764622 us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember 2020-04-01 2020-06-30 0000764622 us-gaap:OtherPostretirementBenefitPlansDefinedBenefitMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SaleLeasebackTransactionPeriodThrough2033Member us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember 1986-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SaleLeasebackTransactionPeriodThrough2023Member us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SaleLeasebackTransactionPeriod2024Through2033Member us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SaleLeasebackTransactionPeriod2016Through2023Member us-gaap:VariableInterestEntityPrimaryBeneficiaryMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SaleLeasebackTransactionPeriod2024Through2033Member us-gaap:VariableInterestEntityPrimaryBeneficiaryMember srt:MaximumMember 2020-01-01 2020-06-30 0000764622 us-gaap:OtherInvestmentsMember us-gaap:CommodityContractMember 2020-06-30 0000764622 pnw:DeferredCreditsMember us-gaap:CommodityContractMember 2020-06-30 0000764622 us-gaap:CommodityContractMember 2020-06-30 0000764622 us-gaap:OtherAssetsMember us-gaap:CommodityContractMember 2020-06-30 0000764622 us-gaap:OtherLiabilitiesMember us-gaap:CommodityContractMember 2020-06-30 0000764622 us-gaap:CommodityContractMember 2019-12-31 0000764622 pnw:RiskManagementAssetsMember us-gaap:CreditConcentrationRiskMember 2020-06-30 2020-06-30 0000764622 pnw:RiskManagementAssetsMember us-gaap:CreditConcentrationRiskMember 2020-06-30 0000764622 us-gaap:CommodityContractMember us-gaap:DesignatedAsHedgingInstrumentMember 2020-01-01 2020-06-30 0000764622 us-gaap:CommodityContractMember us-gaap:NondesignatedMember us-gaap:CostOfSalesMember 2019-01-01 2019-06-30 0000764622 us-gaap:CommodityContractMember us-gaap:NondesignatedMember us-gaap:CostOfSalesMember 2020-01-01 2020-06-30 0000764622 us-gaap:CommodityContractMember us-gaap:NondesignatedMember us-gaap:CostOfSalesMember 2020-04-01 2020-06-30 0000764622 us-gaap:CommodityContractMember us-gaap:NondesignatedMember us-gaap:CostOfSalesMember 2019-04-01 2019-06-30 0000764622 us-gaap:OtherLiabilitiesMember us-gaap:CommodityContractMember 2019-12-31 0000764622 pnw:DeferredCreditsMember us-gaap:CommodityContractMember 2019-12-31 0000764622 us-gaap:OtherAssetsMember us-gaap:CommodityContractMember 2019-12-31 0000764622 us-gaap:CommodityContractMember us-gaap:DesignatedAsHedgingInstrumentMember us-gaap:CostOfSalesMember 2019-04-01 2019-06-30 0000764622 us-gaap:CommodityContractMember us-gaap:DesignatedAsHedgingInstrumentMember us-gaap:CostOfSalesMember 2019-01-01 2019-06-30 0000764622 us-gaap:CommodityContractMember us-gaap:DesignatedAsHedgingInstrumentMember us-gaap:CostOfSalesMember 2020-01-01 2020-06-30 0000764622 us-gaap:CommodityContractMember us-gaap:DesignatedAsHedgingInstrumentMember us-gaap:CostOfSalesMember 2020-04-01 2020-06-30 0000764622 us-gaap:CommodityContractMember 2019-12-31 2019-12-31 0000764622 us-gaap:CommodityContractMember 2020-06-30 2020-06-30 0000764622 us-gaap:CommodityContractMember us-gaap:DesignatedAsHedgingInstrumentMember 2019-01-01 2019-06-30 0000764622 us-gaap:CommodityContractMember us-gaap:DesignatedAsHedgingInstrumentMember 2019-04-01 2019-06-30 0000764622 us-gaap:CommodityContractMember us-gaap:DesignatedAsHedgingInstrumentMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ContaminatedGroundwaterWellsMember 2016-12-16 2016-12-16 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaPublicServiceCompanyandPaloVerdeOwnersvs.UnitedStatesDepartmentofEnergySpentNuclearFuelandWasteDisposalMember 2020-02-11 2020-02-11 0000764622 pnw:ArizonaPublicServiceCompanyandPaloVerdeOwnersvs.UnitedStatesDepartmentofEnergySpentNuclearFuelandWasteDisposalMember 2020-02-11 2020-02-11 0000764622 pnw:NavajoTransitionalEnergyCompanyLLCMember pnw:FourCornersMember 2016-07-06 2016-07-06 0000764622 pnw:A4CAcquisitionLLCMember pnw:FourCornersMember 2020-06-30 0000764622 pnw:NavajoTransitionalEnergyCompanyLLCMember pnw:CoalSupplyAgreementArbitrationMember pnw:FourCornersMember 2016-07-06 2016-07-06 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaPublicServiceCompanyandPaloVerdeOwnersvs.UnitedStatesDepartmentofEnergySpentNuclearFuelandWasteDisposalMember 2011-07-01 2018-06-30 0000764622 pnw:NavajoTransitionalEnergyCompanyLLCMember pnw:FourCornersMember 2018-07-03 2018-07-03 0000764622 pnw:ArizonaPublicServiceCompanyMember srt:MinimumMember pnw:CoalCombustionWasteMember pnw:ChollaMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NaturalGasTollingLetterOfCreditMember pnw:RegionalHazeRulesMember pnw:FourCornersUnits4And5Member 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember srt:MinimumMember pnw:CoalCombustionWasteMember pnw:ChollaandFourCornersMember 2019-01-01 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyandPaloVerdeOwnersvs.UnitedStatesDepartmentofEnergySpentNuclearFuelandWasteDisposalMember 2011-07-01 2018-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ArizonaPublicServiceCompanyandPaloVerdeOwnersvs.UnitedStatesDepartmentofEnergySpentNuclearFuelandWasteDisposalMember 2019-10-31 2019-10-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ContaminatedGroundwaterWellsMember 2013-08-06 2013-08-06 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:RegionalHazeRulesMember pnw:FourCornersMember pnw:FourCornersUnits4And5Member 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SuretyBondsExpiringin2020Member 2020-06-30 0000764622 pnw:A4CAcquisitionLLCMember pnw:FourCornersMember 2016-07-06 2016-07-06 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ContaminatedGroundwaterWellsMember 2018-04-05 2018-04-05 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:CoalCombustionWasteMember pnw:NavajoGeneratingStationMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:SettledLitigationMember pnw:ContaminatedGroundwaterWellsMember 2018-04-05 2018-04-05 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:RegionalHazeRulesMember pnw:FourCornersUnits4And5Member 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:CoalCombustionWasteMember pnw:FourCornersMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:ContaminatedGroundwaterWellsMember 2020-01-01 2020-06-30 0000764622 pnw:A4CAcquisitionLLCMember pnw:CoalSupplyAgreementArbitrationMember pnw:FourCornersMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember srt:MaximumMember pnw:CoalCombustionWasteMember pnw:ChollaandFourCornersMember 2019-01-01 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyandPaloVerdeOwnersvs.UnitedStatesDepartmentofEnergySpentNuclearFuelandWasteDisposalMember 2019-10-31 2019-10-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:LettersofCreditExpiringin2020Member 2020-06-30 0000764622 pnw:SCRDeferralMember 2020-01-01 2020-06-30 0000764622 pnw:OctotilloDeferralMember 2020-04-01 2020-06-30 0000764622 pnw:OctotilloDeferralMember 2019-04-01 2019-06-30 0000764622 pnw:OctotilloDeferralMember 2019-01-01 2019-06-30 0000764622 pnw:SCRDeferralMember 2019-01-01 2019-06-30 0000764622 pnw:OctotilloDeferralMember 2020-01-01 2020-06-30 0000764622 pnw:SCRDeferralMember 2019-04-01 2019-06-30 0000764622 pnw:SCRDeferralMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SCRDeferralMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OctotilloDeferralMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OctotilloDeferralMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OctotilloDeferralMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OctotilloDeferralMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SCRDeferralMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SCRDeferralMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:SCRDeferralMember 2020-04-01 2020-06-30 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:OtherDebtSecuritiesMember 2019-12-31 0000764622 us-gaap:EquitySecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel1Member 2019-12-31 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:CorporateDebtSecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel3Member pnw:USCommingledFundsMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:USStatesAndPoliticalSubdivisionsMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:USTreasurySecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:MortgageBackedSecuritiesMember 2019-12-31 0000764622 us-gaap:USTreasurySecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel2Member 2019-12-31 0000764622 us-gaap:FairValueInputsLevel3Member 2019-12-31 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:EquitySecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel2Member pnw:USCommingledFundsMember 2019-12-31 0000764622 us-gaap:OtherDebtSecuritiesMember 2019-12-31 0000764622 pnw:USCommingledFundsMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:EquitySecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:USStatesAndPoliticalSubdivisionsMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:USTreasurySecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:OtherDebtSecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:CorporateDebtSecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:MortgageBackedSecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:USStatesAndPoliticalSubdivisionsMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:USTreasurySecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:MortgageBackedSecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:CorporateDebtSecuritiesMember 2019-12-31 0000764622 us-gaap:USStatesAndPoliticalSubdivisionsMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel1Member pnw:USCommingledFundsMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:EquitySecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:OtherDebtSecuritiesMember 2019-12-31 0000764622 us-gaap:MortgageBackedSecuritiesMember 2019-12-31 0000764622 us-gaap:CorporateDebtSecuritiesMember 2019-12-31 0000764622 us-gaap:FairValueMeasuredAtNetAssetValuePerShareMember pnw:USCommingledFundsMember 2019-12-31 0000764622 us-gaap:EquitySecuritiesMember 2020-06-30 0000764622 us-gaap:OtherDebtSecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel2Member 2020-06-30 0000764622 us-gaap:FairValueInputsLevel1Member 2020-06-30 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:EquitySecuritiesMember 2020-06-30 0000764622 us-gaap:USStatesAndPoliticalSubdivisionsMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:USTreasurySecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:MortgageBackedSecuritiesMember 2020-06-30 0000764622 us-gaap:CorporateDebtSecuritiesMember 2020-06-30 0000764622 pnw:USCommingledFundsMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:USTreasurySecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:CorporateDebtSecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:CorporateDebtSecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel3Member 2020-06-30 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:USStatesAndPoliticalSubdivisionsMember 2020-06-30 0000764622 us-gaap:FairValueMeasuredAtNetAssetValuePerShareMember pnw:USCommingledFundsMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:EquitySecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:CorporateDebtSecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:USTreasurySecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:OtherDebtSecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:MortgageBackedSecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel3Member us-gaap:OtherDebtSecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:EquitySecuritiesMember 2020-06-30 0000764622 us-gaap:USTreasurySecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel1Member pnw:USCommingledFundsMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:MortgageBackedSecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:OtherDebtSecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel2Member us-gaap:USStatesAndPoliticalSubdivisionsMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel1Member us-gaap:USStatesAndPoliticalSubdivisionsMember 2020-06-30 0000764622 us-gaap:MortgageBackedSecuritiesMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel3Member pnw:USCommingledFundsMember 2020-06-30 0000764622 us-gaap:FairValueInputsLevel2Member pnw:USCommingledFundsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:FixedIncomeSecuritiesMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:FixedIncomeSecuritiesMember pnw:CoalReclamationEscrowAccountsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:FixedIncomeSecuritiesMember pnw:NuclearDecommissioningTrustsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:FixedIncomeSecuritiesMember pnw:ActiveUnionMedicalTrustMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NuclearDecommissioningTrustsMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NuclearDecommissioningTrustsMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherSpecialUseFundsMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherSpecialUseFundsMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherSpecialUseFundsMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NuclearDecommissioningTrustsMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherSpecialUseFundsMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NuclearDecommissioningTrustsMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:EquitySecuritiesMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NuclearDecommissioningTrustsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:EquitySecuritiesMember pnw:NuclearDecommissioningTrustsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherReceivablesfromBrokerDealersandClearingMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:EquitySecuritiesMember pnw:OtherSpecialUseFundsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherReceivablesfromBrokerDealersandClearingMember pnw:NuclearDecommissioningTrustsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherSpecialUseFundsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:FixedIncomeSecuritiesMember pnw:OtherSpecialUseFundsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherReceivablesfromBrokerDealersandClearingMember pnw:OtherSpecialUseFundsMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:FixedIncomeSecuritiesMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:EquitySecuritiesMember pnw:OtherSpecialUseFundsMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:EquitySecuritiesMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:FixedIncomeSecuritiesMember pnw:OtherSpecialUseFundsMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherReceivablesfromBrokerDealersandClearingMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:FixedIncomeSecuritiesMember pnw:NuclearDecommissioningTrustsMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:EquitySecuritiesMember pnw:NuclearDecommissioningTrustsMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NuclearDecommissioningTrustsMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherSpecialUseFundsMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherReceivablesfromBrokerDealersandClearingMember pnw:NuclearDecommissioningTrustsMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:OtherReceivablesfromBrokerDealersandClearingMember pnw:OtherSpecialUseFundsMember 2019-12-31 0000764622 us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2019-06-30 0000764622 us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2020-04-01 2020-06-30 0000764622 us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2019-03-31 0000764622 us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2019-04-01 2019-06-30 0000764622 us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2020-06-30 0000764622 us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2019-04-01 2019-06-30 0000764622 us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2020-04-01 2020-06-30 0000764622 us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2020-03-31 0000764622 us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2020-06-30 0000764622 us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2019-03-31 0000764622 us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2019-06-30 0000764622 us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2020-03-31 0000764622 us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2020-01-01 2020-06-30 0000764622 us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2020-01-01 2020-06-30 0000764622 us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2019-01-01 2019-06-30 0000764622 us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2019-01-01 2019-06-30 0000764622 us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2019-12-31 0000764622 us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2018-12-31 0000764622 us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2019-12-31 0000764622 us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2018-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2020-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2019-04-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2020-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2019-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2019-03-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2019-01-01 2019-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2018-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedGainLossNetCashFlowHedgeParentMember 2019-12-31 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2020-01-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember us-gaap:AccumulatedDefinedBenefitPlansAdjustmentMember 2018-12-31 0000764622 us-gaap:DomesticCountryMember 2020-01-01 2020-06-30 0000764622 2017-01-01 2017-12-31 0000764622 pnw:LandPropertyandEquipmentLeasesMember 2020-04-01 2020-06-30 0000764622 pnw:PurchasedPowerLeaseContractsMember 2020-04-01 2020-06-30 0000764622 pnw:PurchasedPowerLeaseContractsMember 2019-04-01 2019-06-30 0000764622 pnw:LandPropertyandEquipmentLeasesMember 2019-04-01 2019-06-30 0000764622 pnw:PurchasedPowerLeaseContractsMember 2020-06-30 0000764622 pnw:LandPropertyandEquipmentLeasesMember 2020-06-30 0000764622 pnw:PurchasedPowerLeaseContractsMember 2019-01-01 2019-06-30 0000764622 pnw:LandPropertyandEquipmentLeasesMember 2019-01-01 2019-06-30 0000764622 pnw:PurchasedPowerLeaseContractsMember 2020-01-01 2020-06-30 0000764622 pnw:LandPropertyandEquipmentLeasesMember 2020-01-01 2020-06-30 0000764622 2020-06-01 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:NavajoGeneratingStationMember 2020-04-01 2020-06-30 0000764622 pnw:ArizonaPublicServiceCompanyMember pnw:FourCornersMember 2020-04-01 2020-06-30 xbrli:shares iso4217:USD xbrli:shares iso4217:USD pnw:power_plant pnw:agreement pnw:Lease utreg:Bcf pnw:Defendant pnw:Trust pnw:Facility xbrli:pure pnw:plaintiff utreg:GWh utreg:GW pnw:Customer iso4217:USD utreg:kWh pnw:time_period pnw:claim



 
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
WASHINGTON, D.C. 20549
 
 

FORM 10-Q
 
(Mark One)
 
QUARTERLY REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934
 
For the quarterly period ended June 30, 2020
 
OR
 
TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES EXCHANGE ACT OF 1934
 
For the transition period from              to          
 
Commission File
Number
 
Exact Name of Each Registrant as specified in its
charter; State of Incorporation; Address; and
Telephone Number
 
IRS Employer
Identification No.
1-8962
 
PINNACLE WEST CAPITAL CORPORATION
 
86-0512431
 
 
(an Arizona corporation)
 
 
 
 
400 North Fifth Street, P.O. Box 53999
 
 
 
 
Phoenix
Arizona
85072-3999
 
 
 
 
 
(602)
250-1000
 
 
 
 
1-4473
 
ARIZONA PUBLIC SERVICE COMPANY
 
86-0011170
 
 
(an Arizona corporation)
 
 
 
 
400 North Fifth Street, P.O. Box 53999
 
 
 
 
Phoenix
Arizona
85072-3999
 
 
 
 
 
(602)
250-1000
 
 
 
 
 
Securities registered pursuant to Section 12(b) of the Act:
Title of each class
Trading Symbol(s)
Name of each exchange on which registered
Common Stock
PNW
The New York Stock Exchange

Indicate by check mark whether each registrant (1) has filed all reports required to be filed by Section 13 or 15(d) of the Securities Exchange Act of 1934 during the preceding 12 months (or for such shorter period that the registrant was required to file such reports), and (2) has been subject to such filing requirements for the past 90 days.
 
PINNACLE WEST CAPITAL CORPORATION
Yes
 
 
No 
 
ARIZONA PUBLIC SERVICE COMPANY
Yes
 
 
No 
 
 
Indicate by check mark whether the registrant has submitted electronically every Interactive Data File required to be submitted pursuant to Rule 405 of Regulation S-T during the preceding 12 months (or for such shorter period that the registrant was required to submit and post such files).
PINNACLE WEST CAPITAL CORPORATION
Yes
 
 
No 
 
ARIZONA PUBLIC SERVICE COMPANY
Yes
 
 
No 
 
 
Indicate by check mark whether the registrant is a large accelerated filer, an accelerated filer, a non-accelerated filer, smaller reporting company or an emerging growth company.  See the definitions of "large accelerated filer," "accelerated filer," "smaller reporting company," and "emerging growth company" in Rule 12b-2 of the Exchange Act.

 PINNACLE WEST CAPITAL CORPORATION
Large accelerated filer
 
Accelerated filer
Non-accelerated filer
Smaller reporting company
 
 
 
 
 
 
 
 
Emerging growth company
 
 
 
 
 
 
 
ARIZONA PUBLIC SERVICE COMPANY
Large accelerated filer
Accelerated filer
Non-accelerated filer
 
Smaller reporting company
 
 
 
 
 
 
 
 
Emerging growth company
 
 
 
 
 
 
 
If an emerging growth company, indicate by check mark if the registrant has elected not to use the extended transition period for complying with any new or revised financial accounting standards provided pursuant to Section 13(a) of the Exchange Act.

Indicate by check mark whether each registrant is a shell company (as defined in Rule 12b-2 of the Exchange Act).
PINNACLE WEST CAPITAL CORPORATION
Yes  
 
No 
 
ARIZONA PUBLIC SERVICE COMPANY
Yes    
 
No 
 
 
Indicate the number of shares outstanding of each of the issuer’s classes of common stock, as of the latest practicable date.
 
PINNACLE WEST CAPITAL CORPORATION
Number of shares of common stock, no par value, outstanding as of July 30, 2020:
112,556,967
ARIZONA PUBLIC SERVICE COMPANY
Number of shares of common stock, $2.50 par value, outstanding as of July 30, 2020:
71,264,947
 
Arizona Public Service Company meets the conditions set forth in General Instruction H(1)(a) and (b) of Form 10-Q and is therefore filing this form with the reduced disclosure format allowed under that General Instruction.






TABLE OF CONTENTS
 
 
Page
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
This combined Form 10-Q is separately provided by Pinnacle West Capital Corporation ("Pinnacle West") and Arizona Public Service Company ("APS").  Any use of the words "Company," "we," and "our" refer to Pinnacle West.  Each registrant is providing on its own behalf all of the information contained in this Form 10-Q that relates to such registrant and, where required, its subsidiaries.  Except as stated in the preceding sentence, neither registrant is providing any information that does not relate to such registrant, and therefore makes no representation as to any such information.  The information required with respect to each company is set forth within the applicable items.  Item 1 of this report includes Condensed Consolidated Financial Statements of Pinnacle West and Condensed Consolidated Financial Statements of APS.  Item 1 also includes Combined Notes to Condensed Consolidated Financial Statements.


1



FORWARD-LOOKING STATEMENTS
This document contains forward-looking statements based on current expectations.  These forward-looking statements are often identified by words such as "estimate," "predict," "may," "believe," "plan," "expect," "require," "intend," "assume," "project," "anticipate," "goal," "seek," "strategy," "likely," "should," "will," "could," and similar words.  Because actual results may differ materially from expectations, we caution readers not to place undue reliance on these statements.  A number of factors could cause future results to differ materially from historical results, or from outcomes currently expected or sought by Pinnacle West or APS.  In addition to the Risk Factors described in Part I, Item 1A of the Pinnacle West/APS Annual Report on Form 10-K for the fiscal year ended December 31, 2019 ("2019 Form 10-K"), Part II, Item 1A of the Pinnacle West/APS Quarterly Report on Form 10‑Q for the quarter ended March 31, 2020 ("2020 1st Quarter 10-Q"), Part II, Item 1A of this report and in Part I, Item 2 — "Management’s Discussion and Analysis of Financial Condition and Results of Operations" of this report, these factors include, but are not limited to:
the potential effects of the continued Coronavirus ("COVID-19") pandemic, including, but not limited to, demand for energy, economic growth, our employees and contractors, supply chain, expenses, capital markets, capital projects, operations and maintenance activities, uncollectable accounts, liquidity, cash flows or other unpredictable events;
our ability to manage capital expenditures and operations and maintenance costs while maintaining reliability and customer service levels;
variations in demand for electricity, including those due to weather, seasonality, the general economy or social conditions, customer and sales growth (or decline), the effects of energy conservation measures and distributed generation, and technological advancements;
power plant and transmission system performance and outages;
competition in retail and wholesale power markets;
regulatory and judicial decisions, developments and proceedings;
new legislation, ballot initiatives and regulation, including those relating to environmental requirements, regulatory policy, nuclear plant operations and potential deregulation of retail electric markets;
fuel and water supply availability;
our ability to achieve timely and adequate rate recovery of our costs, including returns on and of debt and equity capital investment;
our ability to meet renewable energy and energy efficiency mandates and recover related costs;
risks inherent in the operation of nuclear facilities, including spent fuel disposal uncertainty;
current and future economic conditions in Arizona, including in real estate markets;
the direct or indirect effect on our facilities or business from cybersecurity threats or intrusions, data security breaches, terrorist attack, physical attack, severe storms, droughts, or other catastrophic events, such as fires, explosions, pandemic health events, or similar occurrences;
the development of new technologies which may affect electric sales or delivery;
the cost of debt and equity capital and the ability to access capital markets when required;
environmental, economic and other concerns surrounding coal-fired generation, including regulation of greenhouse gas emissions;
volatile fuel and purchased power costs;
the investment performance of the assets of our nuclear decommissioning trust, pension, and other postretirement benefit plans and the resulting impact on future funding requirements;
the liquidity of wholesale power markets and the use of derivative contracts in our business;
potential shortfalls in insurance coverage;
new accounting requirements or new interpretations of existing requirements;
generation, transmission and distribution facility and system conditions and operating costs;
the ability to meet the anticipated future need for additional generation and associated transmission facilities in our region;
the willingness or ability of our counterparties, power plant participants and power plant land owners to meet contractual or other obligations or extend the rights for continued power plant operations; and
restrictions on dividends or other provisions in our credit agreements and Arizona Corporation Commission ("ACC") orders. 

2



These and other factors are discussed in the Risk Factors described in Part I, Item 1A of our 2019 Form 10-K, Part II, Item 1A of our 2020 1st Quarter 10-Q, and in Part II, Item 1A of this report, and in Part I, Item 2 — "Management’s Discussion and Analysis of Financial Condition and Results of Operations" of this report, which readers should review carefully before placing any reliance on our financial statements or disclosures.  Neither Pinnacle West nor APS assumes any obligation to update these statements, even if our internal estimates change, except as required by law.

3



PART I — FINANCIAL INFORMATION
 
ITEM 1.  FINANCIAL STATEMENTS
 
 INDEX TO FINANCIAL STATEMENTS AND FINANCIAL STATEMENT SCHEDULES
 
 
Page
 
 
 
 
 
 



4




PINNACLE WEST CAPITAL CORPORATION
CONDENSED CONSOLIDATED STATEMENTS OF INCOME
(unaudited)
(dollars and shares in thousands, except per share amounts)
 
 
 
Three Months Ended
June 30,
 
Six Months Ended
June 30,
 
 
2020
 
2019
 
2020
 
2019
 
 
 
 
 
 
 
 
 
OPERATING REVENUES (NOTE 2)
 
$
929,590

 
$
869,501

 
$
1,591,520

 
$
1,610,031

 
 
 
 
 
 
 
 
 
OPERATING EXPENSES
 
 

 
 

 
 
 
 
Fuel and purchased power
 
238,382

 
242,222

 
426,903

 
472,810

Operations and maintenance
 
219,392

 
227,543

 
440,710

 
473,177

Depreciation and amortization
 
152,482

 
147,374

 
306,561

 
296,081

Taxes other than income taxes
 
56,768

 
55,090

 
113,536

 
110,180

Other expenses
 
692

 
683

 
1,514

 
1,110

Total
 
667,716

 
672,912

 
1,289,224

 
1,353,358

OPERATING INCOME
 
261,874

 
196,589

 
302,296

 
256,673

OTHER INCOME (DEDUCTIONS)
 
 

 
 

 
 
 
 
Allowance for equity funds used during construction
 
8,811

 
7,572

 
16,508

 
18,760

Pension and other postretirement non-service credits - net
 
14,142

 
6,374

 
28,053

 
11,488

Other income (Note 9)
 
16,670

 
12,885

 
29,239

 
20,054

Other expense (Note 9)
 
(4,036
)
 
(4,350
)
 
(8,820
)
 
(8,708
)
Total
 
35,587

 
22,481

 
64,980

 
41,594

INTEREST EXPENSE
 
 

 
 

 
 
 
 
Interest charges
 
62,690

 
57,465

 
121,924

 
118,118

Allowance for borrowed funds used during construction
 
(4,749
)
 
(4,494
)
 
(8,825
)
 
(11,159
)
Total
 
57,941

 
52,971

 
113,099

 
106,959

INCOME BEFORE INCOME TAXES
 
239,520

 
166,099

 
254,177

 
191,308

INCOME TAXES
 
41,061

 
17,080

 
20,852

 
19,498

NET INCOME
 
198,459

 
149,019

 
233,325

 
171,810

Less: Net income attributable to noncontrolling interests (Note 6)
 
4,874

 
4,874

 
9,747

 
9,747

NET INCOME ATTRIBUTABLE TO COMMON SHAREHOLDERS
 
$
193,585

 
$
144,145

 
$
223,578

 
$
162,063

 
 
 
 
 
 
 
 
 
WEIGHTED-AVERAGE COMMON SHARES OUTSTANDING — BASIC
 
112,638

 
112,337

 
112,616

 
112,381

WEIGHTED-AVERAGE COMMON SHARES OUTSTANDING — DILUTED
 
112,879

 
112,651

 
112,871

 
112,734

 
 
 
 
 
 
 
 
 
EARNINGS PER WEIGHTED-AVERAGE COMMON SHARE OUTSTANDING
 
 

 
 

 
 
 
 
Net income attributable to common shareholders — basic
 
$
1.72

 
$
1.28

 
$
1.99

 
$
1.44

Net income attributable to common shareholders — diluted
 
$
1.71

 
$
1.28

 
$
1.98

 
$
1.44

 
The accompanying notes are an integral part of the financial statements.

5



PINNACLE WEST CAPITAL CORPORATION
CONDENSED CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME
(unaudited)
(dollars in thousands)
 
 
Three Months Ended
June 30,
 
Six Months Ended
June 30,
 
2020
 
2019
 
2020
 
2019
 
 
 
 
 
 
 
 
NET INCOME
$
198,459

 
$
149,019

 
$
233,325

 
$
171,810

 
 
 
 
 
 
 
 
OTHER COMPREHENSIVE INCOME, NET OF TAX
 

 
 

 
 
 
 
Derivative instruments:
 

 
 

 
 
 
 
Net unrealized loss, net of tax benefit of $513, $0, $805 and $0
(1,549
)
 

 
(1,257
)
 

Reclassification of net realized loss, net of tax benefit of $87, $134, $481 and $242
262

 
404

 
282

 
732

Pension and other postretirement benefits activity, net of tax benefit of $334, $506, $90 and $218
(1,009
)
 
(1,539
)
 
196

 
(660
)
Total other comprehensive income (loss)
(2,296
)
 
(1,135
)
 
(779
)
 
72

 
 
 
 
 
 
 
 
COMPREHENSIVE INCOME
196,163

 
147,884

 
232,546

 
171,882

Less: Comprehensive income attributable to noncontrolling interests
4,874

 
4,874

 
9,747

 
9,747

 
 
 
 
 
 
 
 
COMPREHENSIVE INCOME ATTRIBUTABLE TO COMMON SHAREHOLDERS
$
191,289

 
$
143,010

 
$
222,799

 
$
162,135

 
The accompanying notes are an integral part of the financial statements.


6



PINNACLE WEST CAPITAL CORPORATION
CONDENSED CONSOLIDATED BALANCE SHEETS
(unaudited)
(dollars in thousands)
 
 
June 30, 2020
 
December 31, 2019
ASSETS
 

 
 

 
 
 
 
CURRENT ASSETS
 

 
 

Cash and cash equivalents
$
6,763

 
$
10,283

Customer and other receivables
279,480

 
266,426

Accrued unbilled revenues
191,578

 
128,165

Allowance for doubtful accounts
(11,579
)
 
(8,171
)
Materials and supplies (at average cost)
318,368

 
331,091

Fossil fuel (at average cost)
17,257

 
14,829

Income tax receivable
17,122

 
21,727

Assets from risk management activities (Note 7)
710

 
515

Deferred fuel and purchased power regulatory asset (Note 4)
101,425

 
70,137

Other regulatory assets (Note 4)
150,169

 
133,070

Other current assets
75,796

 
61,958

Total current assets
1,147,089

 
1,030,030

INVESTMENTS AND OTHER ASSETS
 

 
 

Nuclear decommissioning trust (Notes 11 and 12)
1,024,033

 
1,010,775

Other special use funds (Notes 11 and 12)
253,332

 
245,095

Other assets
92,295

 
96,953

Total investments and other assets
1,369,660

 
1,352,823

PROPERTY, PLANT AND EQUIPMENT
 

 
 

Plant in service and held for future use
20,343,151

 
19,836,292

Accumulated depreciation and amortization
(6,905,049
)
 
(6,637,857
)
Net
13,438,102

 
13,198,435

Construction work in progress
823,691

 
808,133

Palo Verde sale leaseback, net of accumulated depreciation (Note 6)
99,971

 
101,906

Intangible assets, net of accumulated amortization
275,028

 
290,564

Nuclear fuel, net of accumulated amortization
152,219

 
123,500

Total property, plant and equipment
14,789,011

 
14,522,538

DEFERRED DEBITS
 

 
 

Regulatory assets (Note 4)
1,315,846

 
1,304,073

Operating lease right-of-use assets (Note 16)
555,783

 
145,813

Assets for other postretirement benefits (Note 5)
99,801

 
90,570

Other
30,198

 
33,400

Total deferred debits
2,001,628

 
1,573,856

 
 
 
 
TOTAL ASSETS
$
19,307,388

 
$
18,479,247

 
The accompanying notes are an integral part of the financial statements.


7



PINNACLE WEST CAPITAL CORPORATION
CONDENSED CONSOLIDATED BALANCE SHEETS
(unaudited)
(dollars in thousands)
 
June 30, 2020
 
December 31, 2019
LIABILITIES AND EQUITY
 

 
 

 
 
 
 
CURRENT LIABILITIES
 

 
 

Accounts payable
$
316,230

 
$
346,448

Accrued taxes
151,487

 
144,899

Accrued interest
53,503

 
53,534

Common dividends payable
88,066

 
87,982

Short-term borrowings (Note 3)
291,900

 
114,675

Current maturities of long-term debt (Note 3)

 
800,000

Customer deposits
49,132

 
64,908

Liabilities from risk management activities (Note 7)
44,805

 
38,946

Liabilities for asset retirements
10,735

 
11,025

Operating lease liabilities (Note 16)
83,851

 
12,713

Regulatory liabilities (Note 4)
279,479

 
234,912

Other current liabilities
127,175

 
168,323

Total current liabilities
1,496,363

 
2,078,365

LONG-TERM DEBT LESS CURRENT MATURITIES (Note 3)
5,922,161

 
4,832,558

DEFERRED CREDITS AND OTHER
 

 
 

Deferred income taxes
2,070,453

 
1,992,339

Regulatory liabilities (Note 4)
2,089,987

 
2,267,835

Liabilities for asset retirements
657,217

 
646,193

Liabilities for pension benefits (Note 5)
284,585

 
280,185

Liabilities from risk management activities (Note 7)
26,181

 
33,186

Customer advances
213,572

 
215,330

Coal mine reclamation
167,896

 
165,695

Deferred investment tax credit
193,081

 
196,468

Unrecognized tax benefits
6,613

 
6,189

Operating lease liabilities (Note 16)
409,621

 
51,872

Other
159,181

 
159,844

Total deferred credits and other
6,278,387

 
6,015,136

COMMITMENTS AND CONTINGENCIES (SEE NOTE 8)


 


EQUITY
 

 
 

Common stock, no par value; authorized 150,000,000 shares, 112,591,124 and 112,540,126 issued at respective dates
2,665,518

 
2,659,561

Treasury stock at cost; 35,983 and 103,546 shares at respective dates
(3,190
)
 
(9,427
)
Total common stock
2,662,328

 
2,650,134

Retained earnings
2,885,109

 
2,837,610

Accumulated other comprehensive loss
(57,875
)
 
(57,096
)
Total shareholders’ equity
5,489,562

 
5,430,648

Noncontrolling interests (Note 6)
120,915

 
122,540

Total equity
5,610,477

 
5,553,188

 
 
 
 
TOTAL LIABILITIES AND EQUITY
$
19,307,388

 
$
18,479,247

The accompanying notes are an integral part of the financial statements.

