Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 $ 1,324.6
2024 1,500.6
2025 1,411.4
2026 1,323.0
2027 1,304.6
Thereafter 9,685.9
Total 16,550.1
Renewable Energy Purchase Contracts  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 751.8
2024 952.6
2025 954.8
2026 983.0
2027 998.5
Thereafter 8,141.1
Total 12,781.8
Natural Gas Procurement  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 447.1
2024 419.4
2025 340.9
2026 298.5
2027 269.4
Thereafter 1,450.6
Total 3,225.9
Purchased Power and Capacity  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 87.6
2024 86.8
2025 75.2
2026 2.9
2027 2.7
Thereafter 7.2
Total 262.4
Peaker CfDs  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 20.3
2024 21.1
2025 17.9
2026 16.0
2027 11.4
Thereafter 64.4
Total 151.1
Transmission Support Commitments  
Transmission Support Commitments  
2023 17.8
2024 20.7
2025 22.6
2026 22.6
2027 22.6
Thereafter 22.6
Total 128.9
CL&P  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 705.6
2024 722.3
2025 709.4
2026 632.6
2027 629.3
Thereafter 2,326.4
Total 5,725.6
CL&P | Renewable Energy Purchase Contracts  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 594.8
2024 609.1
2025 610.2
2026 607.6
2027 609.0
Thereafter 2,253.1
Total 5,283.8
CL&P | Purchased Power and Capacity  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 83.5
2024 83.9
2025 72.4
2026 0.1
2027 0.0
Thereafter 0.0
Total 239.9
CL&P | Peaker CfDs  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 20.3
2024 21.1
2025 17.9
2026 16.0
2027 11.4
Thereafter 64.4
Total 151.1
CL&P | Transmission Support Commitments  
Transmission Support Commitments  
2023 7.0
2024 8.2
2025 8.9
2026 8.9
2027 8.9
Thereafter 8.9
Total 50.8
NSTAR Electric  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 89.1
2024 281.0
2025 328.2
2026 334.6
2027 340.2
Thereafter 5,535.9
Total 6,909.0
NSTAR Electric | Renewable Energy Purchase Contracts  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 79.2
2024 270.0
2025 316.5
2026 322.9
2027 328.6
Thereafter 5,519.8
Total 6,837.0
NSTAR Electric | Purchased Power and Capacity  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 2.9
2024 2.9
2025 2.8
2026 2.8
2027 2.7
Thereafter 7.2
Total 21.3
NSTAR Electric | Transmission Support Commitments  
Transmission Support Commitments  
2023 7.0
2024 8.1
2025 8.9
2026 8.9
2027 8.9
Thereafter 8.9
Total 50.7
PSNH  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 82.8
2024 77.9
2025 32.9
2026 57.3
2027 65.7
Thereafter 373.0
Total 689.6
PSNH | Renewable Energy Purchase Contracts  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 77.8
2024 73.5
2025 28.1
2026 52.5
2027 60.9
Thereafter 368.2
Total 661.0
PSNH | Purchased Power and Capacity  
Unrecorded Unconditional Purchase Obligation, Fiscal Year Maturity [Abstract]  
2023 1.2
2024 0.0
2025 0.0
2026 0.0
2027 0.0
Thereafter 0.0
Total 1.2
PSNH | Transmission Support Commitments  
Transmission Support Commitments  
2023 3.8
2024 4.4
2025 4.8
2026 4.8
2027 4.8
Thereafter 4.8
Total $ 27.4