1 Months Ended 2 Months Ended 12 Months Ended
Feb. 01, 2017
$ / kWh
Jan. 13, 2017
USD ($)
Dec. 20, 2016
Jul. 12, 2016
USD ($)
Jun. 01, 2016
USD ($)
kWh
$ / kWh
Feb. 01, 2016
$ / kWh
Jan. 15, 2016
USD ($)
Jan. 01, 2016
USD ($)
Dec. 31, 2015
USD ($)
Jun. 01, 2015
USD ($)
Mar. 02, 2015
USD ($)
Feb. 01, 2015
$ / kWh
Jan. 06, 2012
USD ($)
$ / kWh
Jun. 01, 2011
USD ($)
Sep. 30, 2016
Dec. 31, 2014
storage_system
penetration_feeder
MW
Apr. 30, 2014
workshop
Dec. 31, 2016
$ / kWh
Jan. 27, 2017
USD ($)
Dec. 05, 2016
USD ($)
Jul. 01, 2016
USD ($)
Apr. 01, 2016
USD ($)
Jul. 01, 2015
USD ($)
Mar. 20, 2015
USD ($)
project
Lost Fixed Cost Recovery Mechanism                                                
Settlement Agreement                                                
Rate matter cap percentage of retail revenue                                   1.00%            
ACC | 2016 DSMAC                                                
Settlement Agreement                                                
Amount of approved budget                   $ 68,900,000                       $ 68,900,000    
Additional approved budget       $ 4,000,000                                        
ACC | 2017 DSMAC                                                
Settlement Agreement                                                
Amount of proposed budget         $ 62,600,000                                      
ACC | Residential demand response, energy storage and load management program                                                
Settlement Agreement                                                
Additional approved budget                                       $ 4,000,000        
ACC | Electric Energy Efficiency Standard                                                
Settlement Agreement                                                
Public utilities, cost effective energy efficiency programs, number of workshops | workshop                                 3              
Public utilities, cost effective efficiency programs, number of days to convene a workshop       120 days                                        
ACC | Modernization and Expansion of the Renewal Energy Standard                                                
Settlement Agreement                                                
Proposed renewal energy standard, percent of retail sales                             30.00%                  
Current renewal energy standard, percent of retail sales                             15.00%                  
ACC | Net Metering                                                
Settlement Agreement                                                
Cost of service, resource comparison proxy method, maximum annual percentage decrease     10.00%                                          
Cost of service for interconnected DG system customers, grandfathered period     20 years                                          
Rate matters, cost of service for new customers, guaranteed export price period     10 years                                          
ACC | Retail Rate Case Filing with Arizona Corporation Commission                                                
Regulatory Matters [Line Items]                                                
Net retail rate increase         $ 165,900,000                                      
Adjuster account balance transferred into base rates                 $ 267,600,000                              
Approximate percentage of increase in average customer bill         5.74%                                      
Approximate percentage of increase in average residential customer bill         7.96%                                      
original cost rate base         $ 6,800,000,000                                      
Required return on incremental fair value rate base above original cost rate base         1.00%                                      
Base rate for fuel and purchased power costs | $ / kWh         0.029882                                      
Decrease in base rate for fuel and purchased power costs | $ / kWh         0.03207                                      
Plan option, non-partial requirements customers, maximum average monthly energy usage | kWh         600                                      
Case completion term         12 months                                      
Settlement Agreement                                                
Reduced system benefits charge, amount               $ 14,600,000                                
FERC | Transmission rates, transmission cost adjustor and other transmission matters                                                
Settlement Agreement                                                
Increase (decrease) in annual wholesale transmission rates         $ 24,900,000                                      
Filing with the Arizona Corporation Commission | ACC | Retail rate case filing                                                
Regulatory Matters [Line Items]                                                
Net retail rate increase                           $ 95,500,000                    
Approximate percentage of increase in the average retail customer bill                           6.60%                    
Settlement Agreement                                                
Net change in base rates                         $ 0                      
Non-fuel base rate increase                         116,300,000                      
Fuel-related base rate decrease                         $ 153,100,000                      
Current base fuel rate (in dollars per kWh) | $ / kWh                         0.03757                      
Approved base fuel rate (in dollars per kWh) | $ / kWh                         0.03207                      
Estimated amount of transfer of cost recovery for certain renewable energy projects from the RES surcharge to base rates                         $ 36,800,000                      
Authorized return on common equity (as a percent)                         10.00%                      
Percentage of debt in capital structure                         46.10%                      
Percentage of common equity in capital structure                         53.90%                      
Deferral of property taxes in 2012, if Arizona property tax rates increase (as a percent)                         25.00%                      
Deferral of property taxes in 2013, if Arizona property tax rates increase (as a percent)                         50.00%                      