8



PINNACLE WEST CAPITAL CORPORATION
CONDENSED CONSOLIDATED STATEMENTS OF CASH FLOWS
(unaudited)
(dollars in thousands)
 
Six Months Ended
June 30,
 
2020
 
2019
CASH FLOWS FROM OPERATING ACTIVITIES
 

 
 

Net income
$
233,325

 
$
171,810

Adjustments to reconcile net income to net cash provided by operating activities:
 

 
 

Depreciation and amortization including nuclear fuel
343,173

 
332,185

Deferred fuel and purchased power
(26,473
)
 
(16,702
)
Deferred fuel and purchased power amortization
(4,815
)
 
23,307

Allowance for equity funds used during construction
(16,508
)
 
(18,760
)
Deferred income taxes
22,229

 
4,326

Deferred investment tax credit
(3,386
)
 
(2,656
)
Stock compensation
9,130

 
13,725

Changes in current assets and liabilities:
 

 
 

Customer and other receivables
7,767

 
3,543

Accrued unbilled revenues
(63,413
)
 
(56,487
)
Materials, supplies and fossil fuel
10,295

 
(21,287
)
Income tax receivable
4,605

 

Other current assets
(24,896
)
 
(16,121
)
Accounts payable
17,772

 
65,874

Accrued taxes
6,588

 
4,102

Other current liabilities
(45,334
)
 
(61,270
)
Change in other long-term assets
(4,885
)
 
(82,850
)
Change in other long-term liabilities
(96,142
)
 
3,195

Net cash flow provided by operating activities
369,032

 
345,934

CASH FLOWS FROM INVESTING ACTIVITIES
 
 
 

Capital expenditures
(676,973
)
 
(541,401
)
Contributions in aid of construction
31,295

 
18,909

Allowance for borrowed funds used during construction
(8,825
)
 
(11,159
)
Proceeds from nuclear decommissioning trust sales and other special use funds
391,859

 
309,354

Investment in nuclear decommissioning trust and other special use funds
(393,000
)
 
(310,494
)
Other
3,123

 
7,153

Net cash flow used for investing activities
(652,521
)
 
(527,638
)
CASH FLOWS FROM FINANCING ACTIVITIES
 

 
 

Issuance of long-term debt
1,088,886

 
497,324

Short-term borrowing and payments — net
184,225

 
363,973

Short-term debt borrowings
751,690

 
49,000

Short-term debt repayments
(758,690
)
 
(57,000
)
Dividends paid on common stock
(172,566
)
 
(161,979
)
Repayment of long-term debt
(800,000
)
 
(500,000
)
Common stock equity issuance - net of purchases
(2,204
)
 
(2,360
)
Distributions to noncontrolling interests
(11,372
)
 
(11,372
)
Net cash flow provided by financing activities
279,969

 
177,586

NET DECREASE IN CASH AND CASH EQUIVALENTS
(3,520
)
 
(4,118
)
CASH AND CASH EQUIVALENTS AT BEGINNING OF PERIOD
10,283

 
5,766

CASH AND CASH EQUIVALENTS AT END OF PERIOD
$
6,763

 
$
1,648

The accompanying notes are an integral part of the financial statements.

9



PINNACLE WEST CAPITAL CORPORATION
CONDENSED CONSOLIDATED STATEMENTS OF CHANGES IN EQUITY
(unaudited)
(dollars in thousands)
 
Three Months Ended June 30, 2020
 
Common Stock
 
Treasury Stock
 
Retained Earnings
 
Accumulated Other Comprehensive Income (Loss)
 
Noncontrolling Interests
 
Total
 
Shares
 
Amount
 
Shares
 
Amount
 
 
 
 
 
 
 
 
Balance, April 1, 2020
112,563,610

 
$
2,664,387

 
(72,302
)
 
$
(7,000
)
 
$
2,867,610

 
$
(55,579
)
 
$
127,414

 
$
5,596,832

Net income
 
 

 
 
 

 
193,585

 

 
4,874

 
198,459

Other comprehensive loss
 
 

 
 
 

 

 
(2,296
)
 

 
(2,296
)
Dividends on common stock ($1.57 per share)
 
 

 
 
 

 
(176,086
)
 

 

 
(176,086
)
Issuance of common stock
27,514

 
1,131

 
 
 


 

 

 

 
1,131

Purchase of treasury stock (a)
 
 

 
(12,346
)
 
(924
)
 

 

 

 
(924
)
Reissuance of treasury stock for stock-based compensation and other
 
 

 
48,665

 
4,734

 

 

 

 
4,734

Other
 
 

 
 
 

 

 

 
(1
)
 
(1
)
Capital activities by noncontrolling interests
 
 

 

 

 

 

 
(11,372
)
 
(11,372
)
Balance, June 30, 2020
112,591,124

 
$
2,665,518

 
(35,983
)
 
$
(3,190
)
 
$
2,885,109

 
$
(57,875
)
 
$
120,915

 
$
5,610,477


 
Three Months Ended June 30, 2019
 
Common Stock
 
Treasury Stock
 
Retained Earnings
 
Accumulated Other Comprehensive Income (Loss)
 
Noncontrolling Interests
 
Total
 
Shares
 
Amount
 
Shares
 
Amount
 
 
 
 
 
 
 
 
Balance, April 1, 2019
112,340,322

 
$
2,644,063

 
(63,271
)
 
$
(5,586
)
 
$
2,659,086

 
$
(46,501
)
 
$
130,663

 
$
5,381,725

Net income
 
 

 
 
 

 
144,145

 

 
4,874

 
149,019

Other comprehensive loss
 
 

 
 
 

 

 
(1,135
)
 

 
(1,135
)
Dividends on common stock ($1.48 per share)
 
 

 
 
 

 
(165,611
)
 

 

 
(165,611
)
Issuance of common stock
21,273

 
4,171

 
 
 

 

 

 

 
4,171

Reissuance of treasury stock for stock-based compensation and other
 
 

 
5,052

 
446

 

 

 

 
446

Capital activities by noncontrolling interests
 
 

 

 

 

 

 
(11,372
)
 
(11,372
)
Balance, June 30, 2019
112,361,595

 
$
2,648,234

 
(58,219
)
 
$
(5,140
)
 
$
2,637,620

 
$
(47,636
)
 
$
124,165

 
$
5,357,243


(a)
Primarily represents shares of common stock withheld from certain stock awards for tax purposes.
    
The accompanying notes are an integral part of the financial statements.





10



PINNACLE WEST CAPITAL CORPORATION
CONDENSED CONSOLIDATED STATEMENTS OF CHANGES IN EQUITY
(unaudited)
(dollars in thousands)
 
Six Months Ended June 30, 2020
 
Common Stock
 
Treasury Stock
 
Retained Earnings
 
Accumulated Other Comprehensive Income (Loss)
 
Noncontrolling Interests
 
Total
 
Shares
 
Amount
 
Shares
 
Amount
 
 
 
 
 
 
 
 
Balance, January 1, 2020
112,540,126

 
$
2,659,561

 
(103,546
)
 
$
(9,427
)
 
$
2,837,610

 
$
(57,096
)
 
$
122,540

 
$
5,553,188

Net income
 
 

 
 
 

 
223,578

 

 
9,747

 
233,325

Other comprehensive loss
 
 

 
 
 

 

 
(779
)
 

 
(779
)
Dividends on common stock ($1.57 per share)
 
 

 
 
 

 
(176,079
)
 

 

 
(176,079
)
Issuance of common stock
50,998

 
5,957

 
 
 

 

 

 

 
5,957

Purchase of treasury stock (a)
 
 

 
(33,070
)
 
(3,010
)
 

 

 

 
(3,010
)
Reissuance of treasury stock for stock-based compensation and other
 
 

 
100,633

 
9,247

 

 

 

 
9,247

Capital activities by noncontrolling interests
 
 

 
 
 

 

 

 
(11,372
)
 
(11,372
)
Balance, June 30, 2020
112,591,124

 
$
2,665,518

 
(35,983
)
 
$
(3,190
)
 
$
2,885,109

 
$
(57,875
)
 
$
120,915

 
$
5,610,477


 
Six Months Ended June 30, 2019
 
Common Stock
 
Treasury Stock
 
Retained Earnings
 
Accumulated Other Comprehensive Income (Loss)
 
Noncontrolling Interests
 
Total
 
Shares
 
Amount
 
Shares
 
Amount
 
 
 
 
 
 
 
 
Balance, January 1, 2019
112,159,896

 
$
2,634,265

 
(58,135
)
 
$
(4,825
)
 
$
2,641,183

 
$
(47,708
)
 
$
125,790

 
$
5,348,705

Net income
 
 

 
 
 

 
162,063

 

 
9,747

 
171,810

Other comprehensive income
 
 

 
 
 

 

 
72

 

 
72

Dividends on common stock ($1.48 per share)
 
 

 
 
 

 
(165,626
)
 

 

 
(165,626
)
Issuance of common stock
201,699

 
13,969

 
 
 

 

 

 

 
13,969

Purchase of treasury stock (a)
 
 

 
(75,791
)
 
(6,882
)
 

 

 

 
(6,882
)
Reissuance of treasury stock for stock-based compensation and other
 
 

 
75,707

 
6,567

 

 

 

 
6,567

Capital activities by noncontrolling interests
 
 

 
 
 

 

 

 
(11,372
)
 
(11,372
)
Balance, June 30, 2019
112,361,595

 
$
2,648,234

 
(58,219
)
 
$
(5,140
)
 
$
2,637,620

 
$
(47,636
)
 
$
124,165

 
$
5,357,243



(a)
Primarily represents shares of common stock withheld from certain stock awards for tax purposes.
    
The accompanying notes are an integral part of the financial statements.


11




ARIZONA PUBLIC SERVICE COMPANY
CONDENSED CONSOLIDATED STATEMENTS OF INCOME
(unaudited)
(dollars in thousands)
 
 
 
Three Months Ended
June 30,
 
Six Months Ended
June 30,
 
 
2020
 
2019
 
2020
 
2019
 
 
 
 
 
 
 
 
 
OPERATING REVENUES (NOTE 2)
 
$
929,590

 
$
869,501

 
$
1,591,520

 
$
1,610,031

 
 
 
 
 
 
 
 
 
OPERATING EXPENSES
 
 

 
 

 
 
 
 
Fuel and purchased power
 
238,382

 
242,222

 
426,903

 
472,810

Operations and maintenance
 
216,221

 
224,143

 
434,486

 
464,518

Depreciation and amortization
 
152,460

 
147,354

 
306,518

 
296,039

Taxes other than income taxes
 
56,758

 
55,081

 
113,516

 
110,159

Other expenses
 
692

 
683

 
1,514

 
1,110

Total
 
664,513

 
669,483

 
1,282,937

 
1,344,636

OPERATING INCOME
 
265,077

 
200,018

 
308,583

 
265,395

OTHER INCOME (DEDUCTIONS)
 
 

 
 

 
 
 
 
Allowance for equity funds used during construction
 
8,811

 
7,572

 
16,508

 
18,760

Pension and other postretirement non-service credits - net
 
14,421

 
6,757

 
28,683

 
12,256

Other income (Note 9)
 
13,272

 
11,691

 
24,905

 
18,107

Other expense (Note 9)
 
(3,859
)
 
(3,428
)
 
(8,527
)
 
(7,306
)
Total
 
32,645

 
22,592

 
61,569

 
41,817

INTEREST EXPENSE
 
 

 
 

 
 
 
 
Interest charges
 
56,802

 
53,591

 
112,538

 
110,256

Allowance for borrowed funds used during construction
 
(4,749
)
 
(4,494
)
 
(8,825
)
 
(11,159
)
Total
 
52,053

 
49,097

 
103,713

 
99,097

INCOME BEFORE INCOME TAXES
 
245,669

 
173,513

 
266,439

 
208,115

INCOME TAXES
 
43,677

 
18,463

 
24,229

 
19,916

NET INCOME
 
201,992

 
155,050

 
242,210

 
188,199

Less: Net income attributable to noncontrolling interests (Note 6)
 
4,874

 
4,874

 
9,747

 
9,747

NET INCOME ATTRIBUTABLE TO COMMON SHAREHOLDER
 
$
197,118

 
$
150,176

 
$
232,463

 
$
178,452

 
The accompanying notes are an integral part of the financial statements.

12



ARIZONA PUBLIC SERVICE COMPANY
CONDENSED CONSOLIDATED STATEMENTS OF COMPREHENSIVE INCOME
(unaudited)
(dollars in thousands)
 
 
Three Months Ended
June 30,
 
Six Months Ended
June 30,
 
2020
 
2019
 
2020
 
2019
 
 
 
 
 
 
 
 
NET INCOME
$
201,992

 
$
155,050

 
$
242,210

 
$
188,199

 
 
 
 
 
 
 
 
OTHER COMPREHENSIVE INCOME, NET OF TAX
 

 
 

 
 
 
 
Derivative instruments:
 

 
 

 
 
 
 
Net unrealized loss, net of tax benefit of $0, $0, $292 and $0

 

 
292

 

Reclassification of net realized loss, net of tax benefit of $87, $134, $481 and $242
262

 
404

 
282

 
732

Pension and other postretirement benefits activity, net of tax benefit of $361, $544, $124 and $297
(1,090
)
 
(1,653
)
 
(77
)
 
(901
)
Total other comprehensive income (loss)
(828
)
 
(1,249
)
 
497

 
(169
)
 
 
 
 
 
 
 
 
COMPREHENSIVE INCOME
201,164

 
153,801

 
242,707

 
188,030

Less: Comprehensive income attributable to noncontrolling interests
4,874

 
4,874

 
9,747

 
9,747

 
 
 
 
 
 
 
 
COMPREHENSIVE INCOME ATTRIBUTABLE TO COMMON SHAREHOLDER
$
196,290

 
$
148,927

 
$
232,960

 
$
178,283

 
The accompanying notes are an integral part of the financial statements.


13



ARIZONA PUBLIC SERVICE COMPANY
CONDENSED CONSOLIDATED BALANCE SHEETS
(unaudited)
(dollars in thousands)
 
 
June 30,
2020
 
December 31,
2019
ASSETS
 

 
 

 
 
 
 
PROPERTY, PLANT AND EQUIPMENT
 

 
 

Plant in service and held for future use
$
20,339,690

 
$
19,832,805

Accumulated depreciation and amortization
(6,901,805
)
 
(6,634,597
)
Net
13,437,885

 
13,198,208

 
 
 
 
Construction work in progress
823,691

 
808,133

Palo Verde sale leaseback, net of accumulated depreciation (Note 6)
99,971

 
101,906

Intangible assets, net of accumulated amortization
274,873

 
290,409

Nuclear fuel, net of accumulated amortization
152,219

 
123,500

Total property, plant and equipment
14,788,639

 
14,522,156

 
 
 
 
INVESTMENTS AND OTHER ASSETS
 

 
 

Nuclear decommissioning trust (Notes 11 and 12)
1,024,033

 
1,010,775

Other special use funds (Notes 11 and 12)
253,332

 
245,095

Other assets
43,973

 
43,781

Total investments and other assets
1,321,338

 
1,299,651

 
 
 
 
CURRENT ASSETS
 

 
 

Cash and cash equivalents
6,224

 
10,169

Customer and other receivables
275,476

 
255,479

Accrued unbilled revenues
191,578

 
128,165

Allowance for doubtful accounts
(11,579
)
 
(8,171
)
Materials and supplies (at average cost)
318,368

 
331,091

Fossil fuel (at average cost)
17,257

 
14,829

Income tax receivable

 
7,313

Assets from risk management activities (Note 7)
710

 
515

Deferred fuel and purchased power regulatory asset (Note 4)
101,425

 
70,137

Other regulatory assets (Note 4)
150,169

 
133,070

Other current assets
47,588

 
38,895

Total current assets
1,097,216

 
981,492

 
 
 
 
DEFERRED DEBITS
 

 
 

Regulatory assets (Note 4)
1,315,846

 
1,304,073

Operating lease right-of-use assets (Note 16)
554,106

 
144,024

Assets for other postretirement benefits (Note 5)
95,937

 
86,736

Other
29,562

 
32,591

Total deferred debits
1,995,451

 
1,567,424

 
 
 
 
TOTAL ASSETS
$
19,202,644

 
$
18,370,723

 
The accompanying notes are an integral part of the financial statements.


14



ARIZONA PUBLIC SERVICE COMPANY
CONDENSED CONSOLIDATED BALANCE SHEETS
(unaudited)
(dollars in thousands) 
 
June 30,
2020
 
December 31,
2019
LIABILITIES AND EQUITY
 

 
 

 
 
 
 
CAPITALIZATION
 

 
 

Common stock
$
178,162

 
$
178,162

Additional paid-in capital
2,721,696

 
2,721,696

Retained earnings
3,068,389

 
3,011,927

Accumulated other comprehensive loss
(35,025
)
 
(35,522
)
Total shareholder equity
5,933,222

 
5,876,263

Noncontrolling interests (Note 6)
120,915

 
122,540

Total equity
6,054,137

 
5,998,803

Long-term debt less current maturities (Note 3)
5,425,551

 
4,833,133

Total capitalization
11,479,688

 
10,831,936

CURRENT LIABILITIES
 

 
 

Short-term borrowings (Note 3)
219,900

 

Current maturities of long-term debt (Note 3)

 
350,000

Accounts payable
307,931

 
338,006

Accrued taxes
150,879

 
136,328

Accrued interest
52,925

 
52,619

Common dividends payable
88,000

 
88,000

Customer deposits
49,132

 
64,908

Liabilities from risk management activities (Note 7)
44,805

 
38,946

Liabilities for asset retirements
10,735

 
11,025

Operating lease liabilities (Note 16)
83,744

 
12,549

Regulatory liabilities (Note 4)
279,479

 
234,912

Other current liabilities
128,147

 
164,736

Total current liabilities
1,415,677

 
1,492,029

DEFERRED CREDITS AND OTHER
 

 
 

Deferred income taxes
2,106,268

 
2,033,096

Regulatory liabilities (Note 4)
2,089,987

 
2,267,835

Liabilities for asset retirements
657,217

 
646,193

Liabilities for pension benefits (Note 5)
267,386

 
262,243

Liabilities from risk management activities (Note 7)
26,181

 
33,186

Customer advances
213,572

 
215,330

Coal mine reclamation
167,896

 
165,695

Deferred investment tax credit
193,081

 
196,468

Unrecognized tax benefits
39,039

 
40,188

Operating lease liabilities (Note 16)
407,888

 
50,092

Other
138,764

 
136,432

Total deferred credits and other
6,307,279

 
6,046,758

COMMITMENTS AND CONTINGENCIES (SEE NOTE 8)


 


TOTAL LIABILITIES AND EQUITY
$
19,202,644

 
$
18,370,723


The accompanying notes are an integral part of the financial statements.

15



ARIZONA PUBLIC SERVICE COMPANY
CONDENSED CONSOLIDATED STATEMENTS OF CASH FLOWS
(unaudited)
(dollars in thousands)
 
Six Months Ended
June 30,
 
2020
 
2019
CASH FLOWS FROM OPERATING ACTIVITIES
 

 
 

Net income
$
242,210

 
$
188,199

Adjustments to reconcile net income to net cash provided by operating activities:
 

 
 

Depreciation and amortization including nuclear fuel
343,130

 
332,143

Deferred fuel and purchased power
(26,473
)
 
(16,702
)
Deferred fuel and purchased power amortization
(4,815
)
 
23,307

Allowance for equity funds used during construction
(16,508
)
 
(18,760
)
Deferred income taxes
15,233

 
(10,625
)
Deferred investment tax credit
(3,386
)
 
(2,656
)
Changes in current assets and liabilities:
 

 
 

Customer and other receivables
824

 
3,645

Accrued unbilled revenues
(63,413
)
 
(56,487
)
Materials, supplies and fossil fuel
10,295

 
(21,287
)
Income tax receivable
7,313

 

Other current assets
(19,752
)
 
(14,613
)
Accounts payable
17,915

 
68,399

Accrued taxes
14,551

 
(435
)
Other current liabilities
(40,381
)
 
(57,709
)
Change in other long-term assets
(7,356
)
 
(84,946
)
Change in other long-term liabilities
(91,983
)
 
3,253

Net cash flow provided by operating activities
377,404

 
334,726

CASH FLOWS FROM INVESTING ACTIVITIES
 

 
 

Capital expenditures
(676,973
)
 
(541,401
)
Contributions in aid of construction
31,295

 
18,909

Allowance for borrowed funds used during construction
(8,825
)
 
(11,159
)
Proceeds from nuclear decommissioning trust sales and other special use funds
391,859

 
309,354

Investment in nuclear decommissioning trust and other special use funds
(393,000
)
 
(310,494
)
Other
(169
)
 
(1,612
)
Net cash flow used for investing activities
(655,813
)
 
(536,403
)
CASH FLOWS FROM FINANCING ACTIVITIES
 

 
 

Issuance of long-term debt
591,936

 
497,324

Short-term borrowings and payments — net
219,900

 
376,873

Short-term debt borrowings under revolving credit facility
540,000

 

Short-term debt repayments under revolving credit facility
(540,000
)
 

Repayment of long-term debt
(350,000
)
 
(500,000
)
Dividends paid on common stock
(176,000
)
 
(165,500
)
Distributions to noncontrolling interests
(11,372
)
 
(11,372
)
Net cash flow provided by financing activities
274,464

 
197,325

NET DECREASE IN CASH AND CASH EQUIVALENTS
(3,945
)
 
(4,352
)
CASH AND CASH EQUIVALENTS AT BEGINNING OF PERIOD
10,169

 
5,707

CASH AND CASH EQUIVALENTS AT END OF PERIOD
$
6,224

 
$
1,355


The accompanying notes are an integral part of the financial statements.

16




ARIZONA PUBLIC SERVICE COMPANY
CONDENSED CONSOLIDATED STATEMENTS OF CHANGES IN EQUITY
(unaudited)
(dollars in thousands)
 
Three Months Ended June 30, 2020
 
Common Stock
 
Additional Paid-In Capital
 
Retained Earnings
 
Accumulated Other Comprehensive Income (Loss)
 
Noncontrolling Interests
 
Total
 
Shares
 
Amount
 
 
 
 
 
 
 
 
 
 
Balance, April 1, 2020
71,264,947

 
$
178,162

 
$
2,721,696

 
$
3,047,269

 
$
(34,197
)
 
$
127,414

 
$
6,040,344

Net Income
 
 

 

 
197,118

 

 
4,874

 
201,992

Other comprehensive loss
 
 

 

 

 
(828
)
 

 
(828
)
Dividends on common stock
 
 

 

 
(176,000
)
 

 

 
(176,000
)
Other
 
 

 

 
2

 

 
(1
)
 
1

Capital activities by noncontrolling activities
 
 

 

 

 

 
(11,372
)
 
(11,372
)
Balance, June 30, 2020
71,264,947

 
$
178,162

 
$
2,721,696

 
$
3,068,389

 
$
(35,025
)
 
$
120,915

 
$
6,054,137


 
Three Months Ended June 30, 2019
 
Common Stock
 
Additional Paid-In Capital
 
Retained Earnings
 
Accumulated Other Comprehensive Income (Loss)
 
Noncontrolling Interests
 
Total
 
Shares
 
Amount
 
 
 
 
 
 
 
 
 
 
Balance, April 1, 2019
71,264,947

 
$
178,162

 
$
2,721,696

 
$
2,816,532

 
$
(26,027
)
 
$
130,663

 
$
5,821,026

Net Income
 
 

 

 
150,176

 

 
4,874

 
155,050

Other comprehensive loss
 
 

 

 

 
(1,249
)
 

 
(1,249
)
Dividends on common stock
 
 

 

 
(165,598
)
 

 

 
(165,598
)
Capital activities by noncontrolling activities
 
 

 

 

 

 
(11,372
)
 
(11,372
)
Balance, June 30, 2019
71,264,947

 
$
178,162

 
$
2,721,696

 
$
2,801,110

 
$
(27,276
)
 
$
124,165

 
$
5,797,857



The accompanying notes are an integral part of the financial statements.















17






ARIZONA PUBLIC SERVICE COMPANY
CONDENSED CONSOLIDATED STATEMENTS OF CHANGES IN EQUITY
(unaudited)
(dollars in thousands)
 
Six Months Ended June 30, 2020
 
Common Stock
 
Additional Paid-In Capital
 
Retained Earnings
 
Accumulated Other Comprehensive Income (Loss)
 
Noncontrolling Interests
 
Total
 
Shares
 
Amount
 
 
 
 
 
 
 
 
 
 
Balance, January 1, 2020
71,264,947

 
$
178,162

 
$
2,721,696

 
$
3,011,927

 
$
(35,522
)
 
$
122,540

 
$
5,998,803

Net Income
 
 

 

 
232,463

 

 
9,747

 
242,210

Other comprehensive income
 
 

 

 

 
497

 

 
497

Dividends on common stock
 
 

 

 
(176,000
)
 

 

 
(176,000
)
Other
 
 

 

 
(1
)
 

 

 
(1
)
Capital activities by noncontrolling activities
 
 

 

 

 

 
(11,372
)
 
(11,372
)
Balance, June 30, 2020
71,264,947

 
$
178,162

 
$
2,721,696

 
$
3,068,389

 
$
(35,025
)
 
$
120,915

 
$
6,054,137


 
Six Months Ended June 30, 2019
 
Common Stock
 
Additional Paid-In Capital
 
Retained Earnings
 
Accumulated Other Comprehensive Income (Loss)
 
Noncontrolling Interests
 
Total
 
Shares
 
Amount
 
 
 
 
 
 
 
 
 
 
Balance, January 1, 2019
71,264,947

 
$
178,162

 
$
2,721,696

 
$
2,788,256

 
$
(27,107
)
 
$
125,790

 
$
5,786,797

Net Income
 
 

 

 
178,452

 

 
9,747

 
188,199

Other comprehensive loss
 
 

 

 

 
(169
)
 

 
(169
)
Dividends on common stock
 
 

 

 
(165,598
)
 

 

 
(165,598
)
Capital activities by noncontrolling activities
 
 

 

 

 

 
(11,372
)
 
(11,372
)
Balance, June 30, 2019
71,264,947

 
$
178,162

 
$
2,721,696

 
$
2,801,110

 
$
(27,276
)
 
$
124,165

 
$
5,797,857




The accompanying notes are an integral part of the financial statements.




18



COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS
 
1. 
Consolidation and Nature of Operations
 
The unaudited condensed consolidated financial statements include the accounts of Pinnacle West and our subsidiaries:  APS, 4C Acquisition, LLC ("4CA"), Bright Canyon Energy Corporation ("BCE") and El Dorado Investment Company ("El Dorado").  See Note 8 for more information on 4CA matters. Intercompany accounts and transactions between the consolidated companies have been eliminated.  The unaudited condensed consolidated financial statements for APS include the accounts of APS and the Palo Verde Generating Station ("Palo Verde") sale leaseback variable interest entities ("VIEs") (see Note 6 for further discussion).  Our accounting records are maintained in accordance with accounting principles generally accepted in the United States of America ("GAAP").  The preparation of financial statements in accordance with GAAP requires management to make estimates and assumptions that affect the reported amounts of assets and liabilities, disclosure of contingent assets and liabilities at the date of the financial statements and reported amounts of revenues and expenses during the reporting period.  Actual results could differ from those estimates.
 
Amounts reported in our interim Condensed Consolidated Statements of Income are not necessarily indicative of amounts expected for the respective annual periods, due to the effects of seasonal temperature variations on energy consumption, timing of maintenance on electric generating units ("EGU"), and other factors.
 
Our condensed consolidated financial statements reflect all adjustments (consisting only of normal recurring adjustments except as otherwise disclosed in the notes) that we believe are necessary for the fair presentation of our financial position, results of operations, and cash flows for the periods presented. Certain information and footnote disclosures normally included in financial statements prepared in conformity with GAAP have been condensed or omitted pursuant to such regulations, although we believe that the disclosures provided are adequate to make the interim information presented not misleading. The accompanying condensed consolidated financial statements and these notes should be read in conjunction with the audited consolidated financial statements and notes included in our 2019 Form 10-K.

On June 30, 2020, the United States Federal Energy Regulatory Commission ("FERC") issued an order granting a waiver request related to the existing Allowance for Funds Used During Construction ("AFUDC") rate calculation beginning March 1, 2020 through February 28, 2021.  The order provides a simplified approach that companies may elect to implement in order to minimize the significant distorted effect on the AFUDC formula resulting from increased short-term debt financing during the COVID-19 pandemic.  APS has adopted this simplified approach to computing the AFUDC composite rate  by using a simple average of the actual historical short-term debt balances for 2019, instead of current period short-term debt balances, and has left all other aspects of the AFUDC formula composite rate calculation unchanged. This change impacts the AFUDC composite rate in 2020, but does not impact prior years.  Furthermore, the change in the composite rate calculation does not impact our accounting treatment for these costs. The change will not have a material impact on our financial statements. See Note 1 in our 2019 Form 10-K for information on the accounting treatment for AFUDC.


19


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS


Supplemental Cash Flow Information

The following table summarizes supplemental Pinnacle West cash flow information (dollars in thousands):
 
Six Months Ended
June 30,
 
2020
 
2019
Cash paid during the period for:
 
 
 
Income taxes, net of refunds
$
(3,028
)
 
$
10,788

Interest, net of amounts capitalized
107,417

 
114,717

Significant non-cash investing and financing activities:
 
 
 
Accrued capital expenditures
$
87,815

 
$
108,056

Right-of-use operating lease assets obtained in exchange for operating lease liabilities
434,997

 
4,562

Dividends accrued but not yet paid
88,066

 
82,824



The following table summarizes supplemental APS cash flow information (dollars in thousands):
 
Six Months Ended
June 30,
 
2020
 
2019
Cash paid during the period for:
 
 
 
Income taxes, net of refunds
$

 
$
35,573

Interest, net of amounts capitalized
100,991

 
107,169

Significant non-cash investing and financing activities:
 
 
 
Accrued capital expenditures
$
87,815

 
$
108,056

Right-of-use operating lease assets obtained in exchange for operating lease liabilities
434,997

 
4,562

Dividends accrued but not yet paid
88,000

 
82,800




2.    Revenue
Sources of Revenue
The following table provides detail of Pinnacle West's consolidated revenue disaggregated by revenue sources (dollars in thousands):
 
 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
 
2020
2019
 
2020
2019
Retail Electric Revenue
 
 
 
 
 
 
Residential
 
$
515,128

$
432,568

 
$
840,201

$
784,134

Non-Residential
 
381,121

395,929

 
684,472

728,597

Wholesale energy sales
 
15,927

21,991

 
30,595

58,443

Transmission services for others
 
14,766

15,157

 
30,693

30,406

Other sources
 
2,648

3,856

 
5,559

8,451

Total operating revenues
 
$
929,590

$
869,501

 
$
1,591,520

$
1,610,031



20


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS


Retail Electric Revenue. Pinnacle West's retail electric revenue is generated by wholly owned regulated subsidiary APS's sale of electricity to our regulated customers within the authorized service territory at tariff rates approved by the ACC and based on customer usage. Revenues related to the sale of electricity are generally recognized when service is rendered or electricity is delivered to customers. The billing of electricity sales to individual customers is based on the reading of their meters. We obtain customers' meter data on a systematic basis throughout the month, and generally bill customers within a month from when service was provided. Customers are generally required to pay for services within 15 days of when the services are billed.

Wholesale Energy Sales and Transmission Services for Others. Revenues from wholesale energy sales and transmission services for others represent energy and transmission sales to wholesale customers. These activities primarily consist of managing fuel and purchased power risks in connection with the cost of serving our retail customers' energy requirements. We may also sell into the wholesale markets generation that is not needed for APS’s retail load. Our wholesale activities and tariff rates are regulated by FERC.

In the electricity business, some contracts to purchase energy are settled by netting against other contracts to sell electricity. This is referred to as a book-out, and usually occurs in contracts that have the same terms (product type, quantities, and delivery points) and for which power does not flow. We net these book-outs, which reduces both wholesale revenues and fuel and purchased power costs.
 
Revenue Activities

Our revenues primarily consist of activities that are classified as revenues from contracts with customers. We derive our revenues from contracts with customers primarily from sales of electricity to our regulated retail customers. Revenues from contracts with customers also include wholesale and transmission activities. Our revenues from contracts with customers for the three and six months ended June 30, 2020 were $915 million and $1,563 million, respectively and for the three and six months ended June 30, 2019 were $858 million and $1,578 million, respectively.

We have certain revenues that do not meet the specific accounting criteria to be classified as revenues from contracts with customers. For the three and six months ended June 30, 2020 our revenues that do not qualify as revenue from contracts with customers were $15 million and $29 million, respectively, and for the three and six months ended June 30, 2019 were $12 million and $32 million, respectively. This relates primarily to certain regulatory cost recovery mechanisms that are considered alternative revenue programs. We recognize revenue associated with alternative revenue programs when specific events permitting recognition are completed. Certain amounts associated with alternative revenue programs will subsequently be billed to customers; however, we do not reclassify billed amounts into revenue from contracts with customers. See Note 4 for a discussion of our regulatory cost recovery mechanisms.

Contract Assets and Liabilities from Contracts with Customers

There were no material contract assets, contract liabilities, or deferred contract costs recorded on the Condensed Consolidated Balance Sheets as of June 30, 2020 or December 31, 2019.

Allowance for Doubtful Accounts

The allowance for doubtful accounts represents our best estimate of accounts receivable and accrued unbilled revenues that will ultimately be uncollectible due to credit loss risk. The allowance is calculated by applying an estimated write-off factor to retail electric revenues. The write-off factor used to estimate uncollectible accounts is based upon consideration of historical collections experience, the current and

21


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

forecasted economic environment, changes to our collection policies, and management’s best estimate of future collections success.

