Regulatory Matters (Details)
signature in Thousands
2 Months Ended 3 Months Ended 12 Months Ended
Apr. 15, 2016
signature
Feb. 01, 2016
$ / kWh
Jan. 15, 2016
USD ($)
Jun. 01, 2015
USD ($)
Mar. 02, 2015
USD ($)
Apr. 15, 2014
Customer
MW
Mar. 01, 2014
USD ($)
Jan. 01, 2014
USD ($)
$ / kWh
Jan. 06, 2012
USD ($)
$ / kWh
Jun. 01, 2011
USD ($)
Apr. 30, 2014
workshop
Mar. 31, 2016
USD ($)
$ / kWh
Jan. 31, 2016
$ / kWh
Mar. 31, 2015
USD ($)
Dec. 31, 2015
USD ($)
$ / kWh
Apr. 01, 2016
USD ($)
Jan. 12, 2016
USD ($)
Nov. 25, 2015
USD ($)
Mar. 20, 2015
project
Dec. 31, 2014
USD ($)
Dec. 19, 2014
MW
Jul. 01, 2014
USD ($)
Change in regulatory asset                                            
Deferred fuel and purchased power costs — current period                       $ (1,007,000)   $ (17,671,000)                
Amounts charged to customers                       (2,388,000)   (5,614,000)                
APS                                            
Change in regulatory asset                                            
Deferred fuel and purchased power costs — current period                       (1,007,000)   (17,671,000)                
Amounts charged to customers                       $ (2,388,000)   (5,614,000)                
APS | Filing with the Arizona Corporation Commission | ACC | Retail rate case filing                                            
Public Utilities, General Disclosures [Line Items]                                            
Net retail rate increase                   $ 95,500,000                        
Approximate percentage of increase in the average retail customer bill                   6.60%                        
Settlement Agreement                                            
Net change in base rates                 $ 0                          
Non-fuel base rate increase                 116,300,000                          
Fuel-related base rate decrease                 $ 153,100,000                          
Current base fuel rate (in dollars per kWh) | $ / kWh                 0.03757                          
Approved base fuel rate (in dollars per kWh) | $ / kWh                 0.03207                          
Estimated amount of transfer of cost recovery for certain renewable energy projects from the RES surcharge to base rates                 $ 36,800,000                          
Authorized return on common equity (as a percent)                 10.00%                          
Percentage of debt in capital structure                 46.10%                          
Percentage of common equity in capital structure                 53.90%                          
Deferral of property taxes in 2012, if Arizona property tax rates increase (as a percent)                 25.00%                          
Deferral of property taxes in 2013, if Arizona property tax rates increase (as a percent)                 50.00%                          
Deferral of property taxes for 2014 and subsequent years, if Arizona property tax rates increase (as a percent)                 75.00%                          
Deferral of property taxes in all years, if Arizona property tax rates decrease (as a percent)                 100.00%                          
Elimination of the sharing provision of fuel and purchased power costs                 9                          
Period to process the subsequent rate cases                 12 months                          
ACC staff sufficiency findings, general period of time                 30 days                          
APS | Filing with the Arizona Corporation Commission | ACC | Retail rate case filing | Maximum                                            
Settlement Agreement                                            
Annual cost recovery due to modifications to the Environmental Improvement Surcharge                 $ 5,000,000                          
APS | RES | Cost Recovery Mechanisms | ACC                                            
Settlement Agreement                                            
Plan term                       5 years                    
APS | 2014 RES | AZ Sun Program | Filing with the Arizona Corporation Commission                                            
Settlement Agreement                                            
Request to build additional utility scale solar, capacity | MW           20                                
APS | 2014 RES | Alternative to AZ Sun Program | Filing with the Arizona Corporation Commission                                            
Settlement Agreement                                            
Request to build additional utility scale solar, capacity | MW           10                                
Additional capacity from APS-owned non AZ Sun projects, impacted customers | Customer           1,500                                
APS | 2014 RES | Alternative to AZ Sun Program, Phase 1 | Filing with the Arizona Corporation Commission                                            
Settlement Agreement                                            
Request to build additional utility scale solar, capacity | MW                                         8  
