XML 33 R18.htm IDEA: XBRL DOCUMENT v3.20.4
Note 10 - Commitments and Contingencies
12 Months Ended
Dec. 31, 2020
Notes to Financial Statements  
Commitments and Contingencies Disclosure [Text Block]

10.

Commitments and Contingencies

 

At December 31, 2020, we had outstanding commitments of approximately $1.12 billion, net of proceeds from sales or trade-ins during 2021 and 2022, which is primarily related to the acquisition of tractors, containers, chassis, and other trailing equipment.

 

During 2020, we issued financial standby letters of credit as a guaranty of our performance under certain operating agreements and self-insurance arrangements. If we default on our commitments under the agreements or other arrangements, we are required to perform under these guaranties. The undiscounted maximum amount of our obligation to make future payments in the event of defaults is approximately $3.8 million as of December 31, 2020.

 

In January 2017 we exercised our right to utilize the arbitration process to review the division of revenue collected beginning May 1, 2016, as well as to clarify other issues, under our Joint Service Agreement with BNSF Railway Company (BNSF). BNSF requested the same. In October 2019 the arbitrators issued a Final Award and we recorded pretax charges in the third quarter 2019 of $26.8 million related to certain charges claimed by BNSF and $17.4 million for legal fees, cost and interest claimed by BNSF, for a total of $44.2 million. On January 17, 2020, we filed under seal in the United States District Court for the Western District of Arkansas (the Arkansas Federal Court) a motion to confirm and enforce the Final Award, seeking the Court’s specific enforcement of certain confidential contractual rights the arbitrators decided in our favor. BNSF moved to confirm the Final Award in the United States District Court for the District of Columbia, but that requested relief was ultimately denied and dismissed as moot. During the first quarter 2020, we recorded an $8.2 million pretax charge resulting from an adjusted calculation of the revenue divisions owed to BNSF under the Final Award. On July 21, 2020, the Arkansas Federal Court granted our motion in part, entering a judgment confirming the arbitration awards. In a sealed opinion, the Court denied our request for additional enforcement relief but did not foreclose our right to pursue post-confirmation enforcement in court or in arbitration if warranted. We have filed an appeal with the United States Court of Appeals for the Eighth Circuit seeking review of the Arkansas Federal Court’s denial.

 

As the result of state use tax audits, we have been assessed amounts owed for which we are vigorously appealing. If our appeals fail, we could be forced to settle these assessments for a material amount.

 

In June 2019, we recorded pre-tax charges of $20 million for the settlement of a casualty claim within our DCS segment.

 

We are involved in certain other claims and pending litigation arising from the normal conduct of business. Based on present knowledge of the facts and, in certain cases, opinions of outside counsel, we believe the resolution of these claims and pending litigation will not have a material adverse effect on our financial condition, results of operations or liquidity.