During March 2020, due to the COVID-19 pandemic, and to assist customers who may be experiencing economic difficulties, we suspended all service shut-offs due to nonpayment. We are experiencing an increase in the number of customers needing to utilize longer-term payment plans to avoid service disruption. These changes, among others, including the Summer Disconnection Moratorium (defined in Note 4), impacted our write-off factor during the period. We will continue to monitor the impacts of COVID-19 on our write-off factor. See Note 4 for additional details.

The following table provides a rollforward of Pinnacle West’s allowance for doubtful accounts (dollars in thousands):

 
 
June 30, 2020
 
December 31, 2019
Allowance for doubtful accounts, balance at beginning of period
 
$
8,171

 
$
4,069

Bad debt expense
 
9,197

 
11,819

Actual write-offs
 
(5,789
)
 
(7,717
)
Allowance for doubtful accounts, balance at end of period
 
$
11,579

 
$
8,171




3.
Long-Term Debt and Liquidity Matters

Pinnacle West and APS maintain committed revolving credit facilities in order to enhance liquidity and provide credit support for their commercial paper programs, to refinance indebtedness, and for other general corporate purposes.
 
Pinnacle West

On May 5, 2020, Pinnacle West refinanced its 364-day $50 million term loan agreement that would have matured on May 7, 2020 with a new 364-day $31 million term loan agreement that matures May 4, 2021. Borrowings under the agreement bear interest at Eurodollar Rate plus 1.40% per annum. At June 30, 2020, Pinnacle West had $31 million in outstanding borrowings under the current agreement.

On June 17, 2020, Pinnacle West issued $500 million of 1.3% unsecured senior notes that mature June 15, 2025. The net proceeds from the sale were used to repay early its $150 million term loan facility set to mature on December 21, 2020, to repay short-term indebtedness consisting of commercial paper and replenish cash incurred or used to fund capital expenditures, to redeem prior to maturity our $300 million, 2.25% senior notes due November 30, 2020, and for general corporate purposes.

At June 30, 2020, Pinnacle West had a $200 million revolving credit facility that matures in July 2023. Pinnacle West has the option to increase the amount of the facility up to a maximum of $300 million upon the satisfaction of certain conditions and with the consent of the lenders. Interest rates are based on Pinnacle West's senior unsecured debt credit ratings. The facility is available to support Pinnacle West's $200 million commercial paper program, for bank borrowings or for issuances of letters of credits. At June 30, 2020, Pinnacle West had no outstanding borrowings under its credit facility, no letters of credit outstanding and $41 million in commercial paper borrowings.


22


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

APS

On January 15, 2020, APS repaid at maturity the remaining $150 million of the $250 million aggregate principal amount of its 2.2% Senior Notes.

On May 22, 2020, APS issued $600 million of 3.35% unsecured senior notes that mature May 15, 2050. The net proceeds from the sale were used to repay early its $200 million term loan facility and to repay short-term indebtedness, consisting of commercial paper and revolver borrowings, and to replenish cash used to fund capital expenditures.

At June 30, 2020, APS had two revolving credit facilities totaling $1 billion, including a $500 million credit facility that matures in June 2022 and a $500 million facility that matures in July 2023.  APS may increase the amount of each facility up to a maximum of $700 million, for a total of $1.4 billion, upon the satisfaction of certain conditions and with the consent of the lenders.  Interest rates are based on APS’s senior unsecured debt credit ratings. These facilities are available to support APS’s $500 million commercial paper program, for bank borrowings or for issuances of letters of credit.  At June 30, 2020, APS had no outstanding borrowings under its revolving credit facilities, no letters of credit outstanding, and $220 million in commercial paper borrowings.

On November 27, 2018, the ACC issued a financing order in which, subject to specified parameters and procedures, it approved APS’s short-term debt authorization equal to the sum of (i) 7% of APS’s capitalization, and (ii) $500 million (which is required to be used for costs relating to purchases of natural gas and power) and a long-term debt authorization of $5.9 billion. On March 27, 2020, APS filed an application with the ACC to increase the long-term debt limit from $5.9 billion to $7.5 billion and to continue its authorization of short-term debt granted in the 2018 financing order. This application is pending ACC review and approval.
 
See "Financial Assurances" in Note 8 for a discussion of other outstanding letters of credit.
 
Debt Fair Value
 
Our long-term debt fair value estimates are classified within Level 2 of the fair value hierarchy. The following table presents the estimated fair value of our long-term debt, including current maturities (dollars in thousands):

 
As of June 30, 2020
 
As of December 31, 2019
 
Carrying
Amount
 
Fair Value
 
Carrying
Amount
 
Fair Value
Pinnacle West
$
496,610

 
$
507,850

 
$
449,425

 
$
450,822

APS
5,425,551

 
6,386,439

 
5,183,133

 
5,743,570

Total
$
5,922,161

 
$
6,894,289

 
$
5,632,558

 
$
6,194,392



 

23


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

4.    Regulatory Matters
 
COVID-19 Pandemic

Due to the COVID-19 pandemic, APS voluntarily suspended disconnections of customers for nonpayment beginning March 13, 2020.  In addition, APS waived all late payment fees during this current suspension period.  APS currently estimates that the Summer Disconnection Moratorium (see below for discussion of the Summer Disconnection Moratorium), the suspension of disconnections during the COVID-19 pandemic and the increased bad debt expense associated with both events will result in a negative impact to its 2020 operating results of approximately $20 million to $30 million pre-tax above the impact of disconnections on its operating results for years that did not have the Summer Disconnection Moratorium or COVID-19 pandemic. APS is anticipating an increase in bad debt expense associated with the COVID-19 pandemic, but it still believes that costs associated with the Summer Disconnection Moratorium and the COVID-19 disconnection suspensions and related bad debt expense with both events will fall within this estimated $20 million to $30 million range. These estimated impact amounts depend on certain assumptions, including, but not limited to, customer behaviors, population and employment growth, and the impacts of COVID-19 on the economy. Additionally, due to COVID-19, APS delayed the reset of the Environmental Improvement Surcharge ("EIS") adjustor and suspended the discontinuation of TEAM Phase II to the first billing cycle in May 2020 rather than April 2020 (see below for discussion of EIS and TEAM Phase II).

On April 17, 2020, APS filed an application with the ACC requesting a COVID-19 emergency relief package to provide additional assistance to its customers. On May 5, 2020, the ACC approved APS returning $36 million that had been collected through the Demand Side Management ("DSM") Adjustor Charge, but not allocated for current DSM programs, directly to customers through a bill credit in June 2020. As of June 30, 2020, APS had refunded approximately $40 million to customers. The additional $4 million over the approved amount was the result of the kWh credit being based on historic consumption which was different than actual consumption in the refund period. This difference was recorded to the DSM balancing account and will be addressed in subsequent DSM filings (see below for discussion of the DSM Adjustor Charge).

APS has committed in total approximately $8 million to assist customers and local non-profits and community organizations to help with the impact of the COVID-19 pandemic. On May 5, 2020, APS also voluntarily committed to the ACC to contribute $5.3 million of non-ratepayer funds to provide assistance to residential and non-residential customers that have been impacted by the COVID-19 pandemic (“Customer COVID Assistance”). As part of this Customer COVID Assistance, APS has established a $2.3 million program to assist extra small and small non-residential customers that have a delinquency of two or more months with a one-time credit of $1,000 on each such customer's bill. The other $3 million of the Customer COVID Assistance has not yet been assigned to specific programs. Beyond the Customer COVID Assistance, APS has also provided $1.5 million to assist customers with a one-time credit of $100 on their bill, with a priority given to customers on limited-income service plans, and $1.25 million to assist local non-profits and community organizations working to mitigate the impacts of the COVID-19 pandemic.
 

24


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

2019 Retail Rate Case Filing with the Arizona Corporation Commission

In accordance with the requirements of the 2018 rate review order described below, APS filed an application with the ACC on October 31, 2019 seeking an annual increase in retail base rates of $69 million. This amount includes recovery of the deferral and rate base effects of the Four Corners selective catalytic reduction ("SCR") project that is currently the subject of a separate proceeding (see “SCR Cost Recovery” below). It also reflects a net credit to base rates of approximately $115 million primarily due to the prospective inclusion of rate refunds currently provided through the Tax Expense Adjustment Mechanism ("TEAM"). The proposed total revenue increase in APS's application is $184 million. The average annual customer bill impact of APS’s request is an increase of 5.6% (the average annual bill impact for a typical APS residential customer is 5.4%).

The principal provisions of APS's application are:

a test year comprised of twelve months ended June 30, 2019, adjusted as described below;
an original cost rate base of $8.87 billion, which approximates the ACC-jurisdictional portion of the book value of utility assets, net of accumulated depreciation and other credits;
the following proposed capital structure and costs of capital:
 
 
Capital Structure
 
Cost of Capital
 
Long-term debt
 
45.3
%
4.10
%
Common stock equity
 
54.7
%
10.15
%
Weighted-average cost of capital
 
 
 
7.41
%

 
a 1% return on the increment of fair value rate base above APS’s original cost rate base, as provided for by Arizona law;
authorization to defer until APS's next general rate case the increase or decrease in its Arizona property taxes attributable to tax rate changes after the date the rate application is adjudicated;
a number of proposed rate and program changes for residential customers, including:
a super off-peak period during the winter months for APS’s time-of-use with demand rates;
additional $1.25 million in funding for APS's limited-income crisis bill program; and
a flat bill/subscription rate pilot program;
proposed rate design changes for commercial customers, including an experimental program designed to provide access to market pricing for up to 200 MW of medium and large commercial customers;
recovery of the deferral and rate base effects of the construction and operating costs of the Ocotillo modernization project (see discussion below of the 2017 Settlement Agreement); and
continued recovery of the remaining investment and other costs related to the retirement and closure of the Navajo Generating Station (the "Navajo Plant") (see "Navajo Plant" below).

APS requested that the increase become effective December 1, 2020.  The hearing for this rate case was delayed, at the request of ACC Staff and the Residential Utility Consumer Office ("RUCO"), and is currently scheduled to begin December 14, 2020. APS cannot predict the outcome of its request.

25


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS


2016 Retail Rate Case Filing with the Arizona Corporation Commission
 
On June 1, 2016, APS filed an application with the ACC for an annual increase in retail base rates. On March 27, 2017, a majority of the stakeholders in the general retail rate case, including the ACC Staff, RUCO, limited income advocates and private rooftop solar organizations signed a settlement agreement (the "2017 Settlement Agreement") and filed it with the ACC. The 2017 Settlement Agreement provides for a net retail base rate increase of $94.6 million, excluding the transfer of adjustor balances, consisting of: (1) a non-fuel, non-depreciation, base rate increase of $87.2 million per year; (2) a base rate decrease of $53.6 million attributable to reduced fuel and purchased power costs; and (3) a base rate increase of $61.0 million due to changes in depreciation schedules. The average annual customer bill impact under the 2017 Settlement Agreement was calculated as an increase of 3.28% (the average annual bill impact for a typical APS residential customer was calculated as an increase of 4.54%).

Other key provisions of the agreement include the following:

an authorized return on common equity of 10.0%;
a capital structure comprised of 44.2% debt and 55.8% common equity;
a cost deferral order for potential future recovery in APS’s next general retail rate case for the construction and operating costs APS incurs for its Ocotillo modernization project;
a cost deferral and procedure to allow APS to request rate adjustments prior to its next general retail rate case related to its share of the construction costs associated with installing SCR equipment at the Four Corners Power Plant ("Four Corners");
a deferral for future recovery (or credit to customers) of the Arizona property tax expense above or below a specified test year level caused by changes to the applicable Arizona property tax rate;
an expansion of the Power Supply Adjustor (“PSA”) to include certain environmental chemical costs and third-party energy storage costs;
a new AZ Sun II program (now known as "APS Solar Communities") for utility-owned solar distributed generation with the purpose of expanding access to rooftop solar for low and moderate income Arizonans, recoverable through the Arizona Renewable Energy Standard and Tariff ("RES"), to be no less than $10 million per year in capital costs, and not more than $15 million per year in capital costs;
an increase to the per kWh cap for the environmental improvement surcharge from $0.00016 to $0.00050 and the addition of a balancing account;
rate design changes, including:
a change in the on-peak time of use period from noon - 7 p.m. to 3 p.m. - 8 p.m. Monday through Friday, excluding holidays;
non-grandfathered distributed generation ("DG") customers would be required to select a rate option that has time of use rates and either a new grid access charge or demand component;
a Resource Comparison Proxy (“RCP”) for exported energy of 12.9 cents per kWh in year one; and
an agreement by APS not to pursue any new self-build generation (with certain exceptions) having an in-service date prior to January 1, 2022 (extended to December 31, 2027 for combined-cycle generating units), unless expressly authorized by the ACC.

Through a separate agreement, APS, industry representatives, and solar advocates committed to stand by the 2017 Settlement Agreement and refrain from seeking to undermine it through ballot initiatives, legislation or advocacy at the ACC.

26


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS


On August 15, 2017, the ACC approved (by a vote of 4-1), the 2017 Settlement Agreement without material modifications.  On August 18, 2017, the ACC issued a final written Opinion and Order reflecting its decision in APS’s general retail rate case (the "2017 Rate Case Decision"), which is subject to requests for rehearing and potential appeal. The new rates went into effect on August 19, 2017.

On January 3, 2018, an APS customer filed a petition with the ACC that was determined by the ACC Staff to be a complaint filed pursuant to Arizona Revised Statute §40-246 (the “Complaint”). The Complaint was later amended alleging that the rates and charges in the 2017 Rate Case Decision are not just and reasonable. The ACC held a hearing on this matter, and the Administrative Law Judge issued a Recommended Opinion and Order recommending that the Complaint be dismissed. On July 3, 2019, the Administrative Law Judge issued an amendment to the Recommended Opinion and Order that incorporated the requirements of the rate review of the 2017 Rate Case Decision (see below discussion regarding the rate review). On July 10, 2019, the ACC adopted the Administrative Law Judge's amended Recommended Opinion and Order along with several ACC Commissioner amendments and an amendment incorporating the results of the rate review and resolved the Complaint.

ACC Review of APS 2017 Rate Case Decision

On December 24, 2018, certain ACC Commissioners filed a letter stating that because the ACC had received a substantial number of complaints that the rate increase authorized by the 2017 Rate Case Decision was much more than anticipated, they believe there is a possibility that APS is earning more than was authorized by the 2017 Rate Case Decision.  Accordingly, the ACC Commissioners requested the ACC Staff to perform a rate review of APS using calendar year 2018 as a test year. The ACC Commissioners also asked the ACC Staff to evaluate APS’s efforts to educate its customers regarding the new rates approved in the 2017 Rate Case Decision.

On June 4, 2019, the ACC Staff filed a proposed order regarding the rate review of the 2017 Rate Case Decision. On June 11, 2019, the ACC Commissioners approved the proposed ACC Staff order with amendments. The key provisions of the amended order include the following:

APS must file a rate case no later than October 31, 2019, using a June 30, 2019 test-year;
until the conclusion of the rate case being filed no later than October 31, 2019, APS must provide information on customer bills that shows how much a customer would pay on their most economical rate given their actual usage during each month;
APS customers can switch rate plans during an open enrollment period of six months;
APS must identify customers whose bills have increased by more than 9% and that are not on the most economical rate and provide such customers with targeted education materials and an opportunity to switch rate plans;
APS must provide grandfathered net metering customers on legacy demand rates an opportunity to switch to another legacy rate to enable such customers to fully benefit from legacy net metering rates;
APS must fund and implement a supplemental customer education and outreach program to be developed with and administered by ACC Staff and a third-party consultant; and
APS must fund and organize, along with the third-party consultant, a stakeholder group to suggest better ways to communicate the impact of changes to adjustor cost recovery mechanisms (see below for discussion on cost recovery mechanisms), including more effective ways to educate customers on rate plans and to reduce energy usage.


27


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

APS filed its rate case on October 31, 2019 (see "2019 Retail Rate Case Filing with the Arizona Corporation Commission" above for more information). APS does not believe that the implementation of the other key provisions of the amended order regarding the rate review will have a material impact on its financial position, results of operations or cash flows.

On May 19, 2020, the ACC Staff filed a third-party consultant’s report which evaluated the effectiveness of APS’s customer outreach and education program related to the 2017 Rate Case Decision. On May 29, 2020, the Chairman of the ACC filed a letter with the ACC in response to this report and is alleging that APS is out of compliance with the 2017 Rate Case Decision and is over-earning. The Chairman proposed that the current rates should be classified as interim rates and customers held harmless if APS’s activities have caused the rates set in the 2017 Rate Case Decision to not be just and reasonable. Also, on May 29, 2020, a second commissioner filed a letter with the ACC agreeing with the Chairman’s assertions and further asserting that the 2017 Rate Case Decision should be re-opened. On June 18, 2020 at an ACC Open Meeting, the matters raised in these letters were discussed. The ACC did not vote to move forward with any adjustments to APS’s current rates. APS is monitoring this matter, but believes that the proposals are not legal and further that APS has not over-earned. APS cannot predict the outcome of this matter at this time or whether or how further action may be taken by the ACC.

Cost Recovery Mechanisms
 
APS has received regulatory decisions that allow for more timely recovery of certain costs outside of a general retail rate case through the following recovery mechanisms.
 
Renewable Energy Standard.  In 2006, the ACC approved the RES.  Under the RES, electric utilities that are regulated by the ACC must supply an increasing percentage of their retail electric energy sales from eligible renewable resources, including solar, wind, biomass, biogas and geothermal technologies.  In order to achieve these requirements, the ACC allows APS to include a RES surcharge as part of customer bills to recover the approved amounts for use on renewable energy projects.  Each year APS is required to file a five-year implementation plan with the ACC and seek approval for funding the upcoming year’s RES budget. In 2015, the ACC revised the RES rules to allow the ACC to consider all available information, including the number of rooftop solar arrays in a utility’s service territory, to determine compliance with the RES.

On November 20, 2017, APS filed an updated 2018 RES budget to include budget adjustments for APS Solar Communities (formerly known as AZ Sun II), which was approved as part of the 2017 Rate Case Decision. APS Solar Communities is a 3-year program authorizing APS to spend $10 million to $15 million in capital costs each year to install utility-owned DG systems for low to moderate income residential homes, non-profit entities, Title I schools and rural government facilities. The 2017 Rate Case Decision provided that all operations and maintenance expenses, property taxes, marketing and advertising expenses, and the capital carrying costs for this program will be recovered through the RES.

On June 29, 2018, APS filed its 2019 RES Implementation Plan and proposed a budget of approximately $89.9 million.  APS’s budget request supports existing approved projects and commitments and requests a permanent waiver of the residential distributed energy requirement for 2019 contained in the RES rules. On October 29, 2019, the ACC approved the 2019 RES Implementation Plan including a waiver of the residential distributed energy requirements for the 2019 implementation year.
    
On July 1, 2019, APS filed its 2020 RES Implementation Plan and proposed a budget of approximately $86.3 million. APS’s budget request supports existing approved projects and commitments and requests a

28


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

permanent waiver of the residential distributed energy requirement for 2020 contained in the RES rules. The ACC has not yet ruled on the 2020 RES Implementation Plan.

On July 1, 2020, APS filed its 2021 RES Implementation Plan and proposed a budget of approximately $84.7 million.  APS’s budget request supports existing approved projects and commitments and requests a permanent waiver of the residential distributed energy requirement for 2021 contained in the RES rules.  The ACC has not yet ruled on the 2021 RES Implementation Plan.

On July 15, 2020, ACC Staff issued final draft rules which, if approved, would require APS to meet certain clean energy standards, obtain approval for its action plan included in its IRP, and seek cost recovery in a rate process. APS cannot predict the outcome of this matter. See "Energy Modernization Plan" below for more information.

Demand Side Management Adjustor Charge.  The ACC Electric Energy Efficiency Standards require APS to submit a Demand Side Management Implementation Plan ("DSM Plan") annually for review by and approval of the ACC. Verified energy savings from APS's resource savings projects can be counted toward compliance with the Electric Energy Efficiency Standards; however, APS is not allowed to count savings from systems savings projects toward determination of the achievement of performance incentives, nor may APS include savings from these system savings projects in the calculation of its Lost Fixed Cost Recovery (“LFCR”) mechanism (see below for discussion of the LFCR).

On September 1, 2017, APS filed its 2018 DSM Plan, which proposes modifications to the demand side management portfolio to better meet system and customer needs by focusing on peak demand reductions, storage, load shifting and demand response programs in addition to traditional energy savings measures. The 2018 DSM Plan seeks a requested budget of $52.6 million and requests a waiver of the Electric Energy Efficiency Standard for 2018.   On November 14, 2017, APS filed an amended 2018 DSM Plan, which revised the allocations between budget items to address customer participation levels, but kept the overall budget at $52.6 million. The ACC has not yet ruled on the APS 2018 amended DSM Plan.

On December 31, 2018, APS filed its 2019 DSM Plan, which requests a budget of $34.1 million and continues APS's focus on DSM strategies such as peak demand reduction, load shifting, storage and electrification strategies. The ACC has not yet ruled on the APS 2019 DSM Plan.

On December 31, 2019, APS filed its 2020 DSM Plan, which requests a budget of $51.9 million and continues APS's focus on DSM strategies such as peak demand reduction, load shifting, storage and electrification strategies. The 2020 DSM Plan addresses all components of the pending 2018 and 2019 DSM plans, which enables the ACC to review the 2020 DSM Plan only. On May 15, 2020, APS filed an amended 2020 DSM Plan to provide assistance to customers experiencing economic impacts of the COVID-19 pandemic. The amended 2020 DSM Plan requests the same budget amount of $51.9 million. The ACC has not yet ruled on the APS amended 2020 DSM Plan.

On April 17, 2020, APS filed an application with the ACC requesting a COVID-19 emergency relief package to provide additional assistance to its customers. On May 5, 2020, the ACC approved APS returning $36 million that had been collected through the DSM Adjustor Charge, but not allocated for current DSM programs, directly to customers through a bill credit in June 2020. As of June 30, 2020, APS had refunded approximately $40 million to customers. The additional $4 million over the approved amount was the result of the kWh credit being based on historic consumption which was different than actual consumption in the refund period. This difference was recorded to the DSM balancing account and will be addressed in subsequent DSM filings. See "COVID-19 Pandemic" above for more information.

29


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS


 Power Supply Adjustor Mechanism and Balance.  The PSA provides for the adjustment of retail rates to reflect variations primarily in retail fuel and purchased power costs.  The following table shows the changes in the deferred fuel and purchased power regulatory asset for 2020 and 2019 (dollars in thousands):
 
 
Six Months Ended
June 30,
 
2020
 
2019
Beginning balance
$
70,137

 
$
37,164

Deferred fuel and purchased power costs — current period
26,473

 
16,702

Amounts charged to customers
4,815

 
(23,307
)
Ending balance
$
101,425

 
$
30,559


 
The PSA rate for the PSA year beginning February 1, 2018 is $0.004555 per kWh, consisting of a forward component of $0.002009 per kWh and a historical component of $0.002546 per kWh. This represented a $0.004 per kWh increase over the August 19, 2017 PSA, the maximum permitted under the Plan of Administration for the PSA. This left $16.4 million of 2017 fuel and purchased power costs above this annual cap. These costs rolled over into the following year and were reflected in the 2019 reset of the PSA.

The PSA rate for the PSA year beginning February 1, 2019 was $0.001658 per kWh, consisting of a Forward Component of $0.000536 per kWh and a Historical Component of $0.001122 per kWh. This represented a $0.002897 per kWh decrease compared to 2018. These rates went into effect as filed on February 1, 2019.

On November 27, 2019, APS filed its PSA rate for the PSA year beginning February 1, 2020. That rate was $(0.000456) per kWh and consisted of a Forward Component of $(0.002086) per kWh and a Historical Component of $0.001630 per kWh. The 2020 PSA rate is a $0.002115 per kWh decrease compared to the 2019 PSA year. These rates went into effect as filed on February 1, 2020.

On March 15, 2019, APS filed an application with the ACC requesting approval to recover the costs related to two energy storage power purchase tolling agreements through the PSA. This application is pending with the ACC. APS cannot predict the outcome of this matter.

Environmental Improvement Surcharge. The EIS permits APS to recover the capital carrying costs (rate of return, depreciation and taxes) plus incremental operations and maintenance expenses associated with environmental improvements made outside of a test year to comply with environmental standards set by federal, state, tribal, or local laws and regulations.  A filing is made on or before February 1st for qualified environmental improvements made during the prior calendar year, and the new charge becomes effective April 1 unless suspended by the ACC.  There is an overall cap of $0.0005 per kWh (approximately $13 - 14 million per year).  APS’s February 1, 2020 application requested an increase in the charge to $8.75 million, or $2.0 million over the charge in effect for the 2019-2020 rate effective year. On March 19, 2020, due to the COVID-19 pandemic, APS delayed the reset of the EIS adjustor to the first billing cycle in May 2020 rather than April 2020.
 
Transmission Rates, Transmission Cost Adjustor ("TCA") and Other Transmission Matters In July 2008, FERC approved a modification to APS’s Open Access Transmission Tariff to allow APS to move from fixed rates to a formula rate-setting methodology in order to more accurately reflect and recover the costs

30


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

that APS incurs in providing transmission services.  A large portion of the rate represents charges for transmission services to serve APS's retail customers ("Retail Transmission Charges").  In order to recover the Retail Transmission Charges, APS was previously required to file an application with, and obtain approval from, the ACC to reflect changes in Retail Transmission Charges through the TCA.  Under the terms of the settlement agreement entered into in 2012 regarding APS's rate case ("2012 Settlement Agreement"), however, an adjustment to rates to recover the Retail Transmission Charges will be made annually each June 1 and will go into effect automatically unless suspended by the ACC.
 
The formula rate is updated each year effective June 1 on the basis of APS's actual cost of service, as disclosed in APS's FERC Form 1 report for the previous fiscal year.  Items to be updated include actual capital expenditures made as compared with previous projections, transmission revenue credits and other items.  The resolution of proposed adjustments can result in significant volatility in the revenues to be collected.  APS reviews the proposed formula rate filing amounts with the ACC Staff.  Any items or adjustments which are not agreed to by APS and the ACC Staff can remain in dispute until settled or litigated at FERC.  Settlement or litigated resolution of disputed issues could require an extended period of time and could have a significant effect on the Retail Transmission Charges because any adjustment, though applied prospectively, may be calculated to account for previously over- or under-collected amounts.

On March 7, 2018, APS made a filing to make modifications to its annual transmission formula to provide transmission customers the benefit of the reduced federal corporate income tax rate resulting from the Tax Cuts and Jobs Act ("Tax Act") beginning in its 2018 annual transmission formula rate update filing. These modifications were approved by FERC on May 22, 2018 and reduced APS’s transmission rates compared to the rate that would have gone into effect absent these changes. On March 17, 2020, APS made a filing to make further modifications to its annual transmission formula to provide additional transparency for excess and deficient Accumulated Deferred Income Taxes resulting from the Tax Act, as well as for future local, state, and federal statutory tax rate changes. This filing is pending with FERC.

Effective June 1, 2018, APS's annual wholesale transmission rates for all users of its transmission system decreased by approximately $22.7 million for the twelve-month period beginning June 1, 2018 in accordance with the FERC-approved formula.  Of this amount, retail customer rates decreased by approximately $26.9 million. An adjustment to APS’s retail rates to recover FERC approved transmission charges went into effect automatically on June 1, 2018.

Effective June 1, 2019, APS's annual wholesale transmission rates for all users of its transmission system increased by approximately $25.8 million for the twelve-month period beginning June 1, 2019 in accordance with the FERC-approved formula. Of this amount, retail customer rates increased by approximately $4.7 million. An adjustment to APS’s retail rates to recover FERC approved transmission charges went into effect automatically on June 1, 2019.

Effective June 1, 2020, APS's annual wholesale transmission rates for all users of its transmission system decreased by approximately $6.1 million for the twelve-month period beginning June 1, 2020 in accordance with the FERC-approved formula.  Of this amount, retail customer rates decreased by approximately $10.9 million. An adjustment to APS’s retail rates to recover FERC approved transmission charges went into effect automatically on June 1, 2020.

 Lost Fixed Cost Recovery Mechanism.  The LFCR mechanism permits APS to recover on an after-the-fact basis a portion of its fixed costs that would otherwise have been collected by APS in the kWh sales lost due to APS energy efficiency programs and to DG such as rooftop solar arrays.  The fixed costs recoverable by the LFCR mechanism are currently 2.5 cents for both lost residential and non-residential kWh as set forth in

31


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

the 2017 Settlement Agreement.  The LFCR adjustment has a year-over-year cap of 1% of retail revenues.  Any amounts left unrecovered in a particular year because of this cap can be carried over for recovery in a future year.  The kWhs lost from energy efficiency are based on a third-party evaluation of APS’s energy efficiency programs.  DG sales losses are determined from the metered output from the DG units.
 
On February 15, 2018, APS filed its 2018 annual LFCR adjustment, requesting that effective May 1, 2018, the LFCR be adjusted to $60.7 million. On February 6, 2019, the ACC approved the 2018 annual LFCR adjustment to become effective March 1, 2019. On February 15, 2019, APS filed its 2019 annual LFCR adjustment, requesting that effective May 1, 2019, the annual LFCR recovery amount be reduced to $36.2 million (a $24.5 million decrease from previous levels). On July 10, 2019, the ACC approved APS’s 2019 LFCR adjustment as filed, effective with the next billing cycle of July 2019. On February 14, 2020, APS filed its 2020 annual LFCR adjustment, requesting that effective May 1, 2020, the annual LFCR recovery amount be reduced to $26.6 million (a $9.6 million decrease from previous levels). On April 14, 2020, the ACC approved the 2020 LFCR adjustment as filed, effective with the first billing cycle in May 2020.

Tax Expense Adjustor Mechanism.  As part of the 2017 Settlement Agreement, the parties agreed to a rate adjustment mechanism to address potential federal income tax reform and enable the pass-through of certain income tax effects to customers. The TEAM expressly applies to APS's retail rates with the exception of a small subset of customers taking service under specially-approved tariffs. On December 22, 2017, the Tax Act was enacted.  This legislation made significant changes to the federal income tax laws including a reduction in the corporate tax rate from 35% to 21% effective January 1, 2018.

On January 8, 2018, APS filed an application with the ACC that addressed the change in the marginal federal tax rate from 35% to 21% resulting from the Tax Act and reduced rates by $119.1 million annually through an equal cents per kWh credit ("TEAM Phase I").  On February 22, 2018, the ACC approved the reduction of rates through an equal cents per kWh credit. The rate reduction was effective for the first billing cycle in March 2018.

The impact of the TEAM Phase I, over time, is expected to be earnings neutral. However, on a quarterly basis, there is a difference between the timing and amount of the income tax benefit and the reduction in revenues refunded through the TEAM Phase I related to the lower federal income tax rate. The amount of the benefit of the lower federal income tax rate is based on quarterly pre-tax results, while the reduction in revenues refunded through the TEAM Phase I is based on a per kWh sales credit which follows our seasonal kWh sales pattern and is not impacted by earnings of the Company.

On August 13, 2018, APS filed a second request with the ACC that addressed the return of an additional $86.5 million in tax savings to customers related to the amortization of non-depreciation related excess deferred taxes previously collected from customers ("TEAM Phase II"). The ACC approved this request on March 13, 2019, effective the first billing cycle in April 2019 through the last billing cycle in March 2020. On March 19, 2020, due to the COVID-19 pandemic, APS delayed the discontinuation of TEAM Phase II until the first billing cycle in May 2020.  Amounts credited to customers after the last billing cycle in March 2020 will be recorded as a part of the balancing account and will be addressed for recovery as part of APS's 2019 ACC rate case. Both the timing of the reduction in revenues refunded through TEAM Phase II and the offsetting income tax benefit are recognized based upon our seasonal kWh sales pattern.
    
On April 10, 2019, APS filed a third request with the ACC that addressed the amortization of depreciation related excess deferred taxes over a 28.5 year period consistent with IRS normalization rules (“TEAM Phase III”).  On October 29, 2019, the ACC approved TEAM Phase III providing both (i) a one-time bill credit of $64 million which was credited to customers on their December 2019 bills, and (ii) a monthly bill

32


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

credit effective the first billing cycle in December 2019 which will provide an additional benefit of $39.5 million to customers through December 31, 2020. It is currently anticipated that benefits related to the amortization of depreciation related excess deferred taxes for periods beginning after December 31, 2020 will be fully incorporated into the 2019 rate case.

Net Metering

APS's 2017 Rate Case Decision provides that payments by utilities for energy exported to the grid from DG solar facilities will be determined using a RCP methodology, a method that is based on the most recent five-year rolling average price that APS pays for utility-scale solar projects, while a forecasted avoided cost methodology is being developed.  The price established by this RCP method will be updated annually (between general retail rate cases) but will not be decreased by more than 10% per year. Once the avoided cost methodology is developed, the ACC will determine in APS's subsequent rate cases which method (or a combination of methods) is appropriate to determine the actual price to be paid by APS for exported distributed energy.

In addition, the ACC made the following determinations:

Customers who have interconnected a DG system or submitted an application for interconnection for DG systems prior to September 1, 2017, based on APS's 2017 Rate Case Decision, will be grandfathered for a period of 20 years from the date the customer’s interconnection application was accepted by the utility;
Customers with DG solar systems are to be considered a separate class of customers for ratemaking purposes; and
Once an export price is set for APS, no netting or banking of retail credits will be available for new DG customers, and the then-applicable export price will be guaranteed for new customers for a period of 10 years.

This decision of the ACC addresses policy determinations only. The decision states that its principles will be applied in future general retail rate cases, and the policy determinations themselves may be subject to future change, as are all ACC policies. A first-year export energy price of 12.9 cents per kWh was included in the 2017 Settlement Agreement and became effective on September 1, 2017.

In accordance with the 2017 Rate Case Decision, APS filed its request for a second-year export energy price of 11.6 cents per kWh on May 1, 2018.  This price reflected the 10% annual reduction discussed above. The new rate rider became effective on October 1, 2018. APS filed its request for a third-year export energy price of 10.5 cents per kWh on May 1, 2019.  This price also reflects the 10% annual reduction discussed above. The new rate rider became effective on October 1, 2019. APS filed its request for a fourth-year export energy price of 9.4 cents per kWh on May 1, 2020, with a requested effective date of September 1, 2020.  This price reflects the 10% annual reduction discussed above. The ACC has not yet ruled on this request.