APS | 2014 RES | Alternative to AZ Sun Program Phase 2 | Filing with the Arizona Corporation Commission                                            
Settlement Agreement                                            
Request to build additional utility scale solar, capacity | MW                                         2  
APS | 2015 RES | Cost Recovery Mechanisms | ACC                                            
Settlement Agreement                                            
Amount of proposed budget                                           $ 154,000,000
Amount of approved budget                                       $ 152,000,000    
APS | 2016 RES | Cost Recovery Mechanisms | ACC                                            
Settlement Agreement                                            
Amount of approved budget                                 $ 148,000,000          
APS | 2015 DSMAC | Cost Recovery Mechanisms | ACC                                            
Settlement Agreement                                            
Amount of approved budget                                   $ 68,900,000        
Number of resource savings projects | project                                     3      
APS | 2016 DSMAC | Cost Recovery Mechanisms | ACC                                            
Settlement Agreement                                            
Amount of proposed budget       $ 68,900,000                                    
APS | Electric energy efficiency standard | ACC                                            
Settlement Agreement                                            
Number of workshops | workshop                     3                      
APS | Power Supply Adjustor (PSA) | Cost Recovery Mechanisms | ACC                                            
Change in regulatory asset                                            
Beginning balance                       $ (9,688,000)   6,925,000 $ 6,925,000              
Deferred fuel and purchased power costs — current period                       (1,007,000)   (17,671,000)                
Amounts charged to customers                       (2,388,000)   (5,614,000)                
Ending balance                       $ (13,083,000)   $ (16,360,000) $ (9,688,000)              
PSA rate (in dollars per kWh) | $ / kWh   0.001678                                        
PSA rate for prior year (in dollars per kWh) | $ / kWh                             0.000887              
Forward component of increase in PSA (in dollars per kWh) | $ / kWh   0.001975                                        
Historical component of increase in PSA (in dollars per kWh) | $ / kWh   (0.000297)                                        
Transition component increase in PSA (in dollars per kWh) | $ / kWh                         (0.004936)                  
APS | Transmission Rates, Transmission Cost Adjustor and Other Transmission Matters | Cost Recovery Mechanisms | FERC                                            
Change in regulatory asset                                            
Increase in annual wholesale transmission rates       $ 17,600,000                                    
APS | Lost Fixed Cost Recovery Mechanism                                            
Change in regulatory asset                                            
Percentage of retail revenues                       1.00%                    
APS | Lost Fixed Cost Recovery Mechanism | Cost Recovery Mechanisms                                            
Change in regulatory asset                                            
Fixed costs recoverable per residential power lost (in dollars per kWh) | $ / kWh                       0.031                    
Fixed costs recoverable per non-residential power lost (in dollars per kWh) | $ / kWh                       0.023                    
Amount of adjustment representing prorated sales losses approval         $ 38,500,000   $ 25,300,000                              
Amount of adjustment representing prorated sales losses pending approval     $ 46,400,000                                      
Increase in amount of adjustment representing prorated sales losses     $ 7,900,000                                      
APS | Net Metering | ACC                                            
Change in regulatory asset                                            
Charge on future customers who install rooftop solar panels (in dollars per kWh) | $ / kWh               0.70       0.70                    
Estimated monthly collection due to charge on future customers who install rooftop solar panels               $ 4.90                            
Subsequent Event | APS | 2015 DSMAC | Cost Recovery Mechanisms | ACC                                            
Settlement Agreement                                            
Amount of proposed budget                               $ 68,900,000            
Subsequent Event | APS | Net Metering | Arizona Secretary of State                                            
Change in regulatory asset                                            
Rate benefits preservation initiative, number of signatures required | signature 225