XML 112 R85.htm IDEA: XBRL DOCUMENT v3.3.1.900
Jointly-Owned Facilities (Details) - ARIZONA PUBLIC SERVICE COMPANY
$ in Thousands
Dec. 31, 2015
USD ($)
Palo Verde Units 1 and 3  
Interests in jointly-owned facilities  
Percent Owned 29.10%
Plant in Service $ 1,744,137
Accumulated Depreciation 1,067,376
Construction Work in Progress $ 22,228
Palo Verde Unit 2  
Interests in jointly-owned facilities  
Percent Owned 16.80%
Plant in Service $ 583,633
Accumulated Depreciation 356,767
Construction Work in Progress $ 4,142
Palo Verde Common  
Interests in jointly-owned facilities  
Percent Owned 28.00%
Plant in Service $ 643,201
Accumulated Depreciation 231,609
Construction Work in Progress 64,069
Palo Verde Sale Leaseback  
Interests in jointly-owned facilities  
Plant in Service 351,050
Accumulated Depreciation 233,665
Construction Work in Progress $ 0
Four Corners Units 4, 5 and Common  
Interests in jointly-owned facilities  
Percent Owned 63.00%
Plant in Service $ 857,555
Accumulated Depreciation 577,321
Construction Work in Progress $ 77,317
Navajo Generating Station Units 1, 2 and 3  
Interests in jointly-owned facilities  
Percent Owned 14.00%
Plant in Service $ 274,640
Accumulated Depreciation 168,132
Construction Work in Progress $ 4,460
Cholla common facilities  
Interests in jointly-owned facilities  
Percent Owned 63.30%
Plant in Service $ 158,623
Accumulated Depreciation 53,777
Construction Work in Progress $ 1,390
ANPP 500kV System  
Interests in jointly-owned facilities  
Percent Owned 33.40%
Plant in Service $ 109,348
Accumulated Depreciation 36,576
Construction Work in Progress $ 1,594
Navajo Southern System  
Interests in jointly-owned facilities  
Percent Owned 22.70%
Plant in Service $ 62,139
Accumulated Depreciation 19,361
Construction Work in Progress $ 397
Palo Verde - Yuma 500kV System  
Interests in jointly-owned facilities  
Percent Owned 19.30%
Plant in Service $ 14,043
Accumulated Depreciation 5,226
Construction Work in Progress $ 133
Four Corners Switchyards  
Interests in jointly-owned facilities  
Percent Owned 49.80%
Plant in Service $ 38,420
Accumulated Depreciation 9,833
Construction Work in Progress $ 1,687
Phoenix - Mead System  
Interests in jointly-owned facilities  
Percent Owned 17.10%
Plant in Service $ 39,089
Accumulated Depreciation 13,173
Construction Work in Progress $ 151
Palo Verde - Estrella 500kV System  
Interests in jointly-owned facilities  
Percent Owned 50.00%
Plant in Service $ 89,832
Accumulated Depreciation 18,359
Construction Work in Progress $ 1,008
Morgan-Pinnacle Peak System  
Interests in jointly-owned facilities  
Percent Owned 64.60%
Plant in Service $ 129,855
Accumulated Depreciation 11,087
Construction Work in Progress $ 2,592
Round Valley System  
Interests in jointly-owned facilities  
Percent Owned 50.00%
Plant in Service $ 703
Accumulated Depreciation 286
Construction Work in Progress $ 0
Palo Verde - Morgan System  
Interests in jointly-owned facilities  
Percent Owned 87.70%
Plant in Service $ 12
Accumulated Depreciation 0
Construction Work in Progress $ 133,813
Hassayampa - North Gila System  
Interests in jointly-owned facilities  
Percent Owned 80.00%
Plant in Service $ 164,854
Accumulated Depreciation 1,159
Construction Work in Progress $ 0
Cholla 500 Switchyard  
Interests in jointly-owned facilities  
Percent Owned 85.70%
Plant in Service $ 547
Accumulated Depreciation 15
Construction Work in Progress $ 0
Saquaro 500 Switchyard  
Interests in jointly-owned facilities  
Percent Owned 75.00%
Plant in Service $ 773
Accumulated Depreciation 26
Construction Work in Progress $ 0