On January 23, 2017, The Alliance for Solar Choice ("TASC") sought rehearing of the ACC's decision regarding the value and cost of DG. TASC asserted that the ACC improperly ignored the Administrative Procedure Act, failed to give adequate notice regarding the scope of the proceedings, and relied on information that was not submitted as evidence, among other alleged defects. TASC filed a Notice of Appeal in the Arizona Court of Appeals and filed a Complaint and Statutory Appeal in the Maricopa County Superior Court on March 10, 2017. As part of the 2017 Settlement Agreement described above, TASC agreed to withdraw these appeals when the ACC decision implementing the 2017 Settlement Agreement is no longer subject to appellate review.

33


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS


See "2016 Retail Rate Case Filing with the Arizona Corporation Commission" above for information regarding an ACC order in connection with the rate review of the 2017 Rate Case Decision requiring APS to provide grandfathered net metering customers on legacy demand rates with an opportunity to switch to another legacy rate to enable such customers to benefit from legacy net metering rates.

Subpoena from Arizona Corporation Commissioner Robert Burns

On August 25, 2016, Commissioner Burns, individually and not by action of the ACC as a whole, served subpoenas in APS’s then current retail rate proceeding on APS and Pinnacle West for the production of records and information relating to a range of expenditures from 2011 through 2016. The subpoenas requested information concerning marketing and advertising expenditures, charitable donations, lobbying expenses, contributions to 501(c)(3) and (c)(4) nonprofits and political contributions. The return date for the production of information was set as September 15, 2016. The subpoenas also sought testimony from Company personnel having knowledge of the material, including the Chief Executive Officer.

On September 9, 2016, APS filed with the ACC a motion to quash the subpoenas or, alternatively, to stay APS's obligations to comply with the subpoenas and decline to decide APS's motion pending court proceedings. Contemporaneously with the filing of this motion, APS and Pinnacle West filed a complaint for special action and declaratory judgment in the Superior Court of Arizona for Maricopa County, seeking a declaratory judgment that Commissioner Burns’ subpoenas are contrary to law. On September 15, 2016, APS produced all non-confidential and responsive documents and offered to produce any remaining responsive documents that are confidential after an appropriate confidentiality agreement is signed.

On February 7, 2017, Commissioner Burns opened a new ACC docket and indicated that its purpose is to study and rectify problems with transparency and disclosure regarding financial contributions from regulated monopolies or other stakeholders who may appear before the ACC that may directly or indirectly benefit an ACC Commissioner, a candidate for ACC Commissioner, or key ACC Staff.  As part of this docket, Commissioner Burns set March 24, 2017 as a deadline for the production of all information previously requested through the subpoenas. Neither APS nor Pinnacle West produced the information requested and instead objected to the subpoena. On March 10, 2017, Commissioner Burns filed suit against APS and Pinnacle West in the Superior Court of Arizona for Maricopa County in an effort to enforce his subpoenas. On March 30, 2017, APS filed a motion to dismiss Commissioner Burns' suit against APS and Pinnacle West. In response to the motion to dismiss, the court stayed the suit and ordered Commissioner Burns to file a motion to compel the production of the information sought by the subpoenas with the ACC. On June 20, 2017, the ACC denied the motion to compel.

On August 4, 2017, Commissioner Burns amended his complaint to add all of the ACC Commissioners and the ACC itself as defendants. All defendants moved to dismiss the amended complaint. On February 15, 2018, the Superior Court dismissed Commissioner Burns’ amended complaint. On March 6, 2018, Commissioner Burns filed an objection to the proposed final order from the Superior Court and a motion to further amend his complaint. The Superior Court permitted Commissioner Burns to amend his complaint to add a claim regarding his attempted investigation into whether his fellow commissioners should have been disqualified from voting on APS’s 2017 rate case. Commissioner Burns filed his second amended complaint, and all defendants filed responses opposing the second amended complaint and requested that it be dismissed. Oral argument occurred in November 2018 regarding the motion to dismiss. On December 18, 2018, the trial court granted the defendants’ motions to dismiss and entered final judgment on January 18, 2019. On February 13, 2019, Commissioner Burns filed a notice of appeal. On July 12, 2019, Commissioner Burns filed his opening brief in the Arizona Court of Appeals. APS filed its answering brief on October 21, 2019. The

34


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

Arizona Court of Appeals originally granted the request for oral argument; however, on March 31, 2020, the court vacated the date scheduled for oral argument given the COVID-19 pandemic.  The court determined that the matter could be submitted without oral argument and has taken the matter under advisement and will issue a decision without oral argument. APS and Pinnacle West cannot predict the outcome of this matter.

Information Requests from Arizona Corporation Commissioners

On January 14, 2019, ACC Commissioner Kennedy opened a docket to investigate campaign expenditures and political participation of APS and Pinnacle West. In addition, on February 27, 2019, ACC Commissioners Burns and Dunn opened a new docket and requested documents from APS and Pinnacle West related to ACC elections and charitable contributions related to the ACC. On March 1, 2019, ACC Commissioner Kennedy issued a subpoena to APS seeking several categories of information for both Pinnacle West and APS including political contributions, lobbying expenditures, marketing and advertising expenditures, and contributions made to 501(c)(3) and 501(c)(4) entities, for the years 2013-2018. Pinnacle West and APS voluntarily responded to both sets of requests on March 29, 2019. APS also received and responded to various follow-on requests from ACC Commissioners on these matters. Pinnacle West and APS cannot predict the outcome of these matters. The Company's CEO, Mr. Guldner, appeared at the ACC's January 14, 2020 Open Meeting regarding ACC Commissioners' questions about political spending.  Mr. Guldner committed to the ACC that during his tenure, Pinnacle West and APS, and any of their affiliated companies, will not participate in ACC campaign elections through financial contributions or in-kind contributions.
    
Energy Modernization Plan

On January 30, 2018, former ACC Commissioner Tobin proposed the Energy Modernization Plan, which consisted of a series of energy policies tied to clean energy sources such as energy storage, biomass, energy efficiency, electric vehicles, and expanded energy planning through the integrated resource plan ("IRP") process. In August 2018, the ACC directed ACC Staff to open a new rulemaking docket which will address a wide range of energy issues, including the Energy Modernization Plan proposals. The rulemaking will consider possible modifications to existing ACC rules, such as the RES, Electric and Gas Energy Efficiency Standards, Net Metering, Resource Planning, and the Biennial Transmission Assessment, as well as the development of new rules regarding forest bioenergy, electric vehicles, interconnection of distributed generation, baseload security, blockchain technology and other technological developments, retail competition, and other energy-related topics.

On April 25, 2019, the ACC Staff issued an initial set of draft energy rules and held various workshops to incorporate feedback from stakeholders and ACC Commissioners from April 2019 through July 2020. At the March 11-12, 2020 workshop, the ACC Staff committed to filing a final draft of proposed rules by July 2020. On July 16, 2020, the ACC Staff issued final draft energy rules which propose 100% of retail kWh sales from clean energy resources by the end of 2050. Nuclear is defined as a clean energy resource. The proposed rules also require 50% of retail energy served be renewable by the end of 2035, including a 10% carve out for customer-sited distributed generation with storage. A new energy efficiency standard was not included in the proposed rules. APS would be required to obtain approval of its action plan included in its IRP and seek recovery of prudently incurred costs in a rate process. If approved by the ACC Commissioners, the rules would require utilities to file a Clean Energy Implementation Plan and Energy Efficiency Report as part of their IRP every three years beginning in 2023. In addition, the ACC Staff proposed changing the IRP planning horizon from 15 years to 10 years. On July 30, 2020, the ACC discussed the final draft energy rules but no action was taken by the ACC. APS cannot predict the outcome of this matter.
 

35


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS


Integrated Resource Planning

ACC rules require utilities to develop 15-year IRPs which describe how the utility plans to serve customer load in the plan timeframe.  The ACC reviews each utility’s IRP to determine if it meets the necessary requirements and whether it should be acknowledged.  In March of 2018, the ACC reviewed the 2017 IRPs of its jurisdictional utilities and voted to not acknowledge any of the plans.  APS does not believe that this lack of acknowledgment will have a material impact on our financial position, results of operations or cash flows.  Based on an ACC decision, APS was originally required to file its next IRP by April 1, 2020.  On February 20, 2020, the ACC extended the deadline for all utilities to file their IRP’s from April 1, 2020 to June 26, 2020. On June 26, 2020, APS filed its final IRP. On July 15, 2020, the ACC extended the schedule for final ACC review of utility IRPs to February 2021. See "Energy Modernization Rules" above for information regarding proposed changes to the IRP filings.

Public Utility Regulatory Policies Act ("PURPA")

In August 2016, APS filed an application requesting that all of its contracts with qualifying facilities over 100 kW be set at a presumptive maximum 2 year term. A qualifying facility is an eligible energy-producing facility as defined by FERC regulations within a host electric utility’s service territory that has a right to sell to the host utility. Host utilities are required to purchase power from qualifying facilities at an avoided cost as determined by the utility subject to state commission oversight. A hearing was held in August 2019 and briefing on this matter was completed in October 2019 regarding APS’s application. On December 17, 2019, the ACC denied the application and mandated a minimum contract length of 18 years for qualifying facilities over 100 kW and the rate paid to the qualifying facilities will be based on the long-term avoided cost. APS is in discussions with qualifying facility developers but has not entered into any new qualifying facility agreements that would be subject to the new requirements of the ACC's decision.

On July 16, 2020, FERC issued a final rule revising FERC’s regulations implementing PURPA. The final rule will go into effect 120 days following publication in the Federal Register. APS is evaluating how the revised regulations may impact its operations.

Residential Electric Utility Customer Service Disconnections

On June 13, 2019, APS voluntarily suspended electric disconnections for residential customers who had not paid their bills. On June 20, 2019, the ACC voted to enact emergency rule amendments to prevent residential electric utility customer service disconnections during the period from June 1 through October 15 ("Summer Disconnection Moratorium"). During the Summer Disconnection Moratorium, APS could not charge late fees and interest on amounts that were past due from customers. Customer deposits must also be used to pay delinquent amounts before disconnection can occur and customers will have four months to pay back their deposit and any remaining delinquent amounts. In accordance with the emergency rules, APS began putting delinquent customers on a mandatory four-month payment plan beginning on October 16, 2019. The emergency rule changes will be effective for 180 days and may be renewed for one additional 180-day period.

In addition, in June 2019, the ACC began a formal regular rulemaking process to allow stakeholder input and time for consideration of permanent rule changes. The ACC further ordered that each regulated electric utility serving retail customers in Arizona update its service conditions by incorporating the emergency rule amendments, restore power to any customers who were disconnected during the month of June 2019 and credit any fees that were charged for a reconnection. The ACC Staff issued draft amendments to the customer service disconnections rules. Stakeholders submitted initial comments to the draft amendments on

36


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

September 23, 2019. ACC stakeholder meetings were held in September 2019, October 2019 and January 2020 regarding the customer service disconnections rules.

Although the emergency rules expired in December 2019, the Summer Disconnection Moratorium will remain in effect through utility tariffs for 2020 and beyond until the ACC adopts permanent rules or determines otherwise.

Due to the COVID-19 pandemic, APS voluntarily suspended disconnections of customers for nonpayment beginning March 13, 2020. APS currently estimates that the Summer Disconnection Moratorium, the suspension of disconnections during the COVID-19 pandemic and the increased bad debt expense associated with both events will result in a negative impact to its 2020 operating results of approximately $20 million to $30 million pre-tax above the impact of disconnections on its operating results for years that did not have the Summer Disconnection Moratorium or COVID-19 pandemic. These estimated impact amounts depend on certain assumptions, including, but not limited to, customer behaviors, population and employment growth, the impacts of COVID-19 on the economy and the results of final rulemaking related to the Summer Disconnection Moratorium. See "COVID-19 Pandemic" above for more information.

Retail Electric Competition Rules
On November 17, 2018, the ACC voted to re-examine the facilitation of a deregulated retail electric market in Arizona. An ACC special open meeting workshop was held on December 3, 2018. No substantive action was taken, but interested parties were asked to submit written comments and respond to a list of questions from ACC Staff. On July 1 and July 2, 2019, ACC Staff issued a report and initial proposed draft rules regarding possible modifications to the ACC’s retail electric competition rules. Interested parties filed comments to the ACC Staff report and a stakeholder meeting and workshop to discuss the retail electric competition rules was held on July 30, 2019. ACC Commissioners submitted additional questions regarding this matter. On February 10, 2020, two ACC Commissioners filed two sets of draft proposed retail electric competition rules. On February 12, 2020, ACC staff issued its second report regarding possible modifications to the ACC’s retail electric competition rules. The ACC held a workshop on February 25-26, 2020 for further consideration and discussion of the retail electric competition rules. During the July 15, 2020 ACC Staff meeting, the ACC Commissioners discussed the possible development of a retail competition pilot program, but no action was taken. The ACC Commissioners are continuing to explore the retail electric competition rules. APS cannot predict whether these efforts will result in any changes and, if changes to the rules results, what impact these rules would have on APS.

Rate Plan Comparison Tool

On November 14, 2019, APS learned that its rate plan comparison tool was not functioning as intended due to an integration error between the tool and the Company’s meter data management system. APS immediately removed the tool from its website and notified the ACC. The purpose of the tool was to provide customers with a rate plan recommendation based upon historical usage data. Upon investigation, APS determined that the error may have affected rate plan recommendations to customers between February 4, 2019 and November 14, 2019. By the middle of May 2020, APS provided refunds to approximately 13,000 potentially impacted customers equal to the difference between what they paid for electricity and the amount they would have paid had they selected their most economical rate, as applicable, and a $25 payment for any inconvenience that the customer may have experienced. The refunds and payment for inconvenience being provided did not have a material impact on APS's financial statements. APS developed a new tool for comparing customers’ rate plan options.  APS had an independent third party verify that the new rate comparison tool works correctly.  In February 2020, APS launched the new online rate comparison tool, which

37


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

is now available for its customers. The ACC is currently investigating this matter and has hired an outside consultant to evaluate the extent of the error and the overall effectiveness of the tool. APS received a civil investigative demand from the Office of the Arizona Attorney General, Civil Litigation Division, Consumer Protection & Advocacy Section that seeks information pertaining to the rate plan comparison tool offered to APS customers and other related issues. APS is fully cooperating with the Attorney General’s Office in this matter. APS cannot predict the outcome of these matters.

Four Corners SCR Cost Recovery

On December 29, 2017, in accordance with the 2017 Rate Case Decision, APS filed a Notice of Intent to file its SCR Adjustment to permit recovery of costs associated with the installation of SCR equipment at Four Corners Units 4 and 5.  APS filed the SCR Adjustment request in April 2018.  Consistent with the 2017 Rate Case Decision, the request was narrow in scope and addressed only costs associated with this specific environmental compliance equipment.  The SCR Adjustment request provided that there would be a $67.5 million annual revenue impact that would be applied as a percentage of base rates for all applicable customers.  Also, as provided for in the 2017 Rate Case Decision, APS requested that the adjustment become effective no later than January 1, 2019.  The hearing for this matter occurred in September 2018.  At the hearing, APS accepted ACC Staff's recommendation of a lower annual revenue impact of approximately $58.5 million. The Administrative Law Judge issued a Recommended Opinion and Order finding that the costs for the SCR project were prudently incurred and recommending authorization of the $58.5 million annual revenue requirement related to the installation and operation of the SCRs. Exceptions to the Recommended Opinion and Order were filed by the parties and intervenors on December 7, 2018.  The ACC has not issued a decision on this matter. APS included the costs for the SCR project in the retail rate base in its 2019 retail rate case filing with the ACC. On March 18, 2020, the ACC agreed to take administrative notice to include in the pending rate case portions of the record in this prior proceeding that are relevant to the SCRs. APS cannot predict the outcome or timing of the decision on this matter. APS may be required to record a charge to its results of operations if the ACC issues an unfavorable decision (see SCR deferral in the Regulatory Assets and Liabilities table below).

Cholla

On September 11, 2014, APS announced that it would close Unit 2 of the Cholla Power Plant ("Cholla") and cease burning coal at the other APS-owned units (Units 1 and 3) at the plant by the mid-2020s, if the United States Environmental Protection Agency ("EPA") approved a compromise proposal offered by APS to meet required environmental and emissions standards and rules. On April 14, 2015, the ACC approved APS's plan to retire Unit 2, without expressing any view on the future recoverability of APS's remaining investment in the unit. APS closed Unit 2 on October 1, 2015. In early 2017, EPA approved a final rule incorporating APS's compromise proposal, which took effect on April 26, 2017. In December 2019, PacifiCorp notified APS that it plans to retire Cholla Unit 4 by the end of 2020.

Previously, APS estimated Cholla Unit 2’s end of life to be 2033. APS has been recovering a return on and of the net book value of the unit in base rates. Pursuant to the 2017 Settlement Agreement described above, APS will be allowed continued recovery of the net book value of the unit and the unit’s decommissioning and other retirement-related costs ($65 million as of June 30, 2020), in addition to a return on its investment. In accordance with GAAP, in the third quarter of 2014, Unit 2’s remaining net book value was reclassified from property, plant and equipment to a regulatory asset. The 2017 Settlement Agreement also shortened the depreciation lives of Cholla Units 1 and 3 to 2025.

38


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

On March 20, 2019, APS announced that it began evaluating the feasibility and cost of converting a unit at Cholla to burn biomass. Biomass is a fuel comprised of forest trimmings, and a converted unit at Cholla could assist in forest thinning, responsible forest management, an improved watershed, and a reduced wildfire risk. APS’s ability to operate a biomass power plant would depend on third-parties procuring forest biomass for fuel. APS reported the results of its evaluation on May 9, 2019 to the ACC. On July 10, 2019, the ACC voted to not require APS to file a request for proposal to convert the unit at Cholla to burn biomass.
Navajo Plant
The co-owners of the Navajo Plant and the Navajo Nation agreed that the Navajo Plant would remain in operation until December 2019 under the existing plant lease. The co-owners and the Navajo Nation executed a lease extension on November 29, 2017 that allows for decommissioning activities to begin after the plant ceased operations in November 2019.
  
APS is currently recovering depreciation and a return on the net book value of its interest in the Navajo Plant over its previously estimated life through 2026. APS will seek continued recovery in rates for the book value of its remaining investment in the plant ($77 million as of June 30, 2020) plus a return on the net book value as well as other costs related to retirement and closure, which are still being assessed and may be material. APS believes it will be allowed recovery of the net book value, in addition to a return on its investment. In accordance with GAAP, in the second quarter of 2017, APS's remaining net book value of its interest in the Navajo Plant was reclassified from property, plant and equipment to a regulatory asset. If the ACC does not allow full recovery of the remaining net book value of this interest, all or a portion of the regulatory asset will be written off and APS's net income, cash flows, and financial position will be negatively impacted.    

39


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

Regulatory Assets and Liabilities 
The detail of regulatory assets is as follows (dollars in thousands): 
 
Amortization Through
 
June 30, 2020
 
December 31, 2019
 
 
Current
 
Non-Current
 
Current
 
Non-Current
Pension
(a)
 
$

 
$
663,327

 
$

 
$
660,223

Income taxes — allowance for funds used during construction ("AFUDC") equity
2050
 
6,815

 
156,528

 
6,800

 
154,974

Retired power plant costs
2033
 
28,182

 
128,304

 
28,182

 
142,503

Deferred fuel and purchased power (b) (c)
2021
 
101,425

 

 
70,137

 

Deferred fuel and purchased power — mark-to-market (Note 7)
2024
 
42,911

 
26,151

 
36,887

 
33,185

Ocotillo deferral
N/A
 

 
65,571

 

 
38,144

SCR deferral
N/A
 

 
64,971

 

 
52,644

Deferred property taxes
2027
 
8,569

 
53,911

 
8,569

 
58,196

Deferred compensation
2036
 

 
36,481

 

 
36,464

Four Corners cost deferral
2024
 
8,077

 
28,113

 
8,077

 
32,152

Lost fixed cost recovery (b)
2021
 
34,144

 

 
26,067

 

Income taxes — investment tax credit basis adjustment
2048
 
1,098

 
24,532

 
1,098

 
24,981

Palo Verde VIEs (Note 6)
2046
 

 
20,945

 

 
20,635

Coal reclamation
2026
 
1,068

 
17,533

 
1,546

 
17,688

Loss on reacquired debt
2038
 
1,637

 
11,241

 
1,637

 
12,031

TCA balancing account (b)
2022
 
8,272

 
2,926

 
6,324

 
2,885

Mead-Phoenix transmission line contributions in aid of construction ("CIAC")
2050
 
332

 
9,546

 
332

 
9,712

Tax expense of Medicare subsidy
2024
 
1,238

 
4,444

 
1,235

 
4,940

AG-1 deferral
2022
 
2,787

 
1,322

 
2,787

 
2,716

Tax expense adjuster mechanism (b)
2020
 
3,640

 

 
1,612

 

Other
Various
 
1,399

 

 
1,917

 

Total regulatory assets (d)
 
 
$
251,594

 
$
1,315,846

 
$
203,207

 
$
1,304,073


(a)
This asset represents the future recovery of pension benefit obligations through retail rates.  If these costs are disallowed by the ACC, this regulatory asset would be charged to other comprehensive income ("OCI") and result in lower future revenues.
(b)
See "Cost Recovery Mechanisms" discussion above.
(c)
Subject to a carrying charge.
(d)
There are no regulatory assets for which the ACC has allowed recovery of costs, but not allowed a return by exclusion from rate base.  FERC rates are set using a formula rate as described in "Transmission Rates, Transmission Cost Adjustor and Other Transmission Matters."



40


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

The detail of regulatory liabilities is as follows (dollars in thousands):
 
 
Amortization Through
 
June 30, 2020
 
December 31, 2019
 
 
Current
 
Non-Current
 
Current
 
Non-Current
Excess deferred income taxes - ACC - Tax Cuts and Jobs Act (a)
2046
 
$
113,168

 
$
966,576

 
$
59,918

 
$
1,054,053

Excess deferred income taxes - FERC - Tax Cuts and Jobs Act (a)
2058
 
7,256

 
233,953

 
6,302

 
237,357

Asset retirement obligations
2057
 

 
408,126

 

 
418,423

Removal costs
(c)
 
47,300

 
126,036

 
47,356

 
136,072

Other postretirement benefits
(d)
 
37,575

 
118,398

 
37,575

 
139,634

Four Corners coal reclamation
2038
 
5,461

 
48,795

 
1,059

 
51,704

Spent nuclear fuel
2027
 
6,068

 
47,901

 
6,676

 
51,019

Income taxes — change in rates
2050
 
2,802

 
50,163

 
2,797

 
68,265

Income taxes — deferred investment tax credit
2048
 
2,202

 
49,133

 
2,202

 
50,034

Renewable energy standard (b)
2021
 
38,934

 
22

 
39,287

 
10,300

Sundance maintenance
2031
 
1,100

 
13,001

 
5,698

 
11,319

Demand side management (b)
2021
 
3,068

 
6,138

 
15,024

 
24,146

Property tax deferral
N/A
 

 
8,603

 

 
7,046

FERC transmission true up
2022
 
5,452

 
2,209

 
1,045

 
2,004

Active union medical trust
N/A
 

 
7,629

 

 
2,041

Tax expense adjustor mechanism (b)
2020
 
6,450

 

 
7,018

 

Deferred gains on utility property
2022
 
2,423

 
2,973

 
2,423

 
4,163

Other
Various
 
220

 
331

 
532

 
255

Total regulatory liabilities
 
 
$
279,479

 
$
2,089,987

 
$
234,912

 
$
2,267,835


(a)
For purposes of presentation on the Statement of Cash Flows, amortization of the regulatory liabilities for excess deferred income taxes are reflected as "Deferred income taxes" under Cash Flows From Operating Activities.
(b)
See “Cost Recovery Mechanisms” discussion above.
(c)
In accordance with regulatory accounting guidance, APS accrues removal costs for its regulated assets, even if there is no legal obligation for removal.
(d)
See Note 5.

5.
Retirement Plans and Other Postretirement Benefits
 
Pinnacle West sponsors a qualified defined benefit and account balance pension plan, a non-qualified supplemental excess benefit retirement plan, and an other postretirement benefit plan for the employees of Pinnacle West and our subsidiaries.  Pinnacle West uses a December 31 measurement date for its pension and other postretirement benefit plans.  The market-related value of our plan assets is their fair value at the measurement dates.


41


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

The following table provides details of the plans’ net periodic benefit costs and the portion of these costs charged to expense (including administrative costs and excluding amounts capitalized as overhead construction or billed to electric plant participants) (dollars in thousands):

 
Pension Benefits
 
Other Benefits
 
Three Months Ended
June 30,
 
Six Months Ended
June 30,
 
Three Months Ended
June 30,
 
Six Months Ended
June 30,
 
2020
 
2019
 
2020
 
2019
 
2020
 
2019
 
2020
 
2019
Service cost — benefits earned during the period
$
13,859

 
$
12,408

 
$
28,116

 
$
24,951

 
$
5,401

 
$
4,470

 
$
11,118

 
$
9,184

Non-service costs (credits):
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Interest cost on benefit obligation
29,522

 
34,069

 
59,283

 
68,421

 
6,417

 
7,421

 
12,929

 
14,947

Expected return on plan assets
(46,915
)
 
(43,049
)
 
(93,721
)
 
(85,942
)
 
(10,019
)
 
(9,603
)
 
(20,038
)
 
(19,206
)
  Amortization of:
 

 
 
 
 

 
 

 
 

 
 

 
 

 
 

  Prior service credit

 

 

 

 
(9,394
)
 
(9,455
)
 
(18,788
)
 
(18,910
)
  Net actuarial loss
8,295

 
10,053

 
17,306

 
21,292

 

 

 

 

Net periodic benefit cost (credit)
$
4,761

 
$
13,481

 
$
10,984

 
$
28,722

 
$
(7,595
)
 
$
(7,167
)
 
$
(14,779
)
 
$
(13,985
)
Portion of cost (credit) charged to expense
$
271

 
$
7,000

 
$
1,613

 
$
15,244

 
$
(5,056
)
 
$
(5,063
)
 
$
(10,512
)
 
$
(9,880
)

 
Contributions
 
We have not made voluntary contributions to our pension plan year-to-date in 2020. The minimum required contributions for the pension plan are zero for the next three years. We expect to make voluntary contributions up to $100 million per year during the 2020-2022 period. We do not expect to make any contributions over the next three years to our other postretirement benefit plans.
 
6.
Palo Verde Sale Leaseback Variable Interest Entities
 
In 1986, APS entered into agreements with three separate VIE lessor trust entities in order to sell and lease back interests in Palo Verde Unit 2 and related common facilities. APS will retain the assets through 2023 under one lease and 2033 under the other two leases. APS will be required to make payments relating to these leases of approximately $23 million annually for the period 2020 through 2023, and $16 million annually for the period 2024 through 2033. At the end of the lease period, APS will have the option to purchase the leased assets at their fair market value, extend the leases for up to two years, or return the assets to the lessors.

The leases' terms give APS the ability to utilize the assets for a significant portion of the assets’ economic life, and therefore provide APS with the power to direct activities of the VIEs that most significantly impact the VIEs’ economic performance.  Predominantly due to the lease terms, APS has been deemed the primary beneficiary of these VIEs and therefore consolidates the VIEs.
 
As a result of consolidation, we eliminate lease accounting and instead recognize depreciation expense, resulting in an increase in net income for the three and six months ended June 30, 2020 of $5 million and $10 million, respectively, and for the three and six months ended June 30, 2019 of $5 million and $10 million, respectively, entirely attributable to the noncontrolling interests. Income attributable to Pinnacle West shareholders is not impacted by the consolidation.

42


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS


Our Condensed Consolidated Balance Sheets at June 30, 2020 and December 31, 2019 include the following amounts relating to the VIEs (dollars in thousands):
 
 
June 30, 2020
 
December 31, 2019
Palo Verde sale leaseback property plant and equipment, net of accumulated depreciation
$
99,971

 
$
101,906

Equity — Noncontrolling interests
120,915

 
122,540


 
Assets of the VIEs are restricted and may only be used for payment to the noncontrolling interest holders. These assets are reported on our condensed consolidated financial statements.
 
APS is exposed to losses relating to these VIEs upon the occurrence of certain events that APS does not consider to be reasonably likely to occur.  Under certain circumstances (for example, the Nuclear Regulatory Commission ("NRC") issuing specified violation orders with respect to Palo Verde or the occurrence of specified nuclear events), APS would be required to make specified payments to the VIEs’ noncontrolling equity participants and take title to the leased Unit 2 interests, which, if appropriate, may be required to be written down in value.  If such an event were to occur during the lease periods, APS may be required to pay the noncontrolling equity participants approximately $304 million beginning in 2020, and up to $456 million over the lease extension terms.
 
For regulatory ratemaking purposes, the agreements continue to be treated as operating leases and, as a result, we have recorded a regulatory asset relating to the arrangements.

7.    Derivative Accounting
 
Derivative financial instruments are used to manage exposure to commodity price and transportation costs of electricity, natural gas, emissions allowances, and in interest rates.  Risks associated with market volatility are managed by utilizing various physical and financial derivative instruments, including futures, forwards, options and swaps.  As part of our overall risk management program, we may use derivative instruments to hedge purchases and sales of electricity and fuels.  Derivative instruments that meet certain hedge accounting criteria may be designated as cash flow hedges and are used to limit our exposure to cash flow variability on forecasted transactions.  The changes in market value of such instruments have a high correlation to price changes in the hedged transactions.  Derivative instruments are also entered into for economic hedging purposes.  While economic hedges may mitigate exposure to fluctuations in commodity prices, these instruments have not been designated as accounting hedges.  Contracts that have the same terms (quantities, delivery points and delivery periods) and for which power does not flow are netted, which reduces both revenues and fuel and purchased power costs in our Condensed Consolidated Statements of Income, but does not impact our financial condition, net income or cash flows.
 
Our derivative instruments, excluding those qualifying for a scope exception, are recorded on the balance sheets as an asset or liability and are measured at fair value.  See Note 11 for a discussion of fair value measurements.  Derivative instruments may qualify for the normal purchases and normal sales scope exception if they require physical delivery and the quantities represent those transacted in the normal course of business.  Derivative instruments qualifying for the normal purchases and sales scope exception are accounted for under the accrual method of accounting and excluded from our derivative instrument discussion and disclosures below.

43


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

 
For its regulated operations, APS defers for future rate treatment 100% of the unrealized gains and losses on derivatives pursuant to the PSA mechanism that would otherwise be recognized in income.  Realized gains and losses on derivatives are deferred in accordance with the PSA to the extent the amounts are above or below the Base Fuel Rate (see Note 4).  Gains and losses from derivatives in the following tables represent the amounts reflected in income before the effect of PSA deferrals.
 
As of June 30, 2020 and December 31, 2019, we had the following outstanding gross notional volume of derivatives, which represent both purchases and sales (does not reflect net position): 
 
 
 
Quantity
Commodity
 
Unit of Measure
June 30, 2020
 
December 31, 2019
Power
 
GWh
294

 
193

Gas
 
Billion cubic feet
249

 
257


 
Gains and Losses from Derivative Instruments
 
The following table provides information about gains and losses from derivative instruments in designated cash flow accounting hedging relationships during the three and six months ended June 30, 2020 and 2019 (dollars in thousands):
 
 
 
Financial Statement Location
 
Three Months Ended
June 30,
 
Six Months Ended
June 30,
Commodity Contracts
 
 
2020
 
2019
 
2020
 
2019
Loss Reclassified from Accumulated OCI into Income (Effective Portion Realized) (a)
 
Fuel and purchased power (b)
 
$
(349
)
 
$
(538
)
 
$
(763
)
 
$
(974
)

(a)
During the three and six months ended June 30, 2020 and 2019, we had no gains or losses reclassified from accumulated OCI to earnings related to discontinued cash flow hedges.
(b)
Amounts are before the effect of PSA deferrals.
 
During the next twelve months we estimate that no amounts will be reclassified from accumulated OCI into income. For APS, the delivery period for all derivative instruments in designated cash flow accounting hedging relationship have lapsed.
 

44


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

The following table provides information about gains and losses from derivative instruments not designated as accounting hedging instruments during the three and six months ended June 30, 2020 and 2019 (dollars in thousands):
 
 
 
Financial Statement Location
 
Three Months Ended
June 30,
 
Six Months Ended
June 30,
Commodity Contracts
 
 
2020
 
2019
 
2020
 
2019
Net Loss Recognized in Income
 
Fuel and purchased power (a)
 
$
(4,894
)
 
$
(49,686
)
 
$
(34,971
)
 
$
(41,516
)

(a)
Amounts are before the effect of PSA deferrals.
 
Derivative Instruments in the Condensed Consolidated Balance Sheets
 
Our derivative transactions are typically executed under standardized or customized agreements, which include collateral requirements and, in the event of a default, would allow for the netting of positive and negative exposures associated with a single counterparty.  Agreements that allow for the offsetting of positive and negative exposures associated with a single counterparty are considered master netting arrangements.  Transactions with counterparties that have master netting arrangements are offset and reported net on the Condensed Consolidated Balance Sheets.  Transactions that do not allow for offsetting of positive and negative positions are reported gross on the Condensed Consolidated Balance Sheets.
 
We do not offset a counterparty’s current derivative contracts with the counterparty’s non-current derivative contracts, although our master netting arrangements would allow current and non-current positions to be offset in the event of a default.  These types of transactions may include non-derivative instruments, derivatives qualifying for scope exceptions, trade receivables and trade payables arising from settled positions, and other forms of non-cash collateral (such as letters of credit).  These types of transactions are excluded from the offsetting tables presented below.
 

45


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

The following tables provide information about the fair value of our risk management activities reported on a gross basis, and the impacts of offsetting as of June 30, 2020 and December 31, 2019.  These amounts relate to commodity contracts and are located in the assets and liabilities from risk management activities lines of our Condensed Consolidated Balance Sheets.