Deferral of property taxes for 2014 and subsequent years, if Arizona property tax rates increase (as a percent)                         75.00%                      
Deferral of property taxes in all years, if Arizona property tax rates decrease (as a percent)                         100.00%                      
Elimination of the sharing provision of fuel and purchased power costs                         9                      
Period to process the subsequent rate cases                         12 months                      
ACC staff sufficiency findings, general period of time                         30 days                      
Filing with the Arizona Corporation Commission | ACC | Retail rate case filing | Maximum                                                
Settlement Agreement                                                
Annual cost recovery due to modifications to the Environmental Improvement Surcharge                         $ 5,000,000                      
Cost Recovery Mechanisms | Lost Fixed Cost Recovery Mechanism                                                
Settlement Agreement                                                
Fixed costs recoverable per residential power lost (in dollars per kWh) | $ / kWh                                   0.031            
Fixed costs recoverable per non-residential power lost (in dollars per kWh) | $ / kWh                                   0.023            
Amount of adjustment approved representing prorated sales losses                     $ 38,500,000                          
Amount of adjustment representing prorated sales losses pending approval             $ 46,400,000                                  
Increase in amount of adjustment representing prorated sales losses             $ 7,900,000                                  
Cost Recovery Mechanisms | ACC | 2015 DSMAC                                                
Settlement Agreement                                                
Amount of proposed budget                                               $ 68,900,000
Rate matter number of resource savings projects | project                                               3
Cost Recovery Mechanisms | ACC | RES                                                
Settlement Agreement                                                
Plan term                                   5 years            
Cost Recovery Mechanisms | ACC | Arizona Renewable Energy Standard and Tariff 2016                                                
Settlement Agreement                                                
Amount of proposed budget                                             $ 148,000,000  
Cost Recovery Mechanisms | ACC | Arizona Renewable Energy Standard and Tariff 2017                                                
Settlement Agreement                                                
Amount of proposed budget                                         $ 150,000,000      
Cost Recovery Mechanisms | ACC | Power Supply Adjustor (PSA)                                                
Settlement Agreement                                                
Maximum increase (decrease) in PSA rate (in dollars per kWh) | $ / kWh                       0.004                        
PSA rate (in dollars per kWh) | $ / kWh           0.001678                                    
Cost Recovery Mechanisms | FERC | Transmission rates, transmission cost adjustor and other transmission matters                                                
Settlement Agreement                                                
Increase (decrease) in annual wholesale transmission rates                   $ (17,600,000)                            
Subsequent Event | ACC | 2017 DSMAC                                                
Settlement Agreement                                                
Amount of proposed budget                                     $ 66,600,000          
Subsequent Event | ACC | Power Supply Adjustor (PSA)                                                
Settlement Agreement                                                
PSA rate (in dollars per kWh) | $ / kWh (0.001348)                                              
Forward component of PSA rate (in dollars per kWh) | $ / kWh (0.001027)                                              
Historical component of PSA rate (in dollars per kWh) | $ / kWh (0.000321)                                              
Subsequent Event | ACC | Retail Rate Case Filing with Arizona Corporation Commission                                                
Regulatory Matters [Line Items]                                                
Case completion extension term   33 days                                            
Subsequent Event | Cost Recovery Mechanisms | Lost Fixed Cost Recovery Mechanism                                                
Settlement Agreement                                                
Amount of adjustment representing prorated sales losses pending approval   $ 63,700,000                                            
Increase in amount of adjustment representing prorated sales losses   $ 17,300,000                                            
Four Corners Power Plant | ACC | Retail Rate Case Filing with Arizona Corporation Commission                                                
Regulatory Matters [Line Items]                                                
Authorization to defer for potential future recovery of construction costs         400,000,000                                      
Ocotillo Plant | ACC | Retail Rate Case Filing with Arizona Corporation Commission                                                
Regulatory Matters [Line Items]                                                
Authorization to defer for potential future recovery of construction costs         $ 500,000,000                                      
Alternative to AZ Sun Program, Phase 1 | Arizona Renewable Energy Standard and Tariff 2014                                                
Settlement Agreement                                                
Rate matter additional capacity from AZ Sun projects | MW                               8                
Alternative to AZ Sun Program Phase 2 | Arizona Renewable Energy Standard and Tariff 2014                                                
Settlement Agreement                                                
Rate matter additional capacity from AZ Sun projects | MW                               2                
Number of energy storage systems | storage_system                               2                
Number of high solar penetration feeders | penetration_feeder                               2