As of June 30, 2020:
(dollars in thousands)
 
Gross
 Recognized
 Derivatives
 (a)
 
Amounts
Offset
 (b)
 
Net
 Recognized
 Derivatives
 
Other
 (c)
 
Amount Reported on Balance Sheets
Current assets
 
$
2,989

 
$
(2,279
)
 
$
710

 
$

 
$
710

Investments and other assets
 
540

 
(510
)
 
30

 

 
30

Total assets
 
3,529

 
(2,789
)
 
740

 

 
740

 
 
 
 
 
 
 
 
 
 
 
Current liabilities
 
(45,899
)
 
2,279

 
(43,620
)
 
(1,185
)
 
(44,805
)
Deferred credits and other
 
(26,691
)
 
510

 
(26,181
)
 

 
(26,181
)
Total liabilities
 
(72,590
)
 
2,789

 
(69,801
)
 
(1,185
)
 
(70,986
)
Total
 
$
(69,061
)
 
$

 
$
(69,061
)
 
$
(1,185
)
 
$
(70,246
)

(a)
All of our gross recognized derivative instruments were subject to master netting arrangements.
(b)
No cash collateral has been provided to counterparties, or received from counterparties, that is subject to offsetting.
(c)
Represents cash collateral and cash margin that is not subject to offsetting. Amounts relate to non-derivative instruments, derivatives qualifying for scope exceptions, or collateral and margin posted in excess of the recognized derivative instrument. Includes cash collateral received from counterparties of $1,185 and cash margin provided to counterparties of $0.

As of December 31, 2019:
(dollars in thousands)
 
Gross
Recognized
Derivatives
 (a)
 
Amounts
Offset
(b)
 
Net
 Recognized
 Derivatives
 
Other
 (c)
 
Amount
Reported on
Balance Sheets
Current assets
 
$
584

 
$
(474
)
 
$
110

 
$
405

 
$
515

 
 
 
 
 
 
 
 
 
 
 
Current liabilities
 
(38,235
)
 
474

 
(37,761
)
 
(1,185
)
 
(38,946
)
Deferred credits and other
 
(33,186
)
 

 
(33,186
)
 

 
(33,186
)
Total liabilities
 
(71,421
)
 
474

 
(70,947
)
 
(1,185
)
 
(72,132
)
Total
 
$
(70,837
)
 
$

 
$
(70,837
)
 
$
(780
)
 
$
(71,617
)

(a)
All of our gross recognized derivative instruments were subject to master netting arrangements.
(b)
No cash collateral has been provided to counterparties, or received from counterparties, that is subject to offsetting.
(c)
Represents cash collateral and cash margin that is not subject to offsetting. Amounts relate to non-derivative instruments, derivatives qualifying for scope exceptions, or collateral and margin posted in excess of the recognized derivative instrument.  Includes cash collateral received from counterparties of $1,185 and cash margin provided to counterparties of $405.


46


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

Credit Risk and Credit Related Contingent Features
 
We are exposed to losses in the event of nonperformance or nonpayment by counterparties and have risk management contracts with many counterparties. As of June 30, 2020 we have one counterparty for which our exposure represents approximately 79% of Pinnacle West's $0.7 million of risk management assets. This exposure relates to a master agreement with a counterparty that has a very high credit rating. Our risk management process assesses and monitors the financial exposure of all counterparties.  Despite the fact that the great majority of our trading counterparties' debt is rated as investment grade by the credit rating agencies, there is still a possibility that one or more of these counterparties could default, resulting in a material impact on consolidated earnings for a given period. Counterparties in the portfolio consist principally of financial institutions, major energy companies, municipalities and local distribution companies.  We maintain credit policies that we believe minimize overall credit risk to within acceptable limits.  Determination of the credit quality of our counterparties is based upon a number of factors, including credit ratings and our evaluation of their financial condition.  To manage credit risk, we employ collateral requirements and standardized agreements that allow for the netting of positive and negative exposures associated with a single counterparty.  Valuation adjustments are established representing our estimated credit losses on our overall exposure to counterparties.
 
Certain of our derivative instrument contracts contain credit-risk-related contingent features including, among other things, investment grade credit rating provisions, credit-related cross-default provisions, and adequate assurance provisions.  Adequate assurance provisions allow a counterparty with reasonable grounds for uncertainty to demand additional collateral based on subjective events and/or conditions.  For those derivative instruments in a net liability position, with investment grade credit contingencies, the counterparties could demand additional collateral if our debt credit rating were to fall below investment grade (below BBB- for Standard & Poor’s or Fitch or Baa3 for Moody’s).
 
The following table provides information about our derivative instruments that have credit-risk-related contingent features at June 30, 2020 (dollars in thousands):
 
June 30, 2020
Aggregate fair value of derivative instruments in a net liability position
$
72,590

Cash collateral posted

Additional cash collateral in the event credit-risk-related contingent features were fully triggered (a)
63,880


(a)
This amount is after counterparty netting and includes those contracts which qualify for scope exceptions, which are excluded from the derivative details above.
 
We also have energy-related non-derivative instrument contracts with investment grade credit-related contingent features, which could also require us to post additional collateral of approximately $88 million if our debt credit ratings were to fall below investment grade.


47


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

8.
Commitments and Contingencies
 
Palo Verde Generating Station
 
Spent Nuclear Fuel and Waste Disposal
 
On December 19, 2012, APS, acting on behalf of itself and the participant owners of Palo Verde, filed a second breach of contract lawsuit against the United States Department of Energy ("DOE") in the United States Court of Federal Claims ("Court of Federal Claims").  The lawsuit sought to recover damages incurred due to DOE’s breach of the Contract for Disposal of Spent Nuclear Fuel and/or High Level Radioactive Waste ("Standard Contract") for failing to accept Palo Verde's spent nuclear fuel and high level waste from January 1, 2007 through June 30, 2011, as it was required to do pursuant to the terms of the Standard Contract and the Nuclear Waste Policy Act.  On August 18, 2014, APS and DOE entered into a settlement agreement, stipulating to a dismissal of the lawsuit and payment by DOE to the Palo Verde owners for certain specified costs incurred by Palo Verde during the period January 1, 2007 through June 30, 2011. In addition, the settlement agreement, as amended, provides APS with a method for submitting claims and getting recovery for costs incurred through December 31, 2019. In July 2020, APS accepted DOE's extension of the settlement agreement for recovery of costs incurred through December 31, 2022.

APS has submitted five claims pursuant to the terms of the August 18, 2014 settlement agreement, for five separate time periods during July 1, 2011 through June 30, 2018. The DOE has approved and paid $84.3 million for these claims (APS’s share is $24.5 million). The amounts recovered were primarily recorded as adjustments to a regulatory liability and had no impact on reported net income. In accordance with the 2017 Rate Case Decision, this regulatory liability is being refunded to customers (see Note 4). On October 31, 2019, APS filed its sixth claim pursuant to the terms of the August 18, 2014 settlement agreement in the amount of $16 million (APS’s share is $4.7 million). On February 11, 2020, the DOE approved a payment of $15.4 million (APS's share is $4.5 million) and on April 20, 2020, APS received this payment.

Nuclear Insurance

Public liability for incidents at nuclear power plants is governed by the Price-Anderson Nuclear Industries Indemnity Act ("Price-Anderson Act"), which limits the liability of nuclear reactor owners to the amount of insurance available from both commercial sources and an industry-wide retrospective payment plan.  In accordance with the Price-Anderson Act, the Palo Verde participants are insured against public liability for a nuclear incident of up to approximately $13.8 billion per occurrence. Palo Verde maintains the maximum available nuclear liability insurance in the amount of $450 million, which is provided by American Nuclear Insurers ("ANI").  The remaining balance of approximately $13.3 billion of liability coverage is provided through a mandatory industry-wide retrospective premium program.  If losses at any nuclear power plant covered by the program exceed the accumulated funds, APS could be responsible for retrospective premiums.  The maximum retrospective premium per reactor under the program for each nuclear liability incident is approximately $137.6 million, subject to a maximum annual premium of approximately $20.5 million per incident.  Based on APS’s ownership interest in the three Palo Verde units, APS’s maximum retrospective premium per incident for all three units is approximately $120.1 million, with a maximum annual retrospective premium of approximately $17.9 million.    
    
The Palo Verde participants maintain insurance for property damage to, and decontamination of, property at Palo Verde in the aggregate amount of $2.8 billion.  APS has also secured accidental outage insurance for a sudden and unforeseen accidental outage of any of the three units.  The property damage, decontamination, and accidental outage insurance are provided by Nuclear Electric Insurance

48


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

Limited ("NEIL").  APS is subject to retrospective premium adjustments under all NEIL policies if NEIL’s losses in any policy year exceed accumulated funds. The maximum amount APS could incur under the current NEIL policies totals approximately $25.8 million for each retrospective premium assessment declared by NEIL’s Board of Directors due to losses.  In addition, NEIL policies contain rating triggers that would result in APS providing approximately $75.1 million of collateral assurance within 20 business days of a rating downgrade to non-investment grade.  The insurance coverage discussed in this and the previous paragraph is subject to certain policy conditions, sublimits and exclusions.

Contractual Obligations

As of June 30, 2020, there have been no material changes outside the normal course of business in contractual obligations from the information provided in our 2019 Form 10-K. See Note 3 for discussion regarding changes in our short-term and long-term debt obligations.

Superfund-Related Matters
 
The Comprehensive Environmental Response Compensation and Liability Act ("Superfund" or "CERCLA") establishes liability for the cleanup of hazardous substances found contaminating the soil, water or air.  Those who released, generated, transported to or disposed of hazardous substances at a contaminated site are among the parties who are potentially responsible ("PRPs").  PRPs may be strictly, and often are jointly and severally, liable for clean-up.  On September 3, 2003, EPA advised APS that EPA considers APS to be a PRP in the Motorola 52nd Street Superfund Site, Operable Unit 3 ("OU3") in Phoenix, Arizona.  APS has facilities that are within this Superfund site.  APS and Pinnacle West have agreed with EPA to perform certain investigative activities of the APS facilities within OU3.  In addition, on September 23, 2009, APS agreed with EPA and one other PRP to voluntarily assist with the funding and management of the site-wide groundwater remedial investigation and feasibility study ("RI/FS").  Based upon discussions between the OU3 working group parties and EPA, along with the results of recent technical analyses prepared by the OU3 working group to supplement the RI/FS for OU3, APS anticipates finalizing the RI/FS in the fall of 2020. We estimate that our costs related to this investigation and study will be approximately $3 million.  We anticipate incurring additional expenditures in the future, but because the overall investigation is not complete and ultimate remediation requirements are not yet finalized, at the present time expenditures related to this matter cannot be reasonably estimated.
 
On August 6, 2013, Roosevelt Irrigation District ("RID") filed a lawsuit in Arizona District Court against APS and 24 other defendants, alleging that RID’s groundwater wells were contaminated by the release of hazardous substances from facilities owned or operated by the defendants.  The lawsuit also alleges that, under Superfund laws, the defendants are jointly and severally liable to RID.  The allegations against APS arise out of APS’s current and former ownership of facilities in and around OU3.  As part of a state governmental investigation into groundwater contamination in this area, on January 25, 2015, the Arizona Department of Environmental Quality ("ADEQ") sent a letter to APS seeking information concerning the degree to which, if any, APS’s current and former ownership of these facilities may have contributed to groundwater contamination in this area.  APS responded to ADEQ on May 4, 2015. On December 16, 2016, two RID environmental and engineering contractors filed an ancillary lawsuit for recovery of costs against APS and the other defendants in the RID litigation. That same day, another RID service provider filed an additional ancillary CERCLA lawsuit against certain of the defendants in the main RID litigation, but excluded APS and certain other parties as named defendants. Because the ancillary lawsuits concern past costs allegedly incurred by these RID vendors, which were ruled unrecoverable directly by RID in November of 2016, the additional lawsuits do not increase APS's exposure or risk related to these matters.


49


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

On April 5, 2018, RID and the defendants in that particular litigation executed a settlement agreement, fully resolving RID's CERCLA claims concerning both past and future cost recovery. APS's share of this settlement was immaterial. In addition, the two environmental and engineering vendors voluntarily dismissed their lawsuit against APS and the other named defendants without prejudice. An order to this effect was entered on April 17, 2018. With this disposition of the case, the vendors may file their lawsuit again in the future. On August 16, 2019, Maricopa County, one of the three direct defendants in the service provider lawsuit, filed a third-party complaint seeking contribution for its liability, if any, from APS and 28 other third-party defendants. We are unable to predict the outcome of these matters; however, we do not expect the outcome to have a material impact on our financial position, results of operations or cash flows.
  
Environmental Matters

APS is subject to numerous environmental laws and regulations affecting many aspects of its present and future operations, including air emissions of both conventional pollutants and greenhouse gases, water quality, wastewater discharges, solid waste, hazardous waste, and coal combustion residuals ("CCRs").  These laws and regulations can change from time to time, imposing new obligations on APS resulting in increased capital, operating, and other costs.  Associated capital expenditures or operating costs could be material.  APS intends to seek recovery of any such environmental compliance costs through our rates, but cannot predict whether it will obtain such recovery.  The following proposed and final rules involve material compliance costs to APS.
 
Regional Haze Rules.  APS has received the final rulemaking imposing pollution control requirements on Four Corners. EPA required the plant to install pollution control equipment that constitutes best available retrofit technology ("BART") to lessen the impacts of emissions on visibility surrounding the plant. In addition, EPA issued a final rule for Regional Haze compliance at Cholla that does not involve the installation of new pollution controls and that will replace an earlier BART determination for this facility. See below for details of the Cholla BART approval.

Four Corners. Based on EPA’s final standards, APS's 63% share of the cost of required controls for Four Corners Units 4 and 5 was approximately $400 million, which has been incurred.  In addition, APS and El Paso Electric Company ("El Paso") entered into an asset purchase agreement providing for the purchase by APS, or an affiliate of APS, of El Paso's 7% interest in Four Corners Units 4 and 5. 4CA purchased the El Paso interest on July 6, 2016. Navajo Transitional Energy Company, LLC ("NTEC") purchased the interest from 4CA on July 3, 2018. See "Four Corners - 4CA Matter" below for a discussion of the NTEC purchase. The cost of the pollution controls related to the 7% interest is approximately $45 million, which was assumed by NTEC through its purchase of the 7% interest.

Cholla. APS believed that EPA’s original 2012 final rule establishing controls constituting BART for Cholla, which would require installation of SCR controls, was unsupported and that EPA had no basis for disapproving Arizona’s State Implementation Plan ("SIP") and promulgating a FIP that was inconsistent with the state’s considered BART determinations under the regional haze program.  In September 2014, APS met with EPA to propose a compromise BART strategy, whereby APS would permanently close Cholla Unit 2 and cease burning coal at Units 1 and 3 by the mid-2020s. (See "Cholla" in Note 4 for information regarding future plans for the Cholla plant and details related to the resulting regulatory asset.) APS made the proposal with the understanding that additional emission control equipment is unlikely to be required in the future because retiring and/or converting the units as contemplated in the proposal is more cost effective than, and will result in increased visibility improvement over, the BART requirements for oxides of nitrogen ("NOx") imposed through EPA's BART FIP. In early 2017, EPA approved a final rule incorporating APS's compromise proposal, which took effect for Cholla on April 26, 2017.

50


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

 
Coal Combustion Waste. On December 19, 2014, EPA issued its final regulations governing the handling and disposal of CCR, such as fly ash and bottom ash. The rule regulates CCR as a non-hazardous waste under Subtitle D of the Resource Conservation and Recovery Act ("RCRA") and establishes national minimum criteria for existing and new CCR landfills and surface impoundments and all lateral expansions. These criteria include standards governing location restrictions, design and operating criteria, groundwater monitoring and corrective action, closure requirements and post closure care, and recordkeeping, notification, and internet posting requirements. The rule generally requires any existing unlined CCR surface impoundment that is contaminating groundwater above a regulated constituent’s groundwater protection standard to stop receiving CCR and either retrofit or close, and further requires the closure of any CCR landfill or surface impoundment that cannot meet the applicable performance criteria for location restrictions or structural integrity. Such closure requirements are deemed "forced closure" or "closure for cause" of unlined surface impoundments, and are the subject of recent regulatory and judicial activities described below.
Since these regulations were finalized, EPA has taken steps to substantially modify the federal rules governing CCR disposal. While certain changes have been prompted by utility industry petitions, others have resulted from judicial review, court-approved settlements with environmental groups, and statutory changes to RCRA. The following lists the pending regulatory changes that, if finalized, could have a material impact as to how APS manages CCR at its coal-fired power plants:

Following the passage of the Water Infrastructure Improvements for the Nation Act in 2016, EPA possesses authority to either authorize states to develop their own permit programs for CCR management or issue federal permits governing CCR disposal both in states without their own permit programs and on tribal lands. Although ADEQ has taken steps to develop a CCR permitting program, it is not clear when that program will be put into effect. On December 19, 2019, EPA proposed its own set of regulations governing the issuance of CCR management permits.

On March 1, 2018, as a result of a settlement with certain environmental groups, EPA proposed adding boron to the list of constituents that trigger corrective action requirements to remediate groundwater impacted by CCR disposal activities. Apart from a subsequent proposal issued on August 14, 2019 to add a specific, health-based groundwater protection standard for boron, EPA has yet to take action on this proposal.

Based on an August 21, 2018 D.C. Circuit decision, which vacated and remanded those provisions of the EPA CCR regulations that allow for the operation of unlined CCR surface impoundments, EPA recently proposed corresponding changes to federal CCR regulations. On July 29, 2020, EPA took final action on new regulations establishing April 11, 2021 as the deadline for initiating the closure of unlined CCR surface impoundments.

On November 4, 2019, EPA also proposed to change the manner by which facilities that have committed to cease burning coal in the near-term may qualify for alternative closure. Such qualification would allow CCR disposal units at these plants to continue operating, even though they would otherwise be subject to forced closure under the federal CCR regulations. EPA's July 29, 2020 final regulation adopted this proposal and now requires explicit EPA approval for facilities to utilize an alternative closure deadline.

We cannot at this time predict the outcome of these regulatory proceedings or when the EPA will take final action. Depending on the eventual outcome, the costs associated with APS’s management of CCR could materially increase, which could affect APS’s financial position, results of operations, or cash flows.

51


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

  
APS currently disposes of CCR in ash ponds and dry storage areas at Cholla and Four Corners. APS estimates that its share of incremental costs to comply with the CCR rule for Four Corners is approximately $22 million and its share of incremental costs to comply with the CCR rule for Cholla is approximately $15 million. The Navajo Plant disposed of CCR only in a dry landfill storage area. To comply with the CCR rule for the Navajo Plant, APS's share of incremental costs was approximately $1 million, which has been incurred. Additionally, the CCR rule requires ongoing, phased groundwater monitoring.

As of October 2018, APS has completed the statistical analyses for its CCR disposal units that triggered assessment monitoring. APS determined that several of its CCR disposal units at Cholla and Four Corners will need to undergo corrective action. In addition, under the current regulations, all such disposal units must cease operating and initiate closure by October 31, 2020. APS initiated an assessment of corrective measures on January 14, 2019 and expects such assessment will continue through mid- to late-2020. As part of this assessment, APS continues to gather additional groundwater data and perform remedial evaluations as to the CCR disposal units at Cholla and Four Corners undergoing corrective action. In addition, APS will solicit input from the public, host public hearings, and select remedies as part of this process. Based on the work performed to date, APS currently estimates that its share of corrective action and monitoring costs at Four Corners will likely range from $10 million to $15 million, which would be incurred over 30 years. The analysis needed to perform a similar cost estimate for Cholla remains ongoing at this time. As APS continues to implement the CCR rule’s corrective action assessment process, the current cost estimates may change. Given uncertainties that may exist until we have fully completed the corrective action assessment process, we cannot predict any ultimate impacts to the Company; however, at this time we do not believe the cost estimates for Cholla and any potential change to the cost estimate for Four Corners would have a material impact on our financial position, results of operations or cash flows.
 
Clean Power Plan/Affordable Clean Energy Regulations. On June 19, 2019, EPA took final action on its proposals to repeal EPA's 2015 Clean Power Plan (“CPP”) and replace those regulations with a new rule, the Affordable Clean Energy (“ACE”) regulations. EPA originally finalized the CPP on August 3, 2015, and those regulations had been stayed pending judicial review.

The ACE regulations are based upon measures that can be implemented to improve the heat rate of steam-electric power plants, specifically coal-fired EGUs. In contrast with the CPP, EPA's ACE regulations would not involve utility-level generation dispatch shifting away from coal-fired generation and toward renewable energy resources and natural gas-fired combined cycle power plants. EPA’s ACE regulations provide states and EPA regions such as the Navajo Nation with three years to develop plans establishing source-specific standards of performance based upon application of the ACE rule’s heat-rate improvement emission guidelines.

We cannot at this time predict the outcome of EPA's regulatory actions repealing and replacing the CPP. Various state governments, industry organizations, and environmental and public-health public interest groups have filed lawsuits in the D.C. Circuit challenging the legality of EPA’s action, both in repealing the CPP and issuing the ACE regulations. In addition, to the extent that the ACE regulations go into effect as finalized, it is not yet clear how the state of Arizona or EPA will implement these regulations as applied to APS’s coal-fired EGUs. In light of these uncertainties, APS is still evaluating the impact of the ACE regulations on its coal-fired generation fleet.

Other environmental rules that could involve material compliance costs include those related to effluent limitations, the ozone national ambient air quality standard and other rules or matters involving the Clean Air Act, Clean Water Act, Endangered Species Act, RCRA, Superfund, the Navajo Nation, and water

52


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

supplies for our power plants.  The financial impact of complying with current and future environmental rules could jeopardize the economic viability of our coal plants or the willingness or ability of power plant participants to fund any required equipment upgrades or continue their participation in these plants.  The economics of continuing to own certain resources, particularly our coal plants, may deteriorate, warranting early retirement of those plants, which may result in asset impairments.  APS would seek recovery in rates for the book value of any remaining investments in the plants as well as other costs related to early retirement, but cannot predict whether it would obtain such recovery.
  
Federal Agency Environmental Lawsuit Related to Four Corners

On April 20, 2016, several environmental groups filed a lawsuit against the Office of Surface Mining Reclamation and Enforcement ("OSM") and other federal agencies in the District of Arizona in connection with their issuance of the approvals that extended the life of Four Corners and the adjacent mine.  The lawsuit alleges that these federal agencies violated both the Endangered Species Act ("ESA") and the National Environmental Policy Act ("NEPA") in providing the federal approvals necessary to extend operations at the Four Corners Power Plant and the adjacent Navajo Mine past July 6, 2016.  APS filed a motion to intervene in the proceedings, which was granted on August 3, 2016.

On September 15, 2016, NTEC, the company that owns the adjacent mine, filed a motion to intervene for the purpose of dismissing the lawsuit based on NTEC's tribal sovereign immunity. On September 11, 2017, the Arizona District Court issued an order granting NTEC's motion, dismissing the litigation with prejudice, and terminating the proceedings. On November 9, 2017, the environmental group plaintiffs appealed the district court order dismissing their lawsuit. On July 29, 2019, the Ninth Circuit Court of Appeals affirmed the September 2017 dismissal of the lawsuit, after which the environmental group plaintiffs petitioned the Ninth Circuit for rehearing on September 12, 2019. The Ninth Circuit denied this petition for rehearing on December 11, 2019. On March 24 , 2020, the environmental group plaintiffs filed a Petition for a Writ of Certiorari with the U.S. Supreme Court seeking review of the Ninth Circuit decision. This petition was denied by the U.S. Supreme Court on June 29, 2020. No further legal proceedings related to this matter are expected at this time.

Four Corners National Pollutant Discharge Elimination System ("NPDES") Permit

On July 16, 2018, several environmental groups filed a petition for review before the EPA Environmental Appeals Board ("EAB") concerning the NPDES wastewater discharge permit for Four Corners, which was reissued on June 12, 2018.  The environmental groups allege that the permit was reissued in contravention of several requirements under the Clean Water Act and did not contain required provisions concerning EPA’s 2015 revised effluent limitation guidelines for steam-electric EGUs, 2014 existing-source regulations governing cooling-water intake structures, and effluent limits for surface seepage and subsurface discharges from coal-ash disposal facilities.  To address certain of these issues through a reconsidered permit, EPA took action on December 19, 2018 to withdraw the NPDES permit reissued in June 2018. Withdrawal of the permit moots the EAB appeal, and EPA filed a motion to dismiss on that basis. The EAB thereafter dismissed the environmental group appeal on February 12, 2019. EPA then issued a revised final NPDES permit for Four Corners on September 30, 2019. This permit is now subject to a petition for review before the EAB, based upon a November 1, 2019 filing by several environmental groups. Oral argument on this appeal has been scheduled for September 3, 2020. We cannot predict the outcome of this review and whether the review will have a material impact on our financial position, results of operations or cash flows.
    

53


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

Four Corners - 4CA Matter

On July 6, 2016, 4CA purchased El Paso’s 7% interest in Four Corners. NTEC purchased this 7% interest on July 3, 2018 from 4CA. NTEC purchased the 7% interest at 4CA’s book value, approximately $70 million, and is paying 4CA the purchase price over a period of four years pursuant to a secured interest-bearing promissory note. The note is secured by a portion of APS’s payments to be owed to NTEC under the 2016 Coal Supply Agreement. As of June 30, 2020, the note has a remaining balance of $39 million. NTEC continues to make payments in accordance with the terms of the note. Due to its short-remaining term, among other factors, there are no expected credit losses associated with the note.
In connection with the sale, Pinnacle West guaranteed certain obligations that NTEC will have to the other owners of Four Corners, such as NTEC's 7% share of capital expenditures and operating and maintenance expenses. Pinnacle West's guarantee is secured by a portion of APS's payments to be owed to NTEC under the 2016 Coal Supply Agreement.
The 2016 Coal Supply Agreement contained alternate pricing terms for the 7% interest in the event NTEC did not purchase the interest. Until the time that NTEC purchased the 7% interest, the alternate pricing provisions were applicable to 4CA as the holder of the 7% interest. These terms included a formula under which NTEC must make certain payments to 4CA for reimbursement of operations and maintenance costs and a specified rate of return, offset by revenue generated by 4CA’s power sales. The amount under this formula for calendar year 2018 (up to the date that NTEC purchased the 7% interest) was approximately $10 million, which was due to 4CA on December 31, 2019. Such payment was satisfied in January 2020 by NTEC directing to 4CA a prepayment from APS of future coal payment obligations of which the prepayment has been fully utilized as of June 2020.
Financial Assurances

In the normal course of business, we obtain standby letters of credit and surety bonds from financial institutions and other third parties. These instruments guarantee our own future performance and provide third parties with financial and performance assurance in the event we do not perform. These instruments support commodity contract collateral obligations and other transactions. As of June 30, 2020, standby letters of credit totaled $4.9 million and will expire in 2021. As of June 30, 2020, surety bonds expiring through 2021 totaled $16 million. The underlying liabilities insured by these instruments are reflected on our balance sheets, where applicable. Therefore, no additional liability is reflected for the letters of credit and surety bonds themselves.
 
We enter into agreements that include indemnification provisions relating to liabilities arising from or related to certain of our agreements.  Most significantly, APS has agreed to indemnify the equity participants and other parties in the Palo Verde sale leaseback transactions with respect to certain tax matters.  Generally, a maximum obligation is not explicitly stated in the indemnification provisions and, therefore, the overall maximum amount of the obligation under such indemnification provisions cannot be reasonably estimated.  Based on historical experience and evaluation of the specific indemnities, we do not believe that any material loss related to such indemnification provisions is likely.
 
Pinnacle West has issued parental guarantees and has provided indemnification under certain surety bonds for APS which were not material at June 30, 2020. In connection with the sale of 4CA's 7% interest to NTEC, Pinnacle West is guaranteeing certain obligations that NTEC will have to the other owners of Four Corners. (See "Four Corners - 4CA Matter" above for information related to this guarantee.) Pinnacle West has not needed to perform under this guarantee. A maximum obligation is not explicitly stated in the guarantee and, therefore, the overall maximum amount of the obligation under such guarantee cannot be reasonably

54


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

estimated; however, we consider the fair value of this guarantee, including expected credit losses, to be immaterial.
In connection with BCE’s acquisition of minority ownership positions in the Clear Creek and Nobles 2 wind farms, Pinnacle West has issued parental guarantees to guarantee the obligations of BCE subsidiaries to make required equity contributions to fund project construction (the “Equity Contribution Guarantees”) and to make production tax credit funding payments to borrowers of the projects (the “PTC Guarantees”).  The amounts guaranteed by Pinnacle West reduce as payments are made under the respective guarantee agreements.  The Equity Contribution Guarantees are currently anticipated to be terminated upon completion of construction of the respective projects, which is anticipated to occur prior to December 31, 2020, and the PTC Guarantees (approximately $40 million as of June 30, 2020) are currently expected to be terminated ten years following the commercial operation date of the applicable project.

9.
Other Income and Other Expense
 
The following table provides detail of Pinnacle West's Consolidated other income and other expense (dollars in thousands):

 
Three Months Ended
June 30,
 
Six Months Ended
June 30,
 
2020
 
2019
 
2020
 
2019
Other income:
 

 
 

 
 

 
 

Interest income
$
2,755

 
$
2,699

 
$
6,032

 
$
5,001

Investment gains (losses) - net
2,826

 

 
2,826

 

Debt return on Four Corners SCR deferrals (Note 4)
4,249


4,887

 
7,389

 
9,731

Debt return on Ocotillo modernization project (Note 4)
6,703

 
5,294

 
12,847

 
5,294

Miscellaneous
137

 
5

 
145

 
28

Total other income
$
16,670

 
$
12,885

 
$
29,239

 
$
20,054

Other expense:
 

 
 

 
 

 
 

Non-operating costs
$
(2,290
)
 
$
(3,481
)
 
$
(4,948
)
 
$
(6,185
)
Investment gains (losses) — net

 
(491
)
 
60

 
(729
)
Miscellaneous
(1,746
)
 
(378
)
 
(3,932
)
 
(1,794
)
Total other expense
$
(4,036
)
 
$
(4,350
)
 
$
(8,820
)
 
$
(8,708
)

 

55


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

The following table provides detail of APS’s other income and other expense (dollars in thousands):
 
Three Months Ended
June 30,
 
Six Months Ended
June 30,
 
2020
 
2019
 
2020
 
2019
Other income:
 

 
 

 
 

 
 

Interest income
$
2,183

 
$
1,504

 
$
4,524

 
$
3,054

Debt return on Four Corners SCR deferrals (Note 4)
4,249

 
4,887

 
7,389


9,731

Debt return on Ocotillo modernization project (Note 4)
6,703

 
5,294

 
12,847

 
5,294

Miscellaneous
137

 
6

 
145

 
28

Total other income
$
13,272

 
$
11,691

 
$
24,905

 
$
18,107

Other expense:
 

 
 

 
 

 
 

Non-operating costs
$
(2,113
)
 
$
(3,049
)
 
$
(4,595
)
 
$
(5,517
)
Miscellaneous
(1,746
)
 
(379
)
 
(3,932
)
 
(1,789
)
Total other expense
$
(3,859
)
 
$
(3,428
)
 
$
(8,527
)
 
$
(7,306
)


10.
Earnings Per Share
 
The following table presents the calculation of Pinnacle West’s basic and diluted earnings per share (in thousands, except per share amounts):
 
Three Months Ended June 30,
 
Six Months Ended June 30,
 
2020
 
2019
 
2020
 
2019
Net income attributable to common shareholders
$
193,585

 
$
144,145

 
$
223,578

 
$
162,063

Weighted average common shares outstanding — basic
112,638

 
112,337

 
112,616

 
112,381

Net effect of dilutive securities:
 
 
 
 
 
 
 
Contingently issuable performance shares and restricted stock units
241

 
314

 
255

 
353

Weighted average common shares outstanding — diluted
112,879

 
112,651

 
112,871

 
112,734

Earnings per weighted-average common share outstanding
 
 
 
 
 
 
 
Net income attributable to common shareholders — basic
$
1.72

 
$
1.28

 
$
1.99

 
$
1.44

Net income attributable to common shareholders — diluted
$
1.71

 
$
1.28

 
$
1.98

 
$
1.44



11.
Fair Value Measurements
 
We classify our assets and liabilities that are carried at fair value within the fair value hierarchy.  This hierarchy ranks the quality and reliability of the inputs used to determine fair values, which are then classified and disclosed in one of three categories.  The three levels of the fair value hierarchy are:
 
Level 1 — Inputs are unadjusted quoted prices in active markets for identical assets or liabilities at the measurement date.


56


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

Level 2 — Other significant observable inputs, including quoted prices in active markets for similar assets or liabilities; quoted prices in markets that are not active, and model-derived valuations whose inputs are observable (such as yield curves).
 
 Level 3 — Valuation models with significant unobservable inputs that are supported by little or no market activity.  Instruments in this category may include long-dated derivative transactions where valuations are unobservable due to the length of the transaction, options, and transactions in locations where observable market data does not exist.  The valuation models we employ utilize spot prices, forward prices, historical market data and other factors to forecast future prices.
 
Assets and liabilities are classified in their entirety based on the lowest level of input that is significant to the fair value measurement.  Thus, a valuation may be classified in Level 3 even though the valuation may include significant inputs that are readily observable.  We maximize the use of observable inputs and minimize the use of unobservable inputs.  We rely primarily on the market approach of using prices and other market information for identical and/or comparable assets and liabilities.  If market data is not readily available, inputs may reflect our own assumptions about the inputs market participants would use.  Our assessment of the inputs and the significance of a particular input to the fair value measurement requires judgment and may affect the valuation of fair value assets and liabilities as well as their placement within the fair value hierarchy levels.  We assess whether a market is active by obtaining observable broker quotes, reviewing actual market activity, and assessing the volume of transactions.  We consider broker quotes observable inputs when the quote is binding on the broker, we can validate the quote with market activity, or we can determine that the inputs the broker used to arrive at the quoted price are observable.

Certain instruments have been valued using the concept of Net Asset Value ("NAV"), as a practical expedient. These instruments are typically structured as investment companies offering shares or units to multiple investors for the purpose of providing a return. These instruments are similar to mutual funds; however, their NAV is generally not published and publicly available, nor are these instruments traded on an exchange. Instruments valued using NAV, as a practical expedient are included in our fair value disclosures; however, in accordance with GAAP are not classified within the fair value hierarchy levels.

Recurring Fair Value Measurements
 
We apply recurring fair value measurements to cash equivalents, derivative instruments, and investments held in the Nuclear Decommissioning Trusts and other special use funds. On an annual basis we apply fair value measurements to plan assets held in our retirement and other benefit plans.  See Note 8 in the 2019 Form 10-K for fair value discussion of plan assets held in our retirement and other benefit plans.
 
Cash Equivalents
 
Cash equivalents represent certain investments in money market funds that are valued using quoted prices in active markets.
   
Risk Management Activities — Derivative Instruments
 
Exchange traded commodity contracts are valued using unadjusted quoted prices.  For non-exchange traded commodity contracts, we calculate fair value based on the average of the bid and offer price, discounted to reflect net present value.  We maintain certain valuation adjustments for a number of risks associated with the valuation of future commitments.  These include valuation adjustments for liquidity and credit risks.  The liquidity valuation adjustment represents the cost that would be incurred if all unmatched positions were closed

57


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

out or hedged.  The credit valuation adjustment represents estimated credit losses on our net exposure to counterparties, taking into account netting agreements, expected default experience for the credit rating of the counterparties and the overall diversification of the portfolio.  We maintain credit policies that management believes minimize overall credit risk.
 
Certain non-exchange traded commodity contracts are valued based on unobservable inputs due to the long-term nature of contracts, characteristics of the product, or the unique location of the transactions.  Our long-dated energy transactions consist of observable valuations for the near-term portion and unobservable valuations for the long-term portions of the transaction.  We rely primarily on broker quotes to value these instruments.  When our valuations utilize broker quotes, we perform various control procedures to ensure the quote has been developed consistent with fair value accounting guidance.  These controls include assessing the quote for reasonableness by comparison against other broker quotes, reviewing historical price relationships, and assessing market activity.  When broker quotes are not available, the primary valuation technique used to calculate the fair value is the extrapolation of forward pricing curves using observable market data for more liquid delivery points in the same region and actual transactions at more illiquid delivery points.
 
When the unobservable portion is significant to the overall valuation of the transaction, the entire transaction is classified as Level 3. 
 
Investments Held in Nuclear Decommissioning Trusts and Other Special Use Funds
 
The Nuclear Decommissioning Trusts and other special use funds invest in fixed income and equity securities. Other special use funds include the coal reclamation escrow account and the active union employee medical account. See Note 12 for additional discussion about our investment accounts.

We value investments in fixed income and equity securities using information provided by our trustees and escrow agent. Our trustees and escrow agent use pricing services that utilize the valuation methodologies described below to determine fair market value. We have internal control procedures designed to ensure this information is consistent with fair value accounting guidance. These procedures include assessing valuations using an independent pricing source, verifying that pricing can be supported by actual recent market transactions, assessing hierarchy classifications, comparing investment returns with benchmarks, and obtaining and reviewing independent audit reports on the trustees’ and escrow agent's internal operating controls and valuation processes.

Fixed Income Securities

Fixed income securities issued by the U.S. Treasury are valued using quoted active market prices and are typically classified as Level 1.  Fixed income securities issued by corporations, municipalities, and other agencies, including mortgage-backed instruments, are valued using quoted inactive market prices, quoted active market prices for similar securities, or by utilizing calculations which incorporate observable inputs such as yield curves and spreads relative to such yield curves.  These fixed income instruments are classified as Level 2.  Whenever possible, multiple market quotes are obtained which enables a cross-check validation.  A primary price source is identified based on asset type, class, or issue of securities.

Fixed income securities may also include short-term investments in certificates of deposit, variable rate notes, time deposit accounts, U.S. Treasury and Agency obligations, U.S. Treasury repurchase agreements, commercial paper, and other short-term instruments. These instruments are valued using active market prices or utilizing observable inputs described above.


58


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

Equity Securities

The Nuclear Decommissioning Trusts's equity security investments are held indirectly through commingled funds.  The commingled funds are valued using the funds' NAV as a practical expedient. The funds' NAV is primarily derived from the quoted active market prices of the underlying equity securities held by the funds. We may transact in these commingled funds on a semi-monthly basis at the NAV.  The commingled funds are maintained by a bank and hold investments in accordance with the stated objective of tracking the performance of the S&P 500 Index.  Because the commingled funds' shares are offered to a limited group of investors, they are not considered to be traded in an active market. As these instruments are valued using NAV, as a practical expedient, they have not been classified within the fair value hierarchy.

The Nuclear Decommissioning Trusts and other special use funds may also hold equity securities that include exchange traded mutual funds and money market accounts for short-term liquidity purposes. These short-term, highly-liquid, investments are valued using active market prices.



59


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

Fair Value Tables
 
The following table presents the fair value at June 30, 2020 of our assets and liabilities that are measured at fair value on a recurring basis (dollars in thousands):
 
 
Level 1
 
Level 2
 
Level 3
 
Other
 
 
 
Total
Assets
 

 
 

 
 

 
 

 
 
 
 

Risk management activities — derivative instruments:
 
 
 
 
 
 
 
 
 
 
 
Commodity contracts
$

 
$
3,165

 
$
365

 
$
(2,790
)
 
(a)
 
$
740

Nuclear decommissioning trust:
 
 
 
 
 
 
 
 
 
 
 
Equity securities
15,985

 

 

 
(6,130
)
 
(b)
 
9,855

U.S. commingled equity funds

 

 

 
502,251

 
(c)
 
502,251

U.S. Treasury debt
143,673

 

 

 

 
 
 
143,673

Corporate debt

 
149,672

 

 

 
 
 
149,672

Mortgage-backed securities

 
99,407

 

 

 
 
 
99,407

Municipal bonds

 
106,971

 

 

 
 
 
106,971

Other fixed income

 
12,204

 

 

 
 
 
12,204

Subtotal nuclear decommissioning trust
159,658

 
368,254

 

 
496,121

 
 
 
1,024,033

 
 
 
 
 
 
 
 
 
 
 
 
Other special use funds:
 
 
 
 
 
 
 
 
 
 
 
Equity securities
8,955

 

 

 
526

 
(b)
 
9,481

U.S. Treasury debt
229,858

 

 

 

 

 
229,858

Municipal bonds

 
13,993

 

 

 
 
 
13,993

Subtotal other special use funds
238,813

 
13,993

 

 
526

 
 
 
253,332

 
 
 
 
 
 
 
 
 
 
 
 
Total assets
$
398,471

 
$
385,412

 
$
365

 
$
493,857

 
 
 
$
1,278,105

Liabilities
 

 
 

 
 

 
 

 
 
 
 

Risk management activities — derivative instruments:
 

 
 

 
 

 
 

 
 
 
 

Commodity contracts
$

 
$
(61,974
)
 
$
(10,617
)
 
$
1,605

 
(a)
 
$
(70,986
)

(a)
Represents counterparty netting, margin, and collateral. See Note 7.
(b)
Represents net pending securities sales and purchases.
(c)
Valued using NAV as a practical expedient and, therefore, are not classified in the fair value hierarchy.



60


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

The following table presents the fair value at December 31, 2019 of our assets and liabilities that are measured at fair value on a recurring basis (dollars in thousands):
 
 
Level 1
 
Level 2
 
Level 3
 
Other
 
 
 
Total
Assets
 

 
 

 
 

 
 

 
 
 
 

Risk management activities — derivative instruments:
 
 
 
 
 
 
 
 
 
 
 
Commodity contracts
$

 
$
551

 
$
33

 
$
(69
)
 
(a)
 
$
515

Nuclear decommissioning trust:
 

 
 

 
 

 
 

 
 
 
 

Equity securities
10,872

 

 

 
2,401

 
(b)
 
13,273

U.S. commingled equity funds

 

 

 
518,844

 
(c)
 
518,844

U.S. Treasury debt
160,607

 

 

 

 
 
 
160,607

Corporate debt

 
115,869

 

 

 
 
 
115,869

Mortgage-backed securities

 
118,795

 

 

 
 
 
118,795

Municipal bonds

 
73,040

 

 

 
 
 
73,040

Other fixed income

 
10,347

 

 

 
 
 
10,347

Subtotal nuclear decommissioning trust
171,479

 
318,051

 

 
521,245

 
 
 
1,010,775

 
 
 
 
 
 
 
 
 
 
 
 
Other special use funds:
 
 
 
 
 
 
 
 
 
 
 
Equity securities
7,142

 

 

 
474

 
(b)
 
7,616

U.S. Treasury debt
232,848

 

 

 

 
 
 
232,848

Municipal bonds

 
4,631

 

 

 
 
 
4,631

Subtotal other special use funds
239,990

 
4,631

 

 
474

 
 
 
245,095

 
 
 
 
 
 
 
 
 
 
 
 
Total assets
$
411,469

 
$
323,233

 
$
33

 
$
521,650

 
 
 
$
1,256,385

Liabilities
 

 
 

 
 

 
 

 
 
 
 

Risk management activities — derivative instruments:
 

 
 

 
 

 
 

 
 
 
 

Commodity contracts
$

 
$
(67,992
)
 
$
(3,429
)
 
$
(711
)
 
(a)
 
$
(72,132
)

(a)
Represents counterparty netting, margin, and collateral. See Note 7.
(b)
Represents net pending securities sales and purchases.
(c)
Valued using NAV as a practical expedient and, therefore, are not classified in the fair value hierarchy.

Fair Value Measurements Classified as Level 3
 
The significant unobservable inputs used in the fair value measurement of our energy derivative contracts include broker quotes that cannot be validated as an observable input primarily due to the long-term nature of the quote or other characteristics of the product.  Significant changes in these inputs in isolation would result in significantly higher or lower fair value measurements.  Changes in our derivative contract fair values, including changes relating to unobservable inputs, typically will not impact net income due to regulatory accounting treatment (see Note 4).
 
Because our forward commodity contracts classified as Level 3 are currently in a net purchase position, we would expect price increases of the underlying commodity to result in increases in the net fair value of the

61


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

related contracts.  Conversely, if the price of the underlying commodity decreases, the net fair value of the related contracts would likely decrease.
 
Other unobservable valuation inputs include credit and liquidity reserves which do not have a material impact on our valuations; however, significant changes in these inputs could also result in higher or lower fair value measurements.
 
Financial Instruments Not Carried at Fair Value
 
The carrying value of our short-term borrowings approximate fair value and are classified within Level 2 of the fair value hierarchy. See Note 3 for our long-term debt fair values. The NTEC note receivable related to the sale of 4CA’s interest in Four Corners bears interest at 3.9% per annum and has a book value of $39 million as of June 30, 2020 and $44 million as of December 31, 2019, as presented on the Condensed Consolidated Balance Sheets.  The carrying amount is not materially different from the fair value of the note receivable and is classified within Level 3 of the fair value hierarchy.  See Note 8 for more information on 4CA matters.

12.
Investments in Nuclear Decommissioning Trusts and Other Special Use Funds
 
We have investments in debt and equity securities held in Nuclear Decommissioning Trusts, Coal Mine Reclamation Escrow Account, and an Active Union Employee Medical Account. Investments in debt securities are classified as available-for-sale securities. We record both debt and equity security investments at their fair value on our Condensed Consolidated Balance Sheets. See Note 11 for a discussion of how fair value is determined and the classification of the investments within the fair value hierarchy. The investments in each trust or account are restricted for use and are intended to fund specified costs and activities as further described for each fund below.

Nuclear Decommissioning Trusts - APS established external decommissioning trusts in accordance with NRC regulations to fund the future costs APS expects to incur to decommission Palo Verde.  Third-party investment managers are authorized to buy and sell securities per stated investment guidelines.  The trust funds are invested in fixed income securities and equity securities. Earnings and proceeds from sales and maturities of securities are reinvested in the trusts. Because of the ability of APS to recover decommissioning costs in rates, and in accordance with the regulatory treatment, APS has deferred realized and unrealized gains and losses (including credit losses) in other regulatory liabilities.
 
Coal Mine Reclamation Escrow Account - APS has investments restricted for the future coal mine reclamation funding related to Four Corners. This escrow account is primarily invested in fixed income securities. Earnings and proceeds from sales of securities are reinvested in the escrow account. Because of the ability of APS to recover coal mine reclamation costs in rates, and in accordance with the regulatory treatment, APS has deferred realized and unrealized gains and losses (including credit losses) in other regulatory liabilities. Activities relating to APS coal mine reclamation escrow account investments are included within the other special use funds in the table below.

Active Union Employee Medical Account - APS has investments restricted for paying active union employee medical costs. These investments may be used to pay active union employee medical costs incurred in the current and future periods. The account is invested primarily in fixed income securities. In accordance with the ratemaking treatment, APS has deferred the unrealized gains and losses (including credit losses) in other regulatory liabilities. Activities relating to active union employee medical account investments are included within the other special use funds in the table below.

62


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

    
APS

The following tables present the unrealized gains and losses based on the original cost of the investment and summarizes the fair value of APS's Nuclear Decommissioning Trusts and other special use fund assets (dollars in thousands):  
 
June 30, 2020
 
Fair Value
 
Total
Unrealized
Gains
 
Total
Unrealized
Losses
Investment Type:
Nuclear Decommissioning Trusts
 
Other Special Use Funds
 
Total
 
 
Equity securities
$
518,236

 
$
8,955

 
$
527,191

 
$
316,494

 
$
(58
)
Available for sale-fixed income securities
511,927

 
243,851

 
755,778

(a)
49,693

 
(524
)
Other
(6,130
)
 
526

 
(5,604
)
(b)

 

Total
$
1,024,033

 
$
253,332

 
$
1,277,365

 
$
366,187

 
$
(582
)

(a)
As of June 30, 2020, the amortized cost basis of these available-for-sale investments is $707 million.
(b)
Represents net pending securities sales and purchases.

 
December 31, 2019
 
Fair Value
 
Total
Unrealized
Gains
 
Total
Unrealized
Losses
Investment Type:
Nuclear Decommissioning Trusts
 
Other Special Use Funds
 
Total
 
 
Equity securities
$
529,716

 
$
7,142

 
$
536,858

 
$
337,681

 
$

Available for sale-fixed income securities
478,658

 
237,479

 
716,137

(a)
25,795

 
(669
)
Other
2,401

 
474

 
2,875

(b)

 

Total
$
1,010,775

 
$
245,095

 
$
1,255,870

 
$
363,476

 
$
(669
)

(a)
As of December 31, 2019, the amortized cost basis of these available-for-sale investments is $691 million.
(b)
Represents net pending securities sales and purchases.

    

63


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

The following table sets forth APS's realized gains and losses relating to the sale and maturity of available-for-sale debt securities and equity securities, and the proceeds from the sale and maturity of these investment securities (dollars in thousands):
 
Three Months Ended June 30,
 
Nuclear Decommissioning Trusts
 
Other Special Use Funds
 
Total
2020
 
 
 
 
 
Realized gains
$
4,500

 
$

 
$
4,500

Realized losses
(1,621
)
 

 
(1,621
)
Proceeds from the sale of securities (a)
176,942

 
19,830

 
196,772

2019
 
 
 
 
 
Realized gains
$
2,643

 
$

 
$
2,643

Realized losses
(1,700
)
 

 
(1,700
)
Proceeds from the sale of securities (a)
93,559

 
36,747

 
130,306


(a)
Proceeds are reinvested in the Nuclear Decommissioning Trusts and other special use funds, excluding amounts reimbursed to the Company for active union employee medical claims from the active union employee medical account.

 
Six Months Ended June 30,
 
Nuclear Decommissioning Trusts
 
Other Special Use Funds
 
Total
2020
 
 
 
 
 
Realized gains
$
7,813

 
$

 
$
7,813

Realized losses
(3,848
)
 

 
(3,848
)
Proceeds from the sale of securities (a)
355,138

 
36,721

 
391,859

2019
 
 
 
 
 
Realized gains
$
3,746

 
$

 
$
3,746

Realized losses
(3,105
)
 

 
(3,105
)
Proceeds from the sale of securities (a)
216,152

 
93,202

 
309,354


(a)
Proceeds are reinvested in the Nuclear Decommissioning Trusts and other special use funds, excluding amounts reimbursed to the Company for active union employee medical claims from the active union employee medical account.

    

64


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

The fair value of APS's fixed income securities, summarized by contractual maturities, at June 30, 2020, is as follows (dollars in thousands):
 
Nuclear Decommissioning Trust
 
Coal Mine Reclamation Escrow Account
 
Active Union Employee Medical Account
 
Total
Less than one year
$
21,767

 
$
37,494

 
$
40,673

 
$
99,934

1 year – 5 years
137,754

 
11,371

 
143,406

 
292,531

5 years – 10 years
125,807

 
1,904

 

 
127,711

Greater than 10 years
226,599

 
9,003

 

 
235,602

Total
$
511,927

 
$
59,772

 
$
184,079

 
$
755,778



    
13.    New Accounting Standards

ASU 2016-13, Financial Instruments: Measurement of Credit Losses

In June 2016, a new accounting standard was issued that amends the measurement of credit losses on certain financial instruments. The new standard requires entities to use a current expected credit loss model to measure impairment of certain investments in debt securities, trade accounts receivables, and other financial instruments. Since the issuance of the new standard, various guidance has been issued that amends the new standard, including clarifications of certain aspects of the standard and targeted transition relief, among other changes. The new standard and related amendments were effective for us on January 1, 2020, and must be adopted using a modified retrospective approach for certain aspects of the standard, and a prospective approach for other aspects of the standard. We adopted the standard on January 1, 2020 using primarily the modified retrospective approach. While the adoption of this guidance changed our process and methodology for determining credit losses and resulted in additional disclosures, these changes did not have a material impact on our financial statements. See Note 2 for allowance for doubtful accounts related credit loss disclosures.
    

65


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

14.     Changes in Accumulated Other Comprehensive Loss
 
The following table shows the changes in Pinnacle West's consolidated accumulated other comprehensive loss, including reclassification adjustments, net of tax, by component (dollars in thousands):
 
 Pension and Other Postretirement Benefits
 
 
 
 Derivative Instruments
 
 
 
 Total
Three Months Ended June 30
 
 
 
 
 
 
 
 
 
Balance March 31, 2020
$
(55,317
)
 
 
 
$
(262
)
 
 
 
$
(55,579
)
OCI (loss) before reclassifications
(2,008
)
 
 
 
(1,549
)
 
 
 
(3,557
)
Amounts reclassified from accumulated other comprehensive loss
999

 
 (a)
 
262

 
(b)
 
1,261

Balance June 30, 2020
$
(56,326
)
 
 
 
$
(1,549
)
 
 
 
$
(57,875
)


 
 
 

 
 
 

Balance March 31, 2019
$
(45,118
)
 
 
 
$
(1,383
)
 
 
 
$
(46,501
)
OCI (loss) before reclassifications
(2,422
)
 
 
 

 
 
 
(2,422
)
Amounts reclassified from accumulated other comprehensive loss
883

 
 (a)
 
404

 
(b)
 
1,287

Balance June 30, 2019
$
(46,657
)
 
 
 
$
(979
)
 
 
 
$
(47,636
)

 
Pension and Other Postretirement Benefits
 
 
 
Derivative Instruments
 
 
 
Total
Six Months Ended June 30
 
 
 
 
 
 
 
 
 
Balance December 31, 2019
$
(56,522
)
 
 
 
$
(574
)
 
 
 
$
(57,096
)
OCI (loss) before reclassifications
(2,008
)
 
 
 
(1,257
)
 
 
 
(3,265
)
Amounts reclassified from accumulated other comprehensive loss
2,204

 
(a)
 
282

 
(b)
 
2,486

Balance June 30, 2020
$
(56,326
)
 
 
 
$
(1,549
)
 
 
 
$
(57,875
)
 
 
 
 
 
 
 
 
 
 
Balance December 31, 2018
$
(45,997
)
 
 
 
$
(1,711
)
 
 
 
$
(47,708
)
OCI (loss) before reclassifications
(2,422
)
 
 
 

 
 
 
(2,422
)
Amounts reclassified from accumulated other comprehensive loss
1,762

 
(a)
 
732

 
(b)
 
2,494

Balance June 30, 2019
$
(46,657
)
 
 
 
$
(979
)
 
 
 
$
(47,636
)

(a)
These amounts primarily represent amortization of actuarial loss and are included in the computation of net periodic pension cost.  See Note 5.
(b)
These amounts primarily represent realized gains and losses and are included in the computation of fuel and purchased power costs and are subject to the PSA.  See Note 7.


66


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

The following table shows the changes in APS's consolidated accumulated other comprehensive loss, including reclassification adjustments, net of tax, by component for the three and six months ended June 30, 2020 and 2019 (dollars in thousands): 
 
 Pension and Other Postretirement Benefits
 
 
 
 Derivative Instruments
 
 
 
 Total
Three Months Ended June 30
 
 
 
 
 
 
 
 
 
Balance March 31, 2020
$
(33,935
)
 
 
 
$
(262
)
 
 
 
$
(34,197
)
OCI (loss) before reclassifications
(1,951
)
 
 
 

 
 
 
(1,951
)
Amounts reclassified from accumulated other comprehensive loss
861

 
 (a)
 
262

 
 (b)
 
1,123

Balance June 30, 2020
$
(35,025
)
 
 
 
$

 
 
 
$
(35,025
)


 
 
 

 
 
 

Balance March 31, 2019
$
(24,644
)
 
 
 
$
(1,383
)
 
 
 
$
(26,027
)
OCI (loss) before reclassifications
(2,414
)
 
 
 

 
 
 
(2,414
)
Amounts reclassified from accumulated other comprehensive loss
761

 
 (a)
 
404

 
 (b)
 
1,165

Balance June 30, 2019
$
(26,297
)
 
 
 
$
(979
)
 
 
 
$
(27,276
)

 
 Pension and Other Postretirement Benefits
 
 
 
 Derivative Instruments
 
 
 
 Total
Six Months Ended June 30
 
 
 
 
 
 
 
 
 
Balance December 31, 2019
$
(34,948
)
 
 
 
$
(574
)
 
 
 
$
(35,522
)
OCI (loss) before reclassifications
(1,951
)
 
 
 
292

 
 
 
(1,659
)
Amounts reclassified from accumulated other comprehensive loss
1,874

 
(a)
 
282

 
 (b)
 
2,156

Balance June 30, 2020
$
(35,025
)
 
 
 
$

 
 
 
$
(35,025
)
 
 
 
 
 
 
 
 
 
 
Balance December 31, 2018
$
(25,396
)
 
 
 
$
(1,711
)
 
 
 
$
(27,107
)
OCI (loss) before reclassifications
(2,414
)
 
 
 

 
 
 
(2,414
)
Amounts reclassified from accumulated other comprehensive loss
1,513

 
(a)
 
732

 
 (b)
 
2,245

Balance June 30, 2019
$
(26,297
)
 
 
 
$
(979
)
 
 
 
$
(27,276
)

(a)
These amounts primarily represent amortization of actuarial loss and are included in the computation of net periodic pension cost.  See Note 5.
(b)
These amounts primarily represent realized gains and losses and are included in the computation of fuel and purchased power costs and are subject to the PSA.  See Note 7.


67


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

15. 
Income Taxes
 
The Tax Act reduced the corporate tax rate to 21% effective January 1, 2018. As a result of this rate reduction, the Company recognized a $1.14 billion reduction in its net deferred income tax liabilities as of December 31, 2017. In accordance with accounting for regulated companies, the effect of this rate reduction was substantially offset by a net regulatory liability.

Federal income tax laws require the amortization of a majority of the balance over the remaining regulatory life of the related property. As a result of the modifications made to the annual transmission formula rate during the second quarter of 2018, the Company began amortization of FERC jurisdictional net excess deferred tax liabilities in 2018. On March 13, 2019, the ACC approved the Company's proposal to amortize non-depreciation related net excess deferred tax liabilities subject to its jurisdiction over a twelve-month period. As a result, the Company began amortization in March 2019. As of June 30, 2020, the Company has recorded $14 million of income tax benefit related to the amortization of these non-depreciation related net excess deferred tax liabilities. On October 29, 2019, the ACC approved the Company’s proposal to amortize depreciation related net excess deferred tax liabilities subject to its jurisdiction over a 28.5-year period with amortization to retroactively begin as of January 1, 2018. As of June 30, 2020, the Company has recorded $13.5 million of income tax benefit related to amortization of these depreciation related liabilities. See Note 4 for more details.
    
In August 2018, U.S. Treasury proposed regulations that clarified bonus depreciation transition rules under the Tax Act for regulated public utility property placed in service after September 27, 2017 and before January 1, 2018.  However, these proposed regulations were ambiguous with respect to regulated public utility property placed in service on or after January 1, 2018. In September 2019, U.S. Treasury issued final regulations, which replaced the August 2018 proposed regulations. These final regulations did not materially impact any tax position taken by the Company for property placed in service after September 27, 2017 and before January 1, 2018.

Along with the September 2019 final regulations, U.S. Treasury also issued new proposed regulations which clarify bonus depreciation transition rules under the Tax Act for property placed in service by regulated public utilities after December 31, 2017. The proposed regulations provide that certain regulated public utility property which was under construction prior to September 28, 2017 and placed in service between January 1, 2018 and December 31, 2020 would continue to be eligible for bonus depreciation under the rules and bonus depreciation phase-downs in effect prior to enactment of the Tax Act. 

Net income associated with the Palo Verde sale leaseback VIEs is not subject to tax.  As a result, there is no income tax expense associated with the VIEs recorded on the Pinnacle West Consolidated and APS Consolidated Statements of Income. See Note 6 for additional details related to the Palo Verde sale leaseback VIEs.

As of the balance sheet date, the tax year ended December 31, 2016 and all subsequent tax years remain subject to examination by the IRS.  With a few exceptions, the Company is no longer subject to state income tax examinations by tax authorities for years before 2015.

16. 
Leases
 
We lease certain land, buildings, vehicles, equipment and other property through operating rental agreements with varying terms, provisions, and expiration dates. APS also has certain purchased power

68


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

agreements that qualify as lease arrangements. Our leases have remaining terms that expire in 2020 through 2050. Substantially all of our leasing activities relate to APS.

In 1986, APS entered into agreements with three separate lessor trust entities in order to sell and lease back interests in Palo Verde Unit 2 and related common facilities.  These lessor trust entities have been deemed VIEs for which APS is the primary beneficiary.  As the primary beneficiary, APS consolidated these lessor trust entities.  The impacts of these sale leaseback transactions are excluded from our lease disclosures as lease accounting is eliminated upon consolidation.  See Note 6 for a discussion of VIEs.
On June 1, 2020 APS had two separate purchased power lease contracts that commenced. The lease terms end on September 30, 2025 and September 30, 2026, respectively. Both of these leases allow APS the right to the generation capacity from certain natural-gas fueled generators during the months of June through September over the contract term.  APS does not operate or maintain these leased assets. APS controls the dispatch of the leased assets during the months of June through September and is required to pay a fixed monthly capacity payment during these periods of use. For these types of leased assets APS has elected to combine both the lease and non-lease payment components and accounts for the entire fixed payment as a lease obligation. These purchased power lease contracts are accounted for as operating leases. The contracts do not contain purchase options or term extension options.  In addition to the fixed monthly capacity payment, APS must also pay variable charges based on the actual production volume of the asset. The variable consideration is not included in the measurement of our lease obligation.
The following tables provide information related to our lease costs (dollars in thousands):

 
 
Three Months Ended
June 30, 2020
 
Three Months Ended
June 30, 2019
 
 
Purchased Power Lease Contracts
 
Land, Property & Equipment Leases
 
Total
 
Purchased Power Lease Contracts
 
Land, Property & Equipment Leases
 
Total
Operating lease cost
 
$
17,221

 
$
4,651

 
$
21,872

 
$
14,063

 
$
4,414

 
$
18,477

Variable lease cost
 
40,821

 
255

 
41,076

 
41,529

 
360

 
41,889

Short-term lease cost
 

 
996

 
996

 

 
1,812

 
1,812

Total lease cost
 
$
58,042

 
$
5,902

 
$
63,944

 
$
55,592

 
$
6,586

 
$
62,178




 
 
Six Months Ended
June 30, 2020
 
Six Months Ended
June 30, 2019
 
 
Purchased Power Lease Contracts
 
Land, Property & Equipment Leases
 
Total
 
Purchased Power Lease Contracts
 
Land, Property & Equipment Leases
 
Total
Operating lease cost
 
$
17,221

 
$
9,304

 
$
26,525

 
$
14,063

 
$
8,762

 
$
22,825

Variable lease cost
 
61,394

 
498

 
61,892

 
58,820

 
360

 
59,180

Short-term lease cost
 

 
1,786

 
1,786

 

 
2,665

 
2,665

Total lease cost
 
$
78,615

 
$
11,588

 
$
90,203

 
$
72,883

 
$
11,787

 
$
84,670




69


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

Lease costs are primarily included as a component of operating expenses on our Condensed Consolidated Statements of Income.  Lease costs relating to purchased power lease contracts are recorded in fuel and purchased power on the Condensed Consolidated Statements of Income, and are subject to recovery under the PSA or RES (see Note 4).  The tables above reflect the lease cost amounts before the effect of regulatory deferral under the PSA and RES.  Variable lease costs are recognized in the period the costs are incurred, and primarily relate to renewable purchased power lease contracts.  Payments under most renewable purchased power lease contracts are dependent upon environmental factors, and due to the inherent uncertainty associated with the reliability of the fuel source, the payments are considered variable and are excluded from the measurement of lease liabilities and right-of-use lease assets. Certain of our lease agreements have lease terms with non-consecutive periods of use. For these agreements we recognize lease costs during the periods of use.  Leases with initial terms of 12 months or less are considered short-term leases and are not recorded on the balance sheet.
 
The following table provides information related to the maturity of our operating lease liabilities (dollars in thousands):
 
 
June 30, 2020
Year
 
Purchased Power Lease Contracts
 
Land, Property & Equipment Leases
 
Total
2020 (remaining six months of 2020)
 
$
59,555

 
$
7,817

 
$
67,372

2021
 
66,658

 
13,123

 
79,781

2022
 
68,325

 
9,495

 
77,820

2023
 
70,033

 
7,191

 
77,224

2024
 
71,784

 
4,945

 
76,729

2025
 
73,578

 
3,245

 
76,823

Thereafter
 
36,759

 
36,615

 
73,374

Total lease commitments
 
446,692

 
82,431

 
529,123

Less imputed interest
 
16,844

 
18,807

 
35,651

Total lease liabilities
 
$
429,848

 
$
63,624

 
$
493,472


 
We recognize lease assets and liabilities upon lease commencement. At June 30, 2020, we have additional lease arrangements that have been executed, but have not yet commenced. These arrangements primarily relate to purchased power lease contracts with lease commencement dates beginning in May 2021 with terms ending in October 2027. We expect the total fixed consideration paid for these arrangements, which includes both lease and nonlease payments, will approximate $258 million over the term of the arrangements.


70


COMBINED NOTES TO CONDENSED CONSOLIDATED FINANCIAL STATEMENTS

The following tables provide other additional information related to operating lease liabilities:
 
June 30, 2020
 
December 31, 2019
Weighted average remaining lease term
7 years

 
13 years

Weighted average discount rate (a)
1.66
%
 
3.71
%


(a) Most of our lease agreements do not contain an implicit rate that is readily determinable. For these agreements we use our incremental borrowing rate to measure the present value of lease liabilities.  We determine our incremental borrowing rate at lease commencement based on the rate of interest that we would have to pay to borrow, on a collateralized basis over a similar term, an amount equal to the lease payments in a similar economic environment. We use the implicit rate when it is readily determinable.

 
Six Months Ended
June 30, 2020
 
Six Months Ended June 30, 2019
Cash paid for amounts included in the measurement of lease liabilities - operating cash flows (dollars in thousands):
$
7,624

 
$
11,987



17.     Asset Retirement Obligations

In the first quarter of 2020, APS recognized an ARO for its share of corrective action and water monitoring costs at Four Corners and the Navajo Plant (see additional details in Notes 4 and 8), which resulted in a decrease to the ARO of $11 million for Four Corners and an increase to the ARO of $5 million for the Navajo Plant.

The following schedule shows the change in our asset retirement obligations for the six months ended June 30, 2020 (dollars in thousands): 

 
2020
Asset retirement obligations at January 1, 2020
$
657,218

Changes attributable to:
 

Accretion expense
20,410

Settlements
(4,324
)
Estimated cash flow revisions
(5,352
)
Asset retirement obligations at June 30, 2020
$
667,952



In accordance with regulatory accounting, APS accrues removal costs for its regulated utility assets, even if there is no legal obligation for removal.  See detail of regulatory liabilities in Note 4.

71



ITEM 2.          MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS
 
INTRODUCTION
 
The following discussion should be read in conjunction with Pinnacle West’s Condensed Consolidated Financial Statements and APS’s Condensed Consolidated Financial Statements and the related Combined Notes that appear in Item 1 of this report.  For information on factors that may cause our actual future results to differ from those we currently seek or anticipate, see "Forward-Looking Statements" at the front of this report and "Risk Factors" in Part 1, Item 1A of the 2019 Form 10-K, Part II, Item 1A of the 2020 1st Quarter 10-Q and Part II, Item 1A of this report.
 
OVERVIEW

Business Overview

Pinnacle West is an investor-owned electric utility holding company based in Phoenix, Arizona with consolidated assets of about $19 billion. For over 130 years, Pinnacle West and our affiliates have provided energy and energy-related products to people and businesses throughout Arizona.

Pinnacle West derives essentially all of our revenues and earnings from our principal subsidiary, APS. APS is Arizona’s largest and longest-serving electric company that generates safe, affordable and reliable electricity for approximately 1.3 million retail customers in 11 of Arizona’s 15 counties. APS is also the operator and co-owner of Palo Verde - a primary source of electricity for the southwest United States and the largest nuclear power plant in the United States.

COVID-19 Pandemic

The COVID-19 pandemic continues to be a rapidly evolving situation. It has led to economic disruption and volatility in financial markets worldwide. The Company is operating under long-standing crisis and business continuity plans that exist to address situations including pandemics like COVID-19. We are focused on ensuring the health and safety of our employees, contractors and the general public by helping limit spread of this virus and ensuring continued, safe and reliable electric service for APS customers.
    
We have identified business-critical positions in both our operations and support organizations and identified backup personnel who are intended to provide support if needed to maintain operations with a reduced workforce. Essential planned work and capital investments are continuing during the pandemic but certain non-essential planned work has been postponed to later in 2020. The Company conducted a contract review to confirm adequacy of needed summer resources and has measures in place to continue to monitor resource needs and supply chain adequacy. At this time, the Company does not believe it has any material supply chain risks due to COVID-19 that would impact its ability to serve customers’ needs. The Company's operations and maintenance expenses, exclusive of bad debt expense, increased by approximately $9 million for the six months ended June 30, 2020 due to costs for personal protective equipment and other health and safety-related costs related to COVID-19.  We expect the Company’s operation and maintenance expenses will continue to be impacted for the remainder of 2020 by the need for additional personal protective equipment and other health and safety-related costs related to COVID-19.

While the total expected impact of COVID-19 on future sales is currently unknown, APS has experienced higher electric residential sales and lower electric commercial and industrial sales since the outset of the pandemic. From March 13th through July 28, 2020, the cumulative impact in weather-normalized usage was negative 1%. During that period, APS’s retail electric residential weather-normalized sales increased 4%,

72



and its retail electric commercial and industrial weather-normalized sales decreased 5% in the aggregate. APS expects the reduction in electric demand from commercial and industrial customers and increased demand from residential customers to continue in the near term. Based on past experience, a 1% variation in our annual kWh sales projections under normal business conditions can result in increases or decreases in annual net income of approximately $20 million.
 
On March 31, 2020, a stay at home order became effective for the state of Arizona and remained in effect until May 16, 2020, when it was lifted and Arizona began reopening. In June 2020, Arizona saw an increase in the number of COVID-19 cases, hospitalizations, and deaths. Accordingly, on June 29, 2020, the governor of Arizona closed bars, indoor gyms and fitness clubs or centers, indoor movie theaters and water parks and tubing operators until July 27, 2020 as a partial reversal of the state’s reopening and to mitigate the spread of COVID-19. On July 23, 2020, the governor of Arizona extended these closures and they will remain in place and continue to be reviewed for repeal or revision every two weeks. We cannot predict the impact of the increased spread of COVID-19 in Arizona and the partial reclosure will have on our financial position, results of operations or cash flows and we are continuing to monitor the impacts.

As a result of the COVID-19 pandemic, in mid-March 2020 the commercial paper markets failed to function normally and we were unable to utilize commercial paper as our primary method of acquiring short-term capital, which resulted in us drawing on our revolving credit facilities during the first quarter of 2020.  In mid-April 2020, we were again able to utilize the commercial paper market and we have paid down the entire amount of the revolving credit facilities that were utilized as a result of the commercial paper market failure. 

The Coronavirus Aid, Relief, and Economic Security (CARES) Act allows employers to defer payments of the employer share of Social Security payroll taxes that would have otherwise been owed from March 27, 2020 through December 31, 2020. We are deferring the cash payment of the employer's portion of Social Security payroll taxes for the period July 1, 2020 through December 31, 2020 that we expect will be in the range of $15 million to $20 million. We will pay half of this cash deferral by December 31, 2021 and the remainder by December 31, 2022.

On June 30, 2020, FERC issued an order granting a waiver request related to the existing AFUDC rate calculation beginning March 1, 2020 through February 28, 2021.  The order provides a simplified approach that companies may elect to implement in order to minimize the significant distorted effect on the AFUDC formula resulting from increased short-term debt financing during the COVID-19 pandemic.  APS has adopted this simplified approach to computing the AFUDC composite rate  by using a simple average of the actual historical short-term debt balances for 2019, instead of current period short-term debt balances, and has left all other aspects of the AFUDC formula composite rate calculation unchanged. This change impacts the AFUDC composite rate in 2020, but does not impact prior years.  Furthermore, the change in the composite rate calculation does not impact our accounting treatment for these costs. The change will not have a material impact on our financial statements. See Note 1 in our 2019 Form 10-K for information on the accounting treatment for AFUDC.  

Due to the COVID-19 pandemic, APS voluntarily suspended disconnections of customers for nonpayment beginning March 13, 2020.  In addition, APS waived all late payment fees during this current suspension period.  APS currently estimates that the Summer Disconnection Moratorium (see Note 4), the suspension of disconnections during the COVID-19 pandemic and the increased bad debt expense associated with both events will result in a negative impact to its 2020 operating results of approximately $20 million to $30 million pre-tax above the impact of disconnections on its operating results for years that did not have the Summer Disconnection Moratorium or COVID-19 pandemic. APS is anticipating an increase in bad debt expense associated with the COVID-19 pandemic, but it still believes that costs associated with the Summer Disconnection Moratorium and the COVID-19 disconnection suspensions and related bad debt expense with both events will fall within this estimated $20 million to $30 million range. These estimated impact amounts

73



depend on certain assumptions, including, but not limited to, customer behaviors, population and employment growth, and the impacts of COVID-19 on the economy. Additionally, due to COVID-19, APS delayed the reset of the EIS adjustor and suspended the discontinuation of TEAM Phase II to the first billing cycle in May 2020 rather than April 2020 (see Note 4 ).

On April 17, 2020, APS filed an application with the ACC requesting a COVID-19 emergency relief package to provide additional assistance to its customers. On May 5, 2020, the ACC approved APS returning $36 million that had been collected through the DSM Adjustor Charge, but not allocated for current DSM programs, directly to customers through a bill credit in June 2020 (see Note 4). As of June 30, 2020, APS had refunded approximately $40 million to customers. The additional $4 million over the approved amount was the result of the kWh credit being based on historic consumption which was different than actual consumption in the refund period. This difference was recorded to the DSM balancing account and will be addressed in subsequent DSM filings.

APS has committed in total approximately $8 million to assist customers and local non-profits and community organizations to help with the impact of the COVID-19 pandemic. On May 5, 2020, APS voluntarily committed to the ACC to contribute $5.3 million of non-ratepayer funds to provide assistance to residential and non-residential customers that have been impacted by the COVID-19 pandemic (“Customer COVID Assistance”). As part of this Customer COVID Assistance, APS has established a $2.3 million program to assist extra small and small non-residential customers that have a delinquency of two or more months with a one-time credit of $1,000 on each such customer's bill. The other $3 million of the Customer COVID Assistance has not yet been assigned to specific programs. Beyond the Customer COVID Assistance, APS has also provided $1.5 million to assist customers with a one-time credit of $100 on their bill, with a priority given to customers on limited-income service plans, and $1.25 million to assist local non-profits and community organizations working to mitigate the impacts of the COVID-19 pandemic.

More detailed discussion of the impacts and future uncertainties related to the COVID‑19 pandemic can be found throughout this Management's Discussion and Analysis of Financial Condition and Results of Operations and the Combined Notes to Pinnacle West's and APS's financial statements that appear in Item 1of this report and  "Risk Factors" in Part II, Item 1A of the 2020 1st Quarter 10-Q and Part II, Item 1A of this report.

Strategic Overview

Our strategy is to deliver shareholder value by creating a sustainable energy future for Arizona with a clean, affordable, reliable and customer-focused plan.

Clean Energy Commitment

We are committed to doing our part to make the future clean and carbon-free. Our vision for APS and Arizona presents an opportunity to engage with customers, communities, employees, policymakers, shareholders and others to achieve a shared, sustainable vision for Arizona. This goal is based on sound science and supports continued growth and economic development while maintaining reliability and affordable prices for APS's customers.

APS's new clean energy goals consist of three parts:
A 2050 goal to provide 100% clean, carbon-free electricity;
A 2030 target of achieving a resource mix that is 65% clean energy, with 45% of the generation portfolio coming from renewable energy; and
A commitment to end APS’s use of coal-fired generation by 2031.

74




APS's ability to successfully execute its clean energy commitment is dependent upon a number of important external factors, some of which include a supportive regulatory environment, sales and customer growth, development of clean energy technologies and continued access to capital markets.

2050 Goal: 100% Clean, Carbon-Free Electricity. Achieving a fully clean, carbon-free energy mix by 2050 is our aspiration. The 2050 goal will involve new thinking and depends on improved and new technologies.

2030 Goal: 65% Clean Energy. APS has an energy mix that is already 50% clean with existing plans to add more renewables and energy storage before 2025. By building on those plans, APS intends to attain an energy mix that is 65% clean by 2030, with 45% of APS's generation portfolio coming from renewable energy. “Clean” is measured as percent of energy mix which includes carbon-free resources like nuclear and demand-side management, and “renewable” is expressed as a percent of retail sales. This target will serve as a checkpoint for our resource planning, investment strategy, and customer affordability efforts as APS moves toward 100% clean, carbon-free energy mix by 2050.

APS understands that closing its coal-fired power plants will significantly impact employees as well as the surrounding communities. APS will continue to engage in meaningful dialogue with these stakeholders in order to explore, better understand and prepare to address a range of potential effects, including environmental, social and economic impacts.

2031 Goal: End APS's Use of Coal-Fired Generation. The commitment to end APS's use of coal-fired generation by 2031 will require APS to cease use of coal-generation at Four Corners. APS has permanently retired more than 1,000 MW of coal-fired electric generating capacity. These closures and other measures taken by APS have resulted in a total reduction of carbon emissions of 26% since 2005. In addition, APS has committed to end the use of coal at its remaining Cholla units by 2025.

Renewables. APS intends to strengthen its already diverse energy mix by increasing its investments in carbon-free resources. Its near-term actions include competitive solicitations to procure clean energy resources such as solar, wind, energy storage, demand response and DSM resources, all of which lead to a cleaner grid.


75



APS has a diverse portfolio of existing and planned renewable resources, including solar, wind, geothermal, biomass and biogas. APS's clean energy strategy includes executing purchased power contracts for new facilities, ongoing development of distributed energy resources and procurement of new facilities to be owned by APS. The following table summarizes the resources in APS's renewable energy portfolio that are in operation and under development as of June 30, 2020. Agreements for the development and completion of future resources are subject to various conditions, including successful siting, permitting and interconnection of the projects to the electric grid.
 
Net Capacity in Operation
(MW)
 
Net Capacity Planned / Under
Development (MW)
 
Total APS Owned: Solar
244

 

 
Purchased Power Agreements:
 

 
 

 
Solar
310

 

 
Solar + Energy Storage

 
50

 
Wind
289

 

 
Geothermal
10

 

 
Biomass
14

 

 
Biogas
3

 

 
Total Purchased Power Agreements
626

 
50

 
Total Distributed Energy: Solar (a) 
1,019

 
29

(b)
Total Renewable Portfolio
1,889

 
79

 

(a)         Includes rooftop solar facilities owned by third parties. Distributed generation is produced in Direct Current and is converted to AC for reporting purposes.
(b)
Applications received by APS that are not yet installed and online.

APS has developed and owns solar resources through the ACC-approved AZ Sun Program.  APS also issued two Requests for Proposal ("RFP") in September 2019. The first RFP seeks competitive proposals for up to 150 MW of APS-owned solar resources to be in service by 2021. This solar generation will be designed with the flexibility to add energy storage as a future option. A second RFP requests up to 250 MW of wind resources to be in service as soon as possible, but no later than 2022.

Palo Verde. Palo Verde, the nation’s largest carbon-free, clean energy resource, will continue to be a foundational part of APS's resource portfolio. The plant supplies nearly 70% of our clean energy and provides the foundation for the reliable and affordable service for APS customers. Palo Verde is not just the cornerstone of our current clean energy mix, it also is a significant provider of clean energy to the southwest United States. The plant’s continued operation is important to a carbon-free and clean energy future for Arizona and the region, as a reliable, continuous, affordable resource and as a large contributor to the local economy.

Affordable

We believe it is APS's responsibility to deliver electric services to customers in the most cost-effective manner. Since January 2018 through June 2020, the average residential bill decreased by 7.3% or $10.95.

Building upon existing cost management efforts, APS launched a customer affordability initiative in 2019. The initiative was implemented company-wide to thoughtfully and deliberately assess our business processes and organizational approaches to completing high-value work and internal efficiencies. Through the initiative and existing cost management practices, APS identified $20 million in possible cost savings for 2020.


76



Participation in the EIM continues to be an effective tool for creating savings for our customers from the real-time, voluntary market. As of June 30, 2020, the EIM has delivered approximately $158 million in gross benefits to APS customers since APS began participating in EIM in 2016. APS is in discussions with the EIM operator, CAISO, and other EIM participants about the feasibility of creating a voluntary day-ahead market to achieve more cost savings and use the region’s renewable resources more efficiently.

Reliable

While our energy mix evolves, the obligation to deliver reliable service to our customers remains. Excluding voluntary outages and proactive fire mitigation efforts, APS finished 2019 with its best score for frequency of customer power outages.
    
Planned investments will support operating and maintaining the grid, updating technology, accommodating customer growth and enabling more renewable energy resources. Our advanced distribution management system allows operators to locate outages, control line devices remotely and helps them coordinate more closely with field crews to safely maintain an increasingly dynamic grid. The system also integrates a new meter data management system that increases grid visibility and gives customers access to more of their energy usage data.

Wildfire safety remains a critical focus for APS and other utilities. We increased investment in fire mitigation efforts to clear defensible space around our infrastructure, build partnerships with government entities and first responders and educate customers and communities. These programs contribute to customer reliability, responsible forest management and safe communities.

The new units at our modernized Ocotillo power plant provide cleaner-running and more efficient units. They support reliability by responding quickly to the variability of solar generation, and delivering energy in the late afternoon and early evening, when solar production declines as the sun sets and customer demand peaks.

Customer-Focused

Customers are at the core of what APS does every day and APS is committed to providing options that make it easier for its customers to do business with them. In 2019, APS launched its redesigned aps.com website and mobile app, giving customers upgraded access to their energy usage data and billing information. APS's Customer Care team is using speech analytics to enrich advisors’ interactions with customers over the telephone, and customers can also communicate with APS through an online chat.

APS expanded financial help for its most vulnerable customers in 2019, allocating $2.75 million in crisis bill assistance and increasing the individual benefit for qualifying customers from $400 to $800 per year. The APS Solar Communities program has allowed more than 600 limited- and moderate-income customers to support clean energy and save money by hosting APS-owned solar systems on their residences in exchange for a monthly bill credit.

APS continues to develop and deploy innovative programs that connect customers with advanced technologies to help them manage their bills and encourage energy use during midday, when solar power is most abundant. Three energy storage programs incorporating smart thermostats, connected water heaters and batteries are helping customers shift energy use to times when they can take advantage of low-cost, abundant energy and reduce peak demand on APS's system.

In 2020, APS is convening an advisory panel of customers to gain a deeper understanding of the customer experience through their individual perspectives. A group of customer service advisors, in

77



conjunction with local human services agencies, will resume providing in-person customer support in communities APS serves once it is safe to do so because of the COVID-19 pandemic.

APS is also providing assistance to residential and business customers that have been impacted by the COVID-19 pandemic. See "COVID-19 Pandemic" above for more information about pandemic relief.

Emerging Technologies

Energy Storage

APS deploys a number of advanced technologies on its system, including energy storage. Storage can provide capacity, improve power quality, be utilized for system regulation, integrate renewable generation, and in certain circumstances, be used to defer certain traditional infrastructure investments. Energy storage can also aid in integrating higher levels of renewables by storing excess energy when system demand is low and renewable production is high and then releasing the stored energy during peak demand hours later in the day and after sunset. APS is utilizing grid-scale energy storage projects to benefit customers, to increase renewable utilization, and to further our understanding of how storage works with other advanced technologies and the grid. We are preparing for additional energy storage in the future.

In early 2018, APS entered into a 15-year power purchase agreement for a 65 MW solar facility that charges a 50 MW solar-fueled battery. Service under this agreement is scheduled to begin in 2021. In 2018, APS issued an RFP for approximately 106 MW of energy storage to be located at up to five of its AZ Sun sites. Based upon our evaluation of the RFP responses, APS decided to expand the initial phase of battery deployment to 141 MW by adding a sixth AZ Sun site. In February 2019, we contracted for the 141 MW and originally anticipated such facilities could be in service by mid-2020. In April 2019, a battery module in APS’s McMicken battery energy storage facility experienced an equipment failure, which prompted an internal investigation to determine the cause. APS has completed its investigation of the McMicken battery incident and is continuing to determine the timing of future deployment of batteries on APS's system. Due to the McMicken battery incident, APS is working with the counterparty for the AZ Sun sites to determine appropriate timing and path forward for such facilities. Additionally, in February 2019, APS signed two 20-year power purchase agreements for energy storage totaling 150 MW. Service under these power purchase agreements is also dependent on the results of the McMicken battery incident investigation and requires approval from the ACC to allow for recovery of these agreements through the PSA.

We currently plan to install at least 850 MW of energy storage by 2025, including the 150 MW of energy storage projects under power purchase agreements described above.  The additional 700 MW of energy storage is expected to be made up of the retrofits associated with our AZ Sun sites as described above, along with current and future RFPs for energy storage and solar plus energy storage projects. Given the April 2019 event, we continue to evaluate the appropriate timing and path forward to support the overall capacity goals for our system and associated energy storage requirements. Currently, APS is pursuing an RFP for battery-ready solar resources up to 150 MW with results expected in the second half of 2020.

Electric Vehicles

APS plans to make electric vehicle charging more accessible for its customers and help Arizona businesses, schools and governments electrify their fleets. In 2019, APS implemented its Take Charge AZ Pilot Program. The program provides charging equipment, installation, and maintenance to business customers, government agencies, and multifamily housing communities. Rates are designed to encourage charging overnight and during daytime off-peak hours when solar energy is abundant.

78




The ACC ordered the state’s public service corporations, including APS, to develop a long-term, comprehensive Statewide Transportation Electrification Plan (“TE Plan”) for Arizona. The TE Plan is intended to provide a roadmap for Transportation Electrification in Arizona, focused on realizing the associated air quality and economic development benefits for all residents in the state along with understanding the impact of electric vehicle charging on the grid. APS is actively participating in this process, which is scheduled to be completed by the end of 2020 and submitted to the ACC for review and approval.

Hydrogen Production
Palo Verde, in partnership with Idaho National Laboratory and two other utilities, has been chosen by the DOE's Office of Nuclear Energy to participate in a hydrogen production project with the goal to improve the long-term economic competitiveness of the nuclear power industry. The project, planned for 2020 through 2022, will look at how hydrogen produced from Palo Verde energy may be used as energy storage for use in reverse-operable electrolysis or peaking gas turbines during times of the day when photovoltaic solar energy sources are unavailable and energy reserves in the southwest United States are low. It could also be used to support a rapidly increasing hydrogen transportation fuel market.

Experience from the pilot project will offer insights into methods for flexible transitions between electricity and hydrogen generation in solar-dominated electricity markets, and demonstrate how hydrogen may be used as energy storage to provide electricity during operating periods when solar is not available.

Carbon Capture

Carbon capture technologies can isolate CO2 and either sequester it permanently in geologic formations or convert it for use in products. Currently, almost all existing fossil fuel generators do not control carbon emissions the way they control emissions of other air pollutants such as sulfur dioxide or oxides of nitrogen. Carbon capture technologies are still in the demonstration phase and while they show promise, they are still being tested in real-world conditions. These technologies could offer the potential to keep in operation existing generators that otherwise would need to be retired. APS will continue to monitor this emerging technology.

Regulatory Overview

On October 31, 2019, APS filed an application with the ACC seeking an annual increase in retail base rates of $69 million. This amount includes recovery of the deferral and rate base effects of the Four Corners SCR project that is currently the subject of a separate proceeding (see “SCR Cost Recovery” in Note 4). It also reflects a net credit to base rates of approximately $115 million primarily due to the prospective inclusion of rate refunds currently provided through the TEAM. The proposed total revenue increase in APS's application is $184 million. The average annual customer bill impact of APS’s request is an increase of 5.6% (the average annual bill impact for a typical APS residential customer is 5.4%).

The principal provisions of APS's application are:

a test year comprised of twelve months ended June 30, 2019, adjusted as described below;
an original cost rate base of $8.87 billion, which approximates the ACC-jurisdictional portion of the book value of utility assets, net of accumulated depreciation and other credits;
the following proposed capital structure and costs of capital:

79



 
 
Capital Structure
 
Cost of Capital
 
Long-term debt
 
45.3
%
4.10
%
Common stock equity
 
54.7
%
10.15
%
Weighted-average cost of capital
 
 
 
7.41
%
 
a 1% return on the increment of fair value rate base above APS’s original cost rate base, as provided for by Arizona law;
authorization to defer until APS's next general rate case the increase or decrease in its Arizona property taxes attributable to tax rate changes after the date the rate application is adjudicated;
a number of proposed rate and program changes for residential customers, including:
a super off-peak period during the winter months for APS’s time-of-use with demand rates;
additional $1.25 million in funding for APS's limited-income crisis bill program; and
a flat bill/subscription rate pilot program;
proposed rate design changes for commercial customers, including an experimental program designed to provide access to market pricing for up to 200 MW of medium and large commercial customers;
recovery of the deferral and rate base effects of the construction and operating costs of the Ocotillo modernization project (see Note 4 discussion of the 2017 Settlement Agreement); and
continued recovery of the remaining investment and other costs related to the retirement and closure of the Navajo Plant (see Note 4 for details related to the resulting regulatory asset).

APS requested that the increase become effective December 1, 2020.  The hearing for this rate case was delayed, at the request of ACC Staff and RUCO, and is currently scheduled to begin December 14, 2020. APS cannot predict the outcome of its request.

See Note 4 for information regarding additional regulatory matters.

Financial Strength and Flexibility 

Pinnacle West and APS currently have ample borrowing capacity under their respective credit facilities, and may readily access these facilities ensuring adequate liquidity for each company.  Capital expenditures will be funded with internally generated cash and external financings, which may include issuances of long-term debt and Pinnacle West common stock.
 
Other Subsidiaries

Bright Canyon Energy. On July 31, 2014, Pinnacle West announced its creation of a wholly-owned subsidiary, BCE.  BCE's strategy is to develop, own, operate and acquire energy infrastructure in a manner that leverages the Company’s core expertise in the electric energy industry.  In 2014, BCE formed a 50/50 joint venture with BHE U.S. Transmission LLC, a subsidiary of Berkshire Hathaway Energy Company.  The joint venture, named TransCanyon, is pursuing independent transmission opportunities within the eleven states that comprise the Western Electricity Coordinating Council, excluding opportunities related to transmission service that would otherwise be provided under the tariffs of the retail service territories of the venture partners’ utility affiliates.

On December 20, 2019, BCE acquired minority ownership positions in two wind farms under development by Tenaska, the 242 MW Clear Creek wind farm in Missouri ("Clear Creek") and the 250 MW Nobles 2 wind farm in Minnesota ("Nobles 2"). Clear Creek achieved commercial operation in May 2020 and Nobles 2 is expected to achieve commercial operation in 2020 and deliver power later this year. Both wind

80



farms deliver power under long-term power purchase agreements. BCE indirectly owns 9.9% of Clear Creek and 5.1% of Nobles 2.

El Dorado. El Dorado is a wholly-owned subsidiary of Pinnacle West. El Dorado owns debt investments and minority interests in several energy-related investments and Arizona community-based ventures.  El Dorado committed to a $25 million investment in the Energy Impact Partners fund, which is an organization that focuses on fostering innovation and supporting the transformation of the utility industry. The investment will be made by El Dorado as investments are selected by the Energy Impact Partners fund.

Key Financial Drivers
 
In addition to the continuing impact of the matters described above, many factors influence our financial results and our future financial outlook, including those listed below.  We closely monitor these factors to plan for the Company’s current needs, and to adjust our expectations, financial budgets and forecasts appropriately.
 
Electric Operating Revenues.  For the years 2017 through 2019, retail electric revenues comprised approximately 95% of our total operating revenues.  Our electric operating revenues are affected by customer growth or decline, variations in weather from period to period, customer mix, average usage per customer and the impacts of energy efficiency programs, distributed energy additions, electricity rates and tariffs, the recovery of PSA deferrals and the operation of other recovery mechanisms.  These revenue transactions are affected by the availability of excess generation or other energy resources and wholesale market conditions, including competition, demand and prices.
 
Actual and Projected Customer and Sales Growth. Retail customers in APS’s service territory increased 2.3% for the six-month period ended June 30, 2020 compared with the prior-year period.  For the three years 2017 through 2019, APS’s customer growth averaged 1.8% per year.  We currently project annual customer growth to be 1.5 - 2.5% for 2020 and for 2020 through 2022 based on our assessment of steady population growth in Arizona.
 
Retail electricity sales in kWh, adjusted to exclude the effects of weather variations, decreased 0.3% for the six-month period ended June 30, 2020 compared with the prior-year period. While steady customer growth was offset by energy savings driven by customer conservation, energy efficiency, and distributed renewable generation initiatives, the main driver of declining sales for this period was the impact of business closures due to COVID-19.  Though the total expected impact of COVID-19 on future sales is currently unknown, APS has experienced higher electric residential sales and lower electric commercial and industrial sales since the outset of the pandemic. From March 13th through July 28, 2020, the cumulative impact in weather-normalized usage was negative 1%. During that period, APS’s retail electric residential weather-normalized sales increased 4%, and its retail electric commercial and industrial weather-normalized sales decreased 5% in the aggregate. APS expects the reduction in electric demand from commercial and industrial customers and increased demand from residential customers to continue in the near term.

For the three years 2017 through 2019, annual retail electricity sales were about flat, adjusted to exclude the effects of weather variations.  We currently project that annual retail electricity sales in kWh will be flat to negative 1.0% for 2020 and increase on average in the range of 0.5 - 1.5% during 2020 through 2022, including the effects of customer conservation, energy efficiency and distributed renewable generation initiatives, but excluding the effects of weather variations and the impacts of several new large data centers opening operations in Metro Phoenix.  The impact of new large data centers could raise the range of expected annual sales growth rate over the 2020 to 2022 period, but demand from these customers remains uncertain at this time. These estimates could be further impacted by slower than expected growth of the Arizona economy or acceleration of the expected effects of customer conservation, energy efficiency, distributed renewable

81



generation initiatives, or customer and sales growth and the economy that is being impacted by COVID-19 not normalizing in 2020.
 
                Actual sales growth, excluding weather-related variations, may differ from our projections as a result of numerous factors, such as economic conditions, customer growth, usage patterns and energy conservation, impacts of energy efficiency programs and growth in distributed generation, and responses to retail price changes.  Based on past experience, a 1% variation in our annual kWh sales projections attributable to such economic factors under normal business conditions can result in increases or decreases in annual net income of approximately $20 million.
 
Weather.  In forecasting the retail sales growth numbers provided above, we assume normal weather patterns based on historical data.  Historically, extreme weather variations have resulted in annual variations in net income in excess of $25 million.  However, our experience indicates that the more typical variations from normal weather can result in increases or decreases in annual net income of up to $15 million.
 
Fuel and Purchased Power Costs. Fuel and purchased power costs included on our Condensed Consolidated Statements of Income are impacted by our electricity sales volumes, existing contracts for purchased power and generation fuel, our power plant performance, transmission availability or constraints, prevailing market prices, new generating plants being placed in service in our market areas, changes in our generation resource allocation, our hedging program for managing such costs and PSA deferrals and the related amortization.

Operations and Maintenance ExpensesOperations and maintenance expenses are impacted by customer and sales growth, power plant operations, maintenance of utility plant (including generation, transmission, and distribution facilities), inflation, unplanned outages, planned outages (typically scheduled in the spring and fall), renewable energy and demand side management related expenses (which are offset by the same amount of operating revenues) and other factors.

Depreciation and Amortization Expenses.  Depreciation and amortization expenses are impacted by net additions to utility plant and other property (such as new generation, transmission, and distribution facilities), and changes in depreciation and amortization rates.  See "Liquidity and Capital Resources" below for information regarding the planned additions to our facilities.
 
Property Taxes.  Taxes other than income taxes consist primarily of property taxes, which are affected by the value of property in-service and under construction, assessment ratios, and tax rates.  The average property tax rate in Arizona for APS, which owns essentially all of our property, was 10.9% of the assessed value for 2019, 11.0% for 2018 and 11.2% for 2017. We expect property taxes to increase as we add new generating units and continue with improvements and expansions to our existing generating units and transmission and distribution facilities. 

Pension and other postretirement non-service credits - net.  Pension and other postretirement non-service credits can be impacted by changes in our actuarial assumptions. The most relevant actuarial assumptions are the discount rate used to measure our net periodic costs/credit, the expected long-term rate of return on plan assets used to estimate earnings on invested funds over the long-term, the mortality assumptions and the assumed healthcare cost trend rates. We review these assumptions on an annual basis and adjust them as necessary.

Interest Expense.  Interest expense is affected by the amount of debt outstanding and the interest rates on that debt (see Note 3).  The primary factors affecting borrowing levels are expected to be our capital expenditures, long-term debt maturities, equity issuances and internally generated cash flow.  An allowance for

82



borrowed funds used during construction offsets a portion of interest expense while capital projects are under construction.  We stop accruing AFUDC on a project when it is placed in commercial operation.
 
Income Taxes.  Income taxes are affected by the amount of pretax book income, income tax rates, certain deductions and non-taxable items, such as AFUDC.  In addition, income taxes may also be affected by the settlement of issues with taxing authorities. On December 22, 2017, the Tax Act was enacted and was generally effective on January 1, 2018. Changes impacting the Company include a reduction in the corporate tax rate to 21%, revisions to the rules related to tax bonus depreciation, limitations on interest deductibility and an associated exception for certain public utilities, and requirements that certain excess deferred tax amounts of regulated utilities be normalized. (See Note 15 for details of the impacts on the Company as of June 30, 2020.) In APS's 2017 rate case decision, the ACC approved a Tax Expense Adjustor Mechanism which will be used to pass through the income tax effects to retail customers of the Tax Act. (See Note 4 for details of the TEAM.)

RESULTS OF OPERATIONS

Pinnacle West’s only reportable business segment is our regulated electricity segment, which consists of traditional regulated retail and wholesale electricity businesses (primarily sales supplied under traditional cost based rate regulation) and related activities and includes electricity generation, transmission and distribution.

Operating ResultsThree-month period ended June 30, 2020 compared with three-month period ended June 30, 2019.

Our consolidated net income attributable to common shareholders for the three months ended June 30, 2020 was $194 million, compared with consolidated net income attributable to common shareholders of $144 million for the prior-year period.  The results reflect an increase of approximately $48 million for the regulated electricity segment primarily due to higher revenue driven by the effects of weather, lower operations and maintenance expense and higher pension and other postretirement non-service credits, partially offset by higher income taxes. Weather had a significant impact on our result of operations due to the hotter than normal weather in 2020 compared to the milder than normal weather in the same 2019 period. 


83



The following table presents net income attributable to common shareholders by business segment compared with the prior-year period:

 
Three Months Ended
June 30,
 
 
 
2020
 
2019
 
Net Change
 
(dollars in millions)
Regulated Electricity Segment:
 

 
 

 
 

Operating revenues less fuel and purchased power expenses
$
690

 
$
626

 
$
64

Operations and maintenance
(218
)
 
(227
)
 
9

Depreciation and amortization
(152
)
 
(147
)
 
(5
)
Taxes other than income taxes
(57
)
 
(55
)
 
(2
)
Pension and other postretirement non-service credits - net
14

 
6

 
8

All other income and expenses, net
19

 
16

 
3

Interest charges, net of allowance for borrowed funds used during construction
(58
)
 
(53
)
 
(5
)
Income taxes
(41
)
 
(17
)
 
(24
)
Less income related to noncontrolling interests (Note 6)
(5
)
 
(5
)
 

Regulated electricity segment income
192

 
144

 
48

All other
2

 

 
2

Net Income Attributable to Common Shareholders
$
194

 
$
144

 
$
50


Operating revenues less fuel and purchased power expenses.  Regulated electricity segment operating revenues less fuel and purchased power expenses were $64 million higher for the three months ended June 30, 2020 compared with the prior-year period.  The following table summarizes the major components of this change:

 
Increase (Decrease)
 
Operating
revenues
 
Fuel and
purchased
power expenses
 
Net change
 
(dollars in millions)
Effects of weather
$
84

 
$
20

 
$
64

Refunds due to tax reform (Note 4)
14

 

 
14

Changes in net fuel and purchased power costs, including off-system sales margins and related deferrals
(18
)
 
(18
)
 

Lower renewable energy regulatory surcharges, partially offset by operations and maintenance costs
(3
)
 

 
(3
)
Lower retail revenue due to the impacts of energy efficiency, distributed generation and changes in customer usage patterns, including the impacts of COVID-19, partially offset by higher customer growth
(17
)
 
(2
)
 
(15
)
Miscellaneous items, net

 
(4
)
 
4

Total
$
60

 
$
(4
)
 
$
64


84




Operations and maintenance.  Operations and maintenance expenses decreased $9 million for the three months ended June 30, 2020 compared with the prior-year period primarily because of:

A decrease of $13 million primarily related to an increased recovery from contributions of administrative and general costs from Palo Verde owners;

A decrease of $5 million related to consulting costs;

A decrease of $3 million primarily related to costs for renewable energy and similar regulatory programs, which are partially offset in operating revenues and purchased power;

An increase of $3 million for costs related to information technology;

An increase of $4 million related to customer bad debt expenses primarily related to the Summer Disconnection Moratorium and COVID-19 disconnect suspensions (see Note 4);

An increase of $8 million primarily related to personal protective equipment and other health and safety-related costs for COVID-19 response; and

A decrease of $3 million for other miscellaneous factors.

Depreciation and amortization. Depreciation and amortization expenses were $5 million higher for the three months ended June 30, 2020 compared to the prior-year period primarily due to increased plant in service of $8 million, partially offset by the regulatory deferrals for the Ocotillo modernization project of $3 million.

Pension and other postretirement non-service credits, net. Pension and other postretirement non-service credits, net were $8 million higher for the three months ended June 30, 2020 compared to the prior-year period primarily due to higher market returns in 2019.

Interest charges, net of allowance for borrowed funds used during construction. Interest charges, net of allowance for borrowed funds used during construction were $5 million higher for the three months ended June 30, 2020 compared to the prior-year period primarily due to higher debt balances in the current period.

Income taxes.  Income taxes were $24 million higher for the three months ended June 30, 2020 compared with the prior-year period primarily due to higher pre-tax income and reduced amortization of excess deferred taxes (see Note 15).


85



Operating ResultsSix-month period ended June 30, 2020 compared with six-month period ended June 30, 2019.

Our consolidated net income attributable to common shareholders for the six months ended June 30, 2020 was $224 million, compared with consolidated net income attributable to common shareholders of $162 million for the prior-year period. The results reflect an increase of approximately $59 million for the regulated electricity segment primarily due to lower operations and maintenance expense, higher revenue driven by the effects of weather and higher pension and other postretirement non-service credits, partially offset by higher depreciation expense. Weather had a significant impact on our result of operations due to the hotter than normal weather in 2020 compared to the milder than normal weather in the same 2019 period. 

The following table presents net income attributable to common shareholders by business segment compared with the prior-year period:

 
Six Months Ended June 30,
 
 
 
2020
 
2019
 
Net Change
 
(dollars in millions)
Regulated Electricity Segment:
 

 
 

 
 

Operating revenues less fuel and purchased power expenses
$
1,162

 
$
1,135

 
$
27

Operations and maintenance
(439
)
 
(472
)
 
33

Depreciation and amortization
(307
)
 
(296
)
 
(11
)
Taxes other than income taxes
(113
)
 
(110
)
 
(3
)
Pension and other postretirement non-service credits - net
28

 
11

 
17

All other income and expenses, net
34

 
30

 
4

Interest charges, net of allowance for borrowed funds used during construction
(113
)
 
(107
)
 
(6
)
Income taxes
(21
)
 
(19
)
 
(2
)
Less income related to noncontrolling interests (Note 6)
(10
)
 
(10
)
 

Regulated electricity segment income
221

 
162

 
59

All other
3

 

 
3

Net Income Attributable to Common Shareholders
$
224

 
$
162

 
$
62



86



Operating revenues less fuel and purchased power expenses.  Regulated electricity segment operating revenues less fuel and purchased power expenses were $27 million higher for the six months ended June 30, 2020 compared with the prior-year period.  The following table summarizes the major components of this change:

 
Increase (Decrease)
 
Operating
revenues
 
Fuel and
purchased
power expenses
 
Net change
 
(dollars in millions)
Effects of weather
$
67

 
$
15

 
$
52

Changes in net fuel and purchased power costs, including off-system sales margins and related deferrals
(53
)
 
(56
)
 
3

Lower renewable energy regulatory surcharges, partially offset by operations and maintenance costs
(7
)
 

 
(7
)
Refunds due to tax reform (Note 4)
(9
)
 

 
(9
)
Lower retail revenue due to the impacts of energy efficiency, distributed generation and changes in customer usage patterns, including the impacts of COVID-19, partially offset by higher customer growth
(15
)
 

 
(15
)
Miscellaneous items, net
(2
)
 
(5
)
 
3

Total
$
(19
)
 
$
(46
)
 
$
27


Operations and maintenance.  Operations and maintenance expenses decreased $33 million for the six months ended June 30, 2020 compared with the prior-year period primarily because of:

A decrease of $15 million primarily related to an increased recovery from contributions of administrative and general costs from Palo Verde owners;

A decrease of $9 million in fossil generation costs primarily due to lower planned outages and lower operating costs due to the Navajo Plant closure (see Note 4);

A decrease of $9 million primarily related to costs for renewable energy and similar regulatory programs, which are partially offset in operating revenues and purchased power;

A decrease of $6 million related to consulting costs;

A decrease of $3 million related to employee benefit costs;

An increase of $4 million for costs related to information technology;

An increase of $5 million related to customer bad debt expenses primarily related to the Summer Disconnection Moratorium and COVID-19 disconnect suspensions (see Note 4);


87



An increase of $9 million primarily related to personal protective equipment and other health and safety-related costs for COVID-19 response; and

A decrease of $9 million for corporate resources and other miscellaneous factors.

Depreciation and amortization. Depreciation and amortization expenses were $11 million higher for the six months ended June 30, 2020 compared to the prior-year period primarily due to increased plant in service of $22 million, partially offset by the regulatory deferrals for the Ocotillo modernization project and the Four Corners SCR project of $11 million.

Pension and other postretirement non-service credits, net. Pension and other postretirement non-service credits, net were $17 million higher for the six months ended June 30, 2020 compared to the prior-year period primarily due to higher market returns in 2019.

Interest charges, net of allowance for borrowed funds used during construction. Interest charges, net of allowance for borrowed funds used during construction were $6 million higher for the six months ended June 30, 2020 compared to the prior-year period primarily due to higher debt balances in the current period.

Income taxes.  Income taxes were $2 million higher for the six months ended June 30, 2020 compared with the prior-year period primarily due to higher pre-tax net income, partially offset by the amortization of excess deferred taxes (see Note 15).

LIQUIDITY AND CAPITAL RESOURCES
 
Overview
 
Pinnacle West’s primary cash needs are for dividends to our shareholders and principal and interest payments on our indebtedness.  The level of our common stock dividends and future dividend growth will be dependent on declaration by our Board of Directors and based on a number of factors, including our financial condition, payout ratio, free cash flow and other factors.
 
Our primary sources of cash are dividends from APS and external debt and equity issuances.  An ACC order requires APS to maintain a common equity ratio of at least 40%.  As defined in the related ACC order, the common equity ratio is defined as total shareholder equity divided by the sum of total shareholder equity and long-term debt, including current maturities of long-term debt.  At June 30, 2020, APS’s common equity ratio, as defined, was 52%.  Its total shareholder equity was approximately $5.9 billion, and total capitalization was approximately $11.5 billion.  Under this order, APS would be prohibited from paying dividends if such payment would reduce its total shareholder equity below approximately $4.6 billion, assuming APS’s total capitalization remains the same.  This restriction does not materially affect Pinnacle West’s ability to meet its ongoing cash needs or ability to pay dividends to shareholders.
 
APS’s capital requirements consist primarily of capital expenditures and maturities of long-term debt.  APS funds its capital requirements with cash from operations and, to the extent necessary, external debt financing and equity infusions from Pinnacle West.


88



Summary of Cash Flows
 
The following tables present net cash provided by (used for) operating, investing and financing activities (dollars in millions):
 
Pinnacle West Consolidated
 
Six Months Ended
June 30,
 
Net
 
2020
 
2019
 
Change
Net cash flow provided by operating activities
$
370

 
$
346

 
$
24

Net cash flow used for investing activities
(653
)
 
(528
)
 
(125
)
Net cash flow provided by financing activities
280

 
178

 
102

Net change in cash and cash equivalents
$
(3
)
 
$
(4
)
 
$
1


Arizona Public Service Company
 
Six Months Ended
June 30,
 
Net
 
2020
 
2019
 
Change
Net cash flow provided by operating activities
$
378

 
$
335

 
$
43

Net cash flow used for investing activities
(656
)
 
(536
)
 
(120
)
Net cash flow provided by financing activities
274

 
197

 
77

Net change in cash and cash equivalents
$
(4
)
 
$
(4
)
 
$

 
Operating Cash Flows
 
Six-month period ended June 30, 2020 compared with six-month period ended June 30, 2019 Pinnacle West’s consolidated net cash provided by operating activities was $370 million in 2020, compared to $346 million in 2019, an increase of $24 million in net cash provided by operating activities primarily due to lower pension contributions, operations and maintenance cost, income tax payments, property tax payments and interest expense, partially offset by lower cash receipts from electric revenues. The difference between APS and Pinnacle West's net cash provided by operating activities primarily relates to APS's lower income tax payments.

Retirement plans and other postretirement benefits. Pinnacle West sponsors a qualified defined benefit pension plan and a non-qualified supplemental excess benefit retirement plan for the employees of Pinnacle West and our subsidiaries.  The requirements of the Employee Retirement Income Security Act of 1974 ("ERISA") require us to contribute a minimum amount to the qualified plan.  We contribute at least the minimum amount required under ERISA regulations, but no more than the maximum tax-deductible amount.  The minimum required funding takes into consideration the value of plan assets and our pension benefit obligations.  Under ERISA, the qualified pension plan was 117% funded as of January 1, 2020 and 112% as of January 1, 2019.  Under GAAP, the qualified pension plan was 97% funded as of January 1, 2020 and 90% funded as of January 1, 2019. See Note 5 for additional details. The assets in the plan are comprised of fixed-income, equity, real estate, and short-term investments.  Future year contribution amounts are dependent on plan asset performance and plan actuarial assumptions.  We have not made voluntary contributions to our pension plan year-to-date in 2020. The minimum required contributions for the pension plan are zero for the next three years. We expect to make voluntary contributions up to $100 million per year during the 2020-2022 period. We do not expect to make any contributions over the next three years to our other postretirement benefit plans. We continue to monitor COVID-19 and its impact on our retirement plans and other

89



postretirement benefits but we believe, due to our liability driven investment strategy, which helps to minimize the impact of market volatility on our plan’s funded status, our pension plan’s funded status is still above 90% funded as of June 30, 2020.

The Coronavirus Aid, Relief, and Economic Security (CARES) Act allows employers to defer payments of the employer share of Social Security payroll taxes that would have otherwise been owed from March 27, 2020 through December 31, 2020. We are deferring the cash payment of the employer's portion of Social Security payroll taxes for the period July 1, 2020 through December 31, 2020 that we expect will be in the range of $15 million to $20 million. We will pay half of this cash deferral by December 31, 2021 and the remainder by December 31, 2022.

Investing Cash Flows
 
Six-month period ended June 30, 2020 compared with six-month period ended June 30, 2019 Pinnacle West’s consolidated net cash used for investing activities was $653 million in 2020, compared to $528 million in 2019, an increase of $125 million primarily related to increased capital expenditures.
 
Capital Expenditures.  The following table summarizes the estimated capital expenditures for the next three years:

Capital Expenditures
(dollars in millions) 
 
Estimated for the Year Ended
December 31,
 
2020
 
2021
 
2022
APS
 

 
 

 
 

Generation:
 

 
 

 
 

Clean:
 
 
 
 
 
Nuclear Generation
$
129

 
$
123

 
$
123

Renewables and Energy Storage Systems ("ESS") (a)
121

 
490

 
671

Environmental
45

 
53

 
44

Other Generation
141

 
154

 
121

Distribution
556

 
444

 
446

Transmission
181

 
201

 
205

Other (b)
158

 
185

 
115

Total APS
$
1,331

 
$
1,650

 
$
1,725


(a)
APS Solar Communities program, energy storage, renewable projects, and other clean energy projects
(b)
Primarily information systems and facilities projects

 Generation capital expenditures are comprised of various additions and improvements to APS’s clean resources, including nuclear plants, renewables and ESS. Generation capital expenditures also include improvements to existing fossil plants. Examples of the types of projects included in the forecast of generation capital expenditures are additions of renewable and energy storage, and upgrades and capital replacements of various nuclear and fossil power plant equipment, such as turbines, boilers and environmental equipment.  We are monitoring the status of environmental matters, which, depending on their final outcome, could require modification to our planned environmental expenditures.


90



Distribution and transmission capital expenditures are comprised of infrastructure additions and upgrades, capital replacements, and new customer construction.  Examples of the types of projects included in the forecast include power lines, substations, and line extensions to new residential and commercial developments.

Capital expenditures will be funded with internally generated cash and external financings, which may include issuances of long-term debt and Pinnacle West common stock.

Financing Cash Flows and Liquidity
 
Six-month period ended June 30, 2020 compared with six-month period ended June 30, 2019 Pinnacle West’s consolidated net cash provided by financing activities was $280 million in 2020, compared to $178 million in 2019, an increase of $102 million in net cash provided.  The increase in net cash provided by financing activities includes $592 million in higher issuances of long-term debt partially offset by higher long-term debt repayments of $300 million, and a net decrease in short-term borrowings of $179 million.

APS’s consolidated net cash provided by financing activities was $274 million in 2020, compared to $197 million in 2019, an increase of $77 million in net cash provided.  The increase in net cash provided by financing activities includes $95 million in higher issuances of long-term debt and lower long-term debt repayments of $150 million, partially offset by a net decrease in short-term borrowings of $157 million.

Significant Financing Activities.  On June 17, 2020, the Pinnacle West Board of Directors declared a dividend of $0.7825 per share of common stock, payable on September 1, 2020 to shareholders of record on August 3, 2020.

Available Credit Facilities Pinnacle West and APS maintain committed revolving credit facilities in order to enhance liquidity and provide credit support for their commercial paper programs, to finance indebtedness, and other general corporate purposes.
 
On May 5, 2020, Pinnacle West refinanced its 364-day $50 million term loan agreement that would have matured on May 7, 2020 with a new 364-day $31 million term loan agreement that matures May 4, 2021. Borrowings under the agreement bear interest at Eurodollar Rate plus 1.40% per annum. At June 30, 2020, Pinnacle West had $31 million in outstanding borrowings under the current agreement.

On June 17, 2020, Pinnacle West issued $500 million of 1.3% unsecured senior notes that mature June 15, 2025. The net proceeds from the sale were used to repay early its $150 million term loan facility set to mature on December 21, 2020, to repay short-term indebtedness consisting of commercial paper and replenish cash incurred or used to fund capital expenditures, to redeem prior to maturity our $300 million, 2.25% senior notes due November 30, 2020, and for general corporate purposes.

At June 30, 2020, Pinnacle West had a $200 million revolving credit facility that matures in July 2023. Pinnacle West has the option to increase the amount of the facility up to a maximum of $300 million upon the satisfaction of certain conditions and with the consent of the lenders. Interest rates are based on Pinnacle West's senior unsecured debt credit ratings. The facility is available to support Pinnacle West's $200 million commercial paper program, for bank borrowings or for issuances of letters of credits. At June 30, 2020, Pinnacle West had no outstanding borrowings under its credit facility, no letters of credit outstanding and $41 million in commercial paper borrowings.

91




On January 15, 2020, APS repaid at maturity the remaining $150 million of the $250 million aggregate principal amount of its 2.2% Senior Notes.

On May 22, 2020, APS issued $600 million of 3.35% unsecured senior notes that mature May 15, 2050. The net proceeds from the sale were used to repay early its $200 million term loan facility, and to repay short-term indebtedness, consisting of commercial paper and revolver borrowings, and to replenish cash used to fund capital expenditures.

At June 30, 2020, APS had two revolving credit facilities totaling $1 billion, including a $500 million credit facility that matures in June 2022 and a $500 million facility that matures in July 2023.  APS may increase the amount of each facility up to a maximum of $700 million, for a total of $1.4 billion, upon the satisfaction of certain conditions and with the consent of the lenders.  Interest rates are based on APS’s senior unsecured debt credit ratings. These facilities are available to support APS’s $500 million commercial paper program, for bank borrowings or for issuances of letters of credit.  At June 30, 2020, APS had no outstanding borrowings under its revolving credit facilities, no letters of credit outstanding, and $220 million in commercial paper borrowings.

On November 27, 2018, the ACC issued a financing order in which, subject to specified parameters and procedures, it approved APS’s short-term debt authorization equal to a sum of (i) 7% of APS’s capitalization, and (ii) $500 million (which is required to be used for costs relating to purchases of natural gas and power) and a long-term debt authorization of $5.9 billion. On March 27, 2020, APS filed an application with the ACC to increase the long-term debt limit from $5.9 billion to $7.5 billion and to continue its authorization of short-term debt granted in the 2018 financing order.

As a result of the COVID-19 pandemic, in mid-March 2020 the commercial paper markets failed to function normally and we were unable to utilize commercial paper as our primary method of acquiring short-term capital, which resulted in us drawing on our revolving credit facilities during the first quarter of 2020.  In mid-April 2020, we were again able to utilize the commercial paper market and we have paid down the revolving credit facilities completely.  We do not believe this will have a material impact on our financial position, results of operations or cash flows.

See "Financial Assurances" in Note 8 for a discussion of separate outstanding letters of credit and surety bonds.
 
Other Financing Matters. See Note 7 for information related to the change in our margin and collateral accounts.

Debt Provisions
 
Pinnacle West’s and APS’s debt covenants related to their respective bank financing arrangements include maximum debt to capitalization ratios.  Pinnacle West and APS comply with these covenants.  For both Pinnacle West and APS, these covenants require that the ratio of consolidated debt to total consolidated capitalization not exceed 65%.  At June 30, 2020, the ratio was approximately 54% for Pinnacle West and 49% for APS.  Failure to comply with such covenant levels would result in an event of default which, generally speaking, would require the immediate repayment of the debt subject to the covenants and could "cross-default" other debt.  See further discussion of "cross-default" provisions below.

Neither Pinnacle West’s nor APS’s financing agreements contain "rating triggers" that would result in an acceleration of the required interest and principal payments in the event of a rating downgrade.  However,

92



our bank credit agreements contain a pricing grid in which the interest rates we pay for borrowings thereunder are determined by our current credit ratings.
 
All of Pinnacle West’s loan agreements contain "cross-default" provisions that would result in defaults and the potential acceleration of payment under these loan agreements if Pinnacle West or APS were to default under certain other material agreements.  All of APS’s bank agreements contain "cross-default" provisions that would result in defaults and the potential acceleration of payment under these bank agreements if APS were to default under certain other material agreements.  Pinnacle West and APS do not have a material adverse change restriction for credit facility borrowings.

On November 27, 2018, the ACC issued a financing order that, subject to specified parameters and procedures, increased APS’s long-term debt limit from $5.1 billion to $5.9 billion, and authorized APS’s short-term debt limit equal to a sum of (i) 7% of APS’s capitalization, and (ii) $500 million (which is required to be used for costs relating to purchases of natural gas and power). On March 27, 2020, APS filed an application with the ACC to increase the long-term debt limit from $5.9 billion to $7.5 billion and to continue its authorization of short-term debt granted in the 2018 financing order. If the ACC does not approve this
application by December 31, 2020, this could impact APS’s ability to enter into new long-term debt
obligations.
 
Credit Ratings
 
The ratings of securities of Pinnacle West and APS as of August 2, 2020 are shown below.  We are disclosing these credit ratings to enhance understanding of our cost of short-term and long-term capital and our ability to access the markets for liquidity and long-term debt.  The ratings reflect the respective views of the rating agencies, from which an explanation of the significance of their ratings may be obtained.  There is no assurance that these ratings will continue for any given period of time.  The ratings may be revised or withdrawn entirely by the rating agencies if, in their respective judgments, circumstances so warrant.  Any downward revision or withdrawal may adversely affect the market price of Pinnacle West’s or APS’s securities and/or result in an increase in the cost of, or limit access to, capital.  Such revisions may also result in substantial additional cash or other collateral requirements related to certain derivative instruments, insurance policies, natural gas transportation, fuel supply, and other energy-related contracts.  At this time, we believe we have sufficient available liquidity resources to respond to a downward revision to our credit ratings.

 
Moody’s
 
Standard & Poor’s
 
Fitch
Pinnacle West
 
 
 
 
 
Corporate credit rating
A3
 
A-
 
A-
Senior unsecured
A3
 
BBB+
 
A-
Commercial paper
P-2
 
A-2
 
F2
Outlook
Negative
 
Stable
 
Negative
 
 
 
 
 
 
APS
 
 
 
 
 
Corporate credit rating
A2
 
A-
 
A-
Senior unsecured
A2
 
A-
 
A
Commercial paper
P-1
 
A-2
 
F2
Outlook
Negative
 
Stable
 
Negative
 

93



Off-Balance Sheets Arrangements
 
See Note 6 for a discussion of the impacts on our financial statements of consolidating certain VIEs.
 
Contractual Obligations

As of June 30, 2020, there have been no material changes outside the normal course of business in contractual obligations from the information provided in our 2019 Form 10-K. See Note 3 for discussion regarding changes in our short-term and long-term debt obligations.


CRITICAL ACCOUNTING POLICIES
 
In preparing the financial statements in accordance with GAAP, management must often make estimates and assumptions that affect the reported amounts of assets, liabilities, revenues, expenses and related disclosures at the date of the financial statements and during the reporting period.  Some of those judgments can be subjective and complex, and actual results could differ from those estimates.  There have been no changes to our critical accounting policies since our 2019 Form 10-K.  See "Critical Accounting Policies" in Item 7 of the 2019 Form 10-K for further details about our critical accounting policies.


OTHER ACCOUNTING MATTERS

On January 1, 2020 we adopted ASU 2016-13, and related amendments, pertaining to the measurement of credit losses on financial instruments. See Note 13 for additional information related to new accounting standards.


MARKET AND CREDIT RISKS

Market Risks

Our operations include managing market risks related to changes in interest rates, commodity prices, investments held by our Nuclear Decommissioning Trusts, other special use funds and benefit plan assets.

Interest Rate and Equity Risk

We have exposure to changing interest rates.  Changing interest rates will affect interest paid on variable-rate debt and the market value of fixed income securities held by our Nuclear Decommissioning Trusts, other special use funds (see Note 11 and Note 12), and benefit plan assets.  The Nuclear Decommissioning Trusts, other special use funds and benefit plan assets also have risks associated with the changing market value of their equity and other non-fixed income investments.  Nuclear decommissioning and benefit plan costs are recovered in regulated electricity prices.


94



Commodity Price Risk

We are exposed to the impact of market fluctuations in the commodity price and transportation costs of electricity and natural gas.  Our risk management committee, consisting of officers and key management personnel, oversees company-wide energy risk management activities to ensure compliance with our stated energy risk management policies.  We manage risks associated with these market fluctuations by utilizing various commodity instruments that may qualify as derivatives, including futures, forwards, options and swaps.  As part of our risk management program, we use such instruments to hedge purchases and sales of electricity and fuels.  The changes in market value of such contracts have a high correlation to price changes in the hedged commodities.

The following table shows the net pretax changes in mark-to-market of our derivative positions (dollars in millions):
 
Six Months Ended
June 30,
 
2020
 
2019
Mark-to-market of net positions at beginning of period
$
(71
)
 
$
(59
)
Decrease (Increase) in regulatory asset
1

 
(22
)
Recognized in OCI:
 
 
 
Mark-to-market losses realized during the period
1

 
1

Change in valuation techniques

 

Mark-to-market of net positions at end of period
$
(69
)
 
$
(80
)

The table below shows the fair value of maturities of our derivative contracts (dollars in millions) at June 30, 2020 by maturities and by the type of valuation that is performed to calculate the fair values, classified in their entirety based on the lowest level of input that is significant to the fair value measurement.  See Note 1, "Derivative Accounting" and "Fair Value Measurements," in Item 8 of our 2019 Form 10-K and Note 11 for more discussion of our valuation methods.
Source of Fair Value
 
2020
 
2021
 
2022
 
2023
 
2024
 
Total 
Fair 
Value
Observable prices provided by other external sources
 
$
(35
)
 
$
(6
)
 
$
(11
)
 
$
(7
)
 
$

 
$
(59
)
Prices based on unobservable inputs
 
(6
)
 

 

 

 
(4
)
 
(10
)
Total by maturity
 
$
(41
)
 
$
(6
)
 
$
(11
)
 
$
(7
)
 
$
(4
)
 
$
(69
)


95



The table below shows the impact that hypothetical price movements of 10% would have on the market value of our risk management assets and liabilities included on Pinnacle West’s Condensed Consolidated Balance Sheets (dollars in millions):

 
June 30, 2020
 
December 31, 2019
 
Gain (Loss)
 
Gain (Loss)
 
Price Up 10%
 
Price Down 10%
 
Price Up 10%
 
Price Down 10%
Mark-to-market changes reported in:
 

 
 

 
 

 
 

Regulatory asset (a)
 

 
 

 
 

 
 

Electricity
$
1

 
$
(1
)
 
$

 
$

Natural gas
50

 
(50
)
 
55

 
(55
)
Total
$
51

 
$
(51
)
 
$
55

 
$
(55
)

(a)
These contracts are economic hedges of our forecasted purchases of natural gas and electricity.  The impact of these hypothetical price movements would substantially offset the impact that these same price movements would have on the physical exposures being hedged.  To the extent the amounts are eligible for inclusion in the PSA, the amounts are recorded as either a regulatory asset or liability.

Credit Risk

We are exposed to losses in the event of non-performance or non-payment by counterparties.  See Note 7 for a discussion of our credit valuation adjustment policy.


Item 3.        QUANTITATIVE AND QUALITATIVE DISCLOSURES ABOUT MARKET RISK
 
See "Key Financial Drivers" and "Market and Credit Risks" in Item 2 above for a discussion of quantitative and qualitative disclosures about market risks.
 
Item 4.         CONTROLS AND PROCEDURES
 
(a)                                 Disclosure Controls and Procedures
 
The term "disclosure controls and procedures" means controls and other procedures of a company that are designed to ensure that information required to be disclosed by a company in the reports that it files or submits under the Securities Exchange Act of 1934, as amended (the "Exchange Act") (15 U.S.C. 78a et seq.), is recorded, processed, summarized and reported, within the time periods specified in the SEC’s rules and forms.  Disclosure controls and procedures include, without limitation, controls and procedures designed to ensure that information required to be disclosed by a company in the reports that it files or submits under the Exchange Act is accumulated and communicated to a company’s management, including its principal executive and principal financial officers, or persons performing similar functions, as appropriate to allow timely decisions regarding required disclosure.
 
Pinnacle West’s management, with the participation of Pinnacle West’s Chief Executive Officer and Chief Financial Officer, have evaluated the effectiveness of Pinnacle West’s disclosure controls and procedures as of June 30, 2020.  Based on that evaluation, Pinnacle West’s Chief Executive Officer and Chief Financial Officer have concluded that, as of that date, Pinnacle West’s disclosure controls and procedures were effective.
 

96



APS’s management, with the participation of APS’s Chief Executive Officer and Chief Financial Officer, has evaluated the effectiveness of APS’s disclosure controls and procedures as of June 30, 2020.  Based on that evaluation, APS’s Chief Executive Officer and Chief Financial Officer have concluded that, as of that date, APS’s disclosure controls and procedures were effective.
 
(b)                                 Changes in Internal Control Over Financial Reporting
 
The term "internal control over financial reporting" (defined in SEC Rule 13a-15(f)) refers to the process of a company that is designed to provide reasonable assurance regarding the reliability of financial reporting and the preparation of financial statements for external purposes in accordance with GAAP.
 
No change in Pinnacle West’s or APS’s internal control over financial reporting occurred during the fiscal quarter ended June 30, 2020 that materially affected, or is reasonably likely to materially affect, Pinnacle West’s or APS’s internal control over financial reporting.


97



PART II OTHER INFORMATION

Item 1.                   LEGAL PROCEEDINGS
 
See "Business of Arizona Public Service Company — Environmental Matters" in Item 1 of the 2019 Form 10-K with regard to pending or threatened litigation and other disputes.
 
See Note 4 for ACC and FERC-related matters.
 
See Note 8 for information regarding environmental matters and Superfund-related matters.

Item 1A.                RISK FACTORS
 
In addition to the other information set forth in this report, you should carefully consider the factors discussed in Part I, Item 1A — Risk Factors in the 2019 Form 10-K and Part II, Item 1A of the 2020 1st Quarter 10-Q, which could materially affect the business, financial condition, cash flows or future results of Pinnacle West and APS.  The risks described in the 2019 Form 10-K and the 2020 1st Quarter 10-Q are not the only risks facing Pinnacle West and APS.  Additional risks and uncertainties not currently known to us or that we currently deem to be immaterial also may materially adversely affect the business, financial condition, cash flows and/or operating results of Pinnacle West and APS. 

The risk factor below is an update to our 2019 Form 10-K and 2020 1st Quarter 10-Q.

The outbreak of the Coronavirus (“COVID-19”) pandemic could negatively affect our business. 

The recent outbreak of COVID-19 is a rapidly developing situation around the globe that has led to economic disruption and volatility in the financial markets. The continued spread of COVID-19 and efforts to contain the virus could decrease demand for energy, lower economic growth, impact our employees and contractors, cause disruptions in our supply chain, increase certain costs, further increase volatility in the capital markets (and result in increases in the cost of capital or an inability to access the capital markets or draw on available credit facilities), delay the completion of capital or other construction projects and other operations and maintenance activities, delay payments or increase uncollectable accounts or cause other unpredictable events, each of which could adversely affect our business, results of operations, cash flows or financial condition.

As a result of the COVID-19 pandemic, from March through July 2020, we have experienced a decrease in demand from commercial and industrial customers and an increase in demand from residential customers which has resulted in a net decrease in weather normalized retail electricity sales as compared to 2019. APS is also experiencing an increase in bad debt expense associated with the COVID-19 pandemic that has resulted in a negative impact to our 2020 operating results. In mid-March 2020, we drew on our revolving credit facilities as a result of the commercial paper markets failing to function normally due to COVID-19, but we were subsequently able to utilize the commercial paper market in April 2020 and we have paid down the revolving credit facilities completely. We are also experiencing increased operations and maintenance expenses due to the need for personal protective equipment and other health and safety-related costs related to COVID-19.

Despite our efforts to manage the impacts, the degree to which the COVID-19 pandemic and related actions ultimately impact our business, financial position, results of operations and cash flows will depend on factors beyond our control including the duration, spread and severity of the outbreak, the actions taken to contain COVID-19 and mitigate its public health effects, the impact on the U.S. and global economies and demand for energy, and how quickly and to what extent normal economic and operating conditions resume.

98




Item 5.                OTHER INFORMATION

None.

    

99



Item 6.                 EXHIBITS
(a) Exhibits
Exhibit No.
 
Registrant(s)
 
Description
 
 
 
 
 
31.1
 
Pinnacle West
 
 
 
 
 
 
31.2
 
Pinnacle West
 
 
 
 
 
 
31.3
 
APS
 
 
 
 
 
 
31.4
 
APS
 
 
 
 
 
 
32.1*
 
Pinnacle West
 
 
 
 
 
 
32.2*
 
APS
 
 
 
 
 
 
101.INS
 
Pinnacle West
APS
 
XBRL Instance Document - the instance document does not appear in the interactive data file because its XBRL tags are embedded within the inline XBRL document.
 
 
 
 
 
101.SCH
 
Pinnacle West
APS
 
XBRL Taxonomy Extension Schema Document
 
 
 
 
 
101.CAL
 
Pinnacle West
APS
 
XBRL Taxonomy Extension Calculation Linkbase Document
 
 
 
 
 
101.LAB
 
Pinnacle West
APS
 
XBRL Taxonomy Extension Label Linkbase Document
 
 
 
 
 
101.PRE
 
Pinnacle West
APS
 
XBRL Taxonomy Extension Presentation Linkbase Document
 
 
 
 
 
101.DEF
 
Pinnacle West
APS
 
XBRL Taxonomy Definition Linkbase Document
 
 
 
 
 
104
 
Pinnacle West
APS
 
Cover Page Interactive Data File (formatted as Inline XBRL and contained in Exhibit 101)
 
 
 
 
 
________________________________
*Furnished herewith as an Exhibit.

100



In addition, Pinnacle West and APS hereby incorporate the following Exhibits pursuant to Exchange Act Rule 12b-32 and Regulation §229.10(d) by reference to the filings set forth below:
 
Exhibit No.
 
Registrant(s)
 
Description
 
Previously Filed as Exhibit(1)
 
Date Filed
 
 
 
 
 
 
 
 
 
3.1

 
Pinnacle West
 
 
3.1 to Pinnacle West/APS February 25, 2020 Form 8-K Report, File Nos. 1-8962 and 1-4473
 
2/25/2020
 
 
 
 
 
 
 
 
 
3.2

 
Pinnacle West
 
 
3.1 to Pinnacle West/APS June 30, 2008 Form 10-Q Report, File Nos. 1-8962 and 1-4473
 
8/7/2008
 
 
 
 
 
 
 
 
 
3.3

 
APS
 
Articles of Incorporation, restated as of May 25, 1988
 
4.2 to APS’s Form S-3 Registration Nos. 33-33910 and 33-55248 by means of September 24, 1993 Form  8-K Report, File No. 1-4473
 
9/29/1993
 
 
 
 
 
 
 
 
 
3.4

 
APS
 
 
3.1 to Pinnacle West/APS May 22, 2012 Form 8-K Report, File Nos. 1-8962 and 1-4473
 
5/22/2012
 
 
 
 
 
 
 
 
 
3.5

 
APS
 
 
3.4 to Pinnacle West/APS December 31, 2008 Form 10-K, File Nos. 1-8962 and 1-4473
 
2/20/2009
_______________________________
(1)  Reports filed under File Nos. 1-4473 and 1-8962 were filed in the office of the Securities and Exchange Commission located in Washington, D.C.

101



SIGNATURES
 
Pursuant to the requirements of the Securities Exchange Act of 1934, each registrant has duly caused this report to be signed on its behalf by the undersigned thereunto duly authorized.
 
 
 
 
PINNACLE WEST CAPITAL CORPORATION
 
 
 
(Registrant)
 
 
 
 
 
 
 
 
 
 
Dated:
August 6, 2020
 
By:
/s/ Theodore N. Geisler
 
 
 
 
Theodore N. Geisler
 
 
 
 
Senior Vice President and
 
 
 
 
Chief Financial Officer
 
 
 
 
(Principal Financial Officer and
 
 
 
 
Officer Duly Authorized to sign this Report)
 
 
 
 
 
 
 
 
 
 
 
 
 
ARIZONA PUBLIC SERVICE COMPANY
 
 
 
(Registrant)
 
 
 
 
 
 
 
 
 
Dated:
August 6, 2020
 
By:
/s/ Theodore N. Geisler
 
 
 
 
Theodore N. Geisler
 
 
 
 
Senior Vice President and
 
 
 
 
Chief Financial Officer
 
 
 
 
(Principal Financial Officer and
 
 
 
 
Officer Duly Authorized to sign this Report